PAGE_2_-_A003.doc
DOC document 27 KB Posted
- Solicitation number
- HSCG85-16-R-P45G03
About this file
PAGE 2 OF SF-30
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30-A003.pdf | ||
| Sxx_51700_JAH_0915_378W_BOILER_SHELL_RENEWAL_modified_updated_-_no_5_year_cert.pdf | ||
| PAGE_2_-_A002.doc | DOC document | |
| SF30-A002.pdf | ||
| Attachment_4_-_Schedule_of_Items(REVISED).doc | DOC document | |
| Sxx_51700_JAH_0915_378W_BOILER_SHELL_RENEWAL_modified.doc | DOC document | |
| SF30-A001.pdf | ||
| REV0_MORGENTHAU_INPORT_MINI_FY16_Q4.pdf | ||
| Attachment_3_-_Solicitations_Provisions_(MORG).doc | DOC document | |
| Attachment_6-_GOVERNMENT_PROPERTY_REPORT.doc | DOC document | |
| ATACHMENT_5_-_Request_for_Clarification_Form.doc | DOC document | |
| Attachment_4_-_Schedule_of_Items.doc | DOC document | |
| ATTACHMENT_2_CONTRACT_CLAUSES_AND_SUPPLEMENTAL_TERMS_AND_CONDITIONS_(MORG).doc | DOC document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. HSCG85-16-R-P45G03
Unplanned Dockside Repairs of CGC MORGENTHAU (WHEC 722)
Amendment 0003
The purpose of this amendment is as follows:
a.
The following are the answers to the Request for Clarifications:
QUESTION NO. 1: Work Item O-06, Boiler Shell, Renew, paragraph 3.1.4; Contractor is requesting confirmation, if ship force is removing and reinstalling plenum cover?
ANSWER: Cutter personnel will not be responsible for removing or reinstalling plenum covers (interior or exterior). This will be the responsible of the contractor. CG crane will not be provided for this purpose.
QUESTION NO. 2: Work Item O-06, Boiler Shell, as paragraph 1.1, is it the Government’s intent to add an additional work item to complete 5 year certification? Or should contractor disregard this requirement?
ANSWER: Delete the 5 year certification.
b.
Offerors are also advised that the following paragraphs of O-06 specification are revised:
paragraph 3.2.3 through 3.2.3.4;
paragraph 3.3.3;
paragraph 3.4.2 through 3.4.3;
paragraph 3.6.2;
paragraph 3.6.4;
paragraph 3.9;
paragraph 3.12.2; and paragraph 3.13.
c.
A copy of the revised specification is incorporated as an attachment to this Amendment. Offerors are advised to utilize the revised specification in preparation of their price proposal.
d.
The due date to submit proposal for this requirement is extended until 22 June 2016 at 2:00 P.M., Pacific Standard Time. As stated on the original solicitation, proposals must be either e-mailed or mailed to Valerie.S.Riverachase@uscg.mil. Facsimile proposal will not be accepted and will be rejected.
e.
All other terms, conditions and provisions cited on the basic solicitation remain unchanged.