SPECIFICATIONS

View the file

Other files

File Type Posted
USCGC_WILLIAM_TATE_(WLM_560)_-_COMBINED_SYNOPSIS_(Final).docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC WILLIAM TATE (WLM 560)

SPECIFICATION FOR UNPLANNED DRYDOCK REPAIRS

FY2015

Developed By: Brian D Kist

(Rev-0, 15 September 2015)

USCGC WILLIAM TATE (WLM-175) UNPLANNED DRYDOCK AVAILABILITY FY2015

ii (Rev-0)

TABLE OF CONTENTS

iii (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.

All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:

• MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm

• Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp

• Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::

www.gpoaccess.gov

The Government is aware of the following internet web links where contractors may procure commercial specifications:

• American Welding Society (AWS): http://www.awspubs.com/index.php

• ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/

• NFPA: http://www.nfpa.org

• SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace

COAST GUARD DRAWINGS

Coast Guard Drawing 175 WLM 801-001, Rev A, Hull Lines Coast Guard Drawing 175 WLM 801-003, Rev A, Curves of Form Coast Guard Drawing 175 WLM 801-006, Rev J, Docking Drawing Coast Guard Drawing 175-WLM 568-001, Rev B, Bow Thruster Arrangement & Detail

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors

Manual Coast Guard Technical Publication (TP) 3628, 1/1/1999; Vol 4 of 9, Instruction Manual, Bow Thruster Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General

Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and

Allied Processes Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2014, Auxiliary

Machine Systems Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2014, Drydocking Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2014, Temporary

Services http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace v (Rev-0)

OTHER REFERENCES

None vi (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM

DESCRIPTION

NSN/PN QTY ESTIMATED

COST

($/UNIT)

1 N Seal Kit, Bow

Thruster NSN: 2010-01-555-9048 1 ea. 3,634.00

1 N Anode, Zinc NSN: 5365-01-495-5350 9 ea. 113.75 2 Y *Transducer Cover

Plate N/A 3 ea. 50.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter vii (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item Title

This section is not applicable to this package.

viii (Rev-0)

PRINCIPAL CHARACTERISTICS - TENDER

175' WLM, BUOY TENDER

PHYSICAL

Length overall 174' 8" Length between perpendiculars 155' 1" Depth 14' 8" Maximum beam 36' 0" Designed draft 8' 0" Mast height (above 8' waterline) 58' 8" Frame spacing 20" Full load displacement 855.15 Long Tons SW Light load displacement 719.78 Long Tons SW Minimum op condition displ 852.19 Long Tons SW

HULL

Hull material Steel

MACHINERY

Main propulsion Two Caterpillar 3508 DITA V-8 diesel; 999 BHP ea @ 1500 RPM

Two Ulstein 360 degree steerable Z-Drives, 403 SRPM @ 1600 ERPM Reduction gears Two Z-Drive units, Cardan shafting; 3.973:1 gear ratio Shaft seal John Crane Type ND Shaft bearings Five pedestal mounted, Cooper split roller bearings Number of propellers 2 Number of blades 4 Diameter 57.1" Rudders None; Z-drive Ship's service generators Three Caterpillar Model 3406 DITA Turbocharged; 285KW, 450V, 60 Hz, 1800

RPM

Emergency diesel generator One Caterpillar Model 3406 DIT 210 KW, 24V, 60 Hz, 1800 RPM

TANK CAPACITIES

Diesel oil capacity (100%) 16,385 gal Fresh water capacity (100%) 7,339 gal Lubricating oil (100%) 86 gal

1 (Rev-0)

00000_0315_FLT

REC_00000_FLT_ Commercial Project @ Contractor’ Facility (1212)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General

Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and

Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

2 (Rev-0)

3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, 3 (Rev-0) and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to adequately accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.

3.6 Local Policy. None.

3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:

• None.

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

4 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

Vessel Name Hull # Work Item # Work Item Title

Location of Work (incl. frame #’s) Area (sqft)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max.

threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

Name of QP-1/NACE Inspector Signature Cert. # Date / Time

5 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE &

TIME

ACTIVITY

(Surface preparation, primer coat, barrier coat, top coat, etc…)

LOCATION

(Frame & Deck, relation to equipment, etc.)

TEMPERATURE

% REL.

HUMID-

ITY DEW

PT. SURFACE AMBIENT

ΔT

| DP -

Surface |

6 (Rev-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

Location of Work (Frame References) Area (sqft)

SURFACE PREPARATION METHOD

PROFILE ACHIEVED (mils) Min Max Mean

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

Abrasive Manufacturer and Sieve Size: _________________________________

Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings: ______________

7 (Rev-0)

8 (Rev-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

SURFACE PREPARATION METHOD

PROFILE ACHIEVED (mils) Min Max Mean

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

Abrasive Manufacturer and Sieve Size: _________________________________

Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils Mean Mil Reading (IAW ASTM D4417-Method B) for above 10 readings (by column):

_____ mils _____ mils _____ mils _____ mils _____ mils

9 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15

DATE TEST LOCATIONS CONDUCTIVITY

(microsiemens/cm)

10 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

Coating Mfg Product Name Batch # Induction Time

Coating System Sequence (Primer/Touchup/3rd Coat, etc.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2

SPOT 1 2 3 4 5 AVERAGE

VALUE

*BASE METAL

READING (BMR)

*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

Location (Frame Reference): ___________________

SPOT 1 2 3 4 5

Overall Avg. DFT

ADJUSTMENTS

1 Avg. BMR Deviation 3 Before

Adjustments After Adjustments

Avg.

Location (Frame Reference): ___________________

SPOT 1 2 3 4 5

Overall Avg. DFT

ADJUSTMENTS

1 Avg. BMR Deviation 3 Before

Adjustments After Adjustments

Avg.

Location (Frame Reference): ___________________

SPOT 1 2 3 4 5

Overall Avg. DFT

ADJUSTMENTS

1 Avg. BMR Deviation 3 Before

Adjustments After Adjustments

Avg.

Application Method (Airless, Conventional Spray, Rolled) Average DFT

11 (Rev-0)

56800_CKN_0715_IBCT

REC_56800_Thrstrs_IBCT_175 WLM (ALL) (0715)

WORK ITEM 1: Thruster Unit (General), Overhaul

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to perform overhaul of the Bow Thruster Unit..

1.2 Government-furnished property.

MTI ITEM DESCRIPTION NSN/PN QTY

ESTIMATED

COST

($/UNIT)

N Seal Kit, Bow Thruster NSN: 2010-01-555- 9048 1 ea. 3,634.00

N Anode, Zinc NSN: 5365-01-495- 5350 9 ea. 113.75

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 175-WLM 568-001, Rev B, Bow Thruster Arrangement & Detail

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 3628, 1/1/1999; Vol 4 of 9, Instruction Manual, Bow Thruster Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2014, Auxiliary Machine Systems Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

None

12 (Rev-0)

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.1.1 Tech Rep. The Contractor shall provide the services of qualified Tech Rep, who is familiar with the Rolls Royce (formerly Bird Johnson) equipment/system, to accomplish the following tasks – on site:

• Provide manufacturer's proprietary information, software, and tools pertinent to the equipment/system.

• Assist with proper repair methods, and ensure compliance with manufacturer's procedures and standards during disassembly, inspection, repair, modification, calibration, and reassembly of the equipment/system.

3.1.1.2 The Contractor shall ensure that the Tech Rep is a certified representative of Rolls Royce.

3.1.1.3 The Contractor shall submit the Tech Rep’s name and résumé to the COR at the Arrival Conference.

3.1.2 Protective measures.

3.1.2.1 General. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.2.2 Hydraulic system. The Contractor shall maintain existing hydraulic system cleanliness and take all necessary precautions to prevent the introduction of contaminants into the hydraulic system. Immediately after disconnecting or removing components from the hydraulic system, seal all openings to the rest of the system using caps for externally threaded connection points, bolt-on blanks, or taped-on discs/covers made of durable plastic or sheet-metal that is no less than 1/16-inch thick.

NOTE

Be aware that plastic bags may be used only when arrangement or configuration prevents the use of the other sealing methods specified above.

3.1.3 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:

• Grid Cover on port thruster tube.

• Grid Cover on starboard thruster tube.

13 (Rev-0)

3.2 Operational test - initial. Prior to commencement of work, the Contractor shall witness Coast Guard Personnel perform an initial operational test of the bow thruster unit, to demonstrate existing operational condition. Submit a CFR.

3.3 Fluid disposal. The Contractor shall drain and dispose of all oil from the gear case, approximately 60 gallons, including head tanks in accordance with all applicable Federal, state and local regulations.

3.4 Maintenance. The Contractor shall perform the following maintenance requirements to the thruster units in accordance with TP 3628 and as shown on Coast Guard Drawing 175-WLM 568-001.

3.4.1 Visually inspect the magnetic plug to the gear box for the presence of any metal particles.

Remove all metal particles from the plug. Thoroughly clean each gear box free of sludge and any other foreign particles. Submit a CFR.

3.4.2 Remove and inspect thruster propeller for blade damage, true, and balance.

3.4.3 Remove and dispose of each existing propeller shaft seal. Clean and visually inspect each shaft surface for excessive wear.

3.4.4 Visually check for any excessive wear or damage to the teeth of the gears. Check the wear pattern on the spiral bevel gears to diagnose any problems. Submit a CFR.

3.4.5 Measure the shaft runout to inspect for bends. Take gear backlash readings on each gear set and compare results with the number etched on the back of the gear. Submit a CFR.

3.4.6 Renew the pinion gear seal in accordance with TP 3628.

3.4.7 Reassemble and reinstall all removed components, with new Government-furnished propeller shaft seal kit.

3.4.8 Oil renewal. In the presence of the Coast Guard Inspector, the Contractor shall renew the system oil in accordance with TP 3556, 8-6.2 (Charging the Thruster System), and SFLC Std Spec 5000, Appendix C, Paragraph C2.1 (Fluids). The system shall be renewed with Neptune AW Series 68 Biodegradable hydraulic fluid.

3.5 Zinc renewal. The Contractor shall renew zincs located on the thruster gearbox with Government-furnished zinc anodes as needed.

3.6 Touch-up preservation, general. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces, as applicable, to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs.)

3.7 Operational test – post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate the Bow Thruster System to be in satisfactory operating condition. Submit a CFR.

3.7.1 Test Bow Thruster both at dockside and at sea trials.

14 (Rev-0)

3.7.2 Operate thruster over entire range of RPM in both directions.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

4. NOTES

This section is not applicable to this work item.

15 (Rev-0)

86340_0115_FLT

REC_86340_FLT_175 WLM (ALL) (1214)

WORK ITEM 2: Drydock

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to drydock and undock the vessel and perform various drydocking-related tasks.

1.2 Government-furnished property.

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

Y *Transducer Cover Plate N/A 3 ea. 50.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 175 WLM 801-001, Rev A, Hull Lines Coast Guard Drawing 175 WLM 801-003, Rev A, Curves of Form Coast Guard Drawing 175 WLM 801-006, Rev J, Docking Drawing

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2014, Drydocking

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

16 (Rev-0)

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Key personnel. The Contractor shall determine key personnel and require their presence during all drydocking phases.

3.3 Docking requirements. The Contractor shall perform drydock and undock in accordance with SFLC Std Spec 8634, using Coast Guard Drawing 175 WLM 801-001, 175 WLM 801-003, and 175 WLM 801-006 for guidance.

3.4 Cutter conditions. The Contractor shall use the Full Load Condition, listed below for purposes of performing Pre-Award calculations as described in Appendix A (Requirements for Calculations) of SFLC Std Spec 8634.

• Displacement (LT SW): 855.15

• VCG (FT ABL): 13.76

• LCG (FT aft FP): 88.24

• LCF (FT aft FP): 91.37

• Trim (FT by stern): 0.19

• MT1” (LT-FT/Inch): 136.03

3.4.1 Cable, sling, or strap tension calculation. If the Contractor plans to use a vertical lift, crane, or travel/mobile lift to haul out the vessel, the Contractor shall submit the cable, sling, or strap tension calculation specified in Table A1 and paragraph A2.7.2.7 of SFLC Std Spec 8634 with the Pre-Award calculations, using the loading condition specified in paragraph 3.2.1.

3.4.2 Blocking. The Contractor shall facilitate docking the vessel in block position by arranging keel and side blocks and ensuring minimum block heights as shown on the vessel's docking plan.

TABLE 1 - BLOCKING

POS

BLOCK HEIGHT ABOVE

DOCKING FACILITY DECK

STEEL

PLAT

E

SITUATION

AWARENES

S

FIN

STABILIZER

S

ADDITIONA

L

Minimu m

Rudder Remova l

Propelle r Remova l

48" NA NA NA Sonar. Ensure NA None

17 (Rev-0) clearance around sonar(s) at Frames 21-22 and Frames 51-52.

NOTE

This vessel has a Z-drive propulsion system.

3.5 Pre-award calculations. The Contractor shall provide to the KO a set of pre-award calculations, as described in SFLC Std Spec 8634 Appendix A.

3.5.1 The Contractor shall provide vertical side/bilge block offsets for any side blocks placed in a location where vertical offsets are not already defined by the docking plan.

3.5.2 The Contractor shall submit an alternate blocking arrangement, as part of the pre-award calculation submission, to compensate for any changes from the docking plan.

NOTE

1. The USCG has established several approved alternate docking plans for each vessel-class, to facilitate complete access to the entire U/W body structure, for periodic comprehensive inspection and/or 100% preservation. This inspection and preservation pattern and periodicity is a configuration management concern that is a vital requirement of the contract. Intention to deviate from these plans (fewer blocks, block spacing, additional blocks, etc) shall be identified on pre-award calculations (Paragraph 3.5.2); an alternate docking plan and mitigation strategy shall be provided to maintain preservation and inspection configuration.

2. Pre-award calculations may be deemed unsatisfactory - and may adversely affect contract award if they are submitted with the following detrimental factors:

a. No methods have been proposed that meet the requirements for the specified docking plan.

b. Proposed block shifting or fleeting risk-mitigating plan may result in delays in period of performance.

c. Proposed alternate docking plan violates USCG configuration management policies."

NOTE

The Coast Guard Underwater Hull Inspection Board (UWHIB) will recommend the extent of underwater body coating system preservation required based on the conditions found during the underwater hull survey.

18 (Rev-0)

3.6 Unplanned availability: Underwater body cleaning-removal of marine growth. Within four hours after the vessel has been docked, the Contractor shall start cleaning the entire underwater hull from the upper edge of the boot top down, including sea chest gratings, sea chest interiors, fairwaters, rope guards, rudder, shaft strut, z-drive, thruster tunnel, and zinc anodes, as applicable.

The Contractor shall remove all marine growth, fouling, salt, and dirt from the underwater hull by High Pressure Fresh Water Wash, using a minimum pressure at the nozzle of 3,500 psi and maximum pressure of 7,000 psi. Complete the hull cleaning before marine growth hardens.

Removal of gratings is not required. Do not use chemical additives in the freshwater wash. Take extreme care to avoid damaging or removing existing intact underwater body coating. Conduct the work in this paragraph in lieu of the work described in SFLC Std Spec 8634 paragraphs

3.4.4.1 and 3.4.4.2.

3.7 Fuel offloading. The Contractor shall be aware that fuel offloading is not mandatory to drydock the vessel except when specifically required below.

3.8 Fleeting. Not required.

3.9 Additional requirements. None.

4. NOTES

4.1 Arrival conditions. The COR will advise the Contractor of the actual tank and draft readings when the vessel arrives, and will discuss with the Contractor any liquid loading changes necessary.

19 (Rev-0)

86350_1114_FLT

REC_86350_FLT_175 WLM (ALL) (0813)

WORK ITEM 3: Temporary Services, Provide - Cutter

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to provide temporary services to the Cutter, during the performance of this availability.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2014, Temporary Services

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area

20 (Rev-0) against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Temporary service particulars. The Contractor shall provide the below listed temporary services, in accordance with SFLC Std Spec 8635.

TABLE 1 - SERVICE SELECTION

*SUB-

PARAGRAPH TITLE Y/N

3.3.1 Office space N

3.3.2 Telephone N

3.3.3 Parking Y

3.3.4 Duty section berthing: __ male, __ female. Duty section berthing shall be provided for {Note: Choose one and delete the rest: (1) The entire duration of the availability, (2) during disruption of berthing areas or (3) ______ days}

3.3.5 Electrical power (including all requirements in associated sub-paragraphs) Y

3.3.6 Hull grounding straps (not applicable when cutter is waterborne) Y

3.3.7 Compressed air (including all requirements in associated sub-paragraphs) N

3.3.8 Hazardous material/hazardous waste disposal (see Tables 2 and 3 below) Y

3.3.9 Heavy lift equipment: {__day(s)/or __ hour(s)} N

3.3.10 Water supply

3.3.10.1 Potable water: {1200 gallons per day, at 40 psig.} Y

3.3.10.2 Hot-circulating water N

3.3.10.3 Cooling water Y

3.3.10.4 Firemain system (including all requirements in associated sub-paragraphs) Y

3.3.11 Steam (including all requirements in associated sub-paragraphs) N

3.3.12 Refuse disposal Y

3.3.13 Sewage and grey water disposal (including all requirements in associated sub-paragraphs) Y

3.3.14 Storage – General (including all requirements in associated sub-paragraphs):

3.3.14 Dry stores. N

3.3.14 Paint and flammable stores. N

3.3.14 Refrigerated stores. N

3.3.15 Small boat storage (including all requirements in associated sub-paragraphs) N *Each sub-paragraph number relates directly to the identical sub-paragraph number in SFLC Std Spec 8635.

TABLE 2 - HAZARDOUS WASTE DISPOSAL – LIQUIDS (GALLONS)

PAINT THINNERS ENGINE COOLANT BILGE WATER

xx xx 500

TABLE 3 - HAZARDOUS WASTE DISPOSAL – SOLIDS

OILY

FILTERS

OILY RAGS

(LBS)

EMPTY 1-GAL

CONTAINER*

EMPTY 5-GAL

CONTAINER*

EMPTY 55-GAL

CONTAINER*

xx 30 xx xx xx

21 (Rev-0)

*Previously housed hazardous materials.

3.2 Extended temporary services. If the performance period of the contract is extended by the KO, the contractor shall continue to provide all temporary services as specified herein for the extension period.

4. NOTES

This section is not applicable to this work item.

22 (Rev-0)

86850_0914_FLT

WORK ITEM 4: Sea Trial Performance, Support, Provide

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to provide support for the performance of sea trials.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

23 (Rev-0)

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Trial applicability. The Contractor shall provide support to the vessel crew to perform sea trials for all work items that require conducting operational tests while the vessel is waterborne or underway, prior to the item certification as being complete. The Contractor shall be responsible for ensuring all test procedures are prepared, approved, and distributed for the sea trials, and shall be responsible for recording test data and submitting CFRs to the COR.

3.3 Sea trial agenda. The Contractor shall prepare an agenda that details the Contractor’s plans for ensuring completion of the required sea trials.

3.3.1 Agenda contents. The Contractor shall ensure the agenda consists of chronological list of administrative events, inspection events and test events. Events shall be arranged to permit expeditious conduct with minimum interference between concurrent events.

NOTE

Mutually compatible events may be scheduled simultaneously.

3.3.1.1 The Contractor shall ensure the agenda identifies installation of any test equipment or component modification that could impact the normal operation of equipment or systems during performance of the trials.

3.3.1.2 The Contractor shall ensure the agenda identifies any operating instructions or special test procedures that could impact the normal operations of equipment or systems.

3.3.1.3 The Contractor shall ensure the agenda includes the full name, title, security clearance, home address, home telephone number and name of next of kin of each Contractor-personnel scheduled to ride the ship during performance of the trials.

3.3.2 Agenda submission requirements. The Contractor shall submit four legible copies of the sea trial agenda to the COR two days prior to the scheduled trials. The Contractor shall coordinate both the planning and conduct of the post-overhaul ship trials with the ship’s force (see 4.1 (Equipment operation)).

3.4 Environmental compliance. The Contractor shall abide by the below-listed rules, in addition to all other Federal, state, and local rules governing the overboard discharge of garbage and oil in the water.

3.4.1 Discharge of garbage.

TABLE 1 – GARBAGE RULES

GARBAGE TYPE RULE

Plastics, including synthetic ropes, fishing nets, and plastic bags Prohibited in all areas

Floating dunnage, lining and packing materials Prohibited less than 25 miles from nearest land

Food waste, paper, rags, glass, metal, bottles, crockery and similar refuse

Prohibited less than 12 miles from nearest land

24 (Rev-0)

Comminuted or ground food waste, paper, rags, glass, etc… Prohibited less than 3 miles from nearest land

3.4.2 Discharge of oil. The Contractor shall be aware that the Federal Water Pollution Control Act prohibits the discharge of oil or oily waste upon or into any navigable waters of the U.S. The prohibition includes any discharge that causes a film or discoloration of the surface of the water or causes a sludge or emulsion beneath the surface of the water.

CAUTION

Violators are subject to substantial civil and/or criminal sanctions including fines and imprisonment.

3.5 Dock trials. The Contractor shall conduct dock trials to demonstrate the material readiness of the ship for sea trials. Additionally, all onboard tests conducted after installation and prior to sea trials to prove proper installation and satisfactory operation of equipment shall be conducted in accordance with the requirements specified in the work items designated in paragraph 3.1 (Trial applicability). Ensure that the dock trials are begun no later than 12 hours prior to the scheduled sea trials.

3.5.1 The Contractor shall provide a pier facility (or allow the cutter to move to a Coast Guard pier) in order to support dock trials. Dock trials may not be conducted while the cutter remains floating inside the dry-dock (not touching the blocks).

3.5.2 During dock trials, the Contractor shall ensure the Contractor’s personnel observe tests under their cognizance and make such adjustments and repairs, as required.

3.6 Sea trials. As soon as possible after completion of the dock trials, the Contractor shall coordinate performance of the seal trials, based on the operational tests, as required in the applicable work items, for the following purpose:

• Performing tests that could not be performed while the ship was moored.

• Serving as final step in proving the success of the overhaul/repair tasks required in the designated work items, and ensuring that Contractor and COR are both satisfied that the ship is in all respects ready for final acceptance.

3.6.1 The Contractor shall have representatives on board the cutter to observe the trials for the purpose of observing whether or not the repairs are satisfactory.

3.6.2 The Contractor shall ensure the sea trials are be carried out in free route, away from other shipping, as designated by the COR.

3.7 Post-trial examination. After the completion of the sea trial, the Contractor shall perform a careful and thorough examination of parts of the repaired machinery, as designated by the COR.

If any part of the ship or its equipment fails to meet contractual requirements during trials, perform additional trials after corrective measures have been taken.

25 (Rev-0)

NOTES

1. Examples of dock trials include conducting cold (pre-light off) and hot checks, cycling machinery (rudders, BPU, turning gear, fin stabilizers), and conducting any post-docking shaft alignment verification checks. This time may also be used to on-load fuel, if needed for operations.

2. The conditions of the trials will be determined largely by the character of the work that has been performed in each case, and as designated by the COR. A full power trial should be run at this time unless the COR elects to defer this run until all new machinery parts are run-in or the training status of the crew permits full power operation without undue hazard.

3. This examination may be conducted by the Engineer Officer of the ship, in which case he will report the results of the examination to the COR, fully describing any defects or improper conditions found.

4. Representatives of manufacturers who have furnished ship components may be invited to witness trials subject to approval of the CO or OINC of the ship.

4. NOTES

4.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all tests.

Revisions Record
Consolidated List of References
Consolidated List of Government-furnished Property
Consolidated List of Critical Inspection Items
Principal Characteristics - TENDER
General Requirements
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
SOLUBLE SALT CONDUCTIVITY Measurements IAW SSPC-GUIDE 15
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
Dry Film Thickness (DFT) Measurements IAW SSPC-PA 2
Location (Frame Reference): ___________________
WORK ITEM 1: Thruster Unit (General), Overhaul
Coast Guard personnel will operate all shipboard machinery and equipment.
WORK ITEM 2: Drydock
WORK ITEM 3: Temporary Services, Provide - Cutter
WORK ITEM 4: Sea Trial Performance, Support, Provide