FAR CLAUSE 52.212-2 EVALUATION OF COMMERCIAL ITEMS AMENDMENT
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SCHEDULE_FOR_OBION_(WLR_65503)_DD__NB.xls | XLS spreadsheet | |
| SPEC_for_OBION_(WLR_65B)_DD_FQ4_BGW_14R0.pdf | ||
| SF30_Amendment_04_CGC_OBION_(2).pdf | ||
| SF30_Amendment_03_CGC_OBION.pdf | ||
| SF30_Amendment_02_CGC_OBION.pdf | ||
| SF30_Amendment_01_CGC_OBION.pdf | ||
| GOVERNMENT_PROPERTY_REPORT.pdf | ||
| SOLICITATION_OBION_DRYDOCK.doc | DOC document | |
| Past_Performance_Questionnaire.doc | DOC document | |
| SCHEDULE_FOR_OBION_(WLR_65503)_DD__NB.xls | XLS spreadsheet | |
| SPEC_for_OBION_(WLR_65B)_DD_FQ4_BGW_14R0.doc | DOC document | |
| GOVERNMENT_PROPERTY_REPORT.pdf | ||
| SCHEDULE_FOR_OBION_(WLR_65503)_DD__NB.xls | XLS spreadsheet | |
| SPEC_for_OBION_(WLR_65B)_DD_FQ4_BGW_14R0.doc | DOC document | |
| Past_Performance_Questionnaire.doc | DOC document | |
| SOLICITATION_OBION_DRYDOCK.doc | DOC document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT A00001 TO SOLICITATION HSCG85-14-Q-P45D05
FOR DRYDOCKING AND REPAIRS TO USCGC OBION AND 100 FT BARGE
(1) FAR 52.212-2 EVALUATION-COMMERCIAL ITEMS (JAN 1999)
PROPOSALS SHALL BE EVALUATED USING THE FOLLOWING CRITERIA:
The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The two (2) following factors shall be used to evaluate offers:
FACTOR (1) PAST PERFORMANCE:
The offeror shall identify at least two (2) relevant (construction, overhaul, repair and alteration of ships) and current federal, state or local government or private contracts performed during the last three (3) years. For each contract, list:
a. Contract number and customer point of contact (including two (2) points of contact
b. With telephone numbers)
c. Dollar value of the contract (Original and Final)
d. Type of service performed and whether Prime or subcontractor
e. Required completion date for the contract
f. Date the services were actually completed
g. Ship Name, Hull Number
h. Contract type (FFP, IDIQ, Requirement, Cost Type)
i. Percentage of growth in contract price (Additional work divided by award price)
If subcontracting arrangement is proposed, the above data must also be provided for each first tier subcontractor. If a joint effort or teaming arrangement is proposed, highlight previous experience with the proposed team or subcontractor.
The past performance evaluation will take into account the guidelines outlined at FAR 15.305(a)(2) Past Performance Evaluation. The Contractor’s past performance will be evaluated according to the following factors and questions:
· Quality of Product or Service Did the customer get what was specified?
Did the customer consider the final product high in quality?
If warranty issues arose, were they promptly corrected?
· Schedule Was the contract completed on time? If not, reason why not (growth work, Contractor delayed, government delayed?)
· Business Relations How was the customer service? Was the Contractor committed to customer satisfaction?
Would you use this company again (Why/Why not)?
· Management of Key Personnel Were subcontracts involved? Comments?
In evaluating Contractors past performance, the government intends to also review U.S. Coast Guard Contractor Performance Assessment Reports and other existing past performance ratings on relevant contracts. General trends in a Contractor’s performance will also be considered.
FACTOR (2) PRICE:
Offeror’s price shall represent the best price in response to the request for proposals. The price shall be evaluated to determine fairness and reasonableness. The contracting officer will also calculate the foreseeable cost of transporting the USCGC WYACONDA to offeror’s commercial shipyard. Foreseeable costs will be calculated for the purpose of price evaluation only.
****Past Performance is more important than Price**** Award may be made without any type of discussions or negotiations. This is based on the Contracting Officer’s determination after an evaluation has been completed on all offers.
(2) FAR 52.215-6 PLACE OF PERFORMANCE (OCT 1997)
(a) The offeror or respondent, in the performance of any contract resulting from this solicitation, [ ] intends, [ ] does not intend (check applicable block) to use one or more plants or facilities located at a different address from the address of the offeror or respondent as indicated in this request for proposal.
(b) If the offeror or respondent checks "intends" in paragraph (a) of this provision, it shall insert in the following spaces the required information:
Place of Performance
Name and Address of Owner and
(Street Address, City, County, Operator of the Plant or Facility if Other
State, Zip Code) than Offer or Respondent
(3) DISTANCE FACTOR ADJUSTMENT
(a) The work will be accomplished at the Contractor's Facility and the following distance adjustment factors will be applied to the prices proposed for this work.
(b) The home pier of the vessels is listed at #i on page 31. If the work covered by this solicitation is performed elsewhere than the home pier of the vessel, the Coast Guard will incur certain costs incident to moving the vessel to and from such location. Furthermore, Coast Guard inspection and other support in connection with the work covered by this solicitation will be provided by SFLC Naval Engineering Support Unit (NESU) listed in the following paragraphs, which is responsible for support of the vessel. If work is performed elsewhere than at these SFLC locations, the Coast Guard will incur certain costs incident to providing inspection and other support.
Note: The following foreseeable cost factors may be evaluated. The Contracting Officer will determine the applicability of these costs based on the circumstances of each acquisition.
FORESEEABLE COST FACTORS PERTAINING TO DIFFERENT SHIPYARD LOCATIONS
(1) There will be a transportation cost for one (1) U.S. Coast Guard Representative for NINE (9) round trips between the Contractor's offered place of performance and NESU New Orleans at the cost of coach-type airfare to be taken from the official airline guide or at a cost of $0.565 per mile if no airline service is available.
(2) If the Contractor's offered place of performance is more than fifty (50) driving miles from NESU New Orleans, the "Per Diem" expenses for fifty (50) days to support one (1) U.S. Coast Guard Representative while in the city of the place of contract performance will be determined in accordance with the Joint Federal Travel Regulations (JFTR).
(3) Facility costs to navigate vessel between its home pier and the Contractor's offered place of performance (round trip) is $168.44 per nautical mile based on FY14 Variable Cost Rates.
(4) Family separation allowance: Family separation allowance for EIGHT (8) personnel aboard USCGC OBION with dependents on board at $8.33 per day for each personnel for FIFTY (50) days each when the place of performance is more than fifty (50) driving miles from the home pier of the vessel.
*The entitlement is calculated from the date the vessel leaves homeport and ends upon return to homeport. All travel dates will be included in this calculation. See U.S. Coast Guard Pay Manual, COMDTINST M7220.29, Chapter 3-F.
(5) Crew's transportation during overhaul away from home port. As required by 37 USC 406 b. and Chapter 7, Part F1 of the Joint Federal Travel Regulations (JFTR), on the thirty-first (31) day of a ship being away from home port, and every sixty (60) days thereafter, all personnel with dependents will be provided round trip coach type airfare to the ship's homepier. For USCGC OBION, there will be one (1) home port visits during their 50 day performance period.
USCGC OBION has eight (8) personnel with dependents onboard. The cost of this airfare will be determined from the official airline guide. The calculation of trips does not include travel time to and from the overhaul place of performance. See Joint Federal Travel Regulations (JFTR), Chapter 5, Part C, paragraph U5222 and Chapter 7, Part F, paragraph U7115.
(End of FAR 52.212-2)