Specification CGC DALLAS FY11 MR2 Rev0.pdf

PDF 2 MB Posted

Attached to
CGC DALLAS (WHEC-716) DOCKSIDE REPAIR 2011
Solicitation number
HSCG85-11-Q-P45CJ9
Issued by

About this file

SPEC DALLAS DS

View the file

Other files

File Type Posted
AMENDMENT 2 CGC DALLAS FY11 MR2 DS.docx DOCX document
Specification CGC DALLAS FY11 MR2 Rev1.docx DOCX document
AMENDMENT 1 CGC DALLAS FY11 MR2 DS.docx DOCX document
RFQ CGC DALLAS —
SF1449 CGC DALLAS 2011 DS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC DALLAS (WHEC 716)

378 FOOT "E CLASS" HIGH ENDURANCE CUTTER

SPECIFICATION FOR DOCKSIDE REPAIRS

September 2011

Developed By: LTJG Jennifer L. Rest

(Rev-0, 25 May 2011)

USCGC DALLAS (WHEC-378E) DOCKSIDE AVAILABILITY 2011

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ....................................................................................................................................... iii Consolidated List of References ................................................................................................................ iv Consolidated List of Government-furnished Property ............................................................................. viii Consolidated List of Critical Inspection Items .......................................................................................... ix Principal Characteristics ............................................................................................................................. x

General Requirements

WORK ITEM D-01: CIRCUIT BREAKERS (60 HZ), INSPECT AND TEST

WORK ITEM D-02: CIRCUIT BREAKERS (400 HZ), INSPECT AND TEST

WORK ITEM D-03: ELECTRIC METERS, CALIBRATE

WORK ITEM D-04: HALON SYSTEM, INSPECT AND HYDROSTATIC TEST

WORK ITEM D-05: POTABLE WATER PNEUMATIC TANKS , CLEAN AND INSPECT

WORK ITEM D-06: CLEANING GEAR LOCKER 1-218-2-A DECK PLATING RENEWAL

WORK ITEM D-07: STORAGE LOCKER 2-90-2-A DECK PLATING RENEWAL

WORK ITEM D-08: SK STORES STEEL DECK REPAIRS

WORK ITEM D-09: FAN ROOM 2-160-1-Q COMPLETE PRESERVATION

WORK ITEM D-10: SOUNDING TUBE RENEWAL

WORK ITEM D-11: TANK (MP FUEL), CLEAN

WORK ITEM D-12: BERTHING HEAD RENOVATION

WORK ITEM D-13: GUNWHALE STEEL RENEWAL

WORK ITEM D-14: VENT DRAIN PIPING RENEWAL

WORK ITEM D-15: FANTAIL TAFF RAIL RENEWAL

WORK ITEM D-16: STBD MAIN DECK LONGITUDINAL AND BULKHEAD REPAIR

WORK ITEM D-17: LUBE OIL FILL STATION REPAIR

WORK ITEM D-18: BOSN WORKSHOP HULL INSULATION RENEWAL

WORK ITEM D-19: CAPTAINS CABIN OVERHEAD REPAIRS

WORK ITEM D-20: TEMPORARY SERVICES, PROVIDE

iii (Rev-0)

Revisions Record

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

Consolidated List of References

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.

All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free or charge. Other Government documents may be accessed – free of charge – as follows:

MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm

Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp

Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::

www.gpoaccess.gov

The Government is aware of the following internet web links where contractors may procure commercial specifications:

American Welding Society (AWS): http://www.awspubs.com/index.php

ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/

NFPA: http://www.nfpa.org

SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace

COAST GUARD DRAWINGS

Coast Guard Drawing 378-FRAM-E 320-19, Rev A, As Built Electrical One-Line Dia

Coast Guard Drawing 378-FRAM-E 431-3, Rev C, Lcl IC Swbd Iso - Elem W/D

Coast Guard Drawing 378-FRAM-E 431-4, Rev A, IC Switchboard Groom Label Plates

Coast Guard Drawing 378 FRAM-E 555-002, Rev E, Diag Halon Sys

Coast Guard Drawing 378 FRAM-E 555-003, Rev E, Halon ER & Gas Turbine

Coast Guard Drawing 378 FRAM-E 555-004, Rev E, Halon Sys Outside ER

Coast Guard Drawing 378 FRAM-E 555-005, Rev D, Halon Eng Strm 1

Coast Guard Drawing 378 FRAM-E 555-009, Rev E, Halon Sys ER/GT L/M

Coast Guard Drawing 378 FRAM-E 530-002, Rev B, Potable Water Press & Hot Water Storage Tanks

Coast Guard Drawing 378 FRAM-E 533-001, Rev F, Potable Water Machinery Diagram

Coast Guard Drawing 378-FRAM-E 85-1, Rev -, Booklet of General Plans

Coast Guard Drawing 378-FRAM-E 131-3, Rev -, Mn Dk Pltg & FR – Aft

Coast Guard Drawing 378-FRAM-E 508-1, Rev -, Insulation,Lagging Pipping-Machy

Coast Guard Drawing 378-FRAM-E 635-3, Rev -, Det of Insulation

Coast Guard Drawing 378-FRAM-E 635-6, Rev -, Arrg Insulation Cooling Sheathing

Coast Guard Drawing 378-FRAM-E 132-1, Rev -, 2nd Dk Pltg & FR - Fwd

Coast Guard Drawing 378-FRAM-E 122-4, Rev -, Transv Bhd 72, 80, 96

Coast Guard Drawing 378-FRAM-E 142-1, Rev -, 2nd Dk & 3rd Dk Pl – Aft http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace v (Rev-0)

Coast Guard Drawing 378-FRAM-E 120-3, Rev -, Misc Bhd 2nd & 3rd Dk

Coast Guard Drawing 378-FRAM-E 512-28, Rev -, Vent Fan Rm 2nd Dk

Coast Guard Drawing 378-FRAM-E 506-10, Rev -, Vents, Sounds, Overflows Diag

Coast Guard Drawing 378-FRAM-E 506-13, Rev -, Vents, etc Frames 72-144

Coast Guard Drawing 378-FRAM-E 621-3, Rev -, Typical Joiner Dets

Coast Guard Drawing 378-FRAM-E 621-4, Rev -, Joiner Bhds

Coast Guard Drawing 378-FRAM-E 644-1, Rev -, San Spaces a&D

Coast Guard Drawing 378-FRAM-E 644-2, Rev -, L Plumbing Fixtures

Coast Guard Drawing 378-FRAM-E 635-3, Rev -, Det of Insulation

Coast Guard Drawing 378-FRAM-W 624-1, Rev -, Joiner Doors

Coast Guard Drawing 378-FRAM-W 644-3, Rev -, Shower Stalls

Coast Guard Drawing 378-FRAM-W 801-1, Rev -, Booklet of General Plans

Coast Guard Drawing 378-FRAM-E 85-1, Rev -, Booklet of General Plans

Coast Guard Drawing 378-FRAM-E 123-3, Rev -, Misc Struct Encl

Coast Guard Drawing 378-FRAM-E 526-1, Rev -, Diag Weather Dk Drains

Coast Guard Drawing 378-FRAM-E 526-2, Rev -, Weather Dk Misc Drains Fwd

Coast Guard Drawing 378-FRAM-E 526-4, Rev -, Weather Dk Misc Drains Aft

Coast Guard Drawing 378-FRAM-E 526-6, Rev -, Weather Dk Misc Drains Fwd

Coast Guard Drawing 378-FRAM-E 100-1, Rev -, Struct Pen Pp Cplg

Coast Guard Drawing 378-FRAM-E 136-2, Rev -, 01 Dk Pltg & FR – Aft

Coast Guard Drawing 378-FRAM-E 264-1, Rev -, Diag LO Xfr - Pur Sys

Coast Guard Drawing 378-FRAM-E 131-3, Rev -, Mn Dk Pltg & FR – Aft

NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation For Compartments Installation

Details

Coast Guard Drawing 378-FRAM-E 514-1, Rev -, Hot - Chw Sys Diag

Coast Guard Drawing 378-FRAM-E 514-10, Rev -, AC Hot-Chw 01 LvlCoast Guard Drawing 378-

FRAM-E 635-6, Rev -, Arrg Insulation Cooling Sheathing

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3C, Change 1, Jun 2006, Coatings and

Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes

Coast Guard Technical Publication (TP) 3266, Manufacturers Instruction Book, SWBS Group(s) 324-

421, Change 1, May 1997

Coast Guard Technical Publication (TP) 3268, Manufacturers Instruction Book, SWBS Group(s) 427-

436, Change 2, May 2001

Coast Guard Technical Publication (TP) 3277B, SWBS 555, Feb 1998, Halon 1301 Fire Supression

Sytem vi (Rev-0)

Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), Jan 2009, Install

New Deck Covering Systems

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), Jan 2009, Provide

Temporary Services

OTHER REFERENCES

ASTM International (ASTM) D4417, 2003, Standard Test Methods for Field Measurement of Surface

Profile of Blast Cleaned Steel

Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting

Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters

Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency

Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety

Administration, Department Of Transportation

MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning

The Society for Protective Coatings (SSPC) VIS 1, 2004, Guide and Reference Photographs for Steel

Surfaces Prepared by Dry Abrasive Blast Cleaning

National Electrical Manufacturers Association (NEMA) Stds, Pub. No. AB4, 2003, Guidelines for

Inspection and Preventive Maintenance of Molded Case Circuit Breakers Used in Commercial and Industrial Applications

Underwriters Laboratories Inc. (UL) 489, May 2002, Molded Case Circuit Breaker

Naval Sea Systems Command (NAVSEA) 362-0895, Circuit Breaker Navy Type AQB - A250

Naval Sea Systems Command (NAVSEA) 362-2334, Air Circuit Breaker Navy Type AQB-A800 &

NQB-A800

Naval Sea Systems Command (NAVSEA) 362-2345, Circuit Breaker Navy Type AQB- A101 & NQB-

A101

Naval Sea Systems Command (NAVSEA) 362-2428, Air Circuit Breaker Navy Type ACB-902R

American National Standards Institute (ANSI/NCSL) Z540.3, 2006, General Requirements for

Calibration and Measuring and Test Equipment

National Fire Protection Association (NFPA) 12A, Jan 2009, Standard on Halon 1301 Fire Extinguishing

Systems

ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2002, Disinfection of Water-Storage Facilities

American Welding Society (AWS) D1.1/D1.1M:2006, 2008 Rev 08; Structural Welding Code - Steel, 20TH Edition

The Society for Protective Coatings SSPC-SP 1, 11/1/2004; Solvent Cleaning

The Society for Protective Coatings SSPC-SP 3, 11/1/2004; Power Tool Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal

Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections http://www.techstreet.com/ http://www.techstreet.com/ http://www.techstreet.com/ http://www.techstreet.com/cgi-bin/detail?product_id=1173948 http://www.awspubs.com/ vii (Rev-0)

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and

Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.15 (SSPC-SP 15), 2004, Commercial Grade Power Tool Cleaning

Naval Ship's Technical Manual (NSTM) Chapter 635, Jul 1998, Thermal, Fire and Acoustic Insulation viii (Rev-0)

Consolidated List of Government-furnished Property

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

This section is not applicable to this package.

ix (Rev-0)

Consolidated List of Critical Inspection Items

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000_STD, paragraph

3.2.6.5 (Inspection report particulars)):

Work

Item Title

D-11 Tank (MP Fuel), Clean

This section is not applicable to this package.

x (Rev-0)

PC_378E_WHEC_716_1109

Principal Characteristics

378E WHEC (DALLAS)

PHYSICAL CHARACTERISTICS

Length Overall 378' 4" Length between Perpendiculars 350' 0" Maximum Beam (@ 13' 6" DWL) 42' 3/4" Beam @ Main Deck 42' 0" Depth 26' 0-3/8" Main Deck Camber 6" in 21' 0" Minimum Berth Depth 20' 0" Height of highest projection 115' 0-3/4" Draft, Fwd @ Full Load 14.78' Draft, Aft @ Full Load 15.61' Draft, Fwd @ Minimum Operating 14.63' Draft, Aft @ Minimum Operating 15.33' Full Load Displacement 3150 long tons Minimum Operating Displacement 2760 long tons Light Ship Displacement 2477.20 long tons

HULL CHARACTERISTICS

Frame Spacing 1' 0" Material Deckhouse, fwd of Fr 96 HY-100 Steel Main Deck Frames 183 to 242-1/2 and fwd of

FR 96 HY-80 Steel

01 Level Frames 183 to 316 HY-80 Steel Lower hull around bow thruster, port and starboard Strakes A-3 and A-4, Frames 56 to

HY-80 Steel

Masts and superstructure above the 01 Deck Type 3456 Aluminum Remaining ASTM A-131

MACHINERY CHARACTERISTICS

Type of Propulsion CODOG

Two Diesel Engines Fairbanks Morse 12-cylinder opposed piston 38-TD-8-1/8;

7000 SHP total Two Gas Turbines Pratt and Whitney FT4A-2; 36,000 SHP total

Two Controllable Pitch Propellers Liaaen 4 blade, 13' 0" diameter; 149 RPM max on Diesel engines; 235 RPM max on Gas turbines) Two Reduction Gears Philadelphia Gear

Electrical Characteristics Two 550KW-AC Type, 450V, 60 Hz, 3 Phase, 720 RPM GM

8-645 diesel driven ship's service generators (located in the

Engine Room)

One 500KW-AC Type, 450V, 60 Hz, 3 Phase, Solar Model

101506-2001 gas turbine driven emergency service generator Two 25 KVA (PF = 0.8), 120V, 400 Hz, 3 Phase Electronic xi (Rev-0)

Specialty motor generators

Two 10 KVA (PF = 0.8), 120V, 400 Hz, 3 Phase Electronic

Specialty motor generators

TANK CAPACITIES

Diesel Oil 198,092 gal (95%) Fresh Water 17,794 gal (100%) JP-5 Fuel 25,717 gal (95%) xii (Rev-0)

1 (Rev-0)

00000_PWB_0111_FLT

REC_0000_FLT_ Commercial Project @ CG Facility (0110)

General Requirements

1. SCOPE

1.1 Intent. This item describes the general requirements to be followed by the Contractor while conducting this availability.

2. REFERENCES

COAST GUARD DRAWINGS

None.

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3C, Change 1, Jun 2006, Coatings and

Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes

OTHER REFERENCES

ASTM International (ASTM) D4417, 2003, Standard Test Methods for Field Measurement of Surface

Profile of Blast Cleaned Steel

Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting

Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters

Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency

Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety

Administration, Department Of Transportation

MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning

The Society for Protective Coatings (SSPC) VIS 1, 2004, Guide and Reference Photographs for Steel

Surfaces Prepared by Dry Abrasive Blast Cleaning

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

2 (Rev-0)

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec

0000, in accomplishing the following task:

Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two

Coast Guard fire watch personnel.

Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.

3.4 HW disposal. The Contractor shall be responsible for all hazardous wastes generated by work under this contract. Label and package all hazard wastes in 49 CFR-approved containers, and in accordance with all other applicable Federal, state, and local laws and regulations. In addition, comply with applicable parts of 40 CFR

262, applicable to handling of hazardous wastes.

3.4.1 Along with the Government, the Contractor shall be contractually considered the co-generator of all hazardous wastes; be aware that the Government will make available its facility’s EPA Generator Identification

(ID) Number for manifesting of hazardous wastes.

3.4.2 The Contractor shall identify, arrange, and be responsible for the turnover of all hazardous wastes, within the confines of the Coast Guard shore facility, to the facility’s HM/HW Coordinator. Notify the ship’s HW

Coordinator prior to any transfers of HW from ship to shore.

3.4.3 The Contractor shall prepare a manifest of hazardous waste to be reviewed and signed by the HM/HW

Coordinator. Contact the HM/HW Coordinator for turnover of any hazardous waste; in addition, notify the

COTR 24 hours prior to any waste removals, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.4.4 The Contractor shall be aware of the following:

3.4.4.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the

Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast

Guard facility without COTR or KO-approval.

3.4.4.3 Local environmental regulations at the Government facilities may be more stringent than in many jurisdictions. As with all environmental regulations, it is the Contractor's responsibility to research, prepare for, and comply with, the local and state regulations.

3.4.4.4 Coast Guard facilities do not have Facilities Response Plans (see 33 CFR 154 Subpart F). It is the

Contractor’s responsibility to furnish the Facility Response Plan (FRP) when required for over-the-water liquids transfers to and from vessels. This requirement is applicable to transfers to/from vessels with an oil/fuel capacity of 250 barrels or more.

3 (Rev-0)

3.5 Pre-surface preparation test coupon. In order to ensure production of required surface profile, the Contractor shall accomplish the following, tasks, whenever abrasive-blasting is required in a work item that is deemed a

”critical-coated’ surfaces:

3.5.1 Coupon material and test set-up particulars.

3.5.1.1 Conduct a performance test on all abrasive blasting operations on a Contractor- provided test coupon, prior to starting abrasive blasting operations on the vessel. Ensure the following:

The coupon shall be a new metal plate, of the same metal type and material properties as the vessel area to be blasted - steel or aluminum plate, as applicable, and shall have no existing anchor profile - other than the surface irregularities from the manufacturing process.

The test coupon shall be flat, with nothing welded to the side used for the anchor profile test, no thinner than a 1/8-inch plate and measuring no smaller than 1-foot by 1-foot.

For steel substrates, the coupon shall have the mill scale intact, and be in a Rust Grade "A" condition, in accordance with SSPC-VIS 1.

The test coupon shall be affixed so as to not permit excessive movement during the performance test, but shall not be affixed to the vessel.

3.5.1.2 Ensure that the abrasive-blasting operation for the test coupon is conducted with the identical setup and parameters that will be used blasting the designated vessel surfaces – including, but not limited to:

The abrasive media type and media size selected to achieve the anchor profile range, as specified in the applicable work items.

Nozzle size and type (straight bore, high velocity nozzle, angle nozzle...).

Delivery rate and pressure settings.

3.5.1.3 Blast a one-square foot area on one side of the test coupon to the abrasive surface preparation standard specified in the work item, and perform an anchor profile test of the blasted surface in accordance with ASTM

D4417, Method B or C. Notify the COTR in advance of the abrasive blasting operation test, to permit the witnessing of the test by the COTR. Submit a CFR documenting the results of the abrasive blasting operation test. The CFR shall include at a minimum, the following:

Area of the vessel for which the verified setup will be used to abrasive blast.

The selected abrasive media type and size.

The nozzle size and type.

The delivery rate and pressure.

The test coupon starting properties (material type and surface conditions).

The resultant anchor profile readings from the test (a minimum of 3 locations, separated by a minimum of

2 inches shall be recorded).

NOTES

1. A performance test of the abrasive blasting operations on a test coupon and measuring the resultant anchor profile prior to performing the abrasive blasting operation on the cutter is required. The test coupon will be used to evaluate the anchor profile produced by the equipment setup and selected abrasive media.

2. The reverse side of the test coupon may be used for the subsequent test, provided that the conditions in paragraph 3.5.1 (Coupon material and test set-up particulars) are met.

4 (Rev-0)

3. Ultra high pressure water jetting does not create an anchor profile and is exempt from the anchor profile test coupon check.

3.5.1.4 Repeat the abrasive blasting operation test in the following instances:

The equipment setup, that was evaluated during the test coupon abrasive blasting performance test in paragraph 3.5.1 (Coupon material and test set-up particulars), has changed.

The resultant anchor profile readings observed on the vessel are outside the specified anchor profile range.

Media is changed from MIL-A-22262 to CID A-A-59316 or vice versa.

The supplier of the abrasive blasting media changes, regardless if the new source for the media has the same specifications.

When Directed by the COTR.

CAUTION!

Ensure that blast media from the performance test does not strike the vessel during the test.

3.6 Interim changes to SFLC Std Spec 0000. The Contractor shall be aware of the fact that the requirements of paragraph 3.3.2.1.1 (Water depth) have been revised to read as follows:

“3.3.2.1.1 Water depth. Ensure that water depth is sufficient at the pier to allow the vessel's lowest underwater appendage to clear the bottom by at least two feet at:

Ordinary low water mark on non-tidal rivers.

At all tide conditions predicted during the availability for tidal rivers and other navigable waterways (Bay, Lake, etc.).”

4. NOTES

4.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may be accessed at the following URL address: http://www.uscg.mil/directives/cim.asp

4.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 0000 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

http://www.uscg.mil/directives/cim.asp

5 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

Vessel Name: _______________________ Hull Number: ______________ CLIN No.: _____________ Work Item Title: _______________________________ Area Being Preserved: ___________________________________

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with COMDTINST M10360.3, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating manufacturer(s).

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-based coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating manufacturer(s).

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum

5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-12, SP-11, SP-10…).

Verify surface anchor profile using ASTM D4417-Methods B or C against COMDTINST M10360.3. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000 sqft area

(maximum threshold: 70 microsiemens/cm ,for non-submerged surfaces and 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application:_________/_________; Return to service or removal from environment controls: _______/_______

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

Name of QP-1 or NACE-Certified Inspector: __________________________________________ Cert. No.: ____________ Signature of Inspector: _______________________________________ Date:_______________ Time: _________

6 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

Vessel Name: _______________________ Hull Number: ______________

CLIN No.: _____________ Work Item Title: ________________________________________________

(Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat)

DATE &

TIME

ENTER ACTIVITY

(Surface preparation, primer coat, barrier coat, top coat, etc…)

LOCATION

TEMPERATURE

% REL.

HUMIDITY

SIGNATURE

OF

INSPECTOR DEW

POINT SURFACE AMBIENT

ΔT

| DP - Surface

Name of QP-1 or NACE-Certified Inspector: __________________________________________ Cert. No.: ____________ Signature of Inspector: _______________________________________ Date:_______________ Time: _________

7 (Rev-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

Vessel Name: _______________________ Hull Number: ______________

CLIN No.: _____________ Work Item Title: ________________________________________________

Location of Surface Profile Measurements: __________________________________________________________________

SURFACE PREPARATION METHOD

PROFILE ACHIEVED

(mils) Min Max Mean

SSPC-SP-10/NACE No. 2

SSPC-SP-12/NACE No. 5

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

Abrasive Manufacturer and Sieve Size: _________________________________

Place Surface Profile Replica Tapes In The Spaces Provided Below, To Serve As Permanent QA record. Maintain separate log for each area/location. When an Area Is Divided Into Separate Sections, Maintain A Separate Log for Each Section.

Place Surface Profile

Replica Tape Here

Reading:__________ mils

Place Surface Profile

Replica Tape Here

Reading:__________ mils

Place Surface Profile

Replica Tape Here

Reading:__________ mils

Place Surface Profile

Replica Tape Here

Reading:__________ mils

Place Surface Profile

Replica Tape Here

Reading:__________ mils

Place Surface Profile

Replica Tape Here

Reading:__________ mils

Place Surface Profile

Replica Tape Here

Reading:__________ mils

Place Surface Profile

Replica Tape Here

Reading:__________ mils

Place Surface Profile

Replica Tape Here

Reading:__________ mils

Place Surface Profile

Replica Tape Here

Reading:__________ mils

Place Surface Profile

Replica Tape Here

Reading:__________ mils

Place Surface Profile

Replica Tape Here

Reading:__________ mils

Place Surface Profile

Replica Tape Here

Reading:__________ mils

Place Surface Profile

Replica Tape Here

Reading:__________ mils

Place Surface Profile

Replica Tape Here

Reading:__________ mils

Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings: ______________

Name of QP-1 or NACE-Certified Inspector: __________________________________________ Cert. No.: ____________

8 (Rev-0)

Signature of Inspector: _______________________________________ Date:_______________ Time: _________

9 (Rev-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

Vessel Name: _______________________ Hull Number: ______________

CLIN No.: _____________ Work Item Title: ________________________________________________

Location of Surface Profile Measurements: __________________________________________________________________

SURFACE PREPARATION METHOD

PROFILE ACHIEVED

(mils) Min Max Mean

SSPC-SP-10/NACE No. 2

SSPC-SP-12/NACE No. 5

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

Abrasive Manufacturer and Sieve Size: _________________________________

Record Measurements Taken In The Spaces Provided Below, To Serve As Permanent QA record. Maintain separate log for each area/location. When an Area Is Divided Into Separate Sections, Maintain A Separate Log for Each Section.

Reading: __________ mils __________ mils __________ mils __________ mils __________ mils

Reading: __________ mils __________ mils __________ mils __________ mils __________ mils

Reading: __________ mils __________ mils __________ mils __________ mils __________ mils

Reading: __________ mils __________ mils __________ mils __________ mils __________ mils

Reading: __________ mils __________ mils __________ mils __________ mils __________ mils

Reading: __________ mils __________ mils __________ mils __________ mils __________ mils

Reading: __________ mils __________ mils __________ mils __________ mils __________ mils

Reading: __________ mils __________ mils __________ mils __________ mils __________ mils

Reading: __________ mils __________ mils __________ mils __________ mils __________ mils

Reading: __________ mils __________ mils __________ mils __________ mils __________ mils

Mean Mil Reading (IAW ASTM D4417-Method B) for above 10 readings:

By Column: __________ mils __________ mils __________ mils __________ mils __________ mils

Name of QP-1 or NACE-Certified Inspector: __________________________________________ Cert. No.: ____________ Signature of Inspector: _______________________________________ Date:_______________ Time: _________

10 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

Vessel Name: _______________________ Hull Number: ______________

CLIN No.: _____________ Work Item Title: ________________________________________________

Location of Work (including frame numbers): _______________________________________

Area (square feet): ____________

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15

DATE TEST LOCATIONS CONDUCTIVITY

(microsiemens/cm)

Name of QP-1 or NACE-Certified Inspector: __________________________________________ Cert. No.: ____________ Signature of Inspector: _______________________________________ Date:_______________ Time: _________

11 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

Vessel Name: _______________________ Hull Number: ______________

CLIN No.: _____________ Work Item Title: ________________________________________________

Coating Manufacturer: ___________________Product Name: _______________________Batch Number: ____________ Induction Time: _______________________________________________________________ Coating System Sequence (Indicate Whether: Primer, Touch-Up Primer, Barrier Coat, 3rd Coat…): _______________________

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2

SPOT 1 2 3 4

5 AVERAGE

VALUE

*BASE METAL

READING (BMR)

*Required, If Magnetic Pull-Of (Type I/Banana) Gauge Is Used.

Location (Frame Reference): ___________________

SPOT 1 2 3 4 5

Overall Avg. DFT

ADJUSTMENTS

1 Avg. BMR Deviation 3 Before

Adjustments After Adjustments

Avg.

Location (Frame Reference): ___________________

SPOT 1 2 3 4 5

Overall Avg. DFT

ADJUSTMENTS

1 Avg. BMR Deviation 3 Before

Adjustments After Adjustments

Avg.

Location (Frame Reference): ___________________

SPOT 1 2 3 4 5

Overall Avg. DFT

ADJUSTMENTS

1 Avg. BMR Deviation 3 Before

Adjustments After Adjustments

Avg.

Application Method (Airless, Conventional Spray, Rolled):____________________

Average DFT: __________________________________________________________

Name of QP-1 or NACE-Certified Inspector: __________________________________________ Cert. No.: ____________ Signature of Inspector: _______________________________________ Date:_______________ Time: _________

12 (Rev-0)

32123_JSP_0309_378E

WORK ITEM D-01: CIRCUIT BREAKERS (60 HZ), INSPECT AND TEST

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to inspect and test Circuit Breakers (60

Hz) located on the Main Switchboard.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 378-FRAM-E 320-19, Rev A, As Built Electrical One-Line Dia

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 3266, Manufacturers Instruction Book, SWBS Group(s) 324-

421, Change 1, May 1997

OTHER REFERENCES

National Electrical Manufacturers Association (NEMA) Stds, Pub. No. AB4, 2003, Guidelines for

Inspection and Preventive Maintenance of Molded Case Circuit Breakers Used in Commercial and

Industrial Applications

Underwriters Laboratories Inc. (UL) 489, May 2002, Molded Case Circuit Breaker

Naval Sea Systems Command (NAVSEA) 362-0895, Circuit Breaker Navy Type AQB - A250

Naval Sea Systems Command (NAVSEA) 362-2334, Air Circuit Breaker Navy Type AQB-A800 &

NQB-A800

Naval Sea Systems Command (NAVSEA) 362-2345, Circuit Breaker Navy Type AQB- A101 & NQB-

A101

Naval Sea Systems Command (NAVSEA) 362-2428, Air Circuit Breaker Navy Type ACB-902R

3. REQUIREMENTS

3.1 General. The Contractor shall provide skilled technicians, portable instrument standards and all necessary equipment to inspect and test circuit breakers designated in the work item. The Contractor may remove the

Circuit Breakers from the vessel to a shoreside test facility. If this is done the Contractor shall exercise extreme care in transporting and reinstalling the circuit breakers to original operating condition on Switchboard.

http://www.techstreet.com/ http://www.techstreet.com/ http://www.techstreet.com/ http://www.techstreet.com/cgi-bin/detail?product_id=1173948

13 (Rev-0)

3.1.1 Prior to any wiring disconnection and removal of circuit breakers, the Contractor shall record all wiring information, trip setting adjustments, and equipment locations necessary for use in later reinstallation. Retain all mounting and connecting hardware for later reuse. Submit a CFR.

3.1.2 Disconnect and remove the circuit breakers listed in the Table 1. Coordinate the disconnection and removal of the circuit breakers with the COTR to minimize disruption of power. Temporarily cover or insulate switchboard or panel board openings created by the removal of circuit breakers to prevent personnel contact with energized conductors.

3.1.3 The Contractor shall notify the COTR 48 Hours prior to start work on this item.

3.2 Inspection requirement. The Contractor shall inspect all circuit breaker wire connectors, screws and plating and submit a CFR.

3.2.1 Surface burn marks and hairline cracks are acceptable but shall not deteriorate the mold surface or impair physical strength. Cracks are not permitted in wall section between phase and a ground plane when there is a conducting part in contact with the wall section. Cracks shall not exceed 0.75 inch in length, and in no case should be greater than 50 percent of the length of the surface in which the crack appears. Submit a CFR.

3.3 Circuit breaker testing. The contractor shall test circuit breakers listed in the Table 1 in accordance with the

National Electrical Manufacturers Association (NEMA) AB 4 or UL 489 Molded Case Circuit Breakers. The test shall include, at a minimum:

Mechanical Operation

Insulation Resistance

Individual Pole Resistance

Inverse-Time Over current Tripping

Instantaneous Over current Tripping

Rated Hold-In Current (Note: Perform this test only on the circuit breakers which are tripping under normal load condition. The COTR will identify the circuit breakers).

3.4 Circuit breaker data sheet. The contractor shall provide data sheet of each circuit breaker testing with the following information:

Circuit Breaker Model and Serial Number

Circuit Breaker Service

Circuit Breaker Visual Condition

Test Voltage/Test Amperes

Type of Test/Test Method/Test Date/Name of Test Laboratory

Result of Testing

3.5 Contractor’s option for circuits breaker renewal. The Contractor may elect to renew circuit breakers in lieu of testing (due to high cost of labor for testing or non available near by testing facilities) at no additional cost to the government. Ensure that all circuit breakers shall be UL 489 Certified.

14 (Rev-0)

TABLE 1 – CIRCUIT BREAKER LIST

QUANTITY

CIRCUIT BREAKER

TYPE

DESCRIPTION

6 Navy type ACB-902R S/S Gen Bus Tie and Emergency Gen Bus Tie Circuit

Breakers

54 Navy type AQB-A101LF Ship Service Switchboard (1S & 2S) & Emergency

Switchboard (1E) Circuit Breakers

30 Navy type AQB-A250 Ship Service Switchboard (1S & 2S) & Emergency

Switchboard (1E) Circuit Breakers 2 Navy type AQB-A400 Shore Tie Circuit Breakers (Shor Power Panel) 3 Navy type AQB-A600 Steering Gears & Bow Propulsion Circuit Breaker (1E)

1 Navy type AQB-A800 Emergency Power Load Center (2-323-1) Circuit Breaker

(1E) 6 Navy type AQB-A101 IC Switchboard, Unit #1

3.6 Circuit breaker reinstallation. After all testing is complete, reinstall circuit breakers using previously recorded wiring information to its original operating condition and Coast Guard TP 3266.

3.7 Operational test-post repairs. After completion of the work, the Contractor shall witness an operational test

(by Coast Guard personnel) of all circuit breakers to prove satisfactory operating condition. Submit a CFR.

3.7.1 Operate each Circuit Breaker “ON” and “OFF” several times to exercise the circuit breaker and ensure that mechanical linkages are free.

3.7.2 Direction of Rotation Test – Perform a direction of rotation test on each new and disturbed three-phase motor circuit.

4. NOTES

This section is not applicable to this work item.

15 (Rev-0)

SEQUENCE OF TESTING

NOTE: THE CONTRACTOR SHALL PLAN TESTING OF CIRCUIT BREAKERS TO MINIMIZE

POWER OUTAGE OF THE CUTTER. THE CONTRACTOR SHALL USE SPARE AVAILABLE

CIRCUIT BREAKERS FROM SWITCHBOARD TO POWER CRITICAL LOAD OF THE CUTTER.

SECURE ALL SHORE POWER AND GENERATORS.

REMOVE:

1. ACB-902R – No. 1 SSDG, No. 2 SSDG, EG, and Emergency Bus Tie

2. AQB-A600 – Bow Prop

3. AQB-A400 – Shore Tie Bus A (Note: The Contractor shall remove and test only one Shore Tie Circuit

Breaker at one time. After satisfactory testing of the first removed Shore Tie Circuit Breaker, the

Contractor shall re-install tested Shore Tie Circuit Breaker to it’s original operating condition & The

Contractor shall remove other Shore Tie Circuit Breaker for testing. The Contractor shall install blank cover plate at the removed Shore Tie Circuit Breaker to prevent accidental hazardous condition. During this testing of the Shore Tie Circuit Breaker, Ship’s shore capacity is cut to 400 Amps vice 800 Amp if this is not done.)

4. AQB-A250 – All on 1E Switchboard and Panel 2-232-1

5. AQB-A101LF – All on 1E Switchboard and Panel 2-232-1

REENERGIZE SHORE POWER THROUGH SHORE TIE BUS B (AND BUS A IF AVAILABLE).

2. Perform shop work and testing on removed circuit breakers.

3. Secure all shore power and generators.

4. Reinstall all removed circuit breakers except:

3. ACB-902R – No. 1 SSDG and No. 2 SSDG

4. AQB-A250 – 1-234-3(ALT) AFFF & No. 3 Fire Pump

REMOVE:

1. ACB-902R – Starboard Bus Tie and Port Bus Tie

2. AQB-A400 – Shore Tie Bus B (Note: The Contractor shall remove and test only one Shore Tie Circuit

Breaker at one time. After satisfactory testing of the first removed Shore Tie Circuit Breaker, the

Contractor shall re-install tested Shore Tie Circuit Breaker to it’s original operating condition & The

Contractor shall remove other Shore Tie Circuit Breaker for testing. The Contractor shall install blank cover plate at the removed Shore Tie Circuit Breaker to prevent accidental hazardous condition. During this testing of the Shore Tie Circuit Breaker, Ship’s shore capacity is cut to 400 amps vice 800 if this is not done.) (Note: In warm climates, install a spare AQB-A400 in this space instead of leaving empty so that there is sufficient shore power to run the air conditioning plants.)

3. AQB-A250 – All on 1S Switchboard

16 (Rev-0)

4. AQB-A101LF – All on 1S Switchboard

INSTALL

1. Install SSDG circuit breakers in Starboard and Port bus tie positions.

2. Install 1-234-3(ALT) circuit breaker in 1S-4P-(3-168-1) Miscellaneous Machinery Forward position.

REENERGIZE SHORE POWER THROUGH SHORE TIE BUS A (AND BUS B IF AVAILABLE).

1. Perform shop work and testing on removed circuit breakers.

2. Secure all shore power and generators.

3. Remove SSDG circuit breakers from port and starboard bus tie positions and reinstall in original locations.

REMOVE

1. Remove No. 3 Fire Pump alternate supply circuit breaker from the 1S-4P-(3-168-1) position and reinstall in Panel (2-323-1).

RE-INSTALL

1. Reinstall all removed circuit breakers in their original locations except:

1. AQB-A250

2. 1S-4P-(2-16-1) Anchor Windlass (175 A)

3. 1S-4P-(1-234-3)(NOR) AFFF & No. 3 Fire Pump (125 A)

4. 1S-4P-(3-203-1)(NOR) Vital Auxiliary Starboard (225 A)

5. 1S-4P-(3-247-1)(NOR) Vital Auxiliary Starboard (250 A)

6. AQB-A101LF: 1S-4P-F(NOR) No. 1 Steering Gear (100 A)

TEMPORARILY INSTALL RETAINED 1S SWITCHBOARD CIRCUIT BREAKERS AS FOLLOWS:

1. AQB-A250

2. 250 A in 2S-4P-(1-234-1) Galley position

3. 175 A in 2S-4P-(3-279-2) A/C and Refrigeration Aft position

4. 125 A in 2S-4P-(1-285-2) Vents Aft position

5. 225 A in 2S-4P-(3-176-1) A/C and Refrigeration Forward position

6. AQB-A101LF: 100 A in 2S-4P-(3-279-4) A/C and Refrigeration Aft position

7. Reenergize shore power through both Shore Tie Bus A and Bus B.

8. Perform shop work and testing on removed circuit breakers.

9. Secure all shore power and generators

10. Remove the five above listed temporary circuit breakers and reinstall in original 1S Switchboard locations.

17 (Rev-0)

11. Reinstall all removed 2S Switchboard circuit breakers in their original locations.

12. Reenergize shore power through both Shore Tie Bus A and Bus B.

18 (Rev-0)

43111_JSP_0309_378E

WORK ITEM D-02: CIRCUIT BREAKERS (400 HZ), INSPECT AND TEST

1.1 Intent. This work item describes the requirements for the Contractor to inspect and test circuit breakers (400

Hz) located on the IC Switchboard.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 378-FRAM-E 431-3, Rev C, Lcl IC Swbd Iso - Elem W/D

Coast Guard Drawing 378-FRAM-E 431-4, Rev A, IC Switchboard Groom Label Plates

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 3268, Manufacturers Instruction Book, SWBS Group(s) 427-

436, Change 2, May 2001

OTHER REFERENCES

National Electrical Manufacturers Association (NEMA) Stds, Pub. No. AB4, 2003, Guidelines for

Inspection and Preventive Maintenance of Molded Case Circuit Breakers Used in Commercial and

Industrial Applications

Underwriters Laboratories Inc. (UL) 489, May 2002, Molded Case Circuit Breaker

Naval Sea Systems Command (NAVSEA) 362-0895, Circuit Breaker Navy Type AQB - A250

Naval Sea Systems Command (NAVSEA) 362-2334, Air Circuit Breaker Navy Type AQB-A800 &

NQB-A800

Naval Sea Systems Command (NAVSEA) 362-2345, Circuit Breaker Navy Type AQB- A101 & NQB-

A101

Naval Sea Systems Command (NAVSEA) 362-2428, Air Circuit Breaker Navy Type ACB-902R

3. REQUIREMENTS

3.1 General. The Contractor shall provide skilled technicians, portable instrument standards and all necessary equipment to inspect and test circuit breakers designated in the work item. The Contractor may remove the

Circuit Breakers from the vessel to a shoreside test facility. If this is done the Contractor shall exercise extreme care in transporting and reinstalling the circuit breakers to original operating condition on Switchboard.

http://www.techstreet.com/ http://www.techstreet.com/ http://www.techstreet.com/ http://www.techstreet.com/cgi-bin/detail?product_id=1173948

19 (Rev-0)

3.1.1 Prior to any wiring disconnection and removal of circuit breakers, the Contractor shall record all wiring information, trip setting adjustments, and equipment locations necessary for use in later reinstallation. Retain all mounting and connecting hardware for later reuse. Submit a CFR.

3.1.2 Disconnect and remove the circuit breakers listed in the Table 1. Coordinate the disconnection and removal of the circuit breakers with the COTR to minimize disruption of power. Temporarily cover or insulate switchboard or panel board openings created by the removal of circuit breakers to prevent personnel contact with energized conductors.

3.1.3 The Contractor shall notify the COTR 48 Hours prior to start work on this Item.

3.2 Inspection requirement. The Contractor shall inspect all circuit breaker wire connectors, screws and plating and submit a CFR.

3.2.1 Surface burn marks and hairline cracks are acceptable but shall not deteriorate the mold surface or impair physical strength. Cracks are not permitted in wall section between phase and a ground plane when there is a conducting part in contact with the wall section. Cracks shall not exceed 0.75 inch in length, and in no case should be greater than 50 percent of the length of the surface in which the crack appears. Submit a CFR.

3.3 Circuit breaker testing. The contractor shall test circuit breakers listed in the Table 1 in accordance with the

National Electrical Manufacturers Association (NEMA) AB 4 or UL 489 Molded Case Circuit Breakers. The test shall include, at a minimum:

1. Mechanical Operation

2. Insulation Resistance

3. Individual Pole Resistance

4. Inverse-Time Over current Tripping

5. Instantaneous Over current Tripping

6. Rated Hold-In Current (Note: Perform this test only on the Circuit Breaker which are tripping under normal load condition. The COTR will identify the Circuit Breakers).

3.4 Circuit breaker data sheet. The contractor shall provide data sheet of each circuit breaker testing with the following information:

1. Circuit Breaker Model and Serial Number

2. Circuit Breaker Service

3. Circuit Breaker Visual Condition

4. Test Voltage/Test Amperes

5. Type of Test/Test Method/Test Date/Name of Test Laboratory

6. Result of Testing

3.5 Contractor’s option for circuits breaker renewal. The Contractor may elect to renew circuit breakers in lieu of testing (due to high cost of labor for testing or non available near by testing facilities) at no additional cost to the government. Ensure that all circuit breakers shall be UL 489 Certified.

20 (Rev-0)

TABLE 1 – CIRCUIT BREAKER LIST

QUANTITY CIRCUIT BREAKER TYPE DESCRIPTION

6 Navy type AQB-A101, 400 Hz IC Switchboard, Unit #1 16 Navy type AQB-A101, 400 Hz Electronics/Ordnance SWBD 2 Navy type AQB-LF250, 400 Hz Electronics/Ordnance SWBD 1 Navy type NQB-A101, 400 Hz Avionics Switchboard 14 Westinghouse 15 A, 400 Hz; Avionics Switchboard 1 Westinghouse 100 A, 400 Hz; Helicopter Starter 2 Navy type AQB-A250, 400 Hz Avionics Switchboard

3.6 Circuit breaker reinstallation. After all testing is complete, reinstall circuit breakers using previously recorded wiring information to its original operating condition and Coast Guard TP 3268.

3.7 Operational test-post repairs. After completion of the work, the Contractor shall witness an operational test

(by Coast Guard personnel) of all circuit breakers to prove satisfactory operating condition. Submit a CFR.

3.7.1 Operate each Circuit Breaker “ON” and “OFF” several times to exercise the circuit breaker and ensure that mechanical linkages are free.

3.7.2 Direction of Rotation Test – Perform a direction of rotation test on each new and disturbed three-phase motor circuit.

21 (Rev-0)

31100_JSP_0309_378E

WORK ITEM D-03: ELECTRIC METERS, CALIBRATE

1. SCOPE

1.1 Intent. This work item…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .