Solicitation_Amendment_SF-30_A4_3-4-2016_(Questions_ _Answers).pdf
PDF 233 KB Posted
- Solicitation number
- HSCG84-16-Q-BB8095
About this file
AMENDMENT 0004 QUESTIONS ANSWERS
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HSCG84-16-Q-BB8095 (Sinker Procurement) 1. CONTRACT ID CODE PAGE OF PAGES
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1 3
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
Amendment 0004 04 March 2016
6. ISSUED BY CODE 84 7. ADMINISTERED BY (If other than Item 6) CODE 84
Department of Homeland Security
United States Coast Guard
SILC-COCO-BSS-COB4
300 East Main Street, Suite 965
Norfolk, VA 23510-9112
Same as Item 6
POC: Lucinda P. Williams (757) 628-4125
E-mail: lucinda.p.williams@uscg.mill
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
HSCG84-16-Q-BB8095
X 9B. DATED (SEE ITEM 11)
04 March 2016
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for Receipt of Offers is extended / is not extended.
Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning one copy(s) of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR
ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED
MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc)
SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority).
E. IMPORTANT: Contractor is not / is required to sign this document and return ___ copy(s) to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The subject solicitation is hereby amended as follows:
A. The following page(s) of QUESTIONS and ANSWERS is provided for informational purposes.
B. Attachment 1, USCG DWG 6292 is hereby replaced in its entirety.
C. No additional or follow-up questions will be accepted.
D. The due date for Quotes remains 18 March 2016, 3:00 P.M. EST.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Wendy J. Culbreth
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY:
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITION UNUSABLE Prescribed by GSA, FAR (48 CFR)
53.243 mailto:lucinda.p.williams@uscg.mill
CONTINUATION SHEET FOR:
STANDARD FORM 30
REFERENCE NO. OF DOCUMENT BEING CONTINUED:
Solicitation Number: HSCG84-16-Q-BB8095
PAGE:
AMENDMENT OF SOLICITATION Amendment Number: 0004
NOTE: All referenced pages are the pages in the original Request for Quote (RFQ).
1. Question and Answer
Attachment 4
Question:
Clarification that the form is specifically asking for the price of the material and not any labor that is associated with a component piece. I will use the example of the lifting eyes. Since it would take a piece of steel and labor to form the lifting eye configuration, would only the steel cost be inserted in the column for" Portion of CLIN Price subject to EPA for steel"? Would the labor portion of the lifting eye fabrication be precluded from any contingency increase for subsequent option year? Now that Cement is going to be included in the EPA would the same apply to labor for the cement sinker fabrication?
Answer:
Reference Attachment 4 – EPA Table for Metal and Metal Products, #2 Diesel Fuel, and Ready-mix Concrete.
Regarding the Base Period CLINS (Pages 1-3 of Attachment 4)
* Column 4 labeled “Schedule B Unit Price” should be the same prices as the unit prices from the schedule in the solicitation (pages 7-21 of 80). These prices should include all of your costs for labor, all materials, etc (Note – this will change for the Option Periods Column 4 “Schedule B
Unit Price”).
*Column 5 - “Portion of the CLIN Price Subject to the EPA for Metal and Metal Products”, Column 6 - “Portion of CLIN Subject to the EPA for #2 Diesel Fuel”, and Column 7 – “Portion of CLIN Price Subject to the EPA for Ready-mix Concrete” should be the material costs of the steel (Column 5), diesel fuel (Column 6), and concrete (Column 7) that is already included in the
Column 4 - “Schedule B Unit Price”.
Columns 5 - 7 should not include any costs for labor or any other materials.
Regarding the Option Period CLINS (Pages 4 - 15 of Attachment 4)
* Column 5 - “Portion of the CLIN Price Subject to the EPA for Metal and Metal Products”, Column 6 - “Portion of CLIN Subject to the EPA for #2 Diesel Fuel”, and Column 7 – “Portion of CLIN Price Subject to the EPA for Ready-mix Concrete” should be the same amounts from
Columns 5-7 of the Base Period and should remain constant for each option period for each location (i.e. CLIN 00001AA, 10001AA, 20001AA, 30001AA and 40001AA (USCGC
Gasconade, Omaha, NE).
* Column 4 labeled “Schedule B Unit Price” should be the same prices as the unit prices from the schedule in the solicitation for each option year. The price may increase due to increased
CONTINUATION SHEET FOR:
STANDARD FORM 30
REFERENCE NO. OF DOCUMENT BEING CONTINUED:
Solicitation Number: HSCG84-16-Q-BB8095
PAGE:
AMENDMENT OF SOLICITATION Amendment Number: 0004 labor or any material costs (etc) other than steel, fuel and concrete. The costs for the steel, fuel and concrete should be the same as your costs for the Base Period CLINS. This is where the
EPA will adjust the costs for steel, fuel and concrete each year (if applicable).
2. Question and Answer
Attachment 1.
Attachment 1, USCG DWG 6292 has a reference to 3 other pages that are part of the drawing.
They are not part of the attachment, can they be furnished?
The other pages referenced on the drawing are for sinkers that are not part of this solicitation.
3. Question and Answer
Attachment 1.
Attachment 1, USCG DWG 6292, under notes states the government will furnish the molds.
How will we receive the molds, at whose cost and what is the expectation of condition upon their return?
The notes have been removed from the drawing. Molds will not be supplied. Notes on the drawing were for forms for larger sinkers not listed in the solicitation. The solicitation should be followed for specifications/requirements; the drawings are supplied only as a reference for sinker dimensions
4. Question and Answer
How many molds will be supplied?
ANSWER:
Molds will not be supplied.
File details come from the government source that posted it. Updated .