SPECIFICATION FOR CGC NANTUCKET
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Schedule Supplies_Services Nantucket 1316_DD_FGK_10ER0_BLANK.pdf | ||
| Nantucket_RFQ.DOC | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(June 8, 2009/ Rev-0)
USCGC NANTUCKET (WPB-1316)
110 FOOT A CLASS PATROL BOAT
SPECIFICATION FOR DRYDOCK REPAIRS
Developed By:
CWO F.G.Kiesel
Commander (v) Maintenance and Logistics Command, Atlantic 300 E. Main Street, Suite (600) Norfolk, VA 23510-9102
USCGC NANTUCKET (WPB-1316) DRYDOCK AVAILABILITY 2010
Page i (Rev-0)
TABLE OF CONTENTS
Work Item Title Page
List of Sketches iv
Revisions Record v
List of Applicable References vi
List of Government-furnished Property xiii
List of Critical Inspection Items xv
Specification Feedback xvi
General Requirements 1
1 Routine Drydocking 9
2 Provide Temporary Logistics 14
3 Clean and Inspect Fuel Service Tanks 16
4 Clean and Inspect Fuel Stowage and Overflow Tanks 19
5 Clean and Inspect Oil and Oily Waste Tanks 22
6 Clean and Inspect Sewage Collection and Holding Tanks 24
7 Clean and Inspect Grey Water Collection and Holding Tanks 27
8 Clean Sewage Piping System 30
9 Clean Grey Water Piping System 34
10 Clean and Disinfect Potable Water Tanks 38
11 Preserve and Disinfect Potable Water Tanks - 100% 41
12 Preserve and Disinfect Potable Water Tanks - Partial 44
13 Preserve Sewage Collection and Holding Tanks - 100% 47
Page ii (Rev-0)
14 Preserve Grey Water Collection and Holding Tanks – 100% 49
15 Renew Floating Deck System in Galley and Mess Deck 51
16 Preserve Forward Void 56
17 Renew Main Diesel Engine (s) 58
18 Clean and Inspect Heat Exchangers 63
19 Inspect MDE Exhaust System 67
20 Overhaul Stabilizing Fins 71
21 Overhaul and Renew Sea Valves 76
22 Overhaul and Renew Firemain Valves 79
23 Remove, Inspect, and Reinstall Propellers 82
24 Remove, Inspect, and Reinstall Propeller Shafts 85
25 Overhaul Mechanical Shaft Seal Assemblies 92
26 Renew Water-Lubricated Propeller Shaft Bearings 94
27 Inspect and Maintain Cathodic Protection System 97
28 Remove, Inspect and Reinstall Rudder Assemblies 100
29 Overhaul Steering Gear Components 105
30 Renew Depth Indicating Transducer 110
31 Renew Speed Doppler 113
32 Preserve Underwater Body - "100%" 116
33 Renew Capastic Fairing 119
34 Preserve Stern Tubes 121
35 Preserve Bilge Surfaces In Various Locations 123
36 Prepare Weather Deck Surfaces 126
37 Renew Vaneaxial Fan and Motor Assemblies 129
38 Clean Engine Room Surfaces In Various Locations 132
Page iii (Rev-0)
39 Renew Pilothouse Window 134
40 Repair Damage Control Locker Deck 137
41 Install Gooseneck Vent 139
42 Perform Ultrasonic Thickness Measurements 141
43 Perform Air Test of Interior Compartments 143
44 Perform Aluminum Hull and Structural Repairs - 1/4" Plate 145
45 Perform Aluminum Hull and Structural Repairs - 5/16" Plate 146
46 Perform Hull and Structural Plating Repairs -Crack (Aluminum) 147
47 Perform Hull and Structural Plating Repairs - Eroded Weld (Aluminum) 148
48 Perform Hull and Structural Plating Repairs - Overlay Welding (Aluminum) 149
49 Perform Hull and Structural Plating Repairs - Crack (Steel) 150
50 Perform Hull and Structural Plating Repairs - Eroded Welds (Steel) 151
51 Perform Hull and Structural Plating Repairs - Overlay Welding (Steel) 152
52 Perform Hull and Structural Plating Repairs - Corrugated Plate (4.0-Pound) 153
53 Perform Steel Hull and Structural Plating Repairs (5-Pound) 154
54 Perform Steel Hull and Structural Plating Repairs (6.0-Pound or 5.63-Pound) 156
55 Perform Steel Hull and Structural Plating Repairs (7.5-Pound or 7.65-Pound) 158
56 Perform Steel Structural Member Repairs -Steel Studs 160
Page iv (Rev-0)
List of Sketches
Work Item Sketch Number Page
This section is not applicable to this package.
Page v (Rev-0)
Revisions Record
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package.
Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK ITEM# CHANGES MADE
NOTE: All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
Page vi (Rev-0)
List of Applicable References
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution. Electronic copies of the latest Editions of MLCA Standard Specifications are available on the Internet and may be accessed at the following Internet Uniform Resource Locator (URL) address:
http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp.
Guidance for obtaining copies of all other documents referenced herein is provided in the solicitation.
Order of precedence. In the event of conflicts between text of this specification and the applicable references specified herein, order of precedence shall be in accordance with MLCA Standard Specification 0000_STD, paragraph 3.2 (Order of precedence), unless otherwise specified by the Contracting Officer (KO). The Contractor shall immediately notify the KO in writing of any perceived conflicts contained herein. Nothing in these documents, however, supersedes applicable laws and regulations, unless a specific exemption has been obtained.
FEDERAL AND MILITARY SPECIFICATIONS AND STANDARDS
Federal Specification (Fed Spec), MMM-A-121, Oct 1999, Adhesive Bonding Vulcanized Synthetic Rubber to Steel
MIL-A-24456, Jun 1979, Adhesive for Plastic-Vibration Damping Tile
MIL-PRF-17672, May 1995, Hydraulic Fluid, Petroleum, Inhibited
MIL-STD-2148, Oct 1989, Vibration Damping Materials
DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems
Commercial Item Description (CID) A-A-59588, Jul 2005, Rubber Silicone
OTHER GOVERNMENT DOCUMENTS, DRAWINGS, AND PUBLICATIONS
DOCUMENTS
Page vii (Rev-0)
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2006 Edition, General Requirements
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 1001_STD, 2004 Edition, Temporary Hull Accesses
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 3141_STD, 2004 Edition, Overhaul Electrical Rotating Machines
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 6341_STD, 2004 Edition, Renew Deck Covering Systems
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 8634_STD, 2004 Edition, Drydocking
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 8635_STD, 2004 Edition, Provide Temporary Logistics
DRAWINGS
Coast Guard Drawing 110 WPB 085-002, Rev-, Docking Plan
Coast Guard Drawing 110 WPB 085-010, Rev B, Docking Plan, Docking/Lifting Cradle
Coast Guard Drawing 110 WPB 131-001, Rev A, Deck Construction Plan
Coast Guard Drawing 110 WPB 151-004, Rev -, Superstructure Details
Coast Guard Drawing 110 WPB 161-001, Rev A, Main Shaft Strut Details
Coast Guard Drawing 110 WPB 161-002, Rev-, Main Shaft Strut Installation
Coast Guard Drawing 110 WPB 161-003, Rev A, Intermediate Shaft Strut Details
Page viii (Rev-0)
Coast Guard Drawing 110 WPB 161-004, Rev-, Intermediate Shaft Strut Installation
Coast Guard Drawing 110 WPB 201-002, Rev A, Propulsion Configuration
Coast Guard Drawing 110 WPB 201-003, Rev-, Machinery Arrangement Plan
Coast Guard Drawing 110 WPB 233-001, Rev -, Main Engine Bolting & Pads
Coast Guard Drawing 110 WPB 233-002, Rev -, Remote Emergency Main Engine Shutdown
Coast Guard Drawing 110 WPB 243-002, Rev B, Propulsion Shafting Details
Coast Guard Drawing 110 WPB 243-005, Rev-, Shaft Locking Device
Coast Guard Drawing 110 WPB 243-006, Rev C, Propulsion Shaft Details (Partially supercedes 110 WPB 243-002, 110B WPB 243-002, and 110C WPB 243-002)
Coast Guard Drawing 110 WPB 245-004, Rev A, Propeller Details
Coast Guard Drawing 110 WPB 245-005, Rev-, Assembly of Oil Injection Equipment
Coast Guard Drawing 110 WPB 256-001, Rev A, Main Engine SW Cooling System A&D
Coast Guard Drawing 110 WPB 256-002, Rev-, Aux SW Cooling System A&D
Coast Guard Drawing 110 WPB 256-003, Rev-, Mods to SW Cooling Incidental to Install of Charge Air Cooler Diverter Valve
Coast Guard Drawing 110 WPB 256-004, Rev B, SSDG Seawater Cooling
Coast Guard Drawing 110 WPB 259-001, Rev A, Main Engine Exhaust Piping System
Coast Guard Drawing 110 WPB 259-005, Rev C, 18" Raw Water Discharge Spray Ring Assembly w/ Companion Flanges & Gaskets
Coast Guard Drawing 110 WPB 259-006, Rev D, MDE 8" Exhaust Flapper Valve Assembly (w/Companion Flanges & Gaskets)
Page ix (Rev-0)
Coast Guard Drawing 110 WPB 501-001, Rev D, Piping System Schematics
Coast Guard Drawing 110 WPB 512-001, Rev D, Habitability Vent Modifications
Coast Guard Drawing 110 WPB 528-001, Rev B, Sewage Piping Arrangement
Coast Guard Drawing 110 WPB 561-001, Rev-, Steering System Details
Coast Guard Drawing 110 WPB 561-004, Rev-, Steering System Details / Piping
Coast Guard Drawing 110 WPB 621-001, Rev-, Joiner Work Details
Coast Guard Drawing 110 WPB 633-001, Rev A, Cathodic Protection Plan and Details
Coast Guard Drawing 110 WPB 633-002, Rev-, Cathodic Protection Installation, Schematic, & Layout
Coast Guard Drawing 110 WPB 635-001, Rev-, Linings and Insulation Plan and Details
Coast Guard Drawing 110 WPB 636-001, Rev A, Noise Damping Details
Coast Guard Drawing 110B WPB 111-003, Rev G, Shell Expansion
Coast Guard Drawing 110B WPB 117-001, Rev H, Transverse Sections
Coast Guard Drawing 110C WPB 131-001, Rev A, Deck Construction Plan
Coast Guard Drawing 110C WPB 161-005, Rev E, Stern Tube Installation Details
Coast Guard Drawing 110C WPB 562-001, Rev G, Rudder Details (superceded 110 WPB 562-001)
Coast Guard Drawing 110C WPB 565-001, Rev D, Fin Stabilization System
Coast Guard Drawing 110C WPB 601-027, Rev D, Outboard Profile And Weather Decks
Page x (Rev-0)
Coast Guard Drawing FL 6713-201, Rev B, CRP-V850 Transducer (B-
14) Adapter Assembly
PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Jun 2006, Coatings and Color Manual
Coast Guard Technical Publication (TP) 2931, Oct 2002, Stabilizer Manual
Coast Guard Technical Publication (TP) 2932, SWBS 245-2, Aug 1987, Propeller Renewal Procedure
Coast Guard Technical Publication (TP) 2938, Jul 1991, SWBS 633- 1, Engelhard Industries Cathodic Protection Instruction Manual For USCG Fast Patrol Boat
Coast Guard Technical Publication (TP) 3094, Jan 2002, Manufacturer’s O&M Instruction Book, Paxman Diesels Limited
Coast Guard Technical Publication (TP) 3095, July 2005, Manufacturer’s O&M Instruction Book, Paxman Diesels Limited
Coast Guard Technical Publication (TP) 3495, May 2002, Chapter 243, Installation Duramax Shaft Seal System
Coast Guard Technical Publication (TP) 3906, Oct 2002, Ship's Steering Gear System
Coast Guard Technical Publication (TP) 3907, Oct 2002, Ship's Fin Stabilizing System
Coast Guard Technical Publication TP 3109 (625 B) WINDOWS, FIXED
Vosper Thornycroft Technical Bulletin No. 49, Jul 1992, Procedure for Fitting New Tiller Rod Eye Bearings to Actuators and Removing Redundant Grease Hose On BMS Island Class USCG Cutters
Raytheon V850 Color Echosounder, 2nd Edition, Mar 1993, Operation Manual
INDUSTRY STANDARDS
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2002, Disinfection of Water- Storage Facilities
Page xi (Rev-0)
American National Standards Institute/NSF International (ANSI/NSF) 61, 2005, Drinking Water System Components - Health Effects
American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End
American Society of Mechanical Engineers (ASME) B46.1, 2002, Surface Texture (Surface Roughness, Waviness, and Lay)
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2003 Edition, Bronze Gate, Globe, Angle and Check Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) A 25463, 1999, Adhesive, Film Form, Metallic Structural Sandwich Construction
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) 4348, Core, 1995, Honeycomb, Aluminum Alloy, Corrosion Inhibited for Sandwich Construction 5052, 350 (177)
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2004, Near-White Blast Cleaning
International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller
International Standard Organization (ISO) 4406, 1999, Hydraulic Fluid Power - Fluids - Method for Coding Level of Contamination by Solid Particles
Page xii (Rev-0)
ASTM International (ASTM) A572, 2007, Standard Specification for High-Strength Low-Alloy Columbium-Vanadium Structural Steel
ASTM International (ASTM) A606, 2004, Standard Specification for Steel, Sheet and Strip, High-Strength, Low-Alloy
ASTM International (ASTM) B209, 2007, Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D3951, Reapproved 2004, Standard Practice for Commercial Packaging
ASTM International (ASTM) D4174, Reapproved 2005; Standard Practice for Cleaning, Flushing, and Purification of Petroleum Fluid Hydraulic Systems
ASTM International (ASTM) D5363, 2003, Standard Specification for Anaerobic Single Component Adhesives
ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method
ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates
American Petroleum Institute (API) Specification 5L, 2004, Specification for Line Pipe
American Water Works Association (AWWA) C652, 2002, Disinfection of Water-Storage Facilities
Page xiii (Rev-0)
List of Government-furnished Property
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM MTI ITEM DESCRIPTION NSN/PN QTY
ESTIMATED
COST
($/UNIT)
1 N *Transducer cover plate N/A 1 ea. 1,500.00 17 Y Paxman Valenta Diesel Engine –
Model 16RP200M 1 ea. 368,000.00
Y Engine Mounts P/N: 5540 2 ea. 1,791.96 Y Engine Mounts P/N: 6040 2 ea. 1,791.96 N Install Kit VIKINSTALL 1 ea. 3,700.00 Y Lift Bracket & Engine Stands 1 ea. 20,000.00 19 N Port spray ring NSN: 2990-01-475-9621 1 ea. 1,584.00 N Starboard spray ring NSN: 2990-01-475-9620 1 ea. 1,584.00 N Port 8" flapper valve NSN: 4810-01-475-8648 1 ea. 2,072.00 N Starboard 8" flapper valve NSN: 4810-01-475-8415 1 ea. 2,072.00 N 18” MDE gasket kit NSN: 5330-01-475-8157 4 ea. 389.45
N 18” MDE gasket kit NSN: 5330-01-475-8169 4 ea. 312.52
N 8” exhaust gasket kit
NSN: 5330-01-475-8804
4 ea. 128.24
20 N Spherical Roller Bearing NSN: 3110-00-902-7288 2 ea. 136.00 N Spherical Bearing NSN: 3120-99-806-7289 4 ea. 167.00 N Special Bolt Trunion P/N: 3665208-A
4 ea. 135.00
N Special Bolt Tiller NSN: 5306-99-538-1451 4 ea. 126.00 N Rod Eye Trunion Bolt Nut NSN: 5315-01-485-3148 4 ea. 34.00 N Fin Spacer Bushing NSN: 3120-01-396-1724 4 ea. 81.00 N Fin Spacer Bushing NSN: 5365-99-807-4040 4 ea. 66.00 N Circlip NSN: 5365-99-902-2593 8 ea. 2.00 N Actuator Seals NSN: 5330-99-729-7570 4 sets 98.00 N Rod Eye Bearing NSN: 3120-01-377-1940 4 ea. 530.00 N Rod Eye Locknut NSN: 5310-01-468-7665 4 ea. 13.00 N Tiller Pin Nuts NSN: 5315-01-485-3148 4 ea. 34.00 Y Fin Stabilizer assembly NSN: 2040-99-726-4768 2 ea. 12,200.00 N Lower bearing bushing NSN: 3120-99-726-2345 2 ea. 900.00 23 Y Propeller, LH NSN: 2010-01-222-2440 1 ea. 23,445.00 Y Propeller, RH NSN: 2010-01-222-2441 1 ea. 22,800.00 24 N 4" Diameter x 28' Long, Aquamet-17 propulsion shaft NSN: 2010-01-445-7940 2 ea. 8,700.00
N Forward Bearing Housing NSN: 3130-01-442-2863 2 ea. 5,421.00 N *Oil Injection Equipment Kit N/A 1 set 6,000.00 25 N Shaft seal assembly kit NSN: 5330-01-497-8095 2 ea. 859.48 N **Shaft seal assembly NSN: 4320-01-497-8057 2 ea. 3,111.84
Page xiv (Rev-0)
N
Main Shaft Strut Bearing, Bronze and rubber cutlass bearing, 4" ID x 5" OD x 16" Long
NSN: 3120-01-222-3927 2 ea. 200.00
N
Intermediate Shaft Strut Bearing, Bronze and rubber cutlass bearing, 4" ID x 5" OD x 16" Long
NSN: 3120-01-222-3927 2 ea. 200.00
N
Stern Tube Bearing, Bronze and Rubber cutlass bearing, 4" ID x 5" OD x 8" Long
NSN: 3120-01-238-0689 2 ea. 150.00
27 N Shaft Ground Assembly NSN: 5977-01-204-9914 2 ea. 912.00 N Reference Cell NSN: 5977-01-203-7800 2 ea. 7,300 28 Y Rudder NSN: 2040-01-223-2674 2 ea. 25,000.00 29 N Hydraulic Pump Assy. NSN: 4320-99-771-4207 2 ea. 550.00 30 N ***V850 Color Echo Sounder NSN: 5845-01-518-7245 1 ea. 1,423.41 31 N ***CELZ-SRD-331 Doppler speed log NSN: 5845-01-302-4161 1 ea. 3,255.08
36 N Non-Skid Pads 1’x 10”x 3’ P 170 ft ea. 4,018.80 N Non-Skid Pads 1’x 10”x 3’ S 170 ft ea. 4,018.80 37 N Vaneaxial fan NSN: 4140-01-394-8607 2 4,894.00 N Louvers NSN: 2040-01-486-7595 2 2,246.00 39 N Counterbalance aluminum window
CC-1038
K-322-C Item-D 2 ea. 2,359.00
N Fixed Windows K-325-FN Item-E 4 ea. 448.00 N Fixed Windows KN-325-FN Item-C 7 ea. 2,279.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel, Electronic Systems Support Unit (ESU) or local Electronic Support Detachment (ESD).
Page xv (Rev-0)
List of Critical Inspection Items
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see Std Spec 0000_STD, paragraph 3.6.2 (Inspection report particulars)):
Work Item Title
15 Renew Floating Deck System in Galley and Mess Deck
20 Overhaul Stabilizing Fins
28 Remove, Inspect and Reinstall Rudder Assemblies
39 Renew Pilothouse Window
42 Perform Ultrasonic Thickness Measurements
43 Perform Air Test of Interior Compartments
Page xvi (Rev-0)
Specification Feedback
The intent of this section is to inform all users that a spec feedback mechanism is in place, and is located on the MLCA Naval Engineering Division’s website. Spec feedback is a very important part of our overall continuous improvement process, and is crucial to specification development. It will allow spec writers to capture all specification-related lessons learned, and avoid mistakes or ambiguities in follow-on availabilities.
All feedback will be reviewed, evaluated, and responded to in a timely manner.
If you have access to the CGWeb (Intranet), please use the following link, which will connect you to the MLCA(v) Naval Engineering website, for submitting your feedbacks:
http://webapps.mlca.uscg.mil/vdiv/specifications/feedback/defaul t.cfm
If you do not have access to the CGWeb (Intranet), you may still submit your feedbacks, using the following web link:
http://www.uscg.mil/mlclant/vdiv/specfeedback.asp
Page xvii (Rev-0)
PC_110A_WPB
(22 Jan 2007)
Principal Characteristics
110’(A CLASS) PATROL BOAT
Length Overall 113’0”
Depth (main deck at side to baseline) 10’ 0-1/2”
Maximum Beam 21’ 3”
Height of Highest Projection (above baseline) 54' 11 3/16"
Frame Spacing various
Full Load Draft 6’ 5-3/4”
Full Load Displacement 165.1 long tons
Shore Tie Voltage Requirements 450VAC 400A 3PH 60HZ ungrounded
PROPELLER / SHAFT
Number of Propellers 2
Number of Blades per Propeller 5
Diameter of Propeller 49.6”
Pitch 61.4”
Revolutions per Minute (RPM) N/A
Shaft Diameter 4”
Page 1 (Rev-0)
00000_DLA_FLT (23 Oct 2008)
General Requirements
1. SCOPE
1.1 Intent. This item describes the general requirements to be followed by the Contractor while conducting this availability.
1.2 Government-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2006 Edition, General Requirements
Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Jun 2006, Coatings and Color Manual
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in Std Spec 0000_STD and in this item, as applicable, during the performance of this availability.
NOTICE!
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Contractor-provided fire watch personnel. The Contractor
shall provide fire watch personnel and equipment.
3.3 Welding and brazing requirements. The Contractor shall
perform all welding and allied processes, and nondestructive inspection (NDI), in accordance with Std Spec 0740_STD.
Page 2 (Rev-0)
3.4 Term substitution - COTR for COR. The Contractor shall be aware that the term "COR" (Contracting Officer's Representative) has been discontinued in favor of "COTR" (Contracting Officer's Technical Representative); consequently, whenever "COR" is encountered in this specification package, including referenced standard specifications and other referenced documents, it shall refer to "COTR", explicitly.
3.5 Small boat storage. When a small boat Rigid Hull
Inflatable (RHI) boat) is removed as interference to Contractor-work, the Contractor shall provide a suitable pier side storage cradle, for safely storing said boat.
3.5.1 Cradle design. Ensure that the temporary cradle meets
the following criteria:
1. Structure is templated from the geometry and arrangement of the contact support areas of the existing cradle onboard the vessel, to provide same or more support area as that which is provided by the existing cradle.
2. Arrangement will allow ship's force to perform maintenance on the small boat, without modification of the cradle.
3. Structure is manufactured using the most economical methods and materials available, and is capable of supporting the full weight of the small boat under normal conditions experienced during routine maintenance.
4. Contact surfaces are no harder or rougher than the contact surfaces for existing cradle onboard the vessel.
3.5.2 Boat accessibility. Ensure the storage is located in the vicinity of the vessel, and is unrestricted, to allow for ship's force to complete maintenance during normal working hours for the entire performance period.
3.5.3 Boat protection. Provide full protection that can be
safely and completely secured when the small boat is left unattended (e.g. watertight cover, storage in a warehouse or shop, etc.), in addition to isolating the boat from the elements.
3.5.4 Boat transportation. Transport each small boat to its
storage area within one week of docking the vessel and back to the vessel prior to the end of the performance period.
Page 3 (Rev-0)
4. NOTES
4.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may
be accessed at the following URL address:
http://www.uscg.mil/directives/cim.asp
4.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in Std Spec 0000_STD to be completed and submitted during preservation of "critical-coated surfaces", are provided at the end of this item.
Page 4 (Rev-0)
QA-1: QUALITY ASSURANCE INSPECTION FORM - PRESERVATION CHECKLIST
CHECKPOINT 1 - COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with COMDTINST M10360.3, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating manufacturer(s).
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-based coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating manufacturer(s).
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down
(maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-12, SP-11, SP-10?).
Verify surface anchor profile (1.5-3.5 mils for abrasive-blasted steel surfaces; 1.0 mil (minimum) for power-tool cleaned surfaces; 1.0-1.5 mils for abrasive-blasted aluminum surfaces); and 1.5 -2.5 for surfaces to be coated w/single coat of inorganic zinc).
Measure soluble salt conductivity (5 measurements per 1000 sqft) - maximum threshold: 70 microsiemens/cm for non-submerged surfaces and 30 microsiemens/cm for submerged surfaces.
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the Coating Manufacturer(s).
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 - STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer's instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 - TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer's instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 - FINAL INSPECTION
Verify final system dry film thickness.
Verify system cure for service resumption - U/W Body surfaces: 5-8 hours @ 77 degrees F; Potable water tanks: 7 days @
77 degrees F.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure (minimum 7 days @ 77 degrees F.), to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
CHECKPOINT 10 - RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
Signature of Inspector:______________________________________________________Date:____________
Page 5 (Rev-0)
QA-2. QUALITY ASSURANCE INSPECTION FORM
ENVIRONMENTAL READINGS
(Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat)
DATE TIME
ENTER ACTIVITY
(Surface preparation, primer coat, barrier coat, top coat, etc?)
LOCATION DEW
POINT
SURFACE
TEMP.
% REL.
HUMIDITY
SIGNATURE
OF
INSPECTOR
.Signature of Inspector:__________________________________________________Date:____________
Page 6 (Rev-0)
QA-3 QUALITY ASSURANCE INSPECTION FORM
SURFACE PROFILE LOG
Vessel Name And Hull Number:__________________________________________________
Work Item Title:_______________________________________________________________
Location Of Work (Including Frame Numbers):_____________________________________
Area (Square Feet):_____________
Surface Preparation Method:_____________________________________________________
Abrasive Manufacturer And Size:_________________________________________________
Degreasing Method Used:________________________________________________________
Number Of Hours Surfaces (Steel Only) Left Unpainted:______________________________
Sweep blasting performed to remove flash rusting (steel)? Yes/No:_____________________
Place Surface Profile Replica Tapes In The Spaces Provided Below, To Serve As Permanent QA record.
Maintain separate log for each area/location. When an Area Is Divided Into Separate Sections, Maintain A Separate Log for Each Section.
AVERAGE MILS
(IAW ASTM D4417,
METHOD C)
Place Surface Profile Replica Tape Here
Reading:__________ mils
• Place Surface Profile Replica Tape Here
Date and Time:__________________________________________________
Location of Surface Profile Measurements:___________________________________________________________
Signature of Inspector:____________________________________________________________________________
Page 7 (Rev-0)
QA-4. QUALITY ASSURANCE INSPECTION FORM
SURFACE SOLUBLE SALT CONDUCTIVITY LOG
Vessel Name and Hull Number:__________________________________________________
Work Item Title:_______________________________________________________________
Location of Work (including frame numbers):_______________________________________
Area (square feet):____________
DATE TEST LOCATIONS CONDUCTIVITY
(microsiemens/cm)
Date and Time:_________________________________________
Signature of Inspector:___________________________________
Page 8 (Rev-0)
QA-5. QUALITY ASSURANCE DATA FORM
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC PA-2
(Use one sheet for each sequence)
Vessel Name and Hull Number:__________________________________________________
Work Item Title:______________________________________________________________
Coating Manufacturer:_________________________________________________________
Product Name:________________________________________________________________
Batch Number:________________________________________________________________
Induction Time:_______________________________________________________________
Coating System Sequence (Indicate whether: primer, touch-up primer, barrier coat, 3rd coat?):__________________
DFT
MEASUREMENT
NUMBER
LOCATION OF READINGS MEASURED DFT
Application Method (Airless, Conventional Spray, Rolled):____________________
Average DFT: __________________________________________________________
Date and Time: _________________________________________________________
Signature of Inspector: ___________________________________
Page 9 (Rev-0)
86340_ADB_FLT (18 Sept 2008) 110A (23 Sept 2008)
WORK ITEM 1: Routine Drydocking
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to drydock and undock the cutter, and perform various drydocking-related inspections and tests.
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY
ESTIMATED
COST
($/UNIT)
N *Transducer cover plate N/A 1 ea. 1,500.00
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 8634_STD, 2004 Edition, Drydocking
Coast Guard Drawing 110 WPB 085-002, Rev-, Docking Plan
Coast Guard Drawing 110 WPB 085-010, Rev B, Docking Plan, Docking/Lifting Cradle
3. REQUIREMENTS
3.1 General. The Contractor shall drydock and undock the
cutter, in accordance with Std Spec 8634_STD, Appendix D (Requirements for 110 WPB Lifting/Cradle/Blocking), using a cradle built in accordance with Coast Guard Drawings 110 WPB 085-010 and 110 WPB 085-002.
Page 10 (Rev-0)
3.2 Cutter Conditions. The Contractor shall use the below-
listed information for purposes of performing calculations, as described in paragraph 20.2 of Appendix B of Std Spec 8634_STD.
(See Note 4.4 (Cutter characteristics)). The Contractor shall be responsible for any change to the cutter's loading condition necessary, for drydocking, to meet the capability of the Contractor's dock.
• Displacement (LT): 124.2..
• VCG (FT ABL): 9.73.
• LCG (FT aft/fwd amidships): 6.99 aft
• Length of supported keel (FT): NA
3.3 Blocking position. The Contractor shall arrange keel and
side blocks, as shown on the vessel's docking plan, to facilitate docking of the vessel in blocking position No. 1.
Ensure that the minimum keel block height is 18 inches above the docking facility deck.
3.4 Routine work.
3.4.1 The Contractor shall perform the below-designated routine drydocking work, in accordance with Std Spec 8634_STD, Appendix A (Requirements for Routine Drydocking Work). (See Note 4.3 (Paragraph number relationships)). Follow the timeline for work completion and inspection report submission, as specified in Std Spec, 8634_STD, Appendix A, paragraph 20.2 (Inspections and repair work).
SUBSECTION TITLE
20.1 Underwater hull survey.
20.4 Stern tube and strut bearing
inspection.
20.7 Void inspection.
20.8 Zinc anode inspection.
3.4.2 The Contractor shall be aware that the Coast Guard
Underwater Hull Inspection Board (UWHIB) will recommend the extent of underwater body coating system preservation required, based on the conditions found during the underwater hull survey.
3.5 Hull cleaning - removal of marine growth. The Contractor
shall start cleaning the hull within four hours after the vessel has been lifted, to facilitate marine growth removal. Complete all cleaning operations within 24 hours after the vessel has been lifted.
Page 11 (Rev-0)
3.6 Immediate work. The Contractor shall perform the following work, within 24 hours after the lifting of the vessel.
3.6.1 Temporary protective coverings. As soon as practicable
after drydocking and underwater body surface cleaning, install protective coverings, over zinc anodes, hull fairing materials, rudder bearings, stern tube and strut bearings, fin stabilizer seals, all exterior deck drains and all overboard discharges.
Wrap all bearings and seals immediately after the vessel is drydocked to prevent entry of debris, abrasives, and paint during cleaning, surface preparation, and painting. Insert soft caulking material into the open ends of rudder and shaft stave bearings to prevent entry of grit or other foreign material.
NOTICE!
Do not remove protective covers except for inspection or accomplishing specific work items.
3.6.2 Overboard discharge channeling and plugging. Place drain channels in overboard discharges in use to direct discharges away from the hull. Provide and install wooden plugs or coverings in sea chest spool pieces and overboard discharges not in use to prevent entry of sandblast grit or paint.
3.7 Allowable block timber stresses. The Contractor shall use information contained in the below table, in place of that which is provided in paragraph 20.5.1 (Allowable block timber stresses) of Appendix B, in Std Spec 86340_STD.
WOOD PROPERTIES
Block Material
Permissible Compressive Stress Perpendicular to the grain (psi)
Permissible Compressive Stress Parallel to the grain (psi)
Proportional limit Perpendicular to the grain (psi)
SOFTWOOD
Douglas Fir 400 1400 800 Yellow Pine 300 900 700
HARDWOOD
Red & White Oak 600 1300 1300
3.8 Fluid offload and disposal. The Contractor shall empty all tanks in order to fulfill the drydock requirements shown on Coast Guard Drawing 110 WPB 085-002. Dispose of all fluids in accordance with Federal, State, and local regulations.
3.8.1 Fuel. Remove and dispose of up to 5000 gallons of fuel
from the vessel.
Page 12 (Rev-0)
3.8.2 Dirty oil and oily water. Remove and dispose of up to
155 gallons of dirty oil and up to 155 gallons of oily water from the vessel.
3.8.3 Sewage and grey water. Remove and dispose of up to 500
gallons of sewage and up to 250 gallons of grey water from the vessel..
NOTICE!
The Contractor shall be aware of the requirement in the referenced Docking Plan, which states that CUTTER SHALL BE DOCKED WITH ALL TANKS EMPTY. Normal operational practice of cutters is to operate at a minimum 75% fuel capacity during hurricane season and 50% off season.
4. NOTES
4.1 Drydock terms. As used in these specifications, all
references to drydock facilities include graving drydocks, floating drydocks, marine railways, building ways or vertical lifts.
4.2 Arrival conditions. The Engineering Petty Officer (EPO)
will advise the Contractor of the actual tank and draft readings when the vessel arrives, and will discuss with the Contractor any ballast requirements necessary to accommodate the vessel draft and trim.
4.3 Paragraph number relationships. The paragraph number for
each subsection listed herein relates directly to identical sub-paragraph numbers in Std Spec 8634_STD.
4.4 Cutter Characteristics. The data shown does not represent the arrival displacement or docking displacement of the cutter.
4.5 Cradles. Many of the cradles used to dock the 110's were
built to the early drawing 085-002. The newer cradles have been built to 085-010. The drawings show minor variations in dimensions. It should be noted that while the Standard Spec calls for the cradle to be built just to 085-010, a cradle built to 085-002 is acceptable.
4.6 Tank information. The following are the tanks that require fluid offload along with all relevant information:
TYPE OF TANK LOCATION CAPACITY
(GALLONS)
Page 13 (Rev-0)
Fuel 3-11-1-F 1,023 Fuel 3-11-2-F 1,023 Fuel 3-17-1-F 2,560 Fuel 3-17-2-F 2,560 Fuel 3-18-0-F 1,438 Fuel 3-28-1-F 1,162 Fuel 3-28-2-F 1,162 Dirty oil 3-26.5-1-F 155 Oily Water 3-26.5-2-F 155 Sewage 3-17-0-W 496 Forward Grey Water 3-21.5-0-W 225
Aft Grey Water 3-27.5-0-W 144
Potable Water 3-14-1-W 850
Potable Water 3-14-2-W 850
Page 14 (Rev-0)
86350_LNM_FLT (19 Sep 2008)
WORK ITEM 2: Provide Temporary Logistics
Contractor to provide temporary logistics.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 8635_STD, 2004 Edition, Provide Temporary Logistics
3. REQUIREMENTS
3.1 General. The Contractor shall provide the below listed
temporary logistics, in accordance with Std Spec 8635_STD (see 4.1):
PARAGRAPH TITLE
3.2.1 Office space. (With refrigerator)
3.2.2 Telephone. (To include DSL or greater with long
distance line(s).
3.2.3 Parking.
3.2.4 Duty section berthing: 1 male, 1 female. Duty
section berthing shall be provided for the entire duration of the availability.
3.2.5 Light and power.
3.2.6 Compressed air.
3.2.7 Hazardous Waste Disposal.
LIQUIDS (GALLONS) SOLIDS
Empty Containers* Used Lube Oil
Paint Thinners Engine
Coolant Bilge Water
Oily Filters
Oily Rags (lbs)
1-gal 5-gal 55-gal
75 25 00 25 20 50 20 05 00 *Empty containers that previously housed hazardous materials.
Page 15 (Rev-0)
3.2.8 Heavy Lift Equipment: 2 day(s).
3.2.9 Hot-circulating water.
3.2.10 Potable water: 15 gallons per day, bulk.
3.2.11 Refuse disposal.
3.2.12 Sewage and Grey Water Disposal.
A-Team Action Item: Verify specific storage needs (e.g. Liferafts stored in Dry Stores, etc.).
3.2.14 Storage:
• Dry stores.
• Paint and flammable stores.
3.2 Additional temporary logistics. If the performance period of the contract is extended by the Contracting Officer, the contractor shall continue to provide all temporary logistics as specified herein for the extension period.
4. NOTES
4.1 Paragraph number relationships. The paragraph number for
each paragraph listed in 3.1 (General) relates directly to the identical sub-paragraph number in Std Spec 8635_STD.
Page 16 (Rev-0)
12312_DLA_FLT (10 Sept 2008) 110A WPB (27 Oct 2008)
WORK ITEM 3: Clean and Inspect Fuel Service Tanks
Contractor to clean and inspect the following tank(s):
(gallons) Fuel 3-17-1-F 2,560 Fuel 3-17-2-F 2,560
1.2 Government-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Operational test – initial. Prior to commencement of
work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs to demonstrate existing operational condition. Submit a CFR.
3.1.2 Related work items. The Contractor shall accomplish this work item in conjunction with the following, which is a separate work item in this specification package:
• "Routine Drydocking".
Page 17 (Rev-0)
3.2 Cleaning requirements. The Contractor shall remove tank
cover(s) and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.
3.3 Tank content and waste disposal. The Contractor shall
dispose of tank sludge and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COTR upon completion of work.
3.4 Inspection. The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
• Tank structural condition.
• Inaccessible areas.
• Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
• Tank level indicator (TLI) and/or float switch condition.
• Sounding tube and striker plate condition.
• Suction and discharge piping condition.
• Fastener material and condition (correct fastener material is stainless steel).
3.5 Tank closing. The Contractor shall ensure that the tank(s) remain open for approximately 24 hours after completion of all authorized repair and preservation procedures. Notify the COTR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183.
Page 18 (Rev-0)
3.6 Operational test – final. After all authorized work is
complete, in the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLIs to be in satisfactory operating condition (see 4.1 (Equipment operation)). Submit a CFR.
4. NOTES
4.1 Equipment operation. Coast Guard personnel will operate
all shipboard machinery and equipment during all operational tests.
Page 19 (Rev-0)
12311_DLA_FLT (10 Sept 2008)
WORK ITEM 4: Clean and Inspect Fuel Stowage and Overflow Tanks
Fuel 3-11-1-F 1,023 Fuel 3-11-2-F 1,023 Fuel 3-18-0-F 1,438 Fuel* 3-28-1-F 1,162 Fuel* 3-28-2-F 1,162
*Due to the complex geometrical shape and hard accessibility, it is very difficult to perform thorough visual inspection of these tanks.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Operational test - initial. Prior to commencement of
work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs to demonstrate existing operational condition. Submit a CFR.
Page 20 (Rev-0)
3.1.2 Related work items. The Contractor shall accomplish this work item in conjunction with the following, which is a separate work item in this specification package:
• "Routine Drydocking".
3.2 Cleaning requirements. The Contractor shall remove tank
cover(s) and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.
3.3 Tank content and waste disposal. The Contractor shall
dispose of tank sludge and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COTR upon completion of work.
3.4 Inspection. The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
• Tank structural condition.
• Inaccessible areas.
• Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
• Tank level indicator (TLI) and/or float switch condition.
• Sounding tube and striker plate condition.
• Suction and discharge piping condition.
• Fastener material and condition (correct fastener material is stainless steel).
3.5 Tank closing. The Contractor shall ensure that the tank(s) remain open for approximately 24 hours after completion of all authorized repair and preservation procedures. Notify the COTR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183.
Page 21 (Rev-0)
3.6 Operational test - final. After all authorized work is
completed, in the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLIs to be in satisfactory operating condition (see 4.1 (Equipment operation)). Submit a CFR.
4. NOTES
4.1 Equipment operation. Coast Guard personnel will operate
Page 22 (Rev-0)
12310_DLA_FLT (10 Sept 2008)
WORK ITEM 5: Clean and Inspect Oil and Oily Waste Tanks
Dirty oil** 3-27-1-F 155 Oily Water** 3-27-2-F 155
**These tanks are preserved.
1.2 Government-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Related work items. The Contractor shall accomplish this work item in conjunction with the following, which is a separate work item in this specification package:
• "Routine Drydocking".
3.2 Cleaning requirements. The Contractor shall remove tank
cover(s) and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage
Page 23 (Rev-0) the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths.
3.3 Tank content and waste disposal. The Contractor shall
dispose of tank sludge and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COTR upon completion of work.
3.4 Inspection. The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
• Tank structural condition.
• Inaccessible areas.
• Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
• Sounding tube and striker plate condition.
• Suction and discharge piping condition.
• Fastener material and condition (correct fastener material is stainless steel).
3.5 Tank closing. The Contractor shall ensure that the tank(s) remain open for approximately 24 hours after completion of all authorized repair and preservation procedures. Notify the COTR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183.
4. NOTES
4.1 Equipment operation. Coast Guard personnel will operate
Page 24 (Rev-0)
12319_DLA_FLT (10 Sept 2008)
110 AWPB (23 Apr 2008)
WORK ITEM 6: Clean and Inspect Sewage Collection and Holding Tanks
Contractor to clean and inspect the below designated tank(s):
TYPE OF TANK LOCATION CAPACITY
Sewage 3-17-0-W 496
2. APPLICABLE DOCUMENTS
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 Related work items. The Contractor shall accomplish this work item in conjunction with the following, which is a separate work item in this specification package:
• "Routine Drydocking".
• "Clean and Inspect Grey Water Collection and Holding Tanks".
3.2 Cleaning requirements. The Contractor shall do the
following for the designated tank(s) listed in paragraph 1.1:
3.2.1 Operational test - initial. Prior to commencement of
work, the Contractor shall witness an operational pre-test (by
Page 25 (Rev-0)
Coast Guard personnel) of all designated tank TLIs to demonstrate existing operational condition. Submit a CFR.
3.2.2 Content removal.