USCGC Ida Lewis Spec.doc
DOC document 602 KB Posted
- Attached to
- USCGC IDA LEWIS Dock Side Repairs at Home Pier
- Solicitation number
- HSCG80-08-Q-3FAD08
About this file
USCGC Ida Lewis Specification dated June 9 2008/Rev-1
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT 1 OF SOLICITATION IDA LEWIS 08 DS .doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC IDA LEWIS (WLM-551)
175 FOOT COASTAL BUOY TENDER
SPECIFICATION FOR DOCKSIDE REPAIRS
Developed By:
D. L. Abdella
Commander (v) Maintenance and Logistics Command, Atlantic 300 E. Main Street, Suite (600) Norfolk, VA 23510-9102
TABLE OF CONTENTS
Work Item Title Page iiiList of Sketches
Revisions Record iv List of Applicable References v List of Government-furnished Property ix List of Critical Inspection Items xii Specification Feedback xiii Principal Characteristics xiv General Requirements Clean and Disinfect Potable Water Tanks Clean and Inspect Ballast Tanks and Voids Clean and Inspect Sewage and Grey Water Collection and Holding Tanks and Pumps Clean, Inspect and Test Hot Water Accumulator Tank and Hydro-Pneumatic Tank Inspect and Test Air Receivers and Relief Valves Perform Hydraulic Chain Stopper Maintenance Perform Cross Deck Winch Maintenance Perform Buoy Chain Winch Maintenance Inspect Various Deck Fittings Preserve Ballast Tanks and Voids Preserve Sewage and Grey Water Collection and Holding Tanks Clean Shipboard Ventilation Systems Renew Structural Closures Clean and Inspect Ship Service Diesel Generator Motors Reseal/Renew Cosmetic Polymeric Deck Covering Systems Overcoat Designated Bilge Surfaces - Pier Side Modify Sewage Tank Vent Piping (EC 175-A-057)
List of Sketches
Work
Item Sketch Number Page This section is not applicable to this package.
Revisions Record
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
| DATE |
| REV# |
| WORK ITEM# |
| CHANGES MADE |
| 09 Jun 2008 |
| 1 |
| List of Applicable References |
| Updated weblink. |
| Specification Feedback |
| Updated weblink. |
| General Requirements |
| Updated weblink. |
NOTE: All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
List of Applicable References
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution. Electronic copies of the latest Editions of MLCA Standard Specifications are available on the Internet and may be accessed at the following Internet Uniform Resource Locator (URL) address: http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp.
Guidance for obtaining copies of all other documents referenced herein is provided in the solicitation.
Order of precedence. In the event of conflicts between text of this specification and the applicable references specified herein, order of precedence shall be in accordance with MLCA Standard Specification 0000_STD, paragraph 3.2 (Order of precedence), unless otherwise specified by the Contracting Officer (KO). The Contractor shall immediately notify the KO in writing of any perceived conflicts contained herein. Nothing in these documents, however, supersedes applicable laws and regulations, unless a specific exemption has been obtained.
FEDERAL AND MILITARY SPECIFICATIONS AND STANDARDS
MIL-D-16791, Jan 1993, Detergents, General Purpose (Liquid, Nonionic)
MIL-PRF-24613, Dec 1990, Deck Covering Materials, Interior, Cosmetic Polymeric
OTHER GOVERNMENT DOCUMENTS, DRAWINGS, AND PUBLICATIONS
DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2006 Edition, General Requirements
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 1001_STD, 2004 Edition, Temporary Hull Accesses
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 2350_STD, 2004 Edition; Clean, Inspect, Varnish-Treat, and Test Propulsion Generators and Motors, Ship Service and Emergency Generators in-Place Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 5000_STD, 2004 Edition, Auxiliary Machinery Systems
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 5100_STD, 2004 Edition, Clean Shipboard Ventilation Systems
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 6341_STD, 2004 Edition, Renew Deck Covering Systems
Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Naval Engineering Directive (NED) 5735-01, July 2005, Inspection and Test Procedure for Buoy Chain Winch Model CW-1 Onboard WLM 551-564 and WLB 201-215
DRAWINGS
Coast Guard Drawing 175 WLM 167-001, Rev H, Structural Closures
Coast Guard Drawing 175 WLM 505-001, Rev C, General Requirements of Piping Systems
Coast Guard Drawing 175 WLM 506-009, Rev-, Sewage Tank Vent Mods
Coast Guard Drawing 175 WLM 512-001, Rev E, HVAC Diagram
Coast Guard Drawing 175 WLM 533-001, Rev G, Potable Water System Diagram Coast Guard Drawing 175 WLM 549-001, Rev D, Onboard Lubrication Requirements
Coast Guard Drawing 175 WLM 551-001, Rev H, Compressed Air System Diagram Coast Guard Drawing 175 WLM 573-050, Rev A, Hydraulic Piping Installation for Chain Stopper Coast Guard Drawing 175 WLM 573-051, Rev B, Chain Stopper Structural Modifications for Hydraulic Roller Assembly Coast Guard Drawing 175 WLM 593-001, Rev G, Sewage and Wastewater System Diagram
Coast Guard Drawing 175 WLM 593-005, Rev F, Sewage and Wastewater System A&D
Coast Guard Drawing 175 WLM 593-006, Rev E, Sewage and Wastewater System A&D
Coast Guard Drawing 175 WLM 593-007, Rev D, Sewage and Wastewater System A&D
Coast Guard Drawing 175 WLM 593-009, Rev E; Independent Tanks, Sewage Holding Tanks
Coast Guard Drawing 175 WLM 601-001, Rev H, General Arrangement Inboard and Outboard Profile Coast Guard Drawing 175 WLM 801-019, Rev C, Shell Expansion Coast Guard Drawing FL 2605-13, Rev B, Buoy Chain Winch Model CW1: Pins
Coast Guard Drawing FL 2605-35, Rev-, Buoy Chain Winch Pedestal Bearing Modifications
Coast Guard Drawing FL 2605-29, Rev H, Chain Stopper System Rising Sheave Assembly Coast Guard Drawing FL 2605-30, Rev B, Chain Stopper Plate for Hydraulic Roller Assembly Coast Guard Drawing FL 2605-36, Rev B, Repair Strips for USCG Rising Sheave Chain Stopper System Coast Guard Drawing FL 7101-573, Rev K, Buoy Chain Winch Model CW1
PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), June 2006, Coatings and Color Manual Coast Guard Technical Publication (TP) 3498, Section A, June 2006, Buoy Chain Winch
Coast Guard Technical Publication (TP) 3616, Sep 2002, Manufacturer's Instruction Book, SWBS 310, Generator Set, SSDG & EDG - Model 3406 (Repair Manual)
Coast Guard Technical Publication (TP) 3631, Section 573-B, June 2006, Manufacturer's Instruction Book-SWBS Groups 573-581, Cross Deck Winch
Naval Ships' Technical Manual (NSTM) Chapter 510, Dec 2001, Section 7, Heating Ventilation and Air Conditioning Systems for Surface Ships
INDUSTRY STANDARDS
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2002, Disinfection of Water-Storage Facilities
American National Standards Institute/NSF International (ANSI/NSF) 61, 2005, Drinking Water System Components - Health Effects
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-69, 2003, Pipe Hangers and Supports - Selection and Application
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-89, 2003, Pipe Hangers and Supports – Fabrication and Installation Practices
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2004, Solvent Cleaning
American Society of Mechanical Engineers (ASME), PTC 25, 2001, Pressure Relief Devices
List of Government-furnished Property
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
| WORK ITEM |
| MTI |
| ITEM DESCRIPTION |
| NSN/PN |
| QTY |
| ESTIMATED COST |
($/Unit)
| 6 |
| N |
| Repair Kit assembly |
(for Para. 3.2, Task #4, #5)
| NSN: 2040-01-496-9418 |
| 2 |
| 1,000.00 |
| N |
| **Rod Seal repair kit |
| NSN: 2040-01-496-9422 |
| 2 |
| 400.00 |
| N |
| **Repair Kit, Cable Chain |
| NSN: 3020-01-538-0684 |
| 16 |
| 800.00 |
| N |
| **Cylinder Assembly Actuating, Linear (for Para. 3.2, Task #6) |
| NSN: 3040-01-496-9424 |
| 2 |
| 2,000.00 |
| 7 |
| N |
| Hydraulic Brake Assembly |
O-Ring Kits (for Para. 3.2.2, Task #5)
P/N: 02-500-141
| 4 ea. |
| 105.00 |
| Y |
| Hydraulic brake assembly |
(for Para. 3.2.2, Task #5)
| P/N: YMD-7915 |
| 4 ea. |
| 867.00 |
| N |
| Lining Kit |
(for Para. 3.2.2 , Task #5)
| P/N: 02-060-100 |
| 4 kits |
| 200.00 |
| N |
| Bearing Kit |
(for Para. 3.2.2, Task #5)
DWG: AMD-1111-03 / PG 143
| P/N: 02-500-142 |
| 4 ea. |
| 92.00 |
| Y |
| **Hydraulic motor |
(for Para. 3.2.2, Task #7)
| P/N: YMD-8023 |
| 4 ea. |
| 708.00 |
| N |
| Hydraulic motor |
Seal Kit
| P/N: YMD-5824R |
| 4 ea. |
| 94.00 |
| N |
| **Counter balance valve |
(for Para. 3.2.2, Task #6)
| P/N: CBEH-LJN |
| 8 ea. |
| 142.00 |
| N |
| **Shuttle valve |
(for Para. 3.2.2)
| P/N: CSAD-XXN |
| 8 ea. |
| 37.00 |
| N |
| **Needle valve |
| P/N: NFDC-KAN |
| 4 ea. |
| 92.00 |
| N |
| **Hydraulic Control valve |
(for Para. 3.2.2)
(13 week lead time)
| P/N: YMD-7884 |
| 4 ea. |
| 2,595.00 |
| N |
| **Nord Gear box |
Oil Seal (for Para. 3.2.2, Task #8)
P/N: 25100060
NSN: 5330-01-475-3752
| 8 ea. |
| 24.40 |
| N |
| **Oil Seal |
P/N: 25100050
NSN: 5330-01-475-3745
| 8 ea. |
| 28.00 |
| N |
| Gasket |
P/N: 25312150
NSN: 5330-01-446-0292
| 4 ea. |
| 21.20 |
| N |
| **Electrical Connector, Hirshmann |
P/N: YMD-5956
| 4 ea. |
| 32.00 |
| 8 |
| N |
| Bushing, Pivot |
(for Para. 3.2, Task #9)
| P/N: 01-573-06-17 |
| 1 ea. |
| 469.00 |
| Y |
| Level wind hydraulic cylinder |
(for Para. 3.2, Task #12)
| NSN: 3040-01-441-3721 |
| 1 ea. |
| 7,423.00 |
| N |
| Relief valve |
| P/N: RPEC-LANFB2 |
| 2 ea. |
| 50.00 |
| N |
| Pin, Pivot |
(for Para. 3.2, Task #9)
| P/N: 01-573-06-15 |
| 1 ea. |
| 1,723.08 |
| N |
| Bearing, Thrust |
(for Para. 3.2, Task #9)
| P/N: 01-573-06-16 |
| 2 ea. |
| 443.00 |
| N |
| Flow control valve (for Para. 3.2.3) |
| NSN: 4810-01-505-9289 |
| 1 ea. |
| 300.00 |
| 13 |
| N |
| Trash Locker door |
| ***P/N: PCM-072-F(LHR) |
| 1 ea. |
| 2,050.00 |
| N |
| QAWTD |
| P/N: JE-268-DQ-25 |
| 1 ea. |
| 2,050.00 |
| N |
| QAWTD |
| P/N: JE-268-DQ-26 |
| 1 ea. |
| 2,050.00 |
| N |
| QAWTD |
| P/N: JE-268-DQ-32 |
| 1 ea. |
| 2,050.00 |
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel, Electronic Systems Support Unit (ESU) or local Electronic Support Detachment (ESD).
List of Critical Inspection Items
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see Std Spec 0000_STD, paragraph 3.6.2 (Inspection report particulars)):
Work Item Title Perform Hydraulic Chain Stopper Maintenance
Perform Cross Deck Winch Maintenance
Perform Buoy Chain Winch Maintenance
Specification Feedback
The intent of this section is to inform all users that a spec feedback mechanism is in place, and is located on the MLCA Naval Engineering Division’s website. Spec feedback is a very important part of our overall continuous improvement process, and is crucial to specification development. It will allow spec writers to capture all specification-related lessons learned, and avoid mistakes or ambiguities in follow-on availabilities. All feedback will be reviewed, evaluated, and responded to in a timely manner.
If you have access to the CGWeb (Intranet), please use the following link, which will connect you to the MLCA(v) Naval Engineering website, for submitting your feedbacks:
http://webapps.mlca.uscg.mil/vdiv/specifications/feedback/default.cfm
If you do not have access to the CGWeb (Intranet), you may still submit your feedbacks, using the following web link:
http://www.uscg.mil/mlclant/vdiv/specfeedback.asp
PC_175_WLM
(07 Jan 2004) Principal Characteristics
175' WLM Buoy Tender
| Length Overall |
| 174' 08" |
| Depth (main deck at side to baseline) |
| 14' 08" |
| Maximum Beam |
| 36' 0" |
| Frame Spacing |
| 0' 20" |
| Full Load Draft |
| 9' ¾" |
| Full Load Displacement |
| 906.42 long tons |
PROPELLERS / SHAFT
| Number of Propellers |
| 2 |
| Number of Blades per Propeller |
| 4 |
| Diameter of Propeller |
| 57.1" |
00000N_FLT (20 Apr 2007)
General Requirements
1. SCOPE
1.1 Scope. This item describes the general requirements to be followed by the Contractor while conducting this availability.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2006 Edition, General Requirements Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Jun 2006, Coatings and Color Manual
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in Std Spec 0000_STD and in this item, as applicable, during the performance of this availability.
NOTICE!
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.3 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and nondestructive inspection (NDI), in accordance with Std Spec 0740_STD.
4. QUALITY ASSURANCE
No additional requirements.
5. NOTES
5.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may be accessed at the following URL address: http://www.uscg.mil/directives/cim.asp
5.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in Std Spec 0000_STD to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this item.
QA-1: QUALITY ASSURANCE INSPECTION FORM - PRESERVATION CHECKLIST
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with COMDTINST M10360.3, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating manufacturer(s).
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-based coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating manufacturer(s).
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-12, SP-11, SP-10…).
Verify surface anchor profile (1.5-3.5 mils for abrasive-blasted steel surfaces; 1.0 mil (minimum) for power-tool cleaned surfaces; 1.0-1.5 mils for abrasive-blasted aluminum surfaces); and 1.5 –2.5 for surfaces to be coated w/single coat of inorganic zinc).
Measure soluble salt conductivity (5 measurements per 1000 sqft) – maximum threshold: 70 microsiemens/cm for non-submerged surfaces and 30 microsiemens/cm for submerged surfaces.
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the Coating Manufacturer(s).
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness.
Verify system cure for service resumption - U/W Body surfaces: 5-8 hours @ 77 degrees F; Potable water tanks: 7 days @ 77 degrees F.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure (minimum 7 days @ 77 degrees F.), to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
Signature of Inspector:______________________________________________________Date:____________
QA-2. QUALITY ASSURANCE INSPECTION FORM
ENVIRONMENTAL READINGS
(Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat)
| DATE |
| TIME |
| ENTER ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…) |
| LOCATION |
| DEW POINT |
| SURFACE TEMP. |
| % REL. HUMIDITY |
| SIGNATURE OF INSPECTOR |
.Signature of Inspector:__________________________________________________Date:____________
QA-3 QUALITY ASSURANCE INSPECTION FORM
SURFACE PROFILE LOG
Vessel Name And Hull Number:__________________________________________________ Work Item Title:_______________________________________________________________ Location Of Work (Including Frame Numbers):_____________________________________ Area (Square Feet):_____________ Surface Preparation Method:_____________________________________________________ Abrasive Manufacturer And Size:_________________________________________________ Degreasing Method Used:________________________________________________________ Number Of Hours Surfaces (Steel Only) Left Unpainted:______________________________ Sweep blasting performed to remove flash rusting (steel)? Yes/No:_____________________ Place Surface Profile Replica Tapes In The Spaces Provided Below, To Serve As Permanent QA record.
Maintain separate log for each area/location. When an Area Is Divided Into Separate Sections, Maintain A Separate Log for Each Section.
AVERAGE MILS
(IAW ASTM D4417, METHOD C)
Place Surface Profile Replica Tape Here
Reading:__________ mils
· Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Date and Time:__________________________________________________ Location of Surface Profile Measurements:___________________________________________________________ Signature of Inspector:____________________________________________________________________________
QA-4. QUALITY ASSURANCE INSPECTION FORM
SURFACE SOLUBLE SALT CONDUCTIVITY LOG
Vessel Name and Hull Number:__________________________________________________ Work Item Title:_______________________________________________________________ Location of Work (including frame numbers):_______________________________________ Area (square feet):____________
| DATE |
| TEST LOCATIONS |
| CONDUCTIVITY |
(microsiemens/cm)
Date and Time:_________________________________________ Signature of Inspector:___________________________________
QA-5. QUALITY ASSURANCE DATA FORM
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC PA-2
(Use one sheet for each sequence) Vessel Name and Hull Number:__________________________________________________ Work Item Title:______________________________________________________________ Coating Manufacturer:_________________________________________________________ Product Name:________________________________________________________________ Batch Number:________________________________________________________________ Induction Time:_______________________________________________________________ Coating System Sequence (Indicate whether: primer, touch-up primer, barrier coat, 3rd coat…):__________________
DFT
MEASUREMENT NUMBER
| LOCATION OF READINGS |
| MEASURED DFT |
Application Method (Airless, Conventional Spray, Rolled):____________________ Average DFT: __________________________________________________________ Date and Time: _________________________________________________________ Signature of Inspector: ___________________________________ 12314A_FLT (09 Oct 2007) 175 WLM (20 Oct 2003) WORK ITEM 1: Clean and Disinfect Potable Water Tanks
1. SCOPE
1.1 Scope. This work item describes the requirements for the Contractor to clean and disinfect the following tanks:
| TYPE OF TANK |
| LOCATION |
| CAPACITY |
(gallons)
| Potable Water |
| 1-94-0-W |
| 2,167 |
| Potable Water |
| 2-36-1-W |
| 5,172 |
2. APPLICABLE DOCUMENTS
American National Standards Institute/NSF International (ANSI/NSF) 61, 2005, Drinking Water System Components - Health Effects American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2002, Disinfection of Water-Storage Facilities
3. REQUIREMENTS
3.1 General. The Contractor shall do the following for the designated tank(s):
3.1.1 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs to demonstrate existing operational condition. Submit CFR.
3.1.2 Tank content removal. Remove and dispose of all fluids and/or residues in accordance with all applicable Federal, state, and local regulations.
3.1.3 Cleaning requirements. Remove tank cover(s); clean tank interior surfaces free of all foreign materials, such as sediment or sludge. Remove all persistent residues, taking care not to damage the tank coating system. Remove cleaning media and residues continuously from the tank during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations.
3.1.4 Inspection. Visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
· Tank structural condition.
· Inaccessible areas, if any.
· Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
· Tank level indicator (TLI) and/or float switch condition (if applicable).
· Sounding tube and striker plate condition.
· Suction and discharge piping condition.
· Fastener material and condition (correct fastener material is stainless steel).
3.2 Tank closing. The Contractor shall notify the COR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector, and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to ANSI/NSF 61.
3.3 Tank disinfecting. After all other work involving the potable water system and tank closing have been completed, the Contractor shall disinfect and treat the affected potable water tank(s), as necessary to meet or exceed the requirements of AWWA C652. After tank disinfecting; pump all treated water overboard and dispose of in accordance with all Federal, state and local regulations.
WARNING!
Ensure that no one enters the tanks once disinfection is completed.
4. QUALITY ASSURANCE
4.1 Operational test - final. In the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLIs to be in satisfactory operating condition (see 5.1 (Equipment operation)). Submit CFR.
5. NOTES
5.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.
12316A_FLT (09 Nov 2007)
175 WLM (16 Apr 2007) WORK ITEM 2: Clean and Inspect Ballast Tanks and Voids
1. SCOPE
1.1 Scope. This work item describes the requirements for the Contractor to clean the following:
| TYPE OF STRUCTURE |
| LOCATION |
| CAPACITY |
(gallons)
| Ballast Tank |
| 3-0-0-V |
| 3,309 |
| Ballast Tank |
| 3-35-6-V |
| 7,922 |
| Ballast Tank |
| 3-35-1-V |
| 7,922 |
| Void |
| 3-18-0-T |
| 2,000 |
| Void |
| 3-52-0-V |
| 5,000 |
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General. The Contractor shall do the following for the designated structure(s):
3.1.1 Operational test – initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs to demonstrate existing operational condition. Submit a CFR.
3.1.2 Content removal. Remove and dispose of all fluid contents, in accordance with all applicable Federal, state, and local regulations.
3.1.3 Cleaning requirements. Remove access cover(s). Clean the designated structure’s interior surfaces free of all foreign materials, such as sediment or sludge. Remove all persistent residues, taking care not to damage the tank coating system. Remove cleaning media and residues continuously from the tank during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations.
3.1.4 Inspection. Visually inspect all tank interior surfaces; including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
· Structural condition.
· Inaccessible areas.
· Condition of coating, including measurements taken, percentage, location, and type of coating failure.
· Tank level indicator (TLI) and/or float switch condition.
· Sounding tube and striker plate condition.
· Suction and discharge piping condition.
· Fastener material and condition (correct fastener material is stainless steel).
3.2 Closing. The Contractor shall keep the manhole(s) uncovered for approximately 24 hours, after completion of the tasks specified above and all authorized and approved preservation tasks. Notify the COR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector, and after completion of all authorized work, in the presence of the Coast Guard Inspector reinstall manhole cover(s) with new gasket material conforming to ASTM D1330.
4. QUALITY ASSURANCE
4.1 Operational test – final. In the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLIs to be in satisfactory operating condition (see 5.1 (Equipment operation)). Submit a CFR.
5. NOTES
5.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.
12319A_FLT (09 Oct 2007)
175 WLM (12 Dec 2003)
551_A(28 Dec 2007) WORK ITEM 3: Clean and Inspect Sewage and Grey Water Collection and Holding Tanks and Pumps
1. SCOPE
1.1 Scope. This work item describes the requirements for the Contractor to clean and inspect the below designated tanks and associated system pumps:
| TYPE OF TANK |
| LOCATION |
| CAPACITY (gallons) |
| Sewage Holding Tank |
| 2-84-2-W |
| 847 |
| Grey Water Collection Tank |
| 3-83-1-W |
| 2,822 |
| Grey Water Collection Tank |
| 3-83-2-W |
| 2,822 |
| Vacuum Collection Tank |
| 2-82-2-W |
| 330 |
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.2 Cleaning requirements. The Contractor shall do the following for the designated tank(s) and their associated pumps listed in paragraph 1.1:
3.2.1 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs and system pumps to demonstrate existing operational condition. Submit CFR.
3.2.2 Content removal. Remove and dispose of all contents, fluids, and/or residues in accordance with all applicable Federal, state, and local regulations.
3.2.3 Cleaning requirements. Remove manhole cover(s). Clean the designated tank structure's interior surfaces free of all foreign materials, sediment, and sludge. Remove all persistent residues, taking care not to damage the tank coating system. Remove cleaning media and residues continuously from the tank during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations. Clean the exterior surfaces of the pumps.
3.2.4 Inspection. Visually inspect all interior tank surfaces; including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Visually inspect the system pumps. Submit a CFR including the following, as applicable:
· Tank structural condition.
· Inaccessible areas.
· Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
· Tank level indicator (TLI) and/or float switch condition.
· Suction and discharge piping condition.
· Fastener material and condition (correct fastener material is stainless steel).
· Pump condition and recommendations (if any) for repairs.
3.3 Closing. The Contractor shall ensure that the tanks remain open for approximately 24 hours after completion of the tasks specified above. Notify the COR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector and after authorized repairs, if any, reinstall manhole cover(s) with new gasket material conforming to ASTM D1330. The Contractor shall clean and reseal all tank sight glasses, if applicable, prior to reinstallation. Renew any disturbed pump gaskets.
4. QUALITY ASSURANCE
4.1 Operational test - final. In the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the TLIs, sewage and gray water pumps to be in satisfactory operating condition (see 5.1 (Equipment operation)). Submit CFR.
5. NOTES
5.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.
53310A_FLT (12 Mar 2007) 175 WLM (12 May 2006) WORK ITEM 4: Clean, Inspect and Test Hot Water Accumulator Tank and Hydro-Pneumatic Tank
1.1 Scope. This work item describes the requirements for the Contractor to clean, inspect and test the following tank(s) and renew associated relief valve(s):
| SERVICE |
| LOCATION |
| CAPACITY |
(gallons)
PRESSURE
(psig)
| Hot Water Accumulator |
| 3-42-1-E |
| 90 |
| 30-70 |
| Hydro-Pneumatic |
| 3-42-1-E |
| 100 |
| 40-65 |
Note: Tank relief valves are made by Kunkle or Watts. Includes one ¾” valve set to relieve at 100 psi; and one ½” valve set at 85 psi.
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2006 Edition, General Requirements Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Coast Guard Drawing 175 WLM 533-001, Rev G, Potable Water System Diagram ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General. The Contractor shall clean and inspect the designated tank(s) using Coast Guard Drawing 175 WLM 533-001 as guidance.
3.1.1 Interferences. The Contractor shall be aware that interferences in way of work may include, but are not limited to:
· Piping.
3.2 Preparation. The Contractor shall depressurize and drain the designated tanks before performing any work on them. Dispose of all fluids in accordance with Federal, state, and local environmental regulations.
3.3 Hot water accumulator tank(s). The Contractor shall accomplish the following for the designated tank(s) and associated heaters, as applicable:
3.3.1 Tanks with electrical heating elements. Clean and visually inspect the hot water accumulator tank heaters. Test the electrical resistance and heat conductivity of the heaters. Submit a CFR.
3.3.2 Reinstallation. After all authorized repairs, reinstall the hot water accumulator tank heater(s) to their original configuration with new rubber gaskets conforming to ASTM D1330. Renew all stainless steel fasteners with Monel Grade 400 or 405 fasteners.
3.4 Tanks. The Contractor shall accomplish the following for all designated tank(s):
3.4.1 Visual inspection. Clean and visually inspect the internal and external surfaces of each tank for signs of corrosion, pitting, and other damage.
3.4.2 Tank preservation. If a Change Request has been released and authorized by the Contracting Officer (KO), the Contractor shall preserve each tank’s interior surfaces in accordance with Std Spec 0000_STD, paragraph titled “General preservation requirements”; and in accordance with COMDTINST M10360.3, using the coating system specified for “Tanks and Voids (Potable Water Tanks)” in Appendix B (Cutter and Boat Interior Paint Systems). If preservation is for less than 100 percent of tank interior surfaces, power tool clean all affected surfaces to “bare metal” in lieu of using abrasive blasting, and feather edges of existing intact coating to the prepared areas, in order to provide a smooth transition with the new paint.
WARNING!
Do not drain any fluids (including fresh water) into any space, bilge or exterior location.
3.5 Relief valves. The Contractor shall accomplish the following for all designated tank associated relief valves.
3.5.1 Renewal. The Contractor shall renew all designated relief valves with MSS commercial-standard type valves. New valves shall be equivalent (including identical material) to the valve being renewed.
3.5.2 Lifting pressure test. The Contractor shall perform a lifting test on each tank relief valve at 135% of normal system operating pressure. Ensure that each valve seats cleanly after pressure relief, without simmering, and with no allowable leakage. Accomplish the test using clean, fresh water. Adjust the relief pressure as necessary to obtain the lifting pressure. After adjustment, perform a final test to confirm each relief valve's lifting pressure with the Coast Guard Inspector present. Submit a written CFR. After successful testing, install the relief valves. Renew all software.
3.6 Documentation. The Contractor shall accomplish the following:
3.6.1 Written certification. After completion of testing (and after any authorized repairs) submit written documentation listing each tank and relief valve tested, the date of test, and testing facility to the COR.
3.6.2 Data Plates. Affix to each tank and relief valve body an anodized aluminum test data plate using epoxy resin cement. Engrave the data plate with ¼-inch high letters stating the following:
3.6.2.1 Tank.
· Tank name/number (as applicable).
· Hydrostatic test pressure.
· Date of inspection and test.
· Testing facility.
3.6.2.2 Relief valve.
· Valve number.
· Lifting pressure.
· Date of test and set.
· Name of testing facility.
4. QUALITY ASSURANCE
4.1 Hydrostatic test. After all authorized repairs, the Contractor shall hydrostatically test all new and disturbed piping and components in accordance with Std Spec 0740_STD, Appendix C, “Hydrostatic Test”. Be aware that no leakage or permanent deformation of pressure-containing parts is permissible. Repair all leaks and discrepancies found. Submit a CFR.
4.2 Post-repair operational testing. In the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the designated system(s) to be in satisfactory operating condition (see 5.1 (Equipment operation)). Submit a CFR.
5. NOTES
5.1 Equipment operation. Coast Guard personnel will operate all shipboard machinery and equipment during all operational tests.
55100A_FLT (12 Mar 2007) 175 WLM (10 Sept 2005) WORK ITEM 5: Inspect and Test Air Receivers and Relief Valves
1.1 Scope. This work item describes the requirements for the Contractor to inspect and test the following air receivers and their associated relief valves:
| SERVICE |
| LOCATION |
| QTY |
| OPERATING PRESSURE (psi) |
| RELIEF VALVE SETTING (psi) |
| Ships Service Air Receiver (1/2”) |
| 3-61-0-E |
| 2 |
| 250 |
| 275 |
| Ships Whistle Air Receiver (1/2”) |
| 3-61-0-E |
| 1 |
| 125 |
| 155 |
| Vital Air Reducing Station (1 ½”) |
| 3-61-0-E |
| 2 |
| 125 |
| 155 |
| Seachest blowdown (1/2”) |
| 3-61-0-E |
| 2 |
| N/A |
| 40 |
Coast Guard Drawing 175 WLM 551-001, Rev H, Compressed Air System Diagram American Society of Mechanical Engineers (ASME), PTC 25, 2001, Pressure Relief Devices
3. REQUIREMENTS
3.1 General. The Contractor shall inspect and test each designated (see paragraph 1.1) air receiver and their associated relief valves. Assume one relief valve per receiver unit unless otherwise indicated. Refer to Coast Guard Drawing 175 WLM 551-001 for guidance.
3.2 Air receivers. The Contractor shall do the following for each designated air receiver:
3.2.1 System blowdown. Blowdown the air receivers and collect the blowdown (condensate) into a separate container for inspection.
3.2.2 Inspection and testing. Accomplish the following and submit a CFR.
3.2.2.1 Visual inspection. Visually inspect the blowdown (condensate) under a bright white light for oil or particulate contamination. Clean and visually inspect the internal and external surfaces of the air receiver for signs of corrosion, pitting, and other damage.
3.2.2.2 Hydrostatic testing. Isolate the air receivers by disconnecting all piping, relief valves, and pressure switches. Install pipe plugs/caps to prevent system contamination and in accordance with manufacturer’s testing procedures. Hydrostatically test each compressed air receiver in accordance with manufacturer’s recommended procedures to 1½-times the nominal operating system pressure. Hold for five minutes. There shall be no visible permanent deformation. After testing, drain and thoroughly dry the air receivers with warm air. Dispose of testing water in accordance with all applicable Federal, state, and local regulations. Submit a CFR including test pressure and results.
WARNING!
Do not drain any fluids, including fresh water, into any space, bilge, or exterior location.
Handle nitrogen bottles with extreme caution. They can be easily fractured internally.
3.3 Relief valves.
3.3.1 Option for valve renewal. The Contractor may opt to renew any/all relief valves in lieu of inspection and testing, at no additional cost to the Government if preferable for the Contractor. Ensure all new valves are commercial-standard type valves.
3.3.2 Inspect and test. The Contractor shall do the following for each designated air receiver associated relief valve the Contractor does not elect to renew; and submit a CFR:
3.3.2.1 Visual inspection. Disassemble as required, and visually inspect all parts for defects and deterioration.
3.3.2.2 Lifting pressure test. Perform a lifting test on each air receiver relief valve in accordance with manufacturer’s recommendations and ASME PTC 25. Ensure that each valve seats cleanly after pressure relief (without simmering), and with no allowable leakage.
3.3.3 Adjust and install. The Contractor shall adjust the relief pressure on the designated air receiver relief valves as necessary to obtain the specified lifting pressure. After adjustment, perform a final check to confirm each relief valve's lifting pressure with the COR present. After successful confirmation, install the relief valves. Renew all O-rings and gaskets.
3.4 Data plates. The Contractor shall affix an anodized aluminum test data plate with epoxy resin cement to each air receiver and relief valve body. The data plate shall be engraved with ¼-inch high letters, stating the following:
3.4.1 Air receivers.
· Receiver name/number(as applicable).
· Hydrostatic test pressure.
· Date of inspection and test.
· Testing facility.
3.4.2 Relief valves.
· Valve number.
· Lifting pressure.
· Date of test and set.
· Name of testing facility.
4. QUALITY ASSURANCE
No additional requirements.
5. NOTES
5.1 Air Receiver definition. An air receiver is a pressure vessel for the storage of air at 600 psig and below.
57320W_175(20 Apr 2007)
WORK ITEM 6: Perform Hydraulic Chain Stopper Maintenance
1.1 Scope. This work item describes the requirements for the Contractor to perform maintenance on hydraulic chain stoppers.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 5000_STD, 2004 Edition, Auxiliary Machinery Systems Coast Guard Drawing 175 WLM 549-001, Rev D, Onboard Lubrication Requirements Coast Guard Drawing 175 WLM 573-050, Rev A, Hydraulic Piping Installation for Chain Stopper Coast Guard Drawing 175 WLM 573-051, Rev B, Chain Stopper Structural Modifications for Hydraulic Roller Assembly Coast Guard Drawing FL 2605-29, Rev H, Chain Stopper System Rising Sheave Assembly Coast Guard Drawing FL 2605-30, Rev B, Chain Stopper Plate for Hydraulic Roller Assembly Coast Guard Drawing FL 2605-36, Rev B, Repair Strips for USCG Rising Sheave Chain Stopper System
3. REQUIREMENTS
3.1 General.
3.1.1 Critical Inspection Report. The Contractor shall submit a critical inspection report (CIR) for the inspections listed in the following paragraph(s):
· 3.2 (Level 1 maintenance, task #1).
3.1.2 Reference documents. The Contractor shall perform the work described herein in accordance with Std Spec 5000_STD (see paragraph number relationships in Section 5) and as shown on Coast Guard Drawings 175 WLM 549-001, 175 WLM 573-050, 175 WLM 573-051, FL 2605-029, FL 2605-030 and FL 2605-036.
3.2 Maintenance. The Contractor shall accomplish the following:
3.2.1 Level 1 maintenance.
ADDITIONAL REQUIREMENTS
| # |
| TASK TYPE |
| QTY |
| COMPONENT OR ASSEMBLY |
| APPENDIX AND PARA. FROM 5000_STD |
| OTHER |
| 1 |
| Operate and Inspect |
| 2 |
| Hydraulic Chain Stopper Assemblies |
| N/A |
| Submit (CIR). |
| 2 |
| Weight Test |
| 2 |
| Hydraulic Chain Stopper Assemblies |
| B-20.2 |
| Operational Load Test Weight: 16,500 (+0 -825) pounds |
Submit CFR.
| 3 |
| Fabricate and Install |
| 2 |
| Hydraulic Chain Stopper Assemblies |
| B-20.9 |
| System: Hydraulic Chain Stopper |
Operational Load Test Weight: 16,500#
3.2.2 Level 2 maintenance.
ADDITIONAL REQUIREMENTS
| # |
| TASK TYPE |
| QTY |
| COMPONENT OR ASSEMBLY |
| APPENDIX AND PARA. FROM 5000_STD |
| OTHER |
| 4 |
| Overhaul and Inspect |
| 2 |
| Rising Sheave Assemblies (sheave pin assembly) |
| D-20.1 |
| GFP. |
Renew all fasteners exposed to weather.
Lubricate as shown on Coast Guard Drawing 175 WLM 549-001.
Submit CFR.
| 5 |
| Inspect |
| 2 |
| Wear pads |
| N/A |
| Submit CFR. |
| 6 |
| Service and Inspect |
| 4 |
| Hydraulic cylinders |
| N/A |
| Submit CFR. |
| 7 |
| Service and Inspect |
| 2 |
| Directional control valve assemblies |
| C-20.4 |
| Submit CFR. |
| 8 |
| Service and Inspect |
| All |
| Hydraulic hose assemblies |
| C-20.2 |
| Submit CFR. |
| 9 |
| Preserve and NDE |
| 2 |
| Hydraulic Chain Stopper Assemblies and Machinery Foundations |
| N/A |
| Coating system: "Fittings" |
Finish coat color: black (17038)
Areas to NDE: all weld joints attaching chain stoppers to deck.
Preservation of areas inside the hull of the vessel is not required.
Submit CFR.
| 10 |
| Groom and Lubricate |
| 2 |
| Hydraulic Chain Stopper Assemblies |
| N/A |
| N/A |
4. QUALITY ASSURANCE
No additional requirements.
5. NOTES
5.1 Government-furnished property.
| MTI |
| ITEM DESCRIPTION |
| NSN/PN |
| QTY |
| ESTIMATED COST |
($/UNIT)
| N |
| Repair Kit assembly |
(for Para. 3.2, Task #4, #5)
| NSN: 2040-01-496-9418 |
| 2 |
| 1,000.00 |
| N |
| **Rod Seal repair kit |
| NSN: 2040-01-496-9422 |
| 2 |
| 400.00 |
| N |
| **Repair Kit, Cable Chain |
| NSN: 3020-01-538-0684 |
| 16 |
| 800.00 |
| N |
| **Cylinder Assembly Actuating, Linear (for Para. 3.2, Task #6) |
| NSN: 3040-01-496-9424 |
| 2 |
| 2,000.00 |
5.2 Paragraph number relationships. The appendix and paragraph number for each appendix and paragraph listed as maintenance in Section 3 relates directly to the identical appendix and sub-paragraph number in Std Spec 5000_STD.
57340W_175(04 May 2007)
WORK ITEM 7: Perform Cross Deck Winch Maintenance
1.1 Scope. This work item describes the requirements for the Contractor to perform maintenance on cross deck winches.
2. APPLICABLE DOCUMENTS
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 5000_STD, 2004 Edition, Auxiliary Machinery Systems Coast Guard Drawing 175 WLM 549-001, Rev D, Onboard Lubrication Requirements Coast Guard Technical Publication (TP) 3631, Section 573-B, June 2006, Manufacturer's Instruction Book-SWBS Groups 573-581, Cross Deck Winch
3. REQUIREMENTS
3.1 General.
3.1.1 Critical Inspection Report. The Contractor shall submit a critical inspection report (CIR) for the inspections listed in the following paragraph:
· 3.2.1 (Level 1 maintenance, task #1).
3.1.2 Reference documents. The Contractor shall perform the work described herein in accordance with Std Spec 5000_STD (see paragraph number relationships in Section 5), TP-3631, and as shown on Coast Guard Drawing 175 WLM 549-001.
3.1.3 Related work items. The Contractor shall accomplish this work item in conjunction with the following separate work item in this specification package:
· "Preserve Buoy Working Areas".
3.2 Maintenance. The Contractor shall perform the following:
3.2.1 Level 1 maintenance.
ADDITIONAL REQUIREMENTS
| # |
| TASK TYPE |
| QTY |
| COMPONENT OR ASSEMBLY |
| APPENDIX AND PARA. FROM 5000_STD |
| OTHER |
| 1 |
| Operate and Inspect |
| 4 |
| Cross Deck Winch Assemblies |
| N/A |
| Submit (CIR). |
| 2 |
| Weight Test |
| 4 |
| Cross Deck Winch Assemblies |
| B-20.3 |
| Static Load Test Weight: 9,000 (+450 -0) pounds |
Dynamic Load Test Weight: 7,500 (+375 -0) pounds
Rated Load Test Weight: 6,000 (+0 -300) pounds
Submit CFR.
| 3 |
| Fabricate and Install |
| 4 |
| Label plates |
| B-20.9 |
| System: Cross Deck Winch |
Static Load Test Weight: 9,000#
Dynamic Load Test Weight: 7,500#
Rated Load Test Weight: 6,000#
ADDITIONAL REQUIREMENTS
| # |
| TASK TYPE |
| QTY |
| COMPONENT OR ASSEMBLY |
| APPENDIX AND PARA. FROM 5000_STD |
| OTHER |
| 5 |
| Overhaul, Inspect, and Preserve |
| 4 |
| Brake assemblies |
| D-20.3 |
| Install new "Lining Kit", "Bearing Kit", and "O-ring Kit" in accordance with "MICO Brake" handout in TP-3631. |
Submit CFR.
| 6 |
| Overhaul, Inspect and Preserve |
| 4 |
| Directional Control Valve Assemblies |
| C-20.4 |
| Submit CFR. |
| 7 |
| Service, Inspect, and Preserve |
| 4 |
| Winch Hydraulic Motor Assemblies |
| C-20.4 |
| Submit CFR. |
| 8 |
| Service, Inspect, and Preserve |
| 4 |
| Winch Gearbox Assemblies |
| D-20.4 |
| Submit CFR. |
| 9 |
| Preserve and NDE |
| 4 |
| Cross Deck Winch Foundations |
| N/A |
| Finish coat color: Select to match surrounding surfaces. |
Areas to NDE: All weld joints connecting winch foundations to the deck.
Foundation Bolts Type: 3/4-10UNC, Grade 8
Torque value: min 200 ft-lbs.
Submit CFR.
| 10 |
| Preserve |
| 4 |
| Cross Deck Winch Assemblies |
| N/A |
| None. |
| 11 |
| Groom and Lubricate |
| 4 |
| Cross Deck Winch Assemblies |
| N/A |
| Perform all maintenance in Chapter 4 of TP-3631. |
Adjust load cell readouts to display within 1% of actual load, see "Winch Local Control" and "Winch Remote Control" sections of TP-3631.
Note: Line 4 not required for this work item.
4. QUALITY ASSURANCE
No additional requirements.
5. NOTES
5.1 Paragraph number relationships. The appendix and paragraph number for each appendix and paragraph listed as maintenance in Section 3 relates directly to the identical appendix and sub-paragraph number in Std Spec 5000_STD.
5.2 Government-furnished property.
| MTI |
| ITEM DESCRIPTION |
| NSN/PN |
| QTY |
| ESTIMATED COST |
($/UNIT)
| N |
| Hydraulic Brake Assembly |
O-Ring Kits (for Para. 3.2.2, Task #5)
P/N: 02-500-141
| 4 ea. |
| 105.00 |
| Y |
| Hydraulic brake assembly |
(for Para. 3.2.2, Task #5)
| P/N: YMD-7915 |
| 4 ea. |
| 867.00 |
| N |
| Lining Kit |
(for Para. 3.2.2 , Task #5)
| P/N: 02-060-100 |
| 4 kits |
| 200.00 |
| N |
| Bearing Kit |
(for Para. 3.2.2, Task #5)
DWG: AMD-1111-03 / PG 143
| P/N: 02-500-142 |
| 4 ea. |
| 92.00 |
| Y |
| **Hydraulic motor |
| P/N: YMD-8023 |
| 4 ea. |
| 708.00 |
| N |
| Hydraulic motor |
Seal Kit
| P/N: YMD-5824R |
| 4 ea. |
| 94.00 |
| N |
| **Counter balance valve |
| P/N: CBEH-LJN |
| 8 ea. |
| 142.00 |
| N |
| **Shuttle valve |
| P/N: CSAD-XXN |
| 8 ea. |
| 37.00 |
| N |
| **Needle valve |
| P/N: NFDC-KAN |
| 4 ea. |
| 92.00 |
| N |
| **Hydraulic Control valve |
(for Para. 3.2.2)
(13 week lead time)
| P/N: YMD-7884 |
| 4 ea. |
| 2,595.00 |
| N |
| **Nord Gear box |
Oil Seal
P/N: 25100060
NSN: 5330-01-475-3752
| 8 ea. |
| 24.40 |
| N |
| **Oil Seal |
P/N: 25100050
NSN: 5330-01-475-3745
| 8 ea. |
| 28.00 |
| N |
| Gasket |
P/N: 25312150
NSN: 5330-01-446-0292
| 4 ea. |
| 21.20 |
| N |
| **Electrical Connector, Hirshmann |
P/N: YMD-5956
| 4 ea. |
| 32.00 |
57350W_175_225 (14 December 2005)
551_A(26 Dec 2007)
WORK ITEM 8: Perform Buoy Chain Winch Maintenance
1.1 Scope. This work item describes the requirements for the Contractor to perform maintenance on the buoy chain winch.
2. APPLICABLE DOCUMENTS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 5000_STD, 2004 Edition, Auxiliary Machinery Systems Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Naval Engineering Directive (NED) 5735-01, July 2005, Inspection and Test Procedure for Buoy Chain Winch Model CW-1 Onboard WLM 551-564 and WLB 201-215 Coast Guard Drawing FL 2605-13, Rev B, Buoy Chain Winch Model CW1: Pins Coast Guard Drawing FL 2605-35, Rev-, Buoy Chain Winch Pedestal Bearing Modifications Coast Guard Drawing FL 7101-573, Rev K, Buoy Chain Winch Model CW1 Coast Guard Technical Publication (TP) 3498, Section A, June 2006, Buoy Chain Winch
3. REQUIREMENTS
3.1 General.
3.1.1 Critical Inspection Report. The Contractor shall submit a critical inspection report (CIR) for the inspections listed in the following paragraph(s):
· 3.2.1 (Level 1 maintenance, task #1).
3.1.2 Reference documents. The Contractor shall perform the work described herein in accordance with Std Spec 5000_STD (see paragraph number relationships in Section 5), NED 5735-01, and TP-3498.
3.2 Maintenance. The Contractor shall accomplish the following using Coast Guard…
This is the start of the file's text. The full file is on GovTribe.