SEWARD UPH RENOVATION PROJECT
SUMMARY OF WORK
PSN# 6571515
PART 1 - GENERAL
1.1 INTENT: The intent of this project is to rehab the U. S. Coast Guard Unaccompanied
Personnel Housing (UPH) at Seward, Alaska. The UPH is a two-story dwelling consisting of four 2-bedroom apartments with a common utility room, stairs and entry.
This project will be accomplished while the facility is vacated and the contractor shall coordinate start of work with USCG CEU Juneau prior to the beginning of demolition and construction work. The Contractor shall complete all work within 40 calendar days from notice of award. All work shall be performed between 0830 to 1600, Monday through Friday, no weekends or Federal Holidays.
1.2 SUMMARY OF WORK: The Contractor shall provide all equipment, materials, labor, supervision, transportation, and other related items for work indicated on the drawings, specified in the specifications, and required for a complete and functional installation. The contractor shall also protect all furnishings, appliances, personal property, etc. from damage during demolition or new work. THE CONTRACTOR IS RESPONSIBLE FOR VERIFYING ACTUAL
DIMENSIONS AND SITE CONDITIONS.
A. Renovate bathrooms. Work includes demolition of existing bathroom fixtures and casework. Work includes wall construction, installation of new vanities, counter tops, recessed mirrored medicine cabinets, sinks, faucets, tubs, water closets, associated plumbing, tub surrounds, accessories, flooring and painting. Work includes required plumbing, electrical and mechanical work to bring facilities up to current building codes.
B. Living Rooms and Bedrooms: Remove and replace carpeting with laminate flooring, abate ACM in popcorn ceiling and replace with orange peel texture finish, repair walls and paint all walls and ceilings. Repair/Replace trim work throughout unit. Replace covers for all heat covers.
C. Utility Room: Remove and replace flooring in kind. Paint walls and ceiling.
D. Doors: Replace metal door and frame at building entry, replace entry door and frame to each apartment, and utility room. Paint all doors and frames.
E. Entry Hall and Stairs: Remove and replace carpeting with vinyl sheet flooring, Repair and paint all walls and Ceilings, repair stair treads (not code compliant).
F. Prep and paint all interior paintable surfaces, including but not limited to ceilings and walls. Paint all interior closets, remove all shelving and shelf supports prior to painting .
PROJECT #6571515 01010 - 1 SUMMARY OF WORK
1.2.2 Mechanical work includes:
A. Plumbing: Remove and replace tub and shower fixtures, install access panel for each shower.
B. Ventilation: Remove and replace bath exhaust fans, and fan controls.
1.2.3 Electrical work includes:
A. Install new lighting fixtures in living rooms and bedrooms.
B. Install new vanity light bars in bathrooms.
C. Provide all electrical connections required for installation of bath fans.
D. Relocate vanity receptacles to allow for 36” vanity
1.3 CONSTRUCTION DOCUMENTS:
1.3.1 Drawings, Identified as U. S. Coast Guard No. S-3510, sheets 1 through 3.
1.3.2 Specifications, Flooring: Products: Subject to compliance with requirements, possible products that may be incorporated into the Work include, but are not limited to, the following:
1. Armstrong World Industries, Inc.
2. Congoleum Corporation
3. Mannington Mills, Inc.
4. Tarkett, Inc.
Vinyl Sheet Floor Covering with Backing: ASTM F 1303.
1. Type (Binder Content): Type I, minimum binder content of 90 percent.
2. Wear-Layer Thickness: Grade 1.
3. Overall Thickness: As standard with manufacturer.
4. Backing Class: Class A (fibrous).
1.3 SITE VISIT
To schedule a site visit, contact the Engineering Petty Officer (CGC Mustang ) MKC Jared Larow at 907-224-5202
PART 2 – PICTURES:
Sheetrock around tub and shower surrounds.
PROJECT #6571515 01010 - 2 SUMMARY OF WORK
Heating covers
Tub and shower surround, flooring to be replaced.
***END OF SECTION***
PROJECT #6571515 01010 - 3 SUMMARY OF WORK