SOW - 1

DATE: 06/01/2011

PROJECT NO.: 3457605

PROJECT TITLE: LISTENING STATION REINSTALLATION FOR DOMESTIC WATER SYSTEM,

PHASE 2

PROJECT LOCATION: USCG BSU KODIAK, KODIAK, AK

SUMMARY

The work shall consist of providing all materials, equipment, transportation, and labor required to provide and install 30 listening stations along ~2.5 miles of domestic water line, and a final survey and map of installation locations as shown and described within these specifications. The new stations shall replace existing stations that have been damaged or lost since original installation in 1993. This is the second phase of a two part project, which was initiated in 2010. The listening stations are to be installed on the existing water system throughout the U. S. Coast Guard’s Base Support Unit (BSU), Kodiak, Alaska.

The Contractor is responsible for:

1) Working with Contracting Officer’s Technical Representative (COTR) and Base Operations Support Services (BOSS) Contractor to locate existing domestic waterline.

2) Complying with all USCG Base and State Airport access requirements.

3) Light brushing – alder and salmonberry.

4) Removing existing listening stations.

5) Installing new listening stations at approximately every 300 (if diameter is 16” or greater), or 350 LF (if diameter of line is less than 16”) along each section of water line, per drawings and specifications. No station shall be installed within 300 feet (+/- 50 feet) of any existing valve or fire hydrant that can be used as a listening station.

Installation includes:

a) Excavating to water line, and removing exterior scale for clean attachment.

Measuring and recording depth to top of pipe (typically -4 feet to -8 feet below existing grade).

b) Installing listening stations that are comprised primarily of utility service box which contains and protects a permanently attached listening device with rod from the top of pipe to the surface.

c) Backfilling and compacting to match existing grade per specifications.

d) Patch-pave disturbed asphalt (Not anticipated in Phase 2).

6) Providing a clear marking device (utility delineator post) for each listening station, ensuring that is offset and well protected or designed to resist road grading, plowing, mowing, and brushing equipment and general traffic. Markers on the airport must meet additional FAA requirements. NOTE: Proved 15 of each marker type as critical spare (30 total). The FAA airport area utility markers require a special installation device. Provide one installation device to the GOVT.

7) Professionally survey and map locations (X,Y,Z) of listening stations, utility delineator posts, and provide swing ties to a minimum of 3 surveyed site features (such as nearest utility pole, edge of pavement, building corner, fence line, manhole, etc.) in locally adjusted State Plane coordinate system, utilizing GPS or other traditional survey equipment as approved by the government.

SOW - 2

Anticipated Task Items For Purpose of Bid (NOTE: Actual quantities must be verified by Contractor prior to construction.)

IMPORTANT: Bid each section separately-- project will be awarded on a per section basis, as budget allows:

SECTION 1. Completed 2010. Not in Contract (NIC).

SECTION 2. Completed 2010. (NIC) SECTION 3. Completed 2010. (NIC) SECTION 4. Location on portion of 16” DI water line running between Runway 7-25, and

Taxiway D to Firehall then along Dolphin Avenue to intersection with Narrow Cape St.

Depth is 6’ to 8’. Approximately 5400 LF. Demolish nine (9) existing stations. Fifteen

(15) new stations required at 300 foot intervals.

SECTION 5. Completed 2010. (NIC) SECTION 6. Completed 2010. (NIC) SECTION 7. Scheduled for replacement 2012. (NIC) Location from wastewater treatment plant valve #135 along Taxiway to valve cluster in vicinity of Sarichef Street. Depth of 6”CI water line 4’ to 6’. Approximately 3300 LF. Demolish four (4) existing station. Nine (9) new stations required at 350 foot intervals.

SECTION 8. Location from valve #40 to valve #41 along sea wall near edge of hangar apron. Depth of 8” DI water line 6’ to 8’. Approximately 1700 LF. Demolish four (4) existing stations. Four (4) new stations required at 350 foot intervals.

SECTION 9. Location from valve #58 to valve #239 on Nyman’s Peninsula fuel farm.

Depth of 6” DI water line 4’ to 6’. Approximately 1200 LF. Demolish one (1) existing stations. Two (2) new stations required at 350 foot intervals.

SECTION 10. Location on Nyman’s Peninsula fuel farm from valve #230 to valve #54.

Depth of 6” CI water line 4’ to 6’. Approximately 1900 LF. Demolish two (2) existing stations. Three (3) new stations required at 350 foot intervals.

SECTION 11. Location adjacent to Rezanof Highway from sea wall to Lash Corporation Wharf. Depth of 10” DI line unknown; assume 5’. Approximately 2900 LF. Six (6) new stations required at 350 foot intervals.

SECTION 12. Provide 15 spare airport (FAA) area utility markers and 1 compatible installation device. Also provide 15 spare non-airport area utility markers.

SOW - 3

SCOPE OF WORK

INTENT OF CONTRACT

The intent of the Contract is to provide for the construction and completion of every detail of the described work. The Contractor shall furnish all labor, material, supervision, equipment, tools, transportation, supplies, and other resources required to complete the work in the time specified and in accordance with the Contract.

CLEANUP

The Contractor shall remove all rubbish, temporary structures, excess materials, and equipment from the project site and from all work areas before project completion.

GOVERNMENT-FURNISHED MATERIAL

Digital copies of local survey control data and water system drawings are available upon request.

SITE REQUIREMENTS

1. Salvage: All existing materials which are to be removed, and are not indicated or specified for reuse in the new work, shall, unless otherwise specified, become the property of the contractor, be removed from government property at the Contractor’s expense, and be disposed of in accordance with Federal, State and local regulations. Remove all salvage from government property.

2. Roadways: Seven day notice is required before embarking on any construction work which might block a roadway.

3. Barriers: Furnish, install and maintain suitable barriers as required to provide public safety meeting State of Alaska traffic and OSHA requirements, prevent public entry, and to protect the work and existing facilities during construction operations; remove when no longer need, or at completion of work. Clean and repair damage caused by installation.

4. Contractor’s Storage Area: The Government will furnish material and equipment storage area for the Contractor’s optional use. The Contractor shall be fully responsible for the security of all stored material and equipment, and shall provide any fencing, barriers, or other security measures he deems necessary, at his expense.

PROTECTION OF EXISTING UTILITIES

1. Hand Digging: All excavations with the potential for damaging existing utilities using machine excavation shall be done by hand digging. When digging within 2 feet of any existing utility, locate the utility by hand to expose the pipe or cable rather than machine methods.

2. Contractor shall restore damaged piping, cable(s), and circuits to original condition and full operation if damage occurs through his failure to fully process the digging permit or comply with its instructions, or to obtain utility locations from private utilities. Notification of damage shall be made immediately to the affected utility, to the USCG representative as listed on the digging permit, and to the KO;

restoration efforts shall commence within 1 hour. Failure to commence restoration within the required time limit, or to make continuous progress toward restoration, or to complete acceptable restoration within a 4-hour time limit or an alternate time limit negotiated with and established by the KO, shall result in suspension of all other contract work until acceptable restoration is completed and approved by the KO.

SOW - 4

3. The Contractor shall not operate valves or similar components of existing systems except in an emergency to protect life and property.

4. Down Time: Provide temporary utility service of the same capacity of that which is out of service.

5. Protection: The Contractor shall safeguard and protect from damage all utilities encountered or uncovered during digging, excavation, and backfilling.

6. All work to repair damage to private utilities shall be coordinated through said utility.

7. In cases where a utility is damaged for reasons noted above, the Contractor shall employ or subcontract, as necessary, qualified trades to restore the utility to its original condition and full operations at no expense to the Government.

8. The Government reserves the right to protect damaged communications cables from further damage or deterioration and the right to restore priority circuits; these actions shall not relieve the Contractor of his full responsibility for restoration.

COLD WEATHER OPERATIONS

If any part of this project is pursued during periods of cold or inclement weather, the Contractor shall take all appropriate precautions to protect facilities and work involved in the project scope from damage by cold/or inclement weather. The Contractor shall be responsible for snow removal around project site, parking areas, and thoroughfares to allow passage of traffic.

HIGHWAY LIMITATIONS

The CONTRACTOR shall make its own investigation of the condition of available public and private roads and of clearances, restrictions, bridge load limits, and other limitations affecting transportation and ingress and egress to the site of the WORK. It shall be the CONTRACTOR's responsibility to construct and maintain any haul roads required for its construction operations.

ROAD CLOSURES

1. One lane of the Nymans Peninsula Access Road may be closed to public use during construction.

This lane shall be barricaded off and detour signs placed in the one direction. No flagmen will be required, as long as the detour signs are provided.

2. Before work is started, submit a detailed road closure and traffic plan for any road closures. The plan shall show, but not be limited to traffic flow pattern, location of warning signs, flaggers – if deemed necessary, barricades, etc. The contractor shall evaluate, as part of the road closure plan, any area-wide traffic flow as it is affected by construction activities.

3. Ten day notice is required before embarking on any construction work which may block a roadway.

4. Sign roads in the project area to indicate road closures and alternative routes. Post signs to indicate pending road closures 3 days prior to the actual closure. Coordinate all signage requirements with the COTR, Base Police, and State Highway Department.

SOW - 5

SPECIFIC REQUIREMENTS

1. Lay out listening stations approximately every 300 or 350 LF (+/- 25 feet) along each section of water line shown on the attached site plan drawing. If water line diameter is 16” or greater, install listening stations at 300 foot intervals. If diameter is less than 16”, install stations at 350 foot intervals. No station shall be installed within 300 +/- 50 feet of any existing valve or fire hydrant that can be used as a listening station. No listening station is to be installed in any paved aircraft surface, or the paved surface of Rezanof Highway.

2. Excavate to water line for each station to be installed. Clean loose scale from the water line where listening station is to be placed. Excavation of large rocks, boulders or hard material shall be accomplished at no additional cost to the Government. If station falls within a roadway or paved area, refer to special requirements for paved areas (Not anticipated during Phase 2). When existing utilities are encountered which are not scheduled for removal or abandonment, they shall be adequately supported and protected from damage, and fully repaired if damage occurs.

3. Install each listening station per attached details that are comprised primarily of a recessed utility service box and a cast iron cap which contain and protect a permanently attached listening device with rod from top of pipe to surface. Service box and cap assemblies shall be installed in a vertical and level position. In areas where grading and snow plowing occur, recess cap 6” below grade. In areas where mowing occurs (example: airport), set meter boxes to grade. See attached detail drawing.

4. The contractor shall perform the requirements for all paved areas as follows:

a. No paving anticipated in Phase 2.

5. The contractor shall perform the requirements for all non-paved areas as follows:

a. Backfill with native material in no more than 12 inch lifts to 24 inches of grade, compacting each lift to 90% maximum dry density.

b. Final 24 inches shall be approved native or D-1 material placed in no more than 6 inch lifts, compacting each lift to 90% maximum dry density.

c. Refer to section on Placement and Compaction of Area Fills for further details.

6. Cast Iron Service Boxes. Install cast iron service box top (aka valve box top), approx. 5” diameter, 18” tall with top flange and approximately 1” thick cast iron lid. Recess 1/2” – 3/4" in paved areas and 2” - 6” below grade in all areas subject to plowing, grading, brushing and/or mowing. (Known complier, Olympic Foundry, Part Nos. 940). Submittal required if other than brand name.

7. Service Saddle/Listening Rod Connection. Install a corrosion resistant, double strap service saddle around water main for firmly holding listening rod against the water main per Listening Station Detail.

(Known complier, Romac Industries, Style 202NS, Nylon Coated Saddle with Stainlesss Steel Straps). Submittal required if other than brand name.

SOW - 6

8. Utility Marker Witness Post – Non-Airport Areas: Install utility marker witness post with anchor at a designated offset interval of 5’ (example 5’, 10’, 15’, etc.) perpendicular to waterline to clearly mark location of listening station. Reflective decal shall state “WATER LINE”, “CAUTION WATER PIPELINE” or other similarly approved decal with offset distance noted. Witness posts shall be installed where protected from damage by traffic, or brushing, mowing, plowing, or grading equipment. (Known complier, Bernsten International, Carsonite Utility Marker Post Part No.

CRM3060.) See Utility Marker Specification. Submittal required if other than brand name.

9. Utility Marker Witness Post – Airport Areas: Install utility marker witness post with anchor immediately adjacent to utility cap to clearly mark location of listening station. Post shall have a 360 degree visible reflective decal applied by manufacturer, meet FAA requirements for Type II Elevated Markers, and be able to resist airport mowing, and plowing equipment. (Known complier, FlexStake Ground Mount Tubular Marker with Barbed Roadside Base, Model 652.5.) See Utility Marker Specification. Submittal required if other than brand name.

10. As-Built Survey: Provide a professional survey for each listening station and its associated utility delineator posts, along with a minimum of 3 surveyed site features (such as nearest utility pole, edge of pavement, building corner, fence line, manhole, etc.) in locally adjusted State Plane coordinate system, utilizing GPS or other traditional survey equipment as approved by government. Submit a separate 8.5x11 drawing for each listening station, providing information indicated in attached Drawing Template. This shall be done utilizing the paper space Layout Tab feature in AutoCAD.

NOTE: Prior to surveying, the surveyor shall meet with USCG staff and contractor to review contract requirements, available information, coordinate systems, accuracy, and AutoCAD and surveying standards. See As-Built Survey and Documents Specification. Submittals required.

SOW - 7

UTILITY MARKER SPECIFICATION – (Non-Airport Areas)

A. SCOPE

This specification covers the minimum material, mechanical and performance requirements of continuous glass fiber and resin reinforced Composite Marker. This product may be used to provide daytime and nighttime delineation for utilities or other marking applications requiring assured long-term outdoor durability, vandal resistance, and vehicle impact resistance.

B. GENERAL REQUIREMENTS

1. The marker shall be a single piece marker capable of simple, permanent installation by one person using a manual driving tool. Upon proper installation, marker shall resist displacement from wind and vehicle impact forces. The marker shall be of a constant flat "T" cross sectional design with reinforcing support ribs incorporated longitudinally along each edge to provide sheeting protection and structural rigidity. The bottom end of the marker shall be pointed for ease of ground penetration.

2. The marker shall be constructed of a durable, UV resistant, continuous glass fiber and resin reinforced, thermosetting composite material which is resistant to impact, ozone, and hydrocarbons within a service temperature range of -40°F to +140°F. Color shall be blue.

3. Each marker shall be permanently identified with the manufacturer's name and the month and year of fabrication. The letters shall be a minimum of 3/8-inch in height, and permanently affixed to the rear of the marker. A black line shall be stamped horizontally across the front of the marker near the bottom to indicate proper burial depth.

4. The marker shall conform to the illustration shown in Detail Drawings.

a. Width: The nominal marker width shall be 3.75 inches (minimum) in order to accommodate a three-inch wide reflector and provide adequate daytime delineation.

b. Length: The marker shall be of such length to provide the required height above the road surface with a minimum embedment depth of 18 inches.

c. Color: The marker shall be pigmented throughout the entire cross-section so as to produce a uniform color, which is an integral part of the material. Ultraviolet resistant materials shall be incorporated in the construction to inhibit fading or cracking of the delineator upon field exposure.

SOW - 8

UTILITY MARKER SPECIFICATION – (Airport Areas)

A. SCOPE

This specification covers the minimum material, mechanical and performance requirements of tubular, one-piece flexible ground driven delineator posts. This product may be used to provide daytime and nighttime delineation for utilities or other marking applications requiring assured long-term outdoor durability, vandal resistance, and vehicle impact resistance. This marker shall also conform to Type II Markers per FAA AC 150/5345-39x “Specification for L-853, Runway and Taxiway Lighting Retroreflective Markers”.

B. GENERAL REQUIREMENTS

1. The top portion of the post is made of copolymer material which shall be resistant to impact, ultraviolet light, ozone, hydrocarbons, and shall be self-erecting after withstanding vehicle impacts.

Polycarbonate post shall remain dimensionall stable from -25 deg. F (brittleness point) to 350 deg F (melting point)>

2. Post shall remain intact up to seventy-five impacts at a vehicle speed of 55 MPH by a typical American made car from either direction at temperatures fro -45 deg. F to 350 deg. F.

3. The top section of post shall be connected to ground anchor or surface mount with a poly urethane hinge. The hinge shall have an internal memory and remain dimensionally stable to -30 deg. F .

4. The marker shall conform to the illustration shown in Detail Drawings.

a. Diameter/Thickness: The outside diameter of the post shall be 2 3/8” and the maximum wall thickness shall be 0.20”

b. Length: The marker shall be of such length to provide the required height above the road surface with a minimum embedment depth of 18 inches.

c. Color: The posts shall be pigmented throughout so as to produce a uniform color, which is an integral part of the material. Reflective sheeting shall meet DOT specifications and will be specified on order.

5. Posts shall be free of surface porosity and other defects that may affect appearance and serviceability.

6. Posts shall contain a minimum of 51% (by weight) post consumer recycled material, and all material shall be recyclable.

7. Posts shall be field-repairable by snapping on new post. Posts and other components shall be field replaceable.

8. Posts shall be capable of being mowed over by a standard DOT flail or sickle mower (special attachment required).

SOW - 9

PLACEMENT AND COMPACTION OF AREA FILLS

A. GENERAL

1. This subsection applies to the placement and compaction of fill materials such as borrow, backfill, base, or surface courses. This including fills constructed to support building pads, embankments, roadway pavements, and parking areas.

2. The Contractor shall place fill materials in horizontal layers of uniform thickness.

3. Fill slopes shall be compacted to the required density as the fill is constructed, not afterwards.

4. Do not incorporate frozen materials into fills. When excavation is performed when freezing weather is imminent, place the specified backfill promptly, following the excavation work, at least up to a level which will allow the surface to adequately drain. Make arrangements for the timely availability of such fill materials prior to commencement of the stripping or excavation operations, when required.

B. COMPACTING EARTH FILLS

1. Each layer of the entire fill shall be compacted to a firm and unyielding condition and to at least 90% of the material’s maximum dry density as determined by ASTM D1557.

2. Within the limits described below, the Contractor shall adjust moisture content during compaction to produce a firm and unyielding fill. The Contractor shall not begin compaction until the moisture content is so adjusted.

3. The moisture content shall not vary more than 3-percent above or below optimum as determined by ASTM D1557. Adjust the moisture content of fill materials as necessary to meet the properties requirements specified herein.

4. The Engineer may permit the Contractor to place materials having a higher moisture content than specified in this subsection if:

a. The material consists of free-draining granular material that compacts to a firm, unyielding surface

b. The excess moisture will not impair the fill.

5. However, the Engineer may at any time require the Contractor to return to normal moisture-content specifications.

6. The costs of adjusting the moisture content of fill material to be incidental to other Work.

7. In the top 2 feet, horizontal layers shall not exceed 6-inches in depth before compaction. No layer below the top 2 feet shall exceed 12 inches in depth before compaction.

8. Based on the location and compaction characteristics, the Engineer may permit the Contractor to increase layer thickness up to 18-inches before compaction, provided:

a. Fill material is granular,

b. The layer is more than 2-feet below the top of the fill,

c. An approved vibratory roller is used, and

d. The contractor can document to the satisfaction of the Engineer that the required density is obtained throughout the full depth and width of each layer. This may require that

SOW - 10

additional compaction testing be completed at no cost to the Government.

9. Whatever the method used, any portion of a fill that is inaccessible to large compacting equipment shall be compacted with small mechanical or vibratory compactors.

10. Repair at no cost to the Government any portions of fills that lose stability because of continued hauling across it. Evidence of lost stability shall include pumping or rutting. The Contractor shall also alter hauling equipment or procedures to prevent further damage.

C. COMPACTION AND MOISTURE CONTROL TESTS

1. At least one maximum density and optimum moisture content test shall performed on each material type. The Engineer may request that additional tests be performed if observations indicate that existing test results are not representative of materials being placed in the Work.

Maximum dry density and optimum moisture content tests shall be determined by one of the following methods:

a. Materials with less than 30 percent by weight retained on the U.S. No. 4 sieve shall be determined using ASTM D698 Method A.

b. Materials with 30 percent or more by weight retained on the U.S. No. 4 sieve and less than 30 percent retained on the ¾-inch sieve shall be determined by ASTM D1557 Method D.

c. Materials with 30 percent or more retained on the ¾-inch sieve shall be determined by

ASTM 4253

2. In-place density shall be determined using one of the following methods (i.e., “compaction tests”):

a. ASTM D6938 (nuclear densometer)

b. ASTM D2167 (rubber balloon)

c. ASTM D1556 (sand cone)

3. Field soil moisture content necessary for calculation of dry density can be determined by the following methods:

a. ASTM D2216

b. ASTM D4643

c. ASTM D4944 can be used to expedite field measurements, but tests by one or both of the other methods should be periodically performed to help calibrate the results determined by this method.

d. ASTM D6938 – moisture contents determined using a nuclear densometer will be satisfactory for computation of dry density unless the Engineer indicates otherwise.

4. If any field density test indicates that the materials have not been compacted to the specified dry density, the material represented by that test shall be reworked, or removed and replaced as necessary. At the Contractor’s option, additional tests can be performed to better delineate the areas requiring additional effort. Work shall not proceed until additional testing indicates compliance to the satisfaction of the Engineer.

SOW - 11

LOCAL WORK REQUIREMENTS

1. Utility Outages (including Steam): Submit a Utility Outage Request form a minimum of 10 days prior to the outage. List the work to be performed during the outage, the time required to complete the work, and the crew that will be used. The Government will assist in identifying buildings affected by each outage requested and post outage notices on each affected building. (NOT ANTICPATED)

2. Digging Permit: Before any excavation, alteration or other construction work is begun, the Contractor shall obtain and fully execute a USCG digging permit. The form requires 2 weeks of lead time and extensive coordination with several base agencies, including furnishing all locations, and detailed information and sketches regarding any proposed excavation(s). The contractor is required to coordinate with utilities and other agencies as appropriate. Processing a separate request for each planned excavation is required; each phase of processing the form and its attachments shall be competed at least 48 hours prior to commencing work involving that phase. This form can be obtained from the COR. (REQUIRED, See Attachments)

3. Hot Work Permits: Hot work permits are required for all welding, burning and grinding involved with this project. A current hot work permit must be in the Contractors possession at all times while hot work is being performed at each site. Obtain a hot work permit three days prior to performing the work from the USCG Fire Department by calling (907) 487-5808. (NOT ANTICPATED)

4. Confined Space Entry Permits: The Contractor shall issue and maintain a current Confined Space Entry (CSE) permit for each confined space being entered. The Contractor’s CSE program, permit and field operations shall meet or exceed the requirements in 29 CFR 1910.146, Permit Required Confined Space. A submittal is required for the Contractors CSE program; Confined Space Entry (CSE) program including; entry procedures, forms, procedures and on-site equipment provided for emergency extraction, names of entrants, supervisors and attendants with verification of current training. The contractor’s program shall meet or exceed all requirements for CSE under 29 CFR 1910.146, Permit Required Confined Space. (NOT ANTICPATED)

5. Excavation and Trenching

a. Excavation and open trench work in accordance with current U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1.

b. Provide fencing around the trench and post signs to control traffic.

6. Airport Space Entry: The airport runway and taxiways are secured space. All CONTRACTOR representatives must obtain an Airport ID badge from Robert Green who is the airport manager.

Training is required and should be coordinated with the airport manager. The training is from 1 to 2 hours.

7. Airport Radio Communication: All equipment operators operating within the airport secure space must have VHF radios capable of communicating with the Control Tower. The CONTRACTOR is responsible for determining the detailed requirements of the radio and for providing them for his employees.

8. Airport Object Free Area: No inflexible object higher than 3” above grade may be installed in the Object Free Area of the airport per FAA guidelines. This includes all areas along taxiways and runways.

SOW - 12

AS-BUILT SURVEY AND DOCUMENTS

A. GENERAL

1. All surveying work shall be conducted under the supervision of a state licensed professional land surveyor and shall comply with the standards established herein. Prior to surveying, the surveyor shall meet with USCG staff and contractor to review contract requirements, available information, coordinate systems, accuracy, and AutoCAD and surveying standards.

B. SPECIFIC REQUIREMENTS

1. Survey: Provide a vertical and horizontal survey of all the following:

a. The control points being used, including any new points established for temporary local control.

b. The center of the caps for the new listening stations.

c. The utility marker set for each listening station.

d. Site plainimetrics for easy and precise field location via a minimum of three swing ties.

e. Accuracy shall be per the US Army Corps of Engineers’ EM 1110-1-1005 as follows:

Surveying and Mapping Requirements for Construction and Civil Works Project or Activity Typical

Map Scale 1 in = X ft

Feature Location Tolerance (feet –

RMS)

Control Survey Accuracy

Feature Elevation Tolerance (feet-RMS)

Control Survey Accuracy

Typical Contour Interval

Map Accuracy Class

General Site Plan Features Detail

50 ft 0.1-0.5 ft 3rd-I 0.1-0.3 ft 3rd N/A 1 or 2

Surface/subsurface Utility Detail

50 ft 0.2-0.5 ft 3rd-I 0.1-0.2 ft 3rd N/A 1

2. An as-built drawing shall be submitted for each listening station using the attached template sheet (available digitally) and show the following information, but not be limited thereto:

a. During installation, contractor shall record:

(1) Size of waterline

(2) Depth to top of waterline to nearest 0.25 ft.

(3) Type of waterline – cast iron, ductile iron, etc.

b. Listening station – center of cap shall be surveyed, and include text identifying X-Y coordinates in Lat/Long (WGS 84, DMS) and State Plane (NAD 27, Zone 5, Local).

c. Utility marker – survey center of adjacent utility marker

d. Nearest road, taxiway, apron or visible path - defined by 5 survey shots along each edge at 10 foot intervals.

SOW - 13

e. Buildings – defined by surveying a minimum of two corners.

f. Other nearby utilities such as hydrants (front-center), manholes (center), valves (center), and utility poles (front-center) that will assist in swing-tie locates. Include number in description when available.

g. Survey shots with description and elevation, including all raw data and control points.

h. Swing ties to a minimum of 3 easily identifiable objects and the survey marker.

i. Completed “listening station detail” information.

3. Target computer system. The Contractor shall provide interactive graphic and nongraphic data files that are fully operational on an IBM compatible computer system running AutoCAD 2009/Carlson Survey 2009 software. The files shall be created using a Government-furnished seed file to ensure compatibility with mapping procedures and standards.

4. Utility information. All utilities that are field tied shall be in a format that can be merged into a separate Government-furnished utility drawing. This includes showing manholes, valves, power poles, etc., and connecting lines. Also the attribute information (text) for each utility shall be placed in an appropriate layer. This can include but not be limited to top of rim elevations, invert elevations, pipe size, pipe material, direction, top of valve elevation, etc. All horizontal and vertical control established for ties shall be shown as a symbol with annotation.

5. Map symbols. All symbols shall conform with the National CAD Standard (NCS) and/or the Government-furnished AutoCAD file.

6. Global origin. The Contractor shall use the standard global origin of zero “X” and “Y” coordinates at the lower left corner of the X-Y plane.

7. CAD Drawing requirements. The Contractor shall follow the USCG’s “Architect-Engineer Guide Appendix C: Documentation Standards” for CAD Drawings. In general, all drawings shall be prepared in accordance with this guide and the NCS published by the National Institute of Building Sciences. The current version of the published standard can be obtained from http://www.nationalcadstandard.org/ or the NIBS web site: http://www.nibs.org . Other information can also be obtained via a version of the standard published by the Tri-Services CADD/GIS Technology Center (complies with the National CAD Standard) can be obtained at:

https://cadbim.usace.army.mil/CAD or by contacting the Contracting Officer’s Technical Representative (COTR).

8. The USCG’s Facilities Design & Construction Center Pacific (FD&CC) web site, www.uscg.mil/mlcpac/fdccp/contracting/index.html, contains documentation standards, instructions and downloadable files for providing documents consistent with our practices and procedures.

Drawing files that do not comply with these published standards will be returned for correction at the A-E’s expense, see Paragraph A. Contact the project Contracting Officer for questions and clarifications. The A/E shall show all the information necessary to be consistent with those generally recognized by the construction trades and consistent with the representations as found in Architectural Graphic Standards by Ramsey Sleeper.

9. Text/Font. Most map features constitute either graphics or text and are on separate layers.

However, in some cases, text will be placed on the same level as the graphics. Examples of this would be the “SS” embedded in the line for sanitary sewer or the “W” in the line for water. Text size, layers, fonts, etc. are described in the USCG’s Documentation Standards.

http://www.nationalcadstandard.org/ http://www.nibs.org/ https://cadbim.usace.army.mil/CAD http://www.uscg.mil/mlcpac/fdccp/contracting/index.html

SOW - 14

C. REVIEW/SUBMITTAL:

1. Initial submittal - The Contractor shall provide the Government one (1) completed AutoCAD design file and hard copy at 1” = 50’ for one completed section for review to assure compliance with project specifications. The Government reserves a period of ten (10) calendar days to comment on this submittal.

2. Pre-final submittal - The Contractor shall generate 3D graphic files of utility data (AutoCAD design files) and a 1” = 50’ plot of all files for all areas. Digital data shall be supplied on a CD. The Government reserves a period of ten (10) calendar days to comment on Contractor’s work.

3. Final submittal - The final submittal shall contain all the revisions required as a result of the Government’s pre-final review. The final submittal shall:

a. Utilize the attached AutoCAD template (available digitally).

b. Include 1 CD with AutoCAD drawings and ASCII files (X, Y, Z, Description) that include final adjusted survey points for all raw field data and final coordinate data.

c. 2 copies each of 1” = 50’ plots of individual data files, size 8.5 x 11 inches

d. All field books (or copies) for control points - reduced and checked

e. The survey must be completed within 30 calendar days of final installation of the listening stations.

f. The final drawings must be submitted and completed within 60 calendar days of the survey.

SOW - 15

SPECIAL PROVISIONS

WEATHER

Consider weather conditions and proceed with only those portions of the work that can be undertaken safely and without adversely affecting quality. Keep in mind that 110 mph winds and heavy rains are not uncommon during severe storms and future, in-place work, and/or stored materials must be protected during these and less severe weather conditions. Only time will be granted to the contractor for unusual weather conditions different from the past 5 years.

No work shall be conducted while soils are frozen. Typically this is May 1 – Sept 15, but exceptions may be made upon prior approval by the Engineer.

GENERAL SITE CONDITIONS & SOILS

The construction area is a along existing waterlines, so backfilled soils should be comprised of well-graded fill material containing no large rocks. No excavation of bedrock is anticipated. Most terrain is level, with the exception of a portion of waterline feeding the N9 Nemetz Water Tank. Listening stations were successfully installed in 1993, but most have been significantly damaged by vehicles, heavy equipment, bears, and vandalism.

WORKING HOURS

Normal working hours for this project shall be 0745 to 1630 local time, Monday through Friday. No work shall be accomplished outside of these hours without prior written approval of the Contracting Officer Technical Representative (COTR).

PERMITS &/OR NOTIFICATIONS

Prior to excavating/digging trenches in construction area, Contractor is required to obtain a “dig permit”.

This may be secured though the project’s COTR, who requires a ten (10)-day, prior notification.

All work occurring at the airport requires following strict FAA guidelines including special training, ID badges and direct radio contact with the control tower.

ENVIRONMENTAL REQUIREMENTS

The Contractor is responsible for complying with all federal, state, local, and base environmental regulations, requirements, best management practices, and standard operating procedures. To assist the contractor, the Government will make available a “Contractors Unit Environmental Guide (UEG) at any time. Any failure of the Contractor to take actions necessary to obtain and become familiar with the requirements contained within the UEG will not relieve the Contractor from responsibility for estimating properly the difficulty and cost to successfully perform in accordance with the UEG, or performing the work successfully without additional expense to the Government. The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based upon the information contained within the UEG. Furthermore, the Government assumes no responsibility for the Contractors failure to perform in accordance with applicable federal, state, and local laws, regulations, including any resulting fines, penalties, etc associated with such a failure.

SPECIAL NOTE: This includes sediment control/spill response during construction.

SOW - 16

SECTION B

Listening Station Reinstallation

Estimated Quantities and Pricing

Item Description Estimated Unit Unit Price Amount Totals Quantity

Section 4 Item 4A Demolition 10 Ea $_______ $________ Item 4B New Station 15 Ea $_______ $________ Item 4C Survey 1 LS $_______ $________ Subtotal for 4A-4C $________

Section 8 Item 8A Demolition 4 Ea $_______ $________ Item 8B New Station 4 Ea $_______ $________ Item 8C Survey 1 LS $_______ $________ Subtotal for 8A-8C $________

Section 9 Item 9A Demolition 1 Ea $_______ $________ Item 9B New Station 2 Ea $_______ $________ Item 9C Survey 1 LS $_______ $________ Subtotal for 9A-9C $________

Section 10 Item 10A Demolition 2 Ea $_______ $________ Item 10B New Station 3 Ea $_______ $________ Item 10C Survey 1 LS $_______ $________ Subtotal for 10A-10C $________

Section 11 Item 11A Demolition 0 Ea $_______ $________ Item 11B New Station 6 Ea $_______ $________ Item 11C Survey 1 LS $_______ $________ Subtotal for 11A-11C $________

Section 12 Item 12A Critical Spare 15 Ea $_______ $________ (FAA Utility Mkr) Item 12B 12A Inst. Device 1 Ea $_______ $________ Item 12C Critical Spare (non-FAA Ut Mkr) 15 Ea $_______ $________ Subtotal for 11A-11C $________

Grand Total $________

SOW - 17

Please reference these FARS with full text in the contract:

52.236-2 Differing Site Conditions 52.236-3 Site Investigation

Attach:

Digging Permit Outage Request Site Plan Drawing Details Drawing As-Built Template Drawing