DB wages_NJ34.pdf
PDF 27 KB Posted
- Solicitation number
- HSCG42-11-Q-PFC001
About this file
DB wages_NJ34
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Reference Information form_ shall be completed - return with offer.doc | DOC document | |
| USCG Drawing CM-6130.pdf | ||
| USCG Drawing CM-6131.pdf | ||
| USCG Drawing CM-6128.pdf | ||
| SF1442 - RFQ solic pgs 1-2.doc | DOC document | |
| USCG Drawing CM-6127.pdf | ||
| RFQ solic PFC001 pages 3-FINISH.doc | DOC document | |
| USCG Drawing CM-6129.pdf | ||
| RFI_ Request for Information form.doc | DOC document | |
| USCG spec CMS-1292_Galley head renov.doc | DOC document | |
| USCG Drawing CM-6126.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Decision Number: NJ100034 09/24/2010 NJ34
Superseded General Decision Number: NJ20080034
State: New Jersey
Construction Type: Building
County: Cape May County in New Jersey.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Modification Number Publication Date 0 03/12/2010 1 06/04/2010 2 07/09/2010 3 08/06/2010 4 08/13/2010 5 08/27/2010 6 09/24/2010
ASBE0089-004 07/01/2010
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR ((includes the application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems; also, the application of firestopping material to openings and penetrations in walls, floors, ceilings and curtain walls; also, all lead abatement))......................$ 39.42 22.83
PAID HOLIDAYS:
The last day prior to the Christmas and New Year's Day observed holiday: 4 hrs. pay.
BRNJ0002-013 11/01/2009
10/14/2010http://www.wdol.gov/wdol/scafiles/davisbacon/NJ34.dvb
Rates Fringes
Bricklayer.....................$ 36.70 23.47
Work on high stacks: 22% per hour additional.
BRNJ0007-012 01/01/2009
Rates Fringes
Marble setter...................$ 50.53 24.00
BRNJ0007-013 07/01/2005
Rates Fringes
Terrazzo finisher..............$ 38.37 23.25
BRNJ0007-017 06/01/2008
Rates Fringes
Tile finisher..................$ 32.77 18.15 Tile setter....................$ 37.11 20.40
Tile finisher:
Work grouting all epoxy: $10.00 additional per day.
CARP0006-009 05/01/2009
Rates Fringes
CARPENTER (Scaffold Builder).....$ 39.45 49.75%
The first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter.
CARP0006-010 05/01/2009
Rates Fringes
CARPENTER
Including Acoustical Ceiling Installation, Drywall Hanging, Formwork, Batt and Blown Insulation...$ 39.45 49.75%
CARP0029-006 05/01/2009
Rates Fringes
Soft floor layer...............$ 39.45 49.75%
CARP0715-007 05/01/2009
Rates Fringes
Millwright.....................$ 40.27 49.75%
Work of erection and dismantling of elevators and towers, such as concrete conveyors and temporary material elevators, scaffolding or other structures to be used as scaffolding inside or outside of buildings: the first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter.
* ELEC0351-009 05/03/2010
Rates Fringes
ELECTRICIAN (Teledata Technicians) 15 Voice Data Lines or Less.$ 32.34 68.42% + .50 16 Voice or Data Lines or more and Fiber Optics.......$ 42.36 68.42% + .50
ELEC0351-011 10/05/2009
Rates Fringes
Electricians:
Cable splicer on lead cable.$ 45.33 31.24 Electrician and cable splicer.....................$ 43.17 29.79
ELEV0005-004 01/01/2010
Elevator mechanic..............$ 46.90 20.04
PAID HOLIDAYS:
New Year's Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, the Friday after Thanksgiving Day, and Christmas Day.
PAID VACATION:
Employer contributes 2% of basic hourly rate as vacation pay credit for 6 months to 5 years of service, and 4% for 5 years or more of service.
ENGI0825-017 07/01/2010
Rates Fringes
Power equipment operators:
GROUP 1.....................$ 41.02 25.75
GROUP 2.....................$ 39.43 25.75
GROUP 3.....................$ 37.52 25.75
GROUP 4.....................$ 35.89 25.75
GROUP 5.....................$ 34.18 25.75
Hazardous waste removal work:
Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal protective equipment is required for respiratory, skin and eye protection: 20% per hour additional.
New Year's Day, Washington's Birthday observed, Memorial Day, Independence Day, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day and Christmas Day; provided
1) that the worker works three of the preceding five work days before the holiday; or, the work day before the holiday and the work day after the holiday; and, 2) that the worker works the work day before and the work day after the holiday.
DEFINITION OF GROUPS:
GROUP 1:
Backhoe, Including Backhoe Track; Boom; Concrete Paving Machine; Crane (all types, including overhead and straddle traveling type); Drill (down-the-hole drill, rotary drill, self-propelled hydraulic drill, self-powered drill);
Elevating Grader; Excavator; Front End Loader (5 cu. yd.
and over); Piledriver (length of boom, including length of leads, shall determine premium rate applicable); Trencher
GROUP 2:
Backhoe Loader Combo; Concrete Pumper; Grader/Blade (Finish);
Hoist; Hydraulic Crane, 10 Tons and under; Front End Loader (2 cu. yd. but less than 5 cu. yd.); Scraper; Side Boom
GROUP 3:
Asphalt Spreader; Bulldozer;Compressor(2 or 3) (in Battery) (within 100 ft.); Forklift; Front End Loader (1 cu. yd.
and over but less than 2 cu. yd.); Lull; Man Lift/Outside Elevator; Mechanic; Paver, Asphalt; Roller, Blacktop;
Tractor;
GROUP 4:
Bobcat/Skid Loader; Compressor (Single); Farm Tractor; Front End Loader (under 1 cu. yd.); Hydroseeder; Roller, Grade;
Pump, Hydraulic
GROUP 5:
Oiler
IRON0350-006 07/01/2009
Rates Fringes
Ironworkers:
Reinforcing.................$ 32.97 31.75 Structural and Ornamental...$ 33.97 31.75
LABO0222-006 05/01/2009
Rates Fringes
LABORER
MASON TENDER:
Brick/Cement/Concrete.......$ 28.55 19.42
LABO0222-007 05/01/2009
Rates Fringes
Laborers:
Asphalt Raker, Asphalt Shoveler, Asphalt Spreader, Common or General Laborer, Landscape Laborer, Pipelayer, Power Toole Operator and Screedman...................$ 28.05 19.42
PAIN0021-035 05/01/2009
Rates Fringes
Glazier........................$ 36.64 23.40
Work at 30 ft. above the working surface, or on a swing stage: $1.00 per hour additional.
PAIN0711-018 05/01/2009
Rates Fringes
DRYWALL FINISHER/TAPER...........$ 35.58 17.67
PAIN0711-019 05/01/2009
Rates Fringes
PAINTER (Brush & Roller).........$ 27.72 14.28 PAINTER (Spray)..................$ 30.50 14.28
PLAS0008-007 05/01/2010
Rates Fringes
Plasterer......................$ 32.90 23.35
PLAS0592-036 11/01/2009
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 36.75 24.63
PLUM0322-009 05/01/2010
PIPEFITTER (Including HVAC Pipe Installation)...............$ 42.02 29.74 PLUMBER (Excluding HVAC Pipe Installation)....................$ 42.02 29.74
ROOF0030-027 05/01/2009
Rates Fringes
Roofer
SHINGLES....................$ 23.25 13.77
SLATE AND TILE..............$ 26.25 13.77
ALL OTHER WORK..............$ 30.00 22.70
Mopper, and operator of felt-laying machine: $.50 per hour additional.
Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag dispensing machine is used: $.50 per hour additional.
PAID HOLIDAY:
The last working day before Christmas, to be paid at the rate of four hours pay.
SFNJ0669-006 04/01/2010
Rates Fringes
SPRINKLER FITTER (Fire Sprinklers)......................$ 44.75 19.35
SHEE0027-009 06/01/2009
Rates Fringes
SHEET METAL WORKER (Including HVAC Duct Installation)..........$ 41.61 29.49
TEAM0676-003 05/01/2008
Truck drivers:
Dump Truck Drivers..........$ 26.70 16.485 Off the Road Truck..........$ 27.05 16.485
Hazardous waste removal work:
Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous materials, and when personal protective equipment is required for respiratory, skin and eye protection: $3.00 per hour additional.
Work on a state or federally designated hazardous waste site, where personal protection A, B, C or D is NOT required:
$1.00 per hour additional.
New Year's Day, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Presidential Election Day, Veteran's Day (or the day after Thanksgiving, at the option of the contractor), Thanksgiving Day, the afternoon of the day before Christmas (Dec. 24) provided that the worker works in the morning, and Christmas Day, provided that the worker works or is available for work on at least two days in the week in which the holiday occurs.
BEREAVEMENT PAY:
In case of a death in the worker's immediate famiy (mother, father, wife, husband, children, brother, sister, current mother-in-law, current father-in-law, grandparents), the worker shall be allowed leave not to exceed three (3) days straight-time pay, provided that he or she shall receive no pay unless the day of death and the burial day falls on a regular work day, and not on days off, holidays, vacation, Saturdays or Sundays.
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29 CFR 5.5(a)(1)(ii)).
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in he matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
File details come from the government source that posted it. Updated .