CLIN_List__87_Shaft_Manufacture-Repair_7_15.doc

DOC document 155 KB Posted

Attached to
87' Shafts Manufacture and Repair
Solicitation number
HSCG40-17-Q-19001
Issued by

View the file

Other files

File Type Posted
87-WPB_243_1_4_-_M.pdf PDF
87-WPB_243_1_1_-_M.pdf PDF
87-WPB_243_1_5_-_M.pdf PDF
87-WPB_243_1_2_-_H.pdf PDF
87-WPB_243_50_1_-_-.pdf PDF
87-WPB_243_1_6_-_M.pdf PDF
87-WPB_243_1_3_-_H.pdf PDF
PACKAGING_REQUIREMENTS_Instructions.doc DOC document
P-243-0618_87_Shaft_Man-Repair_-_Nickel_Final_7-15_ds.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM TO STANDARD FORM (SF) 1449 ( BLOCKS 19 – 24

SCHEDULE OF SUPPLIES/SERVICES

PROPULSION SHAFT (NSN: 2010-01-445-7940)

*Note: The hourly rate shall include direct and indirect labor rates, G&A and profit. The estimated number of hours and total cost shown below are intended for evaluation purposes only and may vary based upon the condition of the components as received by Contractor.

SUPPLIES/SERVICES AND PRICES/COSTS FOR:

BASE YEAR (01 April 2017 – 31 March 2018)

ITEM
DESCRIPTION
HOURLY LABOR RATE

(multiply estimated labor hours x hourly rate) = Unit Price

UNIT PRICE
EST QTY
BASE YEAR EXTENDED PRICE
CLIN 0001
Manufacture new propulsion shafts which include material certifications, keys, new shipping container, QA inspection, PP&M and shipping to Baltimore, MD in accordance with specification P-243-0618, section 3.1.
Job
$
10 EA
$
CLIN 0002
For Approval, Certifications of material conformance.
Job
$ NSP
10 EA
$ NSP
CLIN 0003
For Approval, Condition Found Report, Inspection, and Cost Estimate for shaft and shipping crate repair in accordance with specification P-243-0618 section 3.2.
Job
$
25 EA
$
CLIN 0004
Cost to package, pack, mark and deliver to Baltimore, MD any shaft not being repaired in accordance with specification P-243-0618 section 3.2.2.
Job
$
1 EA
$
CLIN 0005
(Optional) Cost - Weld Repairs: General (non-bearing areas) - 3 cubic inch increment (based on 1/8" deep areas to repair, 1" length, 360° undercut as required by MILSPEC).
Job
$
1 EA
$
CLIN 0006
(Optional) Cost - Weld Repairs: Aft bearing repair (entire area) - 18 cubic inch increment (based on 1/16" deep area to repair, full bearing length, 360° around).
Job
$
1 EA
$
CLIN 0007
(Optional) Cost - Weld Repairs: Intermediate bearing repair (entire area) - 12 cubic inch increment (based on 1/16" deep area to repair, full bearing length, 360° around).
Job
$
1 EA
$
CLIN 0008
(Optional) Cold Straightening: Cost estimate (CFR) to cold straighten shafts as necessary in accordance with specification P-243-0618.
Job
$
1 EA
$
CLIN 0009
Cost to blue fit, package, pack, mark, bar-code and ship to Baltimore, MD refurbished propulsion shafts in accordance with specification P-243-0618.
Job
$
25 EA
$
CLIN 0010
(Optional) Cost to manufacture (1) propeller end and (1) coupling end key per specification P-243-0618.
Job
$
25 EA
$
CLIN 0011
For Approval, Final inspection and test report for each manufactured or repaired propulsion shaft in accordance with specification P-243-0618.
Job
$ NSP
35 EA
$ NSP
CLIN 0012
(Optional) Cost to manufacture a new shipping crate as required in accordance with specification P-243-0618 section 5.1.
Job
$
1 EA
$
Total Estimated Amount
$

SUPPLIES/SERVICES AND PRICES/COSTS FOR:

FIRST OPTION YEAR (01 April 2018 – 31 March 2019)

ITEM
DESCRIPTION
HOURLY LABOR RATE

(multiply estimated labor hours x hourly rate) = Unit Price

UNIT PRICE
EST QTY
FIRST OPTION YEAR EXTENDED PRICE
CLIN 1001
Manufacture new propulsion shafts which include material certifications, keys, new shipping container, QA inspection, PP&M and shipping to Baltimore, MD in accordance with specification P-243-0618, section 3.1.
Job
$
10 EA
$
CLIN 1002
For Approval, Certifications of material conformance.
Job
$ NSP
10 EA
$ NSP
CLIN 1003
For Approval, Condition Found Report, Inspection, and Cost Estimate for shaft and shipping crate repair in accordance with specification P-243-0618 section 3.2.
Job
$
10 EA
$
CLIN 1004
Cost to package, pack, mark and deliver to Baltimore, MD any shaft not being repaired in accordance with specification P-243-0618 section 3.2.2.
Job
$
1 EA
$
CLIN 1005
(Optional) Cost - Weld Repairs: General (non-bearing areas) - 3 cubic inch increment (based on 1/8" deep areas to repair, 1" length, 360° undercut as required by MILSPEC).
Job
$
1 EA
$
CLIN 1006
(Optional) Cost - Weld Repairs: Aft bearing repair (entire area) - 18 cubic inch increment (based on 1/16" deep area to repair, full bearing length, 360° around).
Job
$
1 EA
$
CLIN 1007
(Optional) Cost - Weld Repairs: Intermediate bearing repair (entire area) - 12 cubic inch increment (based on 1/16" deep area to repair, full bearing length, 360° around).
Job
$
1 EA
$
CLIN 1008
(Optional) Cold Straightening: Cost estimate (CFR) to cold straighten shafts as necessary in accordance with specification P-243-0618.
Job
$
1 EA
$
CLIN 1009
Cost to blue fit, package, pack, mark, bar-code and ship to Baltimore, MD refurbished propulsion shafts in accordance with specification P-243-0618.
Job
$
25 EA
$
CLIN 1010
(Optional) Cost to manufacture (1) propeller end and (1) coupling end key per specification P-243-0618.
Job
$
25 EA
$
CLIN 1011
For Approval, Final inspection and test report for each manufactured or repaired propulsion shaft in accordance with specification P-243-0618.
Job
$ NSP
35 EA
$ NSP
CLIN 1012
(Optional) Cost to manufacture a new shipping crate as required in accordance with specification P-243-0618 section 5.1.
Job
$
1 EA
$
Total Estimated Amount
$

SUPPLIES/SERVICES AND PRICES/COSTS FOR:

SECOND OPTION YEAR (01 April 2019 – 31 March 2020)

ITEM
DESCRIPTION
HOURLY LABOR RATE

(multiply estimated labor hours x hourly rate) = Unit Price

UNIT PRICE
EST QTY
SECOND OPTION YEAR EXTENDED PRICE
CLIN 2001
Manufacture new propulsion shafts which include material certifications, keys, new shipping container, QA inspection, PP&M and shipping to Baltimore, MD in accordance with specification P-243-0618, section 3.1.
Job
$
10 EA
$
CLIN 2002
For Approval, Certifications of material conformance.
Job
$ NSP
10 EA
$ NSP
CLIN 2003
For Approval, Condition Found Report, Inspection, and Cost Estimate for shaft and shipping crate repair in accordance with specification P-243-0618 section 3.2.
Job
$
10 EA
$
CLIN 2004
Cost to package, pack, mark and deliver to Baltimore, MD any shaft not being repaired in accordance with specification P-243-0618 section 3.2.2.
Job
$
1 EA
$
CLIN 2005
(Optional) Cost - Weld Repairs: General (non-bearing areas) - 3 cubic inch increment (based on 1/8" deep areas to repair, 1" length, 360° undercut as required by MILSPEC).
Job
$
1 EA
$
CLIN 2006
(Optional) Cost - Weld Repairs: Aft bearing repair (entire area) - 18 cubic inch increment (based on 1/16" deep area to repair, full bearing length, 360° around).
Job
$
1 EA
$
CLIN 2007
(Optional) Cost - Weld Repairs: Intermediate bearing repair (entire area) - 12 cubic inch increment (based on 1/16" deep area to repair, full bearing length, 360° around).
Job
$
1 EA
$
CLIN 2008
(Optional) Cold Straightening: Cost estimate (CFR) to cold straighten shafts as necessary in accordance with specification P-243-0618.
Job
$
1 EA
$
CLIN 2009
Cost to blue fit, package, pack, mark, bar-code and ship to Baltimore, MD refurbished propulsion shafts in accordance with specification P-243-0618.
Job
$
25 EA
$
CLIN 2010
(Optional) Cost to manufacture (1) propeller end and (1) coupling end key per specification P-243-0618.
Job
$
25 EA
$
CLIN 2011
For Approval, Final inspection and test report for each manufactured or repaired propulsion shaft in accordance with specification P-243-0618.
Job
$ NSP
35 EA
$ NSP
CLIN 2012
(Optional) Cost to manufacture a new shipping crate as required in accordance with specification P-243-0618 section 5.1.
Job
$
1 EA
$
Total Estimated Amount
$

SUPPLIES/SERVICES AND PRICES/COSTS FOR:

THIRD OPTION YEAR (01 April 2020 – 31 March 2021)

ITEM
DESCRIPTION
HOURLY LABOR RATE

(multiply estimated labor hours x hourly rate) = Unit Price

UNIT PRICE
EST QTY
THIRD OPTION YEAR EXTENDED PRICE
CLIN 3001
Manufacture new propulsion shafts which include material certifications, keys, new shipping container, QA inspection, PP&M and shipping to Baltimore, MD in accordance with specification P-243-0618, section 3.1.
Job
$
10 EA
$
CLIN 3002
For Approval, Certifications of material conformance.
Job
$ NSP
10 EA
$ NSP
CLIN 3003
For Approval, Condition Found Report, Inspection, and Cost Estimate for shaft and shipping crate repair in accordance with specification P-243-0618 section 3.2.
Job
$
10 EA
$
CLIN 3004
Cost to package, pack, mark and deliver to Baltimore, MD any shaft not being repaired in accordance with specification P-243-0618 section 3.2.2.
Job
$
1 EA
$
CLIN 3005
(Optional) Cost - Weld Repairs: General (non-bearing areas) - 3 cubic inch increment (based on 1/8" deep areas to repair, 1" length, 360° undercut as required by MILSPEC).
Job
$
1 EA
$
CLIN 3006
(Optional) Cost - Weld Repairs: Aft bearing repair (entire area) - 18 cubic inch increment (based on 1/16" deep area to repair, full bearing length, 360° around).
Job
$
1 EA
$
CLIN 3007
(Optional) Cost - Weld Repairs: Intermediate bearing repair (entire area) - 12 cubic inch increment (based on 1/16" deep area to repair, full bearing length, 360° around).
Job
$
1 EA
$
CLIN 3008
(Optional) Cold Straightening: Cost estimate (CFR) to cold straighten shafts as necessary in accordance with specification P-243-0618.
Job
$
1 EA
$
CLIN 3009
Cost to blue fit, package, pack, mark, bar-code and ship to Baltimore, MD refurbished propulsion shafts in accordance with specification P-243-0618.
Job
$
25 EA
$
CLIN 3010
(Optional) Cost to manufacture (1) propeller end and (1) coupling end key per specification P-243-0618.
Job
$
25 EA
$
CLIN 3011
For Approval, Final inspection and test report for each manufactured or repaired propulsion shaft in accordance with specification P-243-0618.
Job
$ NSP
35 EA
$ NSP
CLIN 3012
(Optional) Cost to manufacture a new shipping crate as required in accordance with specification P-243-0618 section 5.1.
Job
$
1 EA
$
Total Estimated Amount
$

SUPPLIES/SERVICES AND PRICES/COSTS FOR:

FOURTH OPTION YEAR (01 April 2021 – 31 March 2022)

ITEM
DESCRIPTION
HOURLY LABOR RATE

(multiply estimated labor hours x hourly rate) = Unit Price

UNIT PRICE
EST QTY
FOURTH OPTION YEAR EXTENDED PRICE
CLIN 4001
Manufacture new propulsion shafts which include material certifications, keys, new shipping container, QA inspection, PP&M and shipping to Baltimore, MD in accordance with specification P-243-0618, section 3.1.
Job
$
10 EA
$
CLIN 4002
For Approval, Certifications of material conformance.
Job
$ NSP
10 EA
$ NSP
CLIN 4003
For Approval, Condition Found Report, Inspection, and Cost Estimate for shaft and shipping crate repair in accordance with specification P-243-0618 section 3.2.
Job
$
10 EA
$
CLIN 4004
Cost to package, pack, mark and deliver to Baltimore, MD any shaft not being repaired in accordance with specification P-243-0618 section 3.2.2.
Job
$
1 EA
$
CLIN 4005
(Optional) Cost - Weld Repairs: General (non-bearing areas) - 3 cubic inch increment (based on 1/8" deep areas to repair, 1" length, 360° undercut as required by MILSPEC).
Job
$
1 EA
$
CLIN 4006
(Optional) Cost - Weld Repairs: Aft bearing repair (entire area) - 18 cubic inch increment (based on 1/16" deep area to repair, full bearing length, 360° around).
Job
$
1 EA
$
CLIN 4007
(Optional) Cost - Weld Repairs: Intermediate bearing repair (entire area) - 12 cubic inch increment (based on 1/16" deep area to repair, full bearing length, 360° around).
Job
$
1 EA
$
CLIN 4008
(Optional) Cold Straightening: Cost estimate (CFR) to cold straighten shafts as necessary in accordance with specification P-243-0618.
Job
$
1 EA
$
CLIN 4009
Cost to blue fit, package, pack, mark, bar-code and ship to Baltimore, MD refurbished propulsion shafts in accordance with specification P-243-0618.
Job
$
25 EA
$
CLIN 4010
(Optional) Cost to manufacture (1) propeller end and (1) coupling end key per specification P-243-0618.
Job
$
25 EA
$
CLIN 4011
For Approval, Final inspection and test report for each manufactured or repaired propulsion shaft in accordance with specification P-243-0618.
Job
$ NSP
35 EA
$ NSP
CLIN 4012
(Optional) Cost to manufacture a new shipping crate as required in accordance with specification P-243-0618 section 5.1.
Job
$
1 EA
$
Total Estimated Amount
$

File details come from the government source that posted it. Updated .