USCG 270' WMEC and USCGC EAGLE Specification for Procurement of Centrifugal Oily Water Separator System Dated 6/24/15
View the file
Other files
| File | Type | Posted |
|---|---|---|
| D-084-0481-OWS__Pres Pkg Marking_Requirements.pdf | ||
| Past_Performance_Questionnaire_-_OWS.doc | DOC document | |
| OWS_Solicitation.docx | DOCX document | |
| SF1449-OILY_WATER_SEPARATION_SYSTEM.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JUN 25, 2015
Specification for 270 WMEC Oily Water Separator System
USCG 270 FOOT MEDIUM ENDURANCE CUTTERS AND USCGC EAGLE
SPECIFICATION FOR PROCUREMENT OF CENTRIFUGAL OILY WATER SEPARATOR SYSTEM
June 24, 2015
Developed By:
Joanna Skaredoff
270 WMEC CLASS & CGC EAGLE SPECIFICATION FOR
OILY WATER SEPARATOR SYSTEM
Table of Contents
1.0 SCOPE
1.1 General
1.2 GFE, GFM, and GFP
1.3 GFI
2.0 APPLICABLE DOCUMENTS
2.1 Coast Guard Drawings
2.2 Coast Guard Publication
2.3 Other Documents
2.4 Order of Precedence
3.0 REQUIREMENTS
3.1 OWS System and Warranty
3.2 Commissioning Services
3.3 Training
3.4 Spare Parts
3.5 Technical Services
| 4.0 | NOTES |
| 4.1 | Document Sources |
1.0
SCOPE
1.1 General - This specification covers the requirements for the procurement of a new centrifugal Oily Water Separator (OWS) system to replace the existing gravity OWS system on the 270-FT WMEC Class cutters and CGC EAGLE. The purpose of the Oily Water Separator is to process oily water in accordance with regulatory body requirements. Processed oil will be discharged to an onboard waste oil storage tank. Processed water will either be discharged overboard if less than 15 PPM and beyond 12 NM, or will be re-circulated back to an oily water storage tank.
1.1.1 Contractor shall supply centrifugal Oily Water Separator (OWS) system with warranty.
1.1.2 Contractor shall commission newly installed centrifugal Oily Water Separator system.
1.1.3 Contractor shall provide training.
1.1.4 Contractor shall provide spare parts.
1.1.5 Contractor shall provide technical service.
1.2 Government Furnished Equipment (GFE), Government Furnished Material (GFM) and Government Furnished Property (GFP) – None
1.3 Government Furnished Information (GFI) – As noted in Section 2.0.
2.0 REFERENCES
2.1 Coast Guard Drawings - The following specifications and standards form a part of this specification to the extent specified herein.
a. Coast Guard Drawing 901 WMEC 593-009, Rev H, Oily Bilge A&D
b. Coast Guard Drawing 905 WMEC 593-009, Rev B, Oily Bilge A&D
c. Coast Guard Drawing 327 WIX 4823-004, Rev -, OWS System Operating Instructions and Diagrams
2.2 Coast Guard Publications - The following specifications and standards form a part of this specification to the extent specified herein.
a. Coast Guard Commandant Instruction (COMDTINST) M9085.1C, Naval Engineering Computer Aided Design Standards.
b. CGTO PG-85-00-230-S, USCG Planned Maintenance System Development Process GuideD-083-0351, Rev -, Dated 1/00, Data for Provisioning
c. Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), General Requirements
d. Surface Forces Logistics Center Standard Specification 0085 (SFLC Std Spec 0085), General Requirements for Drawings
e. Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Welding and Allied Processes
2.3 Other Documents - The following specifications and standards form a part of this specification to the extent specified herein.
2.3.1 Federal Standards
a. 46 Code of Federal Regulations, Subchapter 162.050, Pollution Prevention Equipment
b. 46 Code of Federal Regulations, Subchapter 050-37, Vibration Test
2.3.2 International Maritime Organization (IMO)
a. IMO Resolution MEPC 107.49, Revised Guidelines and Specifications for Pollution Prevention Equipment for Machinery Space Bilges of Ships.
2.3.3 Institute of Electrical and Electronics Engineers (IEEE)
a. IEEE Standard 45 (2002), Recommended Practice for Electrical Installations on Shipboard.
2.3.4 Military Specifications
a. MIL-DTL-24643C, Cables, Electrical, Low Smoke Halogen-Free, For Shipboard Use, General Specification
2.3.5 National Electrical Manufacturers Association (NEMA)
a. NEMA 250 (2008), Enclosures for Electrical Equipment (1000 Volts Maximum)
2.4 Order of Precedence – In the event of a conflict between the text of this specification and the references cited herein, this specification shall take precedence. However, nothing in this document supersedes applicable laws and regulations unless a specification exemption has been obtained. The Contractor shall notify the Contracting Officer (KO) in writing for a resolution of any ambiguity or conflict found in these specifications.
3.0 REQUIREMENTS
3.1 Oily Water Separator System - The Contractor shall provide a new IMO certified marine grade centrifugal Oily Water Separator (OWS) system to replace the existing gravity Oily Water Separator system on each 270-FT WMEC Class cutter and CGC EAGLE. Any components, materials or services subcontracted for this procurement shall be the responsibility of the Contractor. The factory assembled and tested OWS must be a stand-alone unit equipped with a Control Panel, Oil Content Detector/Monitor and electric heater (if required for 270-FT WMEC class) or Steam heater (if required for EAGLE).
3.1.1 Standards - New equipment shall meet the requirements of Marine Environment Protection Committee Resolution, MEPC 107(49), of the International Maritime Organization (IMO), and 46CFR 162.050 by reducing oil content in discharged bilge water to 15 PPM (threshold) or less (objective).
3.1.2 Oil Content Detection/Monitor and Automatic Discharge Selection
3.1.2.1 Each OWS must be equipped with an Oil Content Detector/Monitor. The purpose of the Oil Content Detector/Monitor must be to monitor the amount of oil in the water that is flowing from the Oil Water Separator and to automatically open a valve to discharge the water overboard, if the water contains less that 15 PPM of oil or to direct the water flow back to the oily water holding tank by opening a valve, if the oil content is greater than 15 PPM.
3.1.2.2 The Oil Content Detector/Monitor must provide display of the measured oil content of the effluent in PPM.
3.1.3 Capacity – The OWS shall have a throughput capacity of 500 liter per minute for 270 class and 200 liter per hour for EAGLE.
3.1.4 Materials, Parts, and Process – Except as required herein, materials, parts and processes (such as, but not limited to, prohibited materials, metals or coatings, threaded parts and fastening devices, electrical insulation, soldering and brazing) shall be in accordance with IEEE-STD-45.
3.1.5 Environmental Design Conditions
a. Operating Temperature: -18°C to +55°C (0°F to 130°F)
b. Storage Temperature: -40°C to +75°C (-40°F to 167°F)
c. Humidity: 0% to 90%, relative, non-condensing
3.1.6 Equipment Enclosures - Enclosures for all equipment shall be in compliance with NEMA Type 4 in accordance with NEMA 250 or equivalent IP Code specified in IEC 60529.
3.1.7 Workmanship
3.1.7.1 All workmanship, materials and components shall be of the highest quality in every aspect of new manufacture and in full conformance with this specification. No use of used materials or components is permitted.
3.1.7.2 Welded parts shall be free of weld splatter, porosity, undercuts and other defects.
3.1.7.3 All parts shall be free of burrs and sharp or rugged edges.
| 3.1.8 | Departure from Specification - Departure from the Specifications will not be | allowed unless there is a direct benefit to the Government. | ||
| 3.1.8.1 If the Contractor finds it necessary to change or depart from the applicable | requirements he must request permission to do so from the Contracting | Officer (KO) at the earliest possible time. | ||
| 3.1.8.2 Requests by the Contractor for changes shall clearly describe the changes | proposed and the reason for and the advantages of the changes proposed. | Also to be included is a detailed list of additional costs or savings (if any) | that would result. | |
| 3.1.8.3 If the proposed change involves the substitution of another material or | method for one specifically required, the complete specification(s) | covering the requested method or material shall be submitted. | ||
| 3.1.9 | Design Improvements – Proposals submitted for design improvements to equipment or process to simplify or improve reliability and/or maintainability, and to improve performance, are encouraged. Such proposals may be submitted at any time during the contract using the specification departure procedures as outlined herein. | |||
| 3.1.10 | Performance Requirements – The Oily Water Separator equipment shall be a centrifugal type approved to IMO Resolution MEPC 107.49. | |||
| 3.1.11 | Ship Motion – Equipment shall operate satisfactorily when permanently inclined or during temporary inclinations as required below. | |||
| 3.1.11.1 | Heel/List Requirement - The equipment shall be designed to operate in each plane that forms an angle of 22.5 degrees with the plane of its normal operating position as required by 46CFR162.050-21. | |||
| 3.1.11.2 | Maximum Vertical/Horizontal Motion Requirement - The equipment shall be designed to operate with the motions and vibrations required by 46CFR162.050-37. | |||
| 3.1.12 | Mean Time Between Failures (MTBF) – The calculated MTBF shall be not less than 5,000 hours which is the estimated hours of operation annually. The Contractor shall provide a reliability prediction including historical data to prove the design of the Oily Water Separator is adequate. The reliability of the OWS shall be presented in terms of MTBF. The Contractor shall provide the environmental conditions and factors under which the MTBF is defined. The reliability prediction shall be provided with the Contractor’s proposal submission. | |||
| 3.1.13 | Oily Water Separator Physical Characteristics – The Oily Water Separator physical size shall not exceed the dimensional data below: | |||
| 3.1.13.1 270’ WMEC Dimensional data (not to exceed) |
a. 1530 mm x 920 mm
b. Height: 1700 mm
3.1.13.1 EAGLE Dimensional and weight data (not to exceed)
a. 1600 mm x 800 mm
b. Height: 1950 mm
c. Dry weight 700 lbs
The Oily Water Separator shall be designed in a manner which allows it to be permanently attached to the ship’s structure and properly oriented. The Oily Water Separator shall include all necessary hold down hardware required to permanently attach it to the ship’s structure.
| 3.1.14 | Electric Power – The OWS and associated equipment shall operate on the following power requirements. |
| 3.1.14.1 | 270’ WMEC units will receive 450VAC plus or minus 5VAC, 60Hz, three phase ungrounded power from an existing spare 150 amp breaker in the ship’s service power panel number 1. All other power requirements are in accordance with IEEE-STD-45 (2002) Recommended Practice for Electrical Installations on Shipboard. |
| 3.1.14.2 | CGC EAGLE unit will receive 440 VAC, 60Hz, three phase ungrounded power from an existing spare 25 amp breaker in the ship’s service power panel 4-68-2. All other power requirements are in accordance with IEEE-STD-45 (2002) Recommended Practice for Electrical Installations on Shipboard. |
| 3.1.15 | Interface With Coast Guard Machinery Control System – The Oily Water Separator controls and Oil Content Detection/Monitor shall interface with the Coast Guard Machinery Control System (CGMCS) installed on the 270 WMEC cutters. |
| 3.1.15.1 | This interface shall provide a dry contact to indicate the Running status of the OWS system. |
| 3.1.15.2 | This interface shall provide a dry contact to indicate the Fault status of the OWS system. |
| 3.1.15.3 | This interface shall provide a dry contact to indicate whether the OWS is running in Overboard or Recirculate Mode. |
| 3.1.15.4 | This interface shall accept a Stop command in the form of a dry contact. |
| 3.1.15.5 | This interface shall provide a 4-20mA or 0-10VDC signal to indicate the Oil Concentration (in PPM) of the OWS effluent. |
| 3.1.15.6 | The dry contacts that comprise this interface shall be rated for at least 2 Amps |
| 3.1.15.7 | The dry contacts that comprise this interface shall be rated for at least 30 VDC. |
| 3.1.16 | Technical Documentation – Content for technical documentation (technical publications and drawings) to be provided shall be as defined below and as defined in SFLC Document D-086-0508. The Contractor shall provide data rights documentation that allows publication on the Coast Guard Intranet and distribution to the Fleet. Quantities shall be provided as specified herein. Additional requirements for the content of technical documentation shall be as identified in paragraph 3.4.1 (Engineering Data for Provisioning (EDFP)). |
| 3.1.16.1 Technical Publications |
3.1.16.1.1 The Contractor shall develop and provide a Technical Publication for the installation, operation and maintenance of the new oily water separator system and components.
3.1.16.1.2 Draft Deliverable – One (1) paper and one (1) electronic draft copy of the Technical Publication shall be submitted for review and approval. Comments will be returned along with the assignment of a Coast Guard Document number.
3.1.16.1.3 Final Deliverable – One (1) paper (per ship set) and one (1) electronic copy of the Coast Guard approved Technical Publication shall be provided to the Coast Guard Contracting Officer or his/her representative. Electronic files shall include any source files used to produce the Technical Publication.
3.1.16.1.4 Each technical publication shall provide, as a minimum, the necessary information to provide instructions to operate and maintain the equipment at the organizational level. This includes a full description of system start-up, operation, shutdown, safety and emergency procedures. The manuals shall contain information concerning checkout, inspection, preventive and corrective maintenance, calibration, adjustment, troubleshooting, replacement of parts, repair, and use of tools and test equipment in accordance with the maintenance concept. The following sections, as a minimum, shall be included:
| a. General Information and Safety Precautions - Identify and | describe the purpose, interconnection, and functional use of | the equipment | including safety issues. | ||||
| b. Theory of Operation – Identify and describe the theory of | operation of the equipment and all components. | ||||||
| c. System Description – Identify and describe the purpose and | functional operation of the equipment and components. | ||||||
| d. Component Description - Include sufficient information to | identify and describe all major system components. | ||||||
| e. Functional Description - Discuss the control philosophy used | in the system design and provide a detailed description of the | controls used. | |||||
| f. Installation – Include drawings and information sufficient to | install or remove the equipment, including handling | procedures, special tools, access clearances and supporting | services (crane, welding, etc.) required. The locations of | lifting eyes and special rigging shall be discussed. | |||
| g. Operating Procedures - Identify all normal system operations | and evolutions which involve personnel. Detailed step-by- | step operating procedures for these normal operations and | evolutions shall be provided. | ||||
| h. Maintenance Procedures - Identify all preventive | maintenance and corrective maintenance operations and | evolutions, which involve personnel. Detailed step-by-step | procedures shall be provided. | ||||
| i. Emergency Procedures - Identify conditions requiring | emergency operations and provide procedures to be followed | in the event of | their occurrence. Emergency operation is | defined as operation under conditions of system malfunction | or failure such as loss of power, component failure, physical | damage, or fire. Detailed step-by-step procedures for | dealing with emergencies shall be provided. |
| j. Troubleshooting Procedures – Provide detailed instructions | for locating an equipment malfunction including | troubleshooting procedures; troubleshooting diagrams; | maintenance schematics and logic diagrams. | ||||
| k. Equipment Limitations, Precautions, Set Points - Identify all | system operational limitations. State all precautions to be | taken during normal operation to preclude potentially unsafe | conditions. List system operation set points, which represent | the normal operation of the system. | |||
| l. Illustrated Parts Lists - Identify parts associated with the equipment. An exploded illustration shall show the location of the parts. The parts list shall identify the piece part of the illustration, quantity installed, nomenclature, designation, original manufacturer and manufacturer’s part number. Part numbers are not required for common hardware available from multiple sources, provided that | adequate descriptive data is provided. Parts data listed in the technical manual shall be the same as listed on the Provisioning Technical Documentation. If metric system components are provided, they shall be so noted. |
m. Spare Parts – The spare parts lists and recommendations developed for the Integrated Logistic Support (ILS) shall be included in the publication.
n. Appendices (as necessary) – Provide tabular appendices for technical data and literature, repair and overhaul information on major subassemblies and supportable components such as motors, motor controllers, gearboxes,
3.1.16.2 Format
| 3.1.16.2.1 | Text - Text shall be single-column and single-spaced, with | one inch left-hand margins and unjustified right-hand | margins. Text size shall be 12 point in a standard, easily | readable font. Titles and headers shall follow a heading | style hierocracy. Footnotes, notes and other side information | shall be 8 point or larger. | |
| 3.1.16.2.2 | Paper Size – Page size shall be 8-1/2 inches by 11 inches. | Text shall be printed on both sides of the paper, head to | head. Pages shall be three-hole punched with 3/8 inch | diameter holes. | |||
| 3.1.16.2.3 | Prefix - The manual shall have a title page showing the publication title; Technical Publication Number (USCG assigned); hull applicability; the manufacturer’s name; the system or equipment designation and model number; and the equipment serial numbers. The publication shall have a list of effective pages, table of contents, list of illustrations, list of tables, change record Sheet, a listing of applicable abbreviations and acronyms, and a safety summary. | ||||||
| 3.1.16.2.4 | Page Numbers – Pages shall be numbered sequentially within a publication. Page numbers shall be shown at the bottom center. The bottom unbound corner shall be reserved for a change identifier. For fold-in pages, the page number shall be shown at the bottom right hand corner, together with the change identifier. | ||||||
| 3.1.16.2.5 | Dividers - Major chapters, sections, and appendices shall be clearly identified with tab dividers. | ||||||
| 3.1.16.2.6 | Illustrations – Illustrations/figures and parts lists shall be included in the manuals. The maximum illustrations size within the technical publication shall be ANSI size B, 11”h x 17”w, which shall be accordion folded. Prints of larger illustrations sizes shall be reduced, as necessary, to fit the 17-inch wide fold-in, and shall remain legible. | ||||||
| 3.1.16.2.7 | Complete functional block diagrams and schematic diagrams shall be provided for electrical and electronic circuits. Controller schematics shall be provided in the technical publication for the entire electrical system including ladder diagrams. | ||||||
| 3.1.16.2.8 | The Contractor shall provide the proposed manuals for approval by the Government. Comments will be returned along with the assignment of a national stock number and a Coast Guard Technical Publication number, for incorporation into the title page and cover. | ||||||
| 3.1.16.2.9 | Deliverables: The Contractor shall submit one electronic copy for each DRAFT deliverable manual, for review and comment. The Contractor shall provide one electronic copy of each FINAL approved manual. The Government will be responsible for distribution of the completed manuals. | ||||||
| 3.1.16.2.10 | Electronic Format - Technical Publications and Amendment Change packages shall be developed in electronic format, using MICROSOFT OFFICE tm compatible electronic file format, with imbedded text and graphic files. Drawings shall be developed and delivered in AutoCAD tm version 2002 (.dwg | format). All preprinted publications and documents not developed and delivered in Microsoft Office, shall be scanned in and delivered as an unlocked Portable Document Format (.pdf) file. The final deliverable publication may be a compilation of the above formats. The electronic publication shall have Bookmarks to the Table of Contents, List of Tables, List of Illustrations, Chapters and Appendices, to permit ease of navigation by the end users. All Electronic reproducible files (PDF, Office, AutoCAD tm, and so forth) shall be delivered in CD format with electronic file names and revisions clearly identified. | |||||
| 3.1.16.2.11 | In addition, the Contractor shall, over the life of this contract, provide updates to the technical manuals, drawings, and so forth whenever there is a change/update to the equipment. Deliverable requirements are the same as for initial manuals above. Distribution of manual updates will be the responsibility of the government. At the completion of the contract, the contractor shall provide a final update for each manual to record final configurations of equipment and all serial numbers. All technical publications shall become the property of the Government and the Government shall have unlimited production rights. | ||||||
| 3.1.17 | Tests, Inspections, and Reports - The Coast Guard reserves the right to witness any or all tests performed. The Contractor shall retain records of all tests and submit them to the USCG COR. A report on the following tests shall be submitted which shall include description of test set-up and procedure, photographs from two adjacent sides, logs of times for start and finish and any measurements taken during the test. | ||||||
| 3.1.18 | Notifications and Inspections – The Contractor shall notify the COR in writing at least fourteen (14) calendar days prior to the performance of any inspections or testing. | ||||||
| 3.1.19 | Warranty - The Contractor shall provide a minimum of a one-year commercial warranty, from date of installation. The Contractor shall provide a minimum of two years commercial storage warranty from date of delivery. | ||||||
| 3.1.20 | Delivery | ||||||
| 3.1.20.1 | Preservation, Packaging, and Marking | ||||||
| 3.1.20.1.1 | The Oily Water Separator system components shall be preserved, packaged and marked for shipping as an Equipment Unit in accordance with SFLC-D-084-0481. The Oily Water Separator system components shall be packaged in a minimum number of shipping containers suitable for shipment to the Government as directed, temporary storage uncovered in the weather, and then reshipment by the Government (within CONUS) to the installation location if required. | ||||||
| 3.1.20.1.2 | Parts supplied under this contract shall be preserved, packaged and marked for shipping as Parts in accordance with SFLC-D-084-0481. | ||||||
| 3.1.20.1.3 | The Contractor shall prepare a Preservation, Packaging and Marking Plan in accordance with SFLC-D-084-0481. The plan shall be provided to the Government Quality Inspector prior to the preservation, packaging and marking of the first Oily Water Separator system delivery order. The plan shall discuss the proposed preservation and packaging methods, and spare parts. The plan shall also have draft samples of all proposed markings. | ||||||
| 3.1.20.1.4 | The intent is for the Quality Inspector to review and advise the Contractor of potential issues, prior to the preservation, packaging and marking of the first units. The Government reserves the right to inspect the preservation, packaging and marking of all units and parts, prior to release for shipment. | ||||||
| 3.1.20.1.5 | A copy of the packing list for each container shall be prepared and electronically forwarded to the Contracting Officer for use as a check-off sheet by receiving personnel. A copy of the list shall also be posted on the outside of Box 1 inside a waterproof, clear plastic envelope. | ||||||
| 3.1.21 | Shipment | ||||||
| 3.1.21.1 | Each Oily Water Separator system shall be delivered FOB destination. | ||||||
| 3.1.21.2 | Price for the Oily Water Separator system shall include all freight cost for delivery to the location of USCG’s designation in the Contract. | ||||||
| 3.2 | Commissioning | ||||||
| 3.2.1 | The Contractor shall provide Commissioning Services to commission the equipment. The government reserves the right to install Oily Water Separator systems without contractor support. Commissioning Services shall include a technical representative to provide technical assistance to the independent installing activity to ensure that the equipment is installed correctly and to observe and/or participate in the shipboard Installation Testing. | ||||||
| 3.2.1 | The Contractor shall prepare a Completion or Waiver of Commissioning Services release document, for signature by the Commanding Officer of the respective cutter, to document completion of services or waiver of same. The Technical Representative shall obtain a release signature before departure. | ||||||
| 3.2.3 | The Contractor shall forward a copy of the signed release document to the Contracting Officer, with a Commissioning Technical Report. | ||||||
| 3.3 | Training - The Contractor shall provide a one day on-site training of the ship’s personnel for each installed Oily Water Separator system. Training shall comprise operation and maintenance of the new equipment. The contractor shall provide a course document or syllabus to the USCG for review 60 days prior to conducting the first training. The training shall include at a minimum but is not limited to: |
a. Hands on training
b. Operational theory
c. Review of maintenance documentation
d. Review of start-up and operational procedures
e. Safety
f. Settings and adjustments
g. Interpretation of displayed sensor data
h. Emergency procedures
i. Troubleshooting and fault isolation
3.3.14.1 The location of training will be onboard the cutter receiving the installation.
| 3.3.14.2 | Training materials will be limited to the onboard technical documentation provided for the new equipment plus any additional training documents which will be provided by the Contractor and included in the training. |
| 3.3.14.3 | The Contractor shall prepare and sign a statement regarding the completion of training. The Contracting Officer Representative (COR) or his/her representative shall obtain a release signature before departure of the contractor or his/her representative. The Contractor shall forward a copy of the signed release document to the Contracting Officer (KO). |
3.4 Spare Parts
3.4.1 Integrated Logistics Support – The Contractor shall provide the following logistical support and information for the Oily Water Separator system. Revised documentation in response to the Government’s initial review shall be deliverable prior to any subsequent OWS system deliveries. Modifications made to the equipment provided during the term of the contract must be accompanied by updates of all the following that relate to those changes.
| 3.4.1.1 | Engineering Data for Provisioning (EDFP) - The Contractor shall provide Engineering Data for Provisioning (EDFP) including technical manuals, drawings, and specifications in accordance with SFLC Document D-083-0351. The EDFP shall include a parts list containing all of the installed parts, the original equipment manufacturer (OEM), OEM part or assembly numbers, the OEM’s name and address, the OEM’s cage code, quantity used in each equipment, and shall be keyed to the provided drawings. All spare parts necessary for overhaul of a unit shall be identified in the printed technical documents supplied. | ||
| 3.4.1.2 | Recommended Spare Parts List - The Contractor shall provide with the EDFP/PTD a recommended spare parts list for onboard repair parts (OBRP) and stock system parts. The spare parts list shall list applicable manufacturer’s maintenance tasks for each line item (both preventive and corrective). | ||
| 3.4.1.2.1 Onboard Spare Parts – Onboard spare parts are items that unit | personnel can replace without additional special tools or technical | support. | |
| 3.4.1.2.2 System Stock - System stock shall be the long lead time materials | (materials with lead times over 90 days) and manufacturer designated | critical items. |
3.4.1.2.3 The spare parts list shall include spare parts prices and their lead times at the time of delivery of the equipment.
3.4.1.2.4 The OBRP shall be sufficient to perform shipboard maintenance on the equipment for two years.
3.4.1.2.5 The spare parts list shall be quantified into the number of spares needed per the equipment installed.
3.4.1.2.6 OEM Maintenance Requirements - The Contractor shall provide OEM maintenance recommendations, in addition to the maintenance recommendations in the Technical Publication, to allow for USCG development of Maintenance Procedure Cards. Guidance for providing this information can be found in Chapter 5 of the USCG Planned Maintenance System Development Process Guide, CGTO PG-85-00-230-S. The Contractor shall identify at least the following line items:
a. Applicable Maintenance Task Code
b. Maintenance Procedure Title
c. Maintenance Procedure Interval
d. Maintenance Procedure Description
e. Maintenance Procedure Sequenced Tasks
f. Maintenance Procedure
g. Maintenance Procedure Task Type
h. Associated Parts Logistics Code Number
i. Associated Parts Name
j. Associated Parts Part Number
k. Quantity of Parts per Maintenance Task
l. Associated Parts Unit of Issue
m. Associated Parts Shelf Life
n. Associated Parts Unit Price
o. Special Tools and Equipment Nomenclature
p. Special Tools and Equipment Cage
q. Special Tools and Equipment PN/NSN Task Descriptions
3.5 Technical services - The Contractor shall provide a qualified Oily Water Separator (OWS) technician, who is expert in all aspects of the Oily Water Separator and all associated ancillary systems.
| 3.5.1 Tech Rep. | ||||
| 3.5.1.1 The Contractor shall ensure the Tech Rep is a certified representative of the | selected Oily Water Separator manufacturer. | |||
| 3.5.1.2 The Contractor shall submit the Tech Rep’s name, resume and OEM letter | of certification to the COR. | |||
| 3.5.1.3 An additional day rate for any potential future field service support required | after commissioning of the system, outside of required warranty work, shall | be provided. The quoted rate shall be good for one year after installation of | the first Oily Water Separator system. |
3.5.2 Work period - The Contractor shall make available an on-site Tech Rep for a period of 12 months during the base year and each option year. The Tech Rep shall be available up to 40 hours weekly within core hours work hours Monday thru Friday, with the exception of Federal holidays. The number of hours and period of performance shall be delineated on the respective task order(s). Overtime may be required and shall be authorized on in advance by the Contracting Officer. Travel to and from the work location will be the responsibility of the contractor. Core hours may change with prior arrangement and written authorization by the Contracting Officer. Travel to various cutter locations is required.
3.5.3 Location - The Contractor shall locate the Tech Rep within the continental United States.
3.5.4 Travel - The Contractor shall ensure the Tech Rep is available for travel up to 200 days per year.
3.5.5 Employee conduct - Contractor Tech Reps shall comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, etc.) when visiting or working at Government facilities. The Contractor shall ensure the Tech Rep presents a professional appearance at all times and that their conduct shall not reflect discredit on the United States, the Department of Homeland Security, or the U.S. Coast Guard.
3.5.6 Tech Rep removal - The Government may, at its sole discretion, direct the Contractor to remove any Tech Rep from Coast Guard and Department of Homeland Security facilities for misconduct or security reasons. Removal does not relieve the Contractor of the responsibility to continue providing the services required in this work item. The Government will provide the Contractor with an immediate written explanation of the request to remove the Tech Rep through the Coast Guard Contracting Officer.
3.5.7 Conflict of Interest The Contractor shall not employ any person who is an employee of the United States Government if that employment would cause, or appear to cause, a conflict of interest.
3.5.8 Tech Rep identification Contractor employees working on-site at Government facilities shall wear a company issued identification badge. All Contractor employees shall identify themselves as Contractors when their status is not readily apparent and display their badge in plain view above the waist at all times.
3.5.9 Tech Rep performance monitoring The Contractor shall be required to meet with the COR (or designee) during contract on a time and date as required per the COR (or designee) to discuss Tech Rep performance. Upon the completion of each task order, the Contractor shall provide a summary report to the Contract Administrator and COR of no more than four pages that identifies task order budget, costs, travel accomplished and hours charged for technical representative services (monthly total and cumulative). Travel receipts shall be provided with the report in accordance with the Contract regulations. The report shall also identify any issues that the contractor perceives as adversely impacting their ability to satisfy requirements. The monthly report shall be in a contractor developed format approved by the COR.
3.5.10 Duties The Tech Rep shall be responsible and expected to conduct the following:
· Perform casualty repairs on the Oily Water Separator.
· Acknowledge receipt of Coast Guard-generated Request(s) for Quote within 24 hours.
· Conduct visits to verify system configuration, conditions, and to make repairs as required.
· Develop and maintain serial-tracked Oily Water Separator configuration database.
· Alert Coast Guard and disseminate advisories and service bulletins related to the Oily Water Separator.
· Develop failure solutions for the Oily Water Separator.
4.0 NOTES
4.1 Document Sources
4.1.1 Government Documents
a. Code of Federal Regulations http://www.access.gpo.gov/nara/cfr/cfr-table-search.html
b. USCG documents will be made available upon request.
4.1.2 Commercial Documents
a. International Maritime Organization (IMO)
| IMO Publishing |
| 4 Albert Embankment |
| London SE1 7SR |
| United Kingdom |
| +44 (0)20-7735-7611 |
| www.imo.org |
b. Institute of Electrical and Electronics Engineers (IEEE)
| Park Avenue, 17th Floor |
| New York, NY 10016-5997 |
| 212-419-7900 |
| www.ieee.org |
c. National Electrical Manufacturers Association (NEMA)
| 1300 North 17th Street |
| Suite 1752 |
| Rosslyn, Virginia 22209 |
| 703-841-3200 |
| www.nema.org |
image1.jpeg
File details come from the government source that posted it. Updated .