Statement of Work
Machinery Plant Control & Monitoring System Upgrade
VER: 2 Jul 2014
Contents
1.0 General
2.0 Definitions and References
3.0 Performance Tasks
4.0 Verification
5.0 Deliverables
6.0 Contract Line Item Deliverables (CLIN)
1. General
1.1 Background:
1.2 Scope: The Contractor shall provide all management, supervision, personnel, labor, materials, and equipment required to remove, modify, install, test, calibrate, certify, and provide training required to upgrade the Machinery Plant Control & Monitoring System
(MPCMS) installed on U.S.C.G. 225’ WLB Cutters listed in paragraph 2.21 and in accordance with this Statement of Work.
1.3 Personnel Qualification Standards
1.3.1 Program Manager: The Contractor shall provide qualified personnel to perform all of the services for this Statement of Work (SOW). This list shall include a single point of contact (POC), designated as the Program Manager. The Program Manager shall be the Government’s sole access point to the Contractor.
The services required by this SOW shall not be subcontracted to or performed by persons other than the Contractor without prior consent of the Contracting Officer (KO).
The Contractor shall provide a list of personnel that will be performing the services described herein. The Contractor shall notify the KO and Contracting Officer’s
Representative (COR) in writing of changes to personnel working on this contract.
1.3.2 Security Clearance: A security clearance is not required to perform this work; however, all contractor personnel working on or visiting Government installations are required to be U.S. citizens and have valid U.S. Government identification (Social Security
Numbers, driver license, passport, etc.).
1.4 Period of Performance: All work covered by this Statement of Work shall be completed within 3 years of Contract Award.
2. Definitions and References
2.1. U.S. Coast Guard Technical Publication: TP – 3505 A & B MACHINERY PLANT
CONTROL & MONITORING SYSTEM OPERATING MANUAL (MPCMSOM)
2.2. U.S. Coast Guard Technical Publication: TP – 3585 A& B MACHINERY PLANT
CONTROL & MONITORING SYSTEM OPERATING MANUAL (MPCMSOM)
2.3. U.S. Coast Guard Technical Publication: TP – 3932 MPCMS DATA LOGGING SYSTEM
2.4. U.S. Coast Guard Technical Publication: TP – 3589 MPCMS COMPUTER SYSTEM
MANUAL
2.5. U.S. Coast Guard Technical Publication: TP – 3507A MPCMS COMPUTER SYSTEM
OPERATING MANUAL (CSOM)
2.6. U.S. Coast Guard Technical Publication: TP – 3508A MPCMS COMPUTER SYSTEM
DIAGNOSTIC MANUAL (CSDM)
2.7. U.S. Coast Guard Technical Publication: TP – 3509A MPCMS SOFTWARE USER'S
MANUAL (SUM)
2.8. USCG 202 Drawing: 225-WLB_202_1, Rev F, MPCMS CABLING DIAGRAM
2.9. USCG 202 Drawing: 225-WLB_202_2, Rev G, MPCMS COED
2.10. USCG 202 Drawing: 225B-WLB_202_2, Rev D, MPCMS CONNECTION TABLE
2.11. USCG 202 Drawing: 225B-WLB_202_1, Rev G, MPCMS CABLING DIAGRAM
2.12. USCGC JUNIPER INSTRUCTION 3540.1B – WLB Casualty Control Manual (CCM)
2.13. American Bureau of Shipping, Steel Vessel Rules (ABS SVR), 1998, Part 4, Section 11
(Shipboard Automatic or Remote Control and Monitoring Systems) with propulsion class symbol
ACC
2.14. Institute of Electrical and Electronics Engineers (IEEE) Std 45-1998 Recommended
Practice for Electric Installations on Shipboard
2.15. Institute of Electrical and Electronics Engineers (IEEE) Std 829-2008, Standard for
Software and System Test Documentation
2.16. 46CFR 62 (1998) Code of Federal Regulations, subchapter F
2.17. MIL – STD – 1399 Interface Standards for Shipboard Systems, Section 300B, Electric
Power, Alternating Current.
2.18. MIL-DTL-24643C, Cables, Electrical, Low Smoke Halogen-Free, For Shipboard Use, General Specification for
2.19. National Electrical Manufacturers Association (NEMA) 250-2008, Enclosures for
Electrical Equipment (1000 Volts Maximum)
2.20. National Marine Electronics Association (NMEA) 0183, v 4.10, Standard for Interfacing
Marine Electronic Devices
2.21. List of Applicable Cutters and their homeports.
2.21.1 USCGC JUNIPER (WLB-201), Newport, RI
2.21.2 USCGC WILLOW (WLB-202), Newport, RI
2.21.3 USCGC KUKUI (WLB-203), Honolulu, HI
2.21.4 USCGC ELM (WLB-204), Atlantic Beach, NC
2.21.5 USCGC WALNUT (WLB-205), Honolulu, HI
2.21.6 USCGC SPAR (WLB-206), Kodiak, AK
2.21.7 USCGC MAPLE (WLB-207), Seward, AK
2.21.8 USCGC ASPEN (WLB-208), San Francisco, CA
2.21.9 USCGC SYCAMORE (WLB-209), Cordova, AK
2.21.10 USCGC CYPRESS (WLB-210), Pensacola, FL
2.21.11 USCGC OAK (WLB-211), Charleston, SC
2.21.21 USCGC HICKORY (WLB-212), Homer, AK
2.21.13 USCGC FIR (WLB-213), Astoria, OR
2.21.14 USCGC HOLLYHOCK (WLB-214), Port Huron, MI
2.21.15 USCGC SEQUOIA (WLB-215), FPO AP, Guam 96678
2.21.16 USCGC ALDER (WLB-216), Duluth, MN
2.22. USCG Surface Forces Logistics Center (SFLC) Documents
2.22.1. COMDTINST M9085.1C, Naval Engineering Computer Aided Design
Standards
2.22.2. D-086-0508, Technical Documentation Specifications (Tech Publications
& Drawings)
2.22.3. D-084-0481 Rev A, Preservation, Packaging, and Marking
2.22.4. SFLC Std Spec 3042, 2012, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation
3. Performance Tasks
3.1. The Contractor shall provide all resources and materials required to complete the following tasks in accordance with the schedule of deliverables in Section 5.0 Deliverables:
3.2. Host a project kickoff meeting at the contractor’s facility to review the contract documents including the performance tasks and deliverables (CLIN 1.1). The Contractor shall provide the following at the kickoff meeting:
3.2.1. System block diagrams of the existing and proposed system upgrades.
3.2.2. Operator and maintainer training requirements.
3.2.3. A list of components to be removed and installed.
3.2.4. A list of developmental software to be used.
3.2.5. A list of personnel working on the project and their qualifications.
3.2.6. Record and provide meeting minutes.
3.3. Provide a Plan of Action and Milestones (POA&M) (CLIN 1.2) that includes the following:
3.3.1. The performance tasks, including sequencing logic and contractor resources for each item, required to develop the system (CLIN 1and CLIN 2).
3.3.2. The notional deployment schedule for CLIN 3 and CLIN 4 with time line sequences and dates beginning 45 days after the completion of CLIN2.
3.3.3. Mitigation strategies for schedule, technical, and cost risks.
3.3.4. Development start and completion dates for each software module, piece of hardware, test procedure, and draft engineering document.
3.3.5. Bi-weekly progress report to update the developmental schedule, problems encountered, and achieved milestones (CLIN 1.3); however, issues requiring immediate actions shall be conveyed verbally and via email to both the Contracting Officer (KO) and the Contract Officer’s Representative(s)
(COR),.
3.4. Provide bi-weekly progress reports shall be provided to the Government review and comment/approval as required (CLIN 1.3). Issues requiring immediate actions shall be conveyed verbally and via email to both the KO and the COR. The contractor shall conduct all communications with only the KO or the assigned COR(s). Bi weekly progress reports shall include the following:
3.4.1. Updates to the POA&M
3.4.2. HMI screen updates for review, comment and approval as completed.
3.4.3. Schedule issues and risks and the steps taken to manage them.
3.4.4. Project performance issues and risks, including technical and engineering problems, and the steps taken to correct.
3.4.5. An Email or Verbal Means to discuss, review, and/or concerns and HMI
Screen updates.
3.4.6. Completed milestones.
3.5. Upgrade the MPCMS VME Subsystem. The contractor shall replace the obsolete VME computers and associated equipment for the MPCMS. The upgraded system shall retain all of the current capabilities of the existing system as stated in references 2.1-2.7 and meet the requirements of paragraph 2.13 (ABS SVR ACC), paragraph 2.14 (IEEE – STD- 45), and paragraph 2.16 (46CFR 62).
3.5.1. The contractor shall replace the existing system hardware and associated
ADA software with commercial off the shelf hardware and software. The applications shall have two levels of password protected user access.
3.5.1.1. Developer (highest level of access and modification permissions and shall include “Supervisory” permissions).
3.5.1.2. Supervisory (this level provides the ability to change set points, alarm delays, password changes, and logging functions)
3.5.2. Cable and wire markings and identification shall comply with the style and nomenclature used in the existing system and found in references 2.1 through
2.11. The contractor shall provide and install new or reroute existing cable, as necessary, in accordance with paragraph 2.22.4 (SFLC Std Spec 3042).
3.6. The system shall retain or improve upon all of the current capabilities in terms of redundancy, speed, operation, control and monitoring, and graphics. System design shall also include the following changes:
3.6.1. Provide a new direct communications path between DPS and MPCMS that is serial and NMEA 0183 based, independent of the DDS LAN network. The
Contractor shall coordinate this upgrade with the DPS OEM, L-3
Communications Dynamic Positioning and Controls.
3.6.2. Remove the ECDIS interface including alarm exchange and monitoring and the SMG and COG messages found on the WLB B class cutters; however, the MPCMS shall continue to provide the NMEA 0183 $PTAN message for propulsion to the ECDIS by means of a separate one way communications to the DDS LAN from the control computers or via a splitter off of the direct communications installed to DPS in the previous paragraph.
3.6.3. Provide the means to manually enter the system date and time from any ECC workstation keyboard.
3.6.3.1. Date time information shall be retained upon power loss for 48 hours.
3.6.3.2. Software shall be able to detect whether the date and time requires updating upon restoration from a power loss
3.6.3.3. Updating system time at either MPMCS HMI computer in the
Engineering Control Center shall update all computers.
3.6.4. Provide graphical pages with modern mimics and appropriate use of color, similar to those found in industry, to better associate displayed data with the equipment to which it pertains.
3.6.4.1. The graphics shall also provide the user interface, as required, to implement additional features herein. Improved graphics are desired and will be reviewed during HMI product reviews.
3.6.4.2. Provide a propulsion system graphic user interface which allows the operator to utilize a mouse to select an item from a system level arrangement. The selected item shall link to detailed equipment page which includes operating parameters and alarms.
3.6.4.3. When navigating between pages on HMI computers, the new screen shall refresh in less than 1 second, and changing screens shall happen in less than 1 second.
3.6.5. Provide monitoring of communication traffic between external system devices, logging and alarming on NMEA Dynamic Positioning Data strings that are not properly formatted or contain checksum errors. This information shall also be displayed on an alarm page and on a communications page.
3.6.6. Provide data logging with the same or better frequency than the existing system with the additional provisions as follows:
3.6.6.1. Continue to provide the capability of storing 3 years worth of logged data and provide the means to move the data to an exportable media.
3.6.6.2. Provide the capability to log 25 user selectable analog points at a rate of 1 per second. This capability shall provide a log that stores data for
1 month and overwrite data that is more than one month old
3.6.6.3. Provide an alarm set point change log and display graphic providing a list of set point changes from the default.
3.6.6.4. Provide a means to export log data in comma separated value
(CSV) format to CD/RW, DVD/RW.
3.6.7. Provide a laptop computer for quarterdeck operation and the following:
3.6.7.1. Provide a connection port and cables for use on the bridge.
3.6.7.2. Provide a connection port and cables for use on the port and starboard quarterdecks.
3.6.7.3. Provide a connection port and cables for use in the Engineering
Control Center for training.
3.6.7.4. Provide training capabilities to act as the instructor station for the on board trainer.
3.6.8. Onboard Trainer (OBT)
3.6.8.1. Provide the function to allow HMI Panel C5 (outboard starboard bay) of the Engineering Control Center Console shall be capable of operating as an OBT workstation. Distinctive banners shall be displayed on all HMI screens that are in training mode to alert the operator when a simulation is running on the console. While in the training mode, operation of the workstation peripherals (keyboard and trackball) will have no effect on actual equipment, but will be evaluated by the simulation routine to progress the scenario. Displayed status pages and mimics shall update to simulate expected conditions and maintain a sense of realism during each exercise.
3.6.8.2. Develop MPCMS initial conditions and casualty indicators that reflect the WLB casualty Control Manual (CCM) (reference paragraph
2.12) found in chapter 2 of the manual.
3.6.8.3. The Government’s intent for OBT is to have an instructor station
(quarterdeck laptop computer) provide conditions to the student station, HMI computer C5. Both computers shall be placed in training mode. The instructor station shall be capable of sending plant status information to the student station. At a minimum this shall include MDE On/Off, Clutch
On/Off, Engine Speed and Propeller Speed, SSDG and EDG status
On/Off, Bus Status, thruster status, propulsion status (maneuvering mode/transit mode). The instructor station shall be capable of changing the plant status with a series of check boxes and entering analog data manually for display on the student station. The instructor station shall also be able to cause alarms and malfunctions found in the CCM with the same method as initiating plant status.
3.6.8.4. Actions that affect the plant status will be carried on the active part of the MPCMS such as reducing speed, lighting off fire pumps, shutting down engines, etc. However, the instructor shall be able to mimic changes to the plant via the instructor station.
3.6.8.4.1. Basic Engineering Casualty Control Exercises (BECCE) found in chapter 2 of the CCM. At a minimum, the on board trainer shall be capable of realistically simulating underway and dockside conditions including the following engineering casualty scenarios:
3.6.8.4.1.1. CG-ENG-03, Loss of MPCMS
3.6.8.4.1.2. CG-ENG-04, Major Fuel Oil Leak
3.6.8.4.1.3. CG-ENG-05, Loss of Control Air Pressure
3.6.8.4.1.4. CG-ENG-07, Hot Bearing Reduction Gear/Line Shaft
Bearing
3.6.8.4.1.5. CG-ENG-12, Loss of CPP Pitch Control
3.6.8.4.1.6. CG-ENG-13, Overheating Diesel Engine MDE or SSDG
3.6.8.4.1.7. CG-ENG-18, MDE Loss of Lube Oil Pressure
3.6.8.4.1.8. CG-ENG-20, MDE Loss of Fuel Oil Pressure
3.6.8.4.1.9. CG-ENG-24 Loss of Clutch Air Pressure
3.7. Provide a Factory Test (CLIN 1.4) for Government review and approval.
3.7.1. The Contractor shall record test results and meeting minutes. The
Contractor shall provide a pre meeting/discussion test and an after test meeting/discussion
3.7.2. The Contractor shall incorporate comments as directed by the COR that are within the scope of work.
3.7.3. The factory test shall demonstrate the following:
3.7.3.1. Computer and network system redundancy.
3.7.3.2. HMI graphical user screen look and navigation
3.7.3.3. HMI station operation
3.7.3.4. HMI integration and redundancy
3.7.3.5. BECCE screen look and operation
3.7.3.6. Time entry and display
3.7.3.7. Data logging functions and ability
3.7.3.8. TANONET RTU integration
3.7.3.9. Alarm detection, announcing, and display functions
3.7.3.10. Control functions of the plant
3.7.3.11. System malfunction detection BITE and BIT
3.8. Preliminary Engineering Documentation. The Contractor shall develop and provide preliminary engineering documentation (CLIN 1.5) for Government review and approval as follows:
3.8.1. Draft system rip-out and installation drawings, with corresponding written instructions and quality control steps for the technicians performing the work.
3.8.2. Draft condition found test and conditions found reports.
3.8.3. Draft test procedures, in accordance with IEEE – STD – 829 or equal, sufficient to conduct integration and system operation testing at the Command, Control & Communications Engineering Center (C3CEN) Training Lab, Portsmouth, VA. The test plan shall include the following:
3.8.3.1. Level Test Plan Clause 9
3.8.3.2. The Level Test Cases Clause 10, Level Test Procedures Clause
11, and Level Test Logs Clause 12, which may be combined.
3.8.3.3. Anomaly report Clause 14
3.8.3.4. Level Test Report Clause 16
3.8.3.5. Signature/Acceptance block for Government Witness
3.8.4. Software flowcharts.
3.8.5. Draft Condition found report
3.8.6. Draft MPCMS upgrade booklet
3.8.7. Redundancy and error checking flowcharts, including database synchronization.
3.8.8. Serial data flowcharts, including baud rates and polling intervals.
3.8.9. Operating system for installed computers.
3.8.10. Software loading and update instructions for MPMCS computers.
3.8.11. Load analysis to show the expected and maximum power consumed and delivered by each power supply, as well as the maximum demand on the
MPCMS uninterruptable power supply (UPS).
3.8.12. Provide an Interface Design Document (IDD) in the same format as found within the current data logging software “WLB MPMCS.MDB”. The IDD shall include modifications to the base software as modified by this specification.
3.9. Final Engineering Documentation. The Contractor shall develop and provide final engineering documentation (CLIN 2.3) for Government review and approval as follows:
3.9.1. System rip-out and installation drawings, with corresponding written instructions and quality control steps for the technicians performing the work.
3.9.2. Conditions Found Reports.
3.9.3. Test procedures for dockside and underway testing in accordance with
IEEE – STD – 829 or equal, sufficient to conduct integration and system operation testing at the C3CEN Training Lab, Portsmouth, VA. The test plan shall include the following:
3.9.3.1. Level Test Plan Clause 9
3.9.3.2. The Level Test Cases Clause 10, Level Test Procedures Clause
11, and Level Test Logs Clause 12, which may be combined.
3.9.3.3. Anomaly report Clause 14
3.9.3.4. Level Test Report Clause 16
3.9.3.5. Signature/Acceptance block for Government Witness
3.9.4. Software flowcharts.
3.9.5. Redundancy and error checking flowcharts, including database synchronization.
3.9.6. Serial data flowcharts, including baud rates and polling intervals.
3.9.7. Software loading and update instructions for MPMCS computers
3.9.8. Operating system for installed computers.
3.9.9. Load analysis to show the expected and maximum power consumed and delivered by each power supply.
3.9.10. Provide an Interface Design Document (IDD) in the same format as found within the current data logging software “WLB MPMCS.MDB”. The IDD shall include modifications to the base software as modified by this specification.
3.9.11. A complete set of MPCMS screen layouts.
3.9.12. A Copy of all source code developed for the benefit of the Government.
3.9.13. A Copy of all compiled software and executable files.
3.9.14. A Copy of all configuration files, including default or baseline settings.
3.9.15. Original media and licenses for all software.
3.9.16. A Complete revision of all MPCMS technical documentation, reflecting the as built system.
3.9.17. A new MPCMS OBT manual
3.9.18. A MPCMS system upgrade booklet (Paragraph 3.11)
3.10. MPCMS System Upgrade Booklet. The Contractor shall develop and provide a system upgrade booklet that contains all of the information required to install and commission the
MPCMS for Government review and approval as follows:
3.10.1. The booklet shall be submitted to the Government for review and approval.
3.10.2. The booklet shall be divided into sections for each stage of the upgrade, and shall be in a format that flows with the installation.
3.10.3. The booklet shall include an installation time line and names and number of Contractor personnel that will be performing the each stage of work. This information shall be updated prior to each installation.
3.10.4. The booklet shall include instructions on coordinating the upgrade with the DPS OEM, and shall be upgraded to reflect the DPS OEM schedule and level of effort.
3.10.5. The booklet shall include instructions to conduct an in-brief with the cutters Command prior to commencing work that provides an outline of the work to be accomplished.
3.10.5.1. The Command will designate a single Point of Contact (POC) for the Contractor for communications.
3.10.5.2. The Contractor shall coordinate work schedules for each phase of system installation and testing with the POC.
3.10.5.3. The Contractor shall coordinate and work with the POC during each testing phase and each test.
3.10.6. The booklet shall include a pre-installation test plan with a condition found report (CFR) that documents the condition of the MPMCS and the equipment/systems that the MPMCS communicates, controls, and monitors.
3.10.6.1. The report shall be signed by Contractor personnel conducting the testing
3.10.6.2. The report shall provide a signature block for a Government witness to sign.
3.10.6.3. The report shall include instructions to forward the signed CFR to the COR and KO upon completion to allow the Government time to arrange repairs as required.
3.10.7. The booklet shall include a Bill of Materials (BOM) for equipment and cables to be installed. The BOM shall include signature blocks for the
Contractor and the POC to sign verifying that all materials are onsite prior to installation.
3.10.8. The booklet shall include equipment and cable removal instructions, drawings, and photos.
3.10.9. The booklet shall include equipment and cable installation instructions, drawings, and photos.
3.10.10. The booklet shall include test procedures for dockside system startup, integration, and functional testing.
3.10.10.1. Tests shall be performed in the company of a Government witness.
3.10.10.2. The test procedures shall provide a signature block for a
Government witness to sign.
3.10.10.3. Tests shall include DPS integration testing.
3.10.10.4. The report shall be signed by Contractor personnel conducting the testing
3.10.11. The booklet shall include test procedures for conducting underway testing. Underway testing shall include operational testing that demonstrates the system is free of errors and that the system as a whole is working error free.
3.10.11.1. The underway test plan shall be developed starting with the tests performed in paragraph 3.14.19 but reducing the scope of the test to two days.
3.10.11.2. Tests shall include DPS integration testing and DPS operational testing.
3.10.11.3. Tests shall be performed in the company of a Government witness.
3.10.11.4. The test procedures shall provide a signature block for a
Government witness to sign.
3.10.11.5. The test procedures shall be signed by Contractor personnel conducting the testing.
3.10.12. The booklet shall include a section that provides changes made during system installation and commissioning that were required during installations.
3.10.12.1. Changes to equipment and cabling shall be documented as red-line edits to the new drawings. Photos shall also be provided to document differences between expected instructions and actual instructions and forwarded to the KO and COR.
3.10.12.2. Changes made to software shall be documented and forwarded to the KO and COR for review and approval.
3.10.12.3. Changes that are required by vessels shall be distributed, provided, and installed by the contractor.
3.10.13. The Contractor shall update the booklet based on recommendations provided during the execution of this document. New revisions shall be provided to the KO and COR for review and approval.
3.10.14. The booklet shall include a training outline and procedures for system operators and maintainers.
3.10.14.1. Training shall be provided to groups of no more than 4 persons at a time.
3.10.14.2. Training shall include dockside, underway, and OBT.
3.10.14.3. Training shall provide system operators and maintainers verbal and hands-on instruction on the use and maintenance of the MPCMS.
3.10.14.4. Training shall provide system operators and maintainers examples of system operation before and after installation.
3.10.14.5. Training shall be provided separately for bridge and engineering control center crewmembers.
3.10.14.6. A training check off sheet shall be provided to be signed a
Government that the training was conducted in accordance with this section.
3.10.15. The booklet shall include instructions to conduct an out-brief with the command after all work is complete that provides an outline of the work performed and an opportunity for the command to provide positive or negative feedback, and recommendations for future installs.
3.10.16. The booklet shall include a certificate of acceptance to be provided to the
COR after successful installation, test.
3.11. Technical Data (TD). This section defines the requirements for the Contractor to provide
TD necessary to integrate the Contractor’s equipment into the design of Coast Guard Cutters and to begin logistical support documentation. (CLIN 2.1) The Contractor’s TD shall include as applicable:
3.11.1. Equipment technical/performance data for all major components including control unit parts, detectors, alarming devices, and any relevant accessories.
3.11.2. A generic system layout showing how the proposed system components form a complete system and how the system is capable of meeting the requirements of this specification.
3.11.3. A unique assembly part number, nomenclature, and original equipment manufacturer (OEM) Commercial and Government Entity Code (CAGE) Code.
3.11.4. General arrangement drawings detailing overall dimensions; required maintenance area dimensions; locations, size and type of all mechanical, electrical, electronic, and other shipboard installation and operating interface requirements.
3.11.5. Overall component and system weights, including an accounting of the change in weight as a result of old equipment removal and new hardware installation.
3.11.6. Equipment heat rejection values, BTU/hr or kW.
3.11.7. Manual, technical publication, and/or catalogue data detailing the installation requirements for each piece of equipment.
3.11.8. The Contractor’s TD shall include as applicable: The TD identified herein shall be provided within forty-five (45) days after activation of (CLIN-2).
3.11.9. Where system designs differ between A Class and B Class cutters, the following separate TD shall be submitted noting which class it is applicable to.
If tech data is identical, duplicate TD need not be submitted for each cutter class. Drawings shall be in accordance with reference 2.22.1.
3.11.10. System layout drawings identifying each piece of equipment, the location of each piece of equipment and the zone (where applicable) of each piece of equipment. Equipment shall be shown on ship layout drawings. Layout drawings shall identify and include the quantity of each identifiable component shown on the drawings. Drawings shall be based on general ship arrangements (references 2.8 and 2.11).
3.11.11. System block wiring diagram detailing the equipment single line connections, cable types and zone identification.
3.12. Data for Provisioning (DFP). The Contractor shall provide DFP for all components being supplied. DFP shall be provided after contract award as defined herein. DFP includes drawings, technical manuals, catalog data and product specification sheets to allow the provisioning of a system or piece of equipment. The DFP for the base year end item shall include all items listed below. (CLIN 2.1) The Contractor shall provide addendums to the
DFP for each item during the option years as required.
3.12.1. The Contractor shall put provisions in his lower-tier subcontracts and supply agreements requiring compliance with this Specification. The DFP that the Coast Guard requires from the Contractor’s subcontractors shall be provided by the Contractor.
3.12.2. DFP supplied shall include as a minimum:
3.12.2.1. A hierarchical listing of all components which can be assembled, re-assembled, and/or replaced. The listing shall identify primary components and all supporting components/parts. Figure 1 provides an example of how to list information.
Figure 1Example submission of DFP data for component hierarchy.
3.12.2.2. General arrangement and system diagrams.
3.12.3. The contractor shall update all Technical Manuals/Publications to completely describe the end item, end item’s equipment and/or piece parts;
material, mechanical, electrical, dimensional characteristics, location, and their function within the assembly. The technical publications shall include theory of operation, equipment and component set points and related technical information, disassembly procedures, recommended maintenance, maintenance and lay-up procedures, component repair and maintenance instructions, trouble shooting guide, parts schematic/line diagrams, and complete drawings and diagrams.
3.12.4. The contractor shall combine the following technical publications referenced in paragraphs 2.5, 2.6, and 2.7 for the WLB A Class shall be combined into one manual in the same fashion as found in reference 2.4, which is used on the WLB B class cutters. The contractor may further combine the
WLB A and WLB B class manuals referenced in this paragraph into one manual for both classes.
Hierarchy # Major Components Quantity OEM OEM CAGE Part # Estimated Retail Cost Description
Number identifying the hierarchy of the components and sub-components.
Name of major components of the system. Should include at a minimum the items outlined in Spec Section 3.2 but may include additional items per your design. Should not include items such as valves, foundations, hardware, etc. Sub-components should be listed beneath and indented from their main assembly.
Number of each component.
Original Equipment
Manufacturer that
USCG would contact to purchase a direct replacement part.
The Commercial and
Government Entity (CAGE)
Code of the OEM.
Identifying number used by the vendor.
Estimated Retail Cost for purposes of planning maintenance and repairs.
Brief description of the component including purpose, interfaces and other information to assist with understanding the configuration of the system
Service Filter Assembly 2 Company X K1234 12345-AB-6 $17,000 Main assembly that filters the fuel service system.
1.1 Filter Separator 1 1 Company Y B5432 12345-AB-7A $4,300
One of two separators used in parallel as part of the service filter assembly
1.2 Filter Separator 2 1 Company Y B5432 12345-AB-7B $4,300
One of two separators used in parallel as part of the service filter assembly
3.12.5. Illustrated Parts Breakdown- Identify parts associated with the equipment.
An exploded illustrated parts breakdown shall show the location of the parts.
The parts list shall identify the piece part of the illustration, quantity installed, nomenclature, designation, original manufacturer and manufacturer’s part number. Part numbers are not required for common hardware available from multiple sources, if adequate descriptive data is provided. Parts data listed in the technical manual shall be the same as listed on the hierarchical listing. If metric system components are provided, they shall be so noted.
3.12.6. All special tools and test equipment required to maintain the end item.
3.12.7. A list of all software/licenses needed to accomplish diagnostic testing.
3.12.8. Delivery of preliminary DFP shall be no later than sixty (60) days after activation of (CLIN - 2). The Coast Guard requires twenty-one (21) days to review DFP. The Contracting Officer, or his representative, will provide written approval or recommendations for improvement. The Contractor shall have thirty
(30) days to correct and resubmit if the initial delivery is disapproved.
3.12.9. Delivery of final DFP shall be no later than 30 days per the schedule of deliverables.
3.12.10. Data Submission Format. Data files shall be delivered on CD-ROM or
DVD-ROM. A copy of all source documents used to prepare the PDF shall also be provided in their native editable format compatible with Microsoft Office 2007
(DOC, XLS, or MDB) or AutoCAD 2012 (DWG) applications. Where electronic media is submitted, it shall be with the manufacturer’s permission to use the data on Coast Guard drawings. Documentation supplied as electronic media shall be one (1) copy.
3.13. Integration installation and testing at C3CEN WLB Integrated Ships Control System
(ISCS) training facility (CLIN 2.2). The purpose of this installation is to provide an opportunity to develop installation and test procedures for inclusion into the MPCMS 3.11, and test equipment fit, system performance, and operation.
3.13.1. The command at C3CEN will designate a single POC for the Contractor and the COR for communications.
3.13.2. The Contractor shall coordinate work schedules for each phase of system installation and testing with the POC and COR.
3.13.3. The Contractor shall coordinate and work with the POC and COR during each testing phase and each test.
3.13.4. The Contractor shall install the MPCMS upgrade at the ISCS.
3.13.5. The Contractor shall execute verify and the preliminary engineering documentation (Paragraph 3.9)
3.13.6. The Contractor shall use this opportunity to develop the Final Engineering
Documentation.
3.13.7. The Contractor shall coordinate system installation and testing with the
DPS OEM.
3.13.8. The Contractor shall enable data logging to verify correct operation during testing.
3.13.8.1. The contactor shall enable 25 analog point functions for 1 second recording, and populate analog and digital recording for the duration of the test.
3.13.8.1.1. The Contractor shall demonstrate the operation of exporting logs upon completion of integration testing.
3.13.9. The Contractor shall take progress photos of before, during and after installation of equipment.
3.13.10. The Contractor shall coordinate ECDIS testing with the C3CEN POC
3.13.11. The Contractor shall conduct functional testing prior to system integration testing.
3.13.12. The Contractor shall rerun the functional from the start upon failure of a functional test and/or upon making changes to software or hardware.
3.13.13. The system shall run for 4 hours prior to the start of functional testing and shall run for 24 hours upon completion of functional testing without failure to complete the functional test.
3.13.14. The Contractor shall maintain a test and change log documents
3.13.14.1. The test and change logs shall record the results from all tests or changes to technical documentation, hardware and software required to conduct successful functional testing.
3.13.14.2. The Contractor shall submit these documents for Government review and comment and/or Approval
3.13.15. System integration testing shall be conducted after the functional test is complete.
3.13.16. System integration testing shall include operating the MPCMS in all modes with the DPS and the entire suite of ISCS systems and equipments online.
3.13.17. The Contractor shall coordinate modifications and repairs found to be the fault of the DPS with the DPS OEM.
3.13.18. The Contractor shall rerun the functional from the start upon failure of a functional test and/or upon making changes to software or hardware.
3.13.19. System integration testing shall include tests where the Contractor injects bad and malformed data to test DPS communication monitoring and alarm functions.
3.13.19.1. System integration testing shall additional including the following:
3.13.19.1.1. 2 hours of MPCMS operation in transit mode followed by failing the active computer to ensure that the system redundancy functions correctly followed by 2 hours of operation on the backup computer.
3.13.19.1.2. 2 hours of DPS hold position mode operation followed by 1 hour of MPCMS throttle, tiller, and thruster testing in maneuvering mode. This test shall be rerun 2 additional times consecutively. A
DPS follow track mode test shall immediately follow this test.
3.13.19.1.3. 8 hours of DPS follow track mode testing. The test shall demonstrate that DPS integration is functioning. This test shall be rerun two additional times as per 3.14.17.1.1 and 3.14.17.1.3
3.13.19.1.4. 1 hour of MPCMS operation in transit mode followed by 2 hours of DPS joystick operation in maneuvering mode followed by 1 hour of DPS joystick operation in transit mode followed by 2 hours of
DPS hold position mode. A DPS follow track mode test shall immediately follow this test.
3.13.19.1.5. 8 hours of testing where alarms and faults and plant configurations are changed to ensure proper operation and stability of the system. Followed by 48 hours of continuous operational testing.
3.13.20. The Contractor shall provide training to the WLB ISCS course ware developers and training personnel for operators and maintainers.
3.13.21. The Contractor shall provide an acceptance certificate of compliance for signature by the COR.
3.13.22. Progress to CLIN 3 will not begin until Government Acceptance of CLIN 2
3.14. MPCMS prototype installs on one WLB A Class Cutter (CLIN 3.1) and one WLB
B Class Cutter (CLIN 3.2).
3.14.1. The Contractor is responsible for providing the required materials, test equipment, labor, and consumable items for each MPMCS install. The
Contractor shall ship all of these items for arrival prior to beginning the installation of the MPCMS upgrade.
3.14.2. The Contractor shall install and commission the MPCMS upgrade in accordance with the MPCMS System Upgrade Booklet (Paragraph 3.11) on each cutter.
3.14.3. The Contractor shall provide an additional 24 hours of dockside operational testing for the prototype installations.
3.14.4. The Contractor shall provide an additional 48 hours of underway operational testing.
3.14.5. The Government will provide 60 days notice prior to the start of an installation and coordinate site requirements to work on the cutter. The
Government will select prototype cutters based in the continental United States.
3.14.6. The Government will provide notice of installation schedule changes due to Cutter operational requirements.
3.14.7. After successful installation and commissioning the Government will evaluate the prototype for 60 days.
3.14.7.1. During this time the contractor shall provide system upgrades to hardware and software to correct deficiencies that may be reported by the
Government. Modifications made during this period shall be submitted to the Government for review and approval.
3.14.7.2. After the prototype evaluation period the Contractor shall provide a certificate of acceptance to the Government for review and signature.
3.15. MPCMS installs on remaining 225 WLB Class Cutters at the cutters homeport per reference 2.21.
3.15.1. The Contractor shall install the MPCMS upgrade as directed by the COR on WLB A Class Cutter and one WLB B Class Cutter.
3.15.2. The Contractor is responsible for providing the required materials, test equipment, labor, and consumable items for each MPMCS install. The
Contractor shall ship all of these items for arrival prior to beginning the installation of the MPCMS upgrade.
3.15.2.1. Note: Shipping MPCMS upgrade to units in Hawaii, Alaska, and
Guam may take up to 30 days to arrive on-site.
3.15.3. The Contractor shall install and commission the MPCMS upgrade in accordance with the MPCMS System Upgrade Booklet (Paragraph 3.11) on each cutter.
3.15.4. The Government will provide 60 days notice prior to the start of an installation and coordinate site requirements to work on the cutter.
3.15.5. The Government will provide notice of installation schedule changes due to Cutter operational requirements.
4. Verification
4.1. The Contractor shall provide the materials from the kickoff In Accordance With
(I.A.W.) the requirements in paragraph 3.2, and per the deliverable schedule item 5.1 for
Government review and comment.
4.2. The Contractor shall provide the POA&M I.A.W. the requirements of paragraph
3.3, and per the deliverable schedule item 5.2 for Government review and approval.
4.2.1. The Government will review the POA&M for 5 days and provide comments for incorporation into the POA&M.
4.2.2. The Contractor shall incorporate comments within 3 days and resubmit to the Government for review and approval.
4.3. The Contractor shall provide progress reports I.A.W. the requirements of paragraph 3.4 for Government review, comment and/approval.
4.3.1. Items requesting action by the Government will be addressed within 2 days of receipt.
4.3.2. The Contractor shall incorporate Government comments into HMI screens and resubmit for review and approval. Recommendations perceived as outside of the scope of work shall be jointly discussed and adjudicated.
4.4. The contractor shall conduct a Factory Test I.A.W. the paragraph 3.7 and per the deliverable schedule item 5.2.
4.4.1. The Contractor shall plan to receive up to 5 Government representatives for the Factory test.
4.4.2. The Contractor shall provide a copy of the test results and meeting minutes for Government review and comment.
4.4.3. The Contractor shall incorporate Governments and resubmit for review and approval.
4.5. The Contractor shall provide the Preliminary Engineering Documentation package I.A.W. paragraph 3.8 and per the deliverable schedule item 5.5.
4.5.1. The Government will review this document for 14 days and provide comments or approval.
4.5.2. The Contractor shall incorporate Government comments and resubmit for review and approval with 14 days of receipt.
4.6. The Contractor shall not proceed to CLIN 2 until issues, problems, and comments have been of CLIN 1 have been resolved.
4.7. The Contractor shall provide the Preliminary Engineering Documentation package I.A.W. paragraph 3.11 and 3.12, and per the deliverable schedule item 5.6.
4.7.1. The Government will review this documentation for 21 days for comments or approval.
4.7.2. The Contractor shall incorporate Government Comments for review and approval per the deliverable schedule item 5.8.
4.8. The Contractor shall install the MPCMS upgrade at the C3CEN ISCS training facility for integration testing. I.A.W. paragraph 3.13 and per the deliverable schedule item 5.7.
4.8.1. The Contractor shall provide test and change logs to the Government for review/comment/approval. The Contractor shall participate in this review on site at C3CEN. Comments shall be incorporated during the review.
4.8.2. The final document shall be provided to the Government for review/approval.
4.8.3. The Contractor shall provide an acceptance certificate of compliance for signature by the COR upon successful installation and testing of MPCMS upgrade.
4.9. The Contractor shall provide the Final Engineering Documentation package
I.A.W. paragraph 3.9 and per the deliverable schedule item 5.8.
4.9.1. The Government will review this document for 14 days and provide comments or approval.
4.9.2. The Contractor shall incorporate Government comments and resubmit for review and approval within 14 days of receipt.
4.10. The Contractor shall not proceed to CLIN 3 until issues, problems, and comments have been of CLIN 2 have been resolved.
4.11. The Contractor shall install the MPCMS upgrade on yet to be identified WLB A class Cutter. I.A.W. paragraph 3.14 and per the deliverable schedule item 5.10, which is
To Be Determined (TBD).
4.12. The Contractor shall install the MPCMS upgrade on yet to be identified WLB B class Cutter. I.A.W. paragraph 3.14 and per the deliverable schedule item 5.11, which is
To Be Determined (TBD).
4.13. The Contractor shall not proceed to CLIN 4 until issues, problems, and comments have been of CLIN 3 have been resolved.
4.14. The Contractor shall deploy the MPCMS upgrade to the remaining 14 cutters from the reference in paragraph 2.21 and per the deliverable schedule item 5.12, which is To Be Determined (TBD).
5. Deliverables
ITEM # ITEM NAME QTY DATE DUE
5.1 CLIN 1.1 Kick-off meeting 1 each 5 days ARO
5.2 CLIN 1.2 POA&M 1 each 10 days ARO
5.3 CLIN 1.3 Progress reports 1 each, Biweekly
starting 10 days after item
5.1
5.4 CLIN 1.4 HMI Screen Review and
System Functional Test
1 each 160 days ARO
5.5 CLIN 1.5 Preliminary System and
Engineering Documentation
1 each 150 days ARO
5.6 CLIN 2.1 Technical Data and Data for
Provisioning package
200 days ARO
5.7 CLIN 2.2 Integration Installation and
Testing at the USCG lab in Portsmouth, VA
1 Job Plan to start
180 days ARO
5.8 CLIN 2.3 Final Engineering
Documentation Package package
15 Days after completion of item 5.7
5.9 CLIN 2.4 Final Technical Data and
Data for Provisioning package
30 Days after completion of item 5.6
5.10 CLIN 3.1 Prototype Installation on
WLB A Class Cutter
1 job TBD
5.11 CLIN 3.2 Prototype installation on
WLB B Class Cutter
1 job TBD
5.12 6.4. CLIN 4. System installations on
USCG Cutters at homeport
14 jobs TBD
6. Contract Line Item Deliverables (CLIN)
6.1. CLIN 1. System Development
CLIN 1.1 Kick-off meeting
CLIN 1.2 POA&M
CLIN 1.3 Progress reports
CLIN 1.4 HMI Screen Review and System Functional Test
CLIN 1.5 Preliminary System and Engineering Documentation
6.2. CLIN 2. System Integration Installation and Test, Final Engineering and Logistics
Package
CLIN 2.1 Technical Data and Data for Provisioning
CLIN 2.2 Integration Installation and Testing at the USCG lab in Portsmouth, VA
CLIN 2.3 Final Engineering Documentation Package
CLIN 2.4 Final Technical Data and Data for Provisioning
6.3. CLIN 3. Prototype installation on WLB A Class and WLB Class Cutters
CLIN 3.1 Prototype Installation on WLB A Class Cutter
CLIN 3.2 Prototype installation on WLB B Class Cutter
6.4. CLIN 4. System installations on USCG Cutters at homeport
See paragraph 2.21 for the list of cutters and their home ports.