Attachment_5_Past_Performance_Questionnaire.docx

DOCX document 16 KB Posted

Attached to
Parts for MTU on 20V4000M93L
Solicitation number
HSCG40-13-Q-11009
Issued by

About this file

Past Performance Questionnaire

View the file

Other files

File Type Posted
Attachment_1_MTU_Pricing_Spreadsheet_8.19.13.xls XLS spreadsheet
HSCG40-13-Q-11009_Amendment_3_QA.docx DOCX document
HSCG40-13-Q-11009_Amendment_2_QA.docx DOCX document
Attachment_1_MTU_Pricing_Spreadsheet_8.16.13.xls XLS spreadsheet
HSCG40-13-Q-11009_Amendment_1_QA.docx DOCX document
Attachment_1_MTU_Pricing_Spreadsheet.xls XLS spreadsheet
Att_4_OEM.Proposal_Info.pdf PDF
Att_6_FAR_212-5.pdf PDF
Att_2_Brand_Name.pdf PDF
Att_3_Delivery.pdf PDF
Attachment_1_MTU_Pricing_Spreadsheet.xls XLS spreadsheet
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 5

PAST PERFORMANCE QUESTIONNAIRE

1. Contractor Name:
2. Contract Number:

3. Contract Type: ___Firm Fixed Price ___Cost Reimbursement ___ Other (Please Specify)

4. Agency Name:

5. Agency POC:

Phone:

Email:

6. Place of Contract Performance:

7. Period of Performance:

8. Dollar Amount of Award:

Total Dollar Value with Mods:

9. Title of Contract:

10. Description of Contract Service:

11. Complexity of Work: Difficult: ____________ Routine: ____________

NOTE: Please use adjectival ratings from attached sheet.

12. Evaluation Factor
13. Comments (Attach additional sheets, if necessary.)
14. Rating

a. Quality of Work

b. Personnel

c. Subcontractor Mgmt

d. Business Relations

e. Timeliness of Performance

f. Customer Satisfaction

g. Cost/Budget Control

15. Would you select this firm again? Please explain. (Attach additional sheet if necessary.)

16. Name & Date:
17. Title:

PAST PERFORMANCE RATING GUIDELINES

Summarize Contractor Performance in each of the rating areas. Assign each area a rating of Unsatisfactory, Marginal, Satisfactory, Very Good or Exceptional. Use the following instructions as guidance in making these evaluations. Note: There is no corresponding guidance for “Customer Satisfaction”. Please use the comments area on the preceding form to justify the rating given “Customer Satisfaction.”

Ratings
Quality of Work/

Personnel/Service

-Compliance w/contract requirements -Accuracy of reports -Appropriateness of personnel -Technical excellence

Cost Control

-Within budget -Current, accurate, complete billings -Relationship of negotiated costs to actual -Cost efficiencies -Change orders issued Timeliness of Performance

-Met interim milestones -Reliable -Responsive to technical direction -Completed on time Business Relations/Sub Contractor Mgmt

-Effective Mgmt -Businesslike correspondence -Responsive to contract reqmnts -Prompt notification of problems -Reasonable/ cooperative -Flexible -Pro-active -Effective SB/SDB Subcontract Program

Unsatisfactory
Nonconformances

are comprising the achievement of contract reqmnts

Cost issues are comprising performance
Delays are compromising achievement of contract reqmts
Response is not effective
Marginal
Nonconformances

require major agency resources to ensure achievement of contract reqmnts

Cost issues require major agency resources to ensure achievement of contract reqmnts
Delays require major agency resources to ensure achievement of contract reqmnts
Response is marginally effective
Satisfactory
Nonconformances require minor agency resources to ensure achievement of contract reqmnts
Cost issues require minor agency resources to ensure

achievement of contract reqmnts

Delays require minor agency resources to ensure achievement of contract reqmnts
Response is somewhat effective
Very Good
Nonconformances

do not impact achievement of contract reqmnts Cost issues do not impact achievement of contract reqmnts

Delays do not impact achievement of contract reqmnts
Response is usually effective
Exceptional
There are no quality problems
There are no cost issues
There are no delays
Response is effective