(09/07/2011 Rev-4)
USCG 49 FT BUOY UTILITY STERN LOADING BOAT
IDIQ SPECIFICATIONS
Spec Writer:
Bruce Brightman
Commander Surface Forces Logistics Center 300 E Main Street, Suite (550) Norfolk, VA 23510-9111
Page i (Rev 4)
TABLE OF CONTENTS
Work Item Title Page
List of Sketches vii
Revisions Record viii
List of Applicable References xii
List of Government/industrial-furnished Property xx
List of Critical Inspection Items xxii
Specification Feedback xxiii
Principal Characteristics xxiv
General Requirements 1
WORK ITEM 1: General Welding, Provide 3
WORK ITEM 2: Ultrasonic Testing (UT) Shots, Perform 4
WORK ITEM 3: Hull and Structural Plating - 3/16" Steel Plate , Repair 6
WORK ITEM 4: Hull and Structural Plating - Steel Plate, Repair 8
WORK ITEM 5: Hull and Structural Plating – Degraded Weld (Steel), Repair 10
WORK ITEM 6: Lazarette QAWTH (TCTO TB6010.B), Renew 12
WORK ITEM 7: Rub Rail, Inspect 21
WORK ITEM 8: Rub Rail Fender System, Remove and Install 23
WORK ITEM 9: Hull Plating (U/W Body) Ultrasonic Testing, Perform 25
WORK ITEM 10: Bilges, Inspect 27
WORK ITEM 11: Bilges, Preserve 29
WORK ITEM 12: Tank (MP Fuel Service), Clean 31
WORK ITEM 13: Tanks (MP Fuel Service), Inspect 33
WORK ITEM 14: Void (Non-Accessible), Leak Test 36
49 FT BUOY UTILITY STERN LOADING BOAT IDIQ 2011
Page ii (Rev-4)
WORK ITEM 15: Accessible Spaces, Inspect 38
WORK ITEM 16: Accessible Voids, Inspect 40
WORK ITEM 17: Sea Strainers, Inspect 42
WORK ITEM 18: Sea Strainers, Remove and Install 44
WORK ITEM 19: Grid Cooler, Inspect 46
WORK ITEM 20: Grid Cooler, Remove and Install 48
WORK ITEM 21: Watertight Closures, Inspect 49
WORK ITEM 22: Watertight Closure, Remove and Install 51
WORK ITEM 23: Weather-tight Closures, Inspect 53
WORK ITEM 24: Weather-tight Closure, Remove and Install 55
WORK ITEM 25: Mast, Inspect 57
WORK ITEM 26: Mast, Remove and Install 58
WORK ITEM 27: Batteries, Renew 60
WORK ITEM 28: Main Diesel Engine, Remove and Install 61
WORK ITEM 29: Main Diesel Engine, Align 63
WORK ITEM 30: J/W Crossover Piping (TCTO TA5020), Modify 65
WORK ITEM 31: Reduction Gear, Remove and Install 82
WORK ITEM 32: Reduction Gear Coupling (TCTO TA4000), Replace 84
WORK ITEM 33: Propeller Shaft, Remove, Inspect, and Install 94
WORK ITEM 34: Propeller Shaft Seal, Renew 96
WORK ITEM 35: Line Cutter, Remove and Install 98
WORK ITEM 36: Shaft Log, Renew 99
WORK ITEM 37: Propeller Shaft Coupling, Remove and Install 101
WORK ITEM 38: Emergency Inflatable Shaft Seal, Test 103
WORK ITEM 39: Water Lubricated Shaft Bearings, Renew 105
Page iii (Rev-4)
WORK ITEM 40: Propeller Shaft Coupling, Fit and Face 107
WORK ITEM 41: Propeller, Remove and Install 109
WORK ITEM 42: Engine Throttle Control Cable, Inspect 111
WORK ITEM 43: Engine Stop Control Cable, Inspect 112
WORK ITEM 44: Exhaust Muffler, Renew 113
WORK ITEM 45: Exhaust Piping, Inspect 115
WORK ITEM 46: Exhaust System, Renew 117
WORK ITEM 47: Engine Fuel Filter-Water Separator, Inspect 119
WORK ITEM 48: Engine Fuel Filter-Water Separator, Renew 120
WORK ITEM 49: Ship Service Diesel Generator, Remove and Install 121
WORK ITEM 50: Ship Service Diesel Generator, Clean and Inspect 123
WORK ITEM 51: Boat-Side Shore-Tie Receptacle, Inspect 126
WORK ITEM 52: Boat-Side Shore-Tie Receptacle, Remove and Install 128
WORK ITEM 53: Electrical Distribution Panel, Inspect 129
WORK ITEM 54: Isolation Transformer, Renew 131
WORK ITEM 55: Exterior Lights, Inspect 132
WORK ITEM 56: Searchlight, Renew 134
WORK ITEM 57: EC-49BUSL-C-17 Pneumatic Horn, Complete 136
WORK ITEM 58: Air Horn Compressor, Remove and Install 137
WORK ITEM 59: Air Horn, Remove and Install 139
WORK ITEM 60: Standard Hoses, Inspect 141
WORK ITEM 61: Non-Standard Hoses, Inspect 149
WORK ITEM 62: Standard Hoses, Renew 151
WORK ITEM 63: Non-Standard Hoses, Renew 159
WORK ITEM 64: Piping, Inspect 161
Page iv (Rev-4)
WORK ITEM 65: Interior Hull Insulation, Inspect 163
WORK ITEM 66: Interior Hull Insulation, Renew 165
WORK ITEM 67: Defroster, Remove and Install 166
WORK ITEM 68: Air Conditioning Unit, Inspect 167
WORK ITEM 69: Air Conditioning Unit, Remove and Install 168
WORK ITEM 70: Sea Valves, Renew 170
WORK ITEM 71: Sea Water Valves (TCTO BUSL 49 TM2000), Modify 172
WORK ITEM 72: Cooler, Remove, Clean, Test, and Install 187
WORK ITEM 73: Grease Trap, Clean and Inspect 189
WORK ITEM 74: Electric Bilge Pump Float Switches, Test 191
WORK ITEM 75: Bilge Pumps, Inspect 193
WORK ITEM 76: Bilge Pump, Renew 195
WORK ITEM 77: Potable Water Tanks, Clean and Inspect 196
WORK ITEM 78: Valves (Fuel), Renew 198
WORK ITEM 79: Air Compressor, Inspect and Service 201
WORK ITEM 80: Air Receiver, Test and Service 202
WORK ITEM 81: Air Compressor, Remove and Install 203
WORK ITEM 82: CO2 Cylinders, Hydrostatic Test 205
WORK ITEM 83: CO2 Cylinders, Recharge 207
WORK ITEM 84: Hydraulic Steering Oil Tank, Clean and Inspect 208
WORK ITEM 85: Steering System, Inspect 210
WORK ITEM 86: Rudder, Remove, Inspect, and Install 212
WORK ITEM 87: Buoy Handling Equipment (Level 2) Maintenance, Perform 214
WORK ITEM 88: Chain Stopper, Inspect 220
WORK ITEM 89: Chain Stopper, Overhaul 222
Page v (Rev-4)
WORK ITEM 90: Deck Fittings, Inspect 224
WORK ITEM 91: Boat Outfit Storage, Provide 226
WORK ITEM 92: Grey Water Tank, Clean and Inspect 227
WORK ITEM 93: Sewage Holding Tank, Clean and Inspect 230
WORK ITEM 94: Pad Eyes, Inspect 233
WORK ITEM 95: Handrails, Inspect 235
WORK ITEM 96: Windows, Inspect 237
WORK ITEM 97: Window, Renew 239
WORK ITEM 98: Windshield Wipers, Renew 242
WORK ITEM 99: Tanks (Potable Water), Preserve 100 Percent 243
WORK ITEM 100: Tanks (Potable Water), Preserve “Partial” 246
WORK ITEM 101: Tanks ( Grey Water Holding ) , Preserve 100 Percent 249
WORK ITEM 102: Tanks ( Grey Water Holding ) , Preserve “ Partial ” 252
WORK ITEM 103: Accessible Void, Preserve 254
WORK ITEM 104: U/W Body, Preserve 100 Percent 256
WORK ITEM 105: U/W Body, Preserve (“Partial – Condition A ”) 259
WORK ITEM 106: U/W Body, Preserve (“Partial – Condition B ”) 263
WORK ITEM 107: U/W Body, Preserve (“Partial – Condition C ”) 267
WORK ITEM 108: Hull Identification Markings, Apply 271
WORK ITEM 109: Decks - Exterior( Buoy ), Preserve 100 Percent 273
WORK ITEM 110: Deck (Foredeck), Preserve 100 Percent 276
WORK ITEM 111: Hull Plating Freeboard, Preserve “Partial” 278
WORK ITEM 112: Hull Plating Freeboard, Preserve 100 Percent 281
WORK ITEM 113: Mast, Preserve 285
WORK ITEM 114: Cathodic Protection / Zincs, Renew 288
Page vi (Rev-4)
WORK ITEM 115: Exterior Non-Slip Pads, Renew 291
WORK ITEM 116: Temporary Services, Provide 293
WORK ITEM 117: Preventive Maintenance, Perform 296
WORK ITEM 118: OEM Certified Technical Representative Services, Provide 297
WORK ITEM 119: Routine Drydocking, Provide 298
WORK ITEM 120: Time Compliance Technical Order (TCTO), Complete 301
WORK ITEM 121: Casualty Repairs, Perform 303
WORK ITEM 122: Superstructure, Preserve 100 Percent 304
WORK ITEM 123: Superstructure, Preserve “ Partial ” 307
Page vii (Rev-4)
List of Sketches
Work Item Sketch Number Page
None
Page viii (Rev-4)
Revisions Record
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK ITEM# CHANGES MADE
07/13/2011 1 Listed all TCTO‟s and Engineering Changes in the List of Applicable References
07/28/2011 2 2 Par 3.1 Added 100 shots .140 thickness
07/28/2011 2 10 Par 3.2 Added inspection details
07/28/2011 2 11 Par 3.1 Added any fixed equipment to the interference
07/28/2011 2 11 Par 3.2 Deleted Inspection replaced with Preservation
07/28/2011 2 12 Deleted par 4.1
07/28/2011 2 13 Deleted par 4.1
07/28/2011 2 14 Par 3.2 in the caution deleted we advise that the vessel environmental coordinator may assist with determination of waste
07/28/2011 2 14 Par 3.4 Deleted the contractor shall
07/28/2011 2 20 Par 3.1 Deleted the ellipse
07/28/2011 2 22 Par 3.4 Deleted Coast Guard
07/28/2011 2 23 Par 3.4 Deleted Coast Guard
07/28/2011 2 27 Par 3.2 Added disposal
07/28/2011 2 29 Par 3.2.1 Added engine
07/28/2011 2 30 Par 1.2 Added GFP will be provided as per TCTO
TA5020
07/28/2011 2 31 Par 3.2 First note added If leak detected submit a CFR
07/28/2011 2 40 Par 1.2 Added Government furnished property
07/28/2011 2 41 Par 3.1 In the note deleted Coast Guard Inspector added Contractor
07/28/2011 2 41 Par 3.3.1 Added inspector
07/28/2011 2 45 Par 3.5 Second bullet added material shall be fiber nonasbestos
07/28/2011 2 50 Par 4.2 Deleted Generator Overhaul
07/28/2011 2 64 Par 3.5 Second bullet added material shall be fiber nonasbestos
07/28/2011 2 77 Par 3.5 Deleted overboard
07/28/2011 2 82 Par 3.3 Added publications
07/28/2011 2 84 Par 3.3 Added inspection standards
07/28/2011 2 87 Par 3.1.1 Deleted 1 added 2
07/28/2011 2 100 Par 1.2 Deleted 100% added 30%
07/28/2011 2 101 Par 3.1.2 Referenced work item 92
07/28/2011 2 102 Par 1.2 Deleted 100% added 30%
07/28/2011 2 113 Corrected title to read Mast in place of Hand rails
07/28/2011 2 115 Table 1-3 Added information will be provided
07/28/2011 2 119 Par 3.2.2 Added blocking position 1
07/28/2011 2 120 Par 3.1 Deleted Commanding added Contracting
08/05/2011 3 Added Drawings 49A BUSL 310-1, Rev C, 24 VDC Power Distribution System and 49A BUSL 529-1, Rev D, Bilge System to the List of Applicable References
Page ix (Rev-4)
09/07/2011 4
Added the following drawing to the List of Applicable References:
49A BUSL 71-50 Rev B, Weather Tight Doors
49A BUSL 169-001 Sheet 1-2 Machinery Removal Drawing
49A-BUSL 171-002 Rev D, Mast Construction Detail
49A-BUSL 171-002 Rev C, Mast Construction Detail
49A-BUSL 171-002-3- Rev C, Mast Construction Detail
49A-BUSL 171-002-4-Rev D, Mast Construction Detail
49A-BUSL 171-002-5-Rev D, Mast Construction Detail
49A BUSL 233-50 Installation
49A BUSL 243-002, Rev, Propulsion Shaft Modifications
49A BUSL 243-50 7.5 Flange Split Coupling
49A BUSL 252-001 Rev B, Sheets 1-5 Propulsion and generator Engine Controls and Shutdowns
49A BUSL 310-1, Rev C, 24 VDC Power Distribution System
49A BUSL 310-003 Rev E, 120VAC Power Distribution System
49A BUSL 401-001 Rev D, Nav Light ANT Arrangement, Plan View and Antenna Chart
49A BUSL 401-001 Rev C, Nav Light ANT Arrangement, Plan View and Antenna Chart
49A BUSL 422-001 Rev C, Search Light Elementary Wiring Diagram
49A BUSL 443-001 Rev 0, Air Horn Installation Details
49A BUSL 502-051 Rev 1-1/2" End Model Keel Cooler
49A.BUSL 512-001 Rev B, Sheets 3,5 HVAC System Arrangement and Details
49BUSL 528-001 Rev B, Plumbing Hatch and Deck Drains
49A BUSL 529-1, Rev D, Bilge System
Page x (Rev-4)
49A BUSL 533-001 Rev B, Sheets 1-3, Potable Water and Window Washer System
49A BUSL 541-001 Rev A Fuel Oil & Floc System
49A BUSL 555-001 Rev E, Sheets 1-3 Fixed CO2 System
49A BUSL 561-001, Rev B, Sheets 1-4, Hydraulic Steering System
49A BUSL 612-002-Rev C, Rails and Life Lines
49A BUSL 612-002-2 Rev C, Rails and Life Lines
49A BUSL 612-002-3 Rev C, Rails and Life Lines
49A BUSL 625-001 Rev C, Pilothouse Windows Arrangement and Details
49A BUSL 625-050 Rev 0, Vendor Drawing Windows Forward
49A BUSL 625-051 Rev 0, Vendor Drawing Windows Fore and Aft
49A BUSL 625-052 Rev 0, Vendor Drawing Windows Sliding
49A BUSL 625-053 Rev 0, Vendor Drawing Windows Side Middle
49A BUSL 625-054 Rev 0, Vendor Drawing Window Aft
49A BUSL 634-1 Rev B, Deck Covering Schedule
09/07/2011 4
Added the following Coast Guard Technical Manuals to the List of Applicable References:
Coast Guard Technical Publication (TP) 3346- Manufacturer‟s Instruction Book - SWBS Group(s) 302- 490 March 2010
Coast Guard Technical Publication (TP) 3347, Manufacturer's Instruction Book – SWBS Group(s) 502-556, (June 1995)
Coast Guard Technical Publication (TP) 3348, Amendment 4, Section A, SWBS 573, Nov 2003
Coast Guard Technical Publication (TP) 4618-551-A Compressed Air System, October 2006
Page xi (Rev-4)
Coast Guard Technical Publication (TP) 4626 Manufacturer's Instruction Book – SWBS Group(s) 302-390, March 2010
Coast Guard Commandant Instruction (COMDTINST) M6240.5 (series) Ch 1 Potable Water and Waste Water Handling, October 1999
09/07/2011 4 3 Par 2 References Changed drawing from Water Tight to Weather Tight
09/07/2011 4 4 Par 2 References Changed drawing from Water Tight to Weather Tight
09/07/2011 4 5 Par 2 References Changed drawing from Water Tight to Weather Tight
09/07/2011 4 6 Par 2 References Changed drawing from Water Tight to Weather Tight
09/07/2011 4 11 Par 2 References Added Drawing No. 49A BUSL 631- 001 Rev F, Painting Schedule
09/07/2011 4 16 Par 2 References Added Drawing No. 49A BUSL 631- 001 Rev F, Painting Schedule
09/07/2011 4 19 Par 2 References Added Drawing No. 49A BUSL 502-
09/07/2011 4 22 Par 2 References Deleted Drawing No. 051-050
09/07/2011 4 23 Par 2 References Deleted Drawing No. 051-050 Added Drawing No. 071-050
09/07/2011 4 24 Par 2 References Deleted Drawing No. 051-050 Added Drawing No. 071-050
09/07/2011 4 51 Par 2 References Deleted Drawing No. 49A BUSL 320-002 Added Drawing No. 49A BUSL 310-003
09/07/2011 4 52 Par 2 References Deleted Drawing No. 49A BUSL 320-002 Added Drawing No. 49A BUSL 310-003
09/07/2011 4 53 Par 2 References Deleted Drawing No. 49A BUSL 320-002 Added Drawing No. 49A BUSL 310-00303
09/07/2011 4 54 Par 2 References Deleted Drawing No. 49A BUSL 320-002 Added Drawing No. 49A BUSL 310-003
09/07/2011 4 111
Par 2 Reference Deleted Drawing No‟s. Coast Guard Fleet Drawing FL 2804-6, Rev D, Visual ID Numeral & Letter for Ships
Coast Guard Fleet Drawing FL 2804-12, Rev-, U.S.C.G. Emblem
Coast Guard Drawing FL 2804-13, Rev G, Visual ID Kit Sched Coast Guard Drawing FL 2804-15, Rev-, Draft Figs
NOTE: All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
Page xii (Rev-4)
List of Applicable References
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution. Electronic copies of the latest Editions of SFLC Standard Specifications are available on the Internet and may be accessed at the following Internet Uniform Resource Locator (URL) address:
http://www.uscg.mil/SFLC/mlclant/vdiv/standard_specifications.asp
Guidance for obtaining copies of all other documents referenced herein is provided in the solicitation.
Order of precedence: In the event of conflicts between text of this specification and the applicable references specified herein, order of precedence shall be in accordance with SFLC Standard Specification 0000, paragraph 3.2.1.1 (Order of Precedence), unless otherwise specified by the Contracting Officer (KO). The Contractor shall immediately notify the KO in writing of any perceived conflicts contained herein. Nothing in these documents, however, supersedes applicable laws and regulations, unless a specific exemption has been obtained.
FEDERAL AND MILITARY SPECIFICATIONS AND STANDARDS
MIL-PRF-16173, 2006, Corrosion Prevention Compound, Solvent Cutback, Cold- Application
MIL-A-18001, May 2005, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)
MIL-G-24716A, Apr 1993, Gaskets, Metallic-Flexible Graphite, Spiral Wound
MIL-PRF-24647D, Feb 2005, Paint System, Anticorrosive and Antifouling, Ship Hull
Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting
OTHER GOVERNMENT DOCUMENTS, DRAWINGS, AND PUBLICATIONS
DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0000, General Requirements, 2009 Edition
Page xiii (Rev-4)
Surface Forces Logistics Center (SFLC), Standard Specification 5000, Auxiliary Machinery Systems 2009 Edition
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0740, Welding and Allied Processes, 2009 Edition
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 8634, Drydocking, 2009 Edition
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 8635, Provide Temporary Logistics, 2009 Edition
Coast Guard Commandant Instruction (COMDTINST) M6240.5 (series) Ch 1 Potable Water and Waste Water Handling, October 1999
Coast Guard Commandant Instruction (COMDTINST) M9000.6(series) Oct 2004 Naval Engineering Manual, Chapter 570 General Duty and Replenishment Weight Handling systems
Coast Guard Commandant Instruction (COMDTINST) M10360.3(series) Color and Coatings Manual June 2006
Coast Guard Commandant Instruction (COMDTINST) M16500.21(series) ATON Seamanship Manual, 21 May, 1997
DRAWINGS
Coast Guard Drawing 49A BUSL 71-50 Rev B, Weather Tight Doors
Coast Guard Drawing 49A BUSL 085-002, Rev A, Hull Lines and Offsets
Coast Guard Drawing 49A BUSL 085-003, Rev -, Docking Plan
Coast Guard Drawing 49BUSL 114-003, Rev E, Chain Guard and Rub Rails
Coast Guard Drawing 49A BUSL 114-004, Rev F, Skeg and Shaft Tube Arrangement and Details
Coast Guard Drawing 49A BUSL 130-002, Rev D, Main Deck Plating and Framing
Coast Guard Drawing 49A BUSL 169-001 Sheet 1-2 Machinery Removal Drawing
Coast Guard Drawing 49A-BUSL 171-002 Rev D, Mast Construction Detail
Coast Guard Drawing 49A-BUSL 171-002 Rev C, Mast Construction Detail
Coast Guard Drawing 49A-BUSL 171-002-3- Rev C, Mast Construction Detail
Coast Guard Drawing 49A-BUSL 171-002-4-Rev D, Mast Construction Detail
Page xiv (Rev-4)
Coast Guard Drawing 49A-BUSL 171-002-5-Rev D, Mast Construction Detail
Coast Guard Drawing 49A BUSL 200-002, Rev A, Machinery Arrangement
Coast Guard Drawing 49A BUSL 233-50 Installation
Coast Guard Drawing 49A BUSL 243-001, Rev G, Propulsion Shafting and Bearing Arrangement
Coast Guard Drawing 49A BUSL 243-002, Rev, Propulsion Shaft Modifications
Coast Guard Drawing 49A BUSL 243-50 7.5 Flange Split Coupling
Coast Guard Drawing 49A BUSL 252-001 Rev B, Sheets 1-5 Propulsion and generator Engine Controls and Shutdowns
Coast Guard Drawing 49A BUSL 256-001, Rev F, Propulsion and Engine Seawater and Jacket Water Cooling System
Coast Guard Drawing 49A BUSL 259-001, Rev B, Propulsion and Generator Engine Exhaust Systems Arrangement and Details
Coast Guard Drawing 49A BUSL 310-1, Rev C, 24 VDC Power Distribution System
Coast Guard Drawing 49A BUSL 310-003 Rev E, 120VAC Power Distribution System
Coast Guard Drawing 49A BUSL 401-001 Rev D, Nav Light ANT Arrangement, Plan View and Antenna Chart
Coast Guard Drawing 49A BUSL 401-001 Rev C, Nav Light ANT Arrangement, Plan View and Antenna Chart
Coast Guard Drawing 49A BUSL 422-001 Rev C, Search Light Elementary Wiring Diagram
Coast Guard Drawing 49A BUSL 443-001 Rev 0, Air Horn Installation Details
Coast Guard Drawing 49A BUSL 502-051 Rev 1-1/2" End Model Keel Cooler
Coast Guard Drawing 49A.BUSL 512-001 Rev B, Sheets 3,5 HVAC System Arrangement and Details
Coast Guard Drawing 49A BUSL 528-001 Rev B, Plumbing Hatch and Deck Drains
Coast Guard Drawing 49A BUSL 529-1, Rev D, Bilge System
Coast Guard Drawing 49A BUSL 530-001, Rev C, Potable Water and Misc Tanks
Page xv (Rev-4)
Coast Guard Drawing 49A BUSL 533-001 Rev B, Sheets 1-3, Potable Water and Window Washer System
Coast Guard Drawing 49A BUSL 541-001 Rev A Fuel Oil & Floc System
Coast Guard Drawing 49A BUSL 551-001, Rev C, Compressed Air System
Coast Guard Drawing 49A BUSL 555-001 Rev E, Sheets 1-3 Fixed CO2 System
Coast Guard Drawing 49A BUSL 556-002, Rev C, Diagram Buoy Handling Hydraulic System
Coast Guard Drawing 49A BUSL 556-003, Rev C, Arrgt Buoy Handling Hydraulic System
Coast Guard Drawing 49A BUSL 556-004, Rev E, Buoy Handling Hydraulic System Block and Elementary Wrg Diag
Coast Guard Drawing 49A BUSL 556-050, Rev -, Heat Exch Assembly
Coast Guard Drawing 49A BUSL 556-051, Rev -, Cross Deck Manifold
Coast Guard Drawing 49A BUSL 556-052, Rev -, 3 POS D05/W NV
Coast Guard Drawing 49A BUSL 556-053, Rev -, 2 POS D05/W NV
Coast Guard Drawing 49A BUSL 561-001, Rev B, Sheets 1-4, Hydraulic Steering System
Coast Guard Drawing 49A BUSL 562-001, Rev C, Rudder and Steering Gear Arrangement and Details
Coast Guard Drawing 49A BUSL 573-002, Rev F, Stern A-Frame and Chainstopper Construction and Details
Coast Guard Drawing 49A BUSL 573-003, Rev C, Buoy Handling Arrangement and Details
Coast Guard Drawing 49A BUSL 573-004, Rev D, Chainstopper and Release, Fabrication, Assembly, and Installation Details
Coast Guard Drawing 49A BUSL 573-004, Rev D, Chainstopper and Release – Fabrication, Assembly, and Installation Details
Coast Guard Drawing 49A BUSL 573-005, Rev A, Stern A-Frame Construction and Details
Coast Guard Drawing 49A BUSL 601-003, Rev D, Outboard Profile and Main Deck Arrangement
Page xvi (Rev-4)
Coast Guard Drawing 49A BUSL 601-004, Rev A, Inboard Profile/Dk Arrg
Coast Guard Drawing 49A BUSL 602-001 Rev C, Hull LBL Plates/Marks
Coast Guard Drawing 49A BUSL 612-002-Rev C, Rails and Life Lines
Coast Guard Drawing 49A BUSL 612-002-2 Rev C, Rails and Life Lines
Coast Guard Drawing 49A BUSL 612-002-3 Rev C, Rails and Life Lines
Coast Guard Drawing 49A BUSL 625-001 Rev C, Pilothouse Windows Arrangement and Details
Coast Guard Drawing 49A BUSL 625-050 Rev 0, Vendor Drawing Windows Forward
Coast Guard Drawing 49A BUSL 625-051 Rev 0, Vendor Drawing Windows Fore and Aft
Coast Guard Drawing 49A BUSL 625-052 Rev 0, Vendor Drawing Windows Sliding
Coast Guard Drawing 49A BUSL 625-053 Rev 0, Vendor Drawing Windows Side Middle
Coast Guard Drawing 49A BUSL 625-054 Rev 0, Vendor Drawing Window Aft
Coast Guard Drawing 49A BUSL 631-001, Rev F, Paint Schedule
Coast Guard Drawing 49A BUSL 633-001, Rev B, Cathodic Protection
Coast Guard Drawing 49A BUSL 634-1 Rev B, Deck Covering Schedule
Coast Guard Drawing 49A BUSL 635-001, Rev D, Hull Insulation Schedule and Insulation Details
Coast Guard Drawing FL-2605-022, Rev E, Chain Stopper, 1-1/4 inch Buoy Chain
Coast Guard Fleet Drawing FL 2804-6, Rev D, Visual ID Numeral & Letter for Ships
Coast Guard Fleet Drawing FL 2804-12, Rev-, U.S.C.G. Emblem
Coast Guard Drawing FL 2804-13, Rev G, Visual ID Kit Sched
Coast Guard Drawing FL 2804-15, Rev-, Draft Figs
NAVSEA Drawing 803-921865, Rev R, Cathodic Protection Hull Zinc Anodes
NAVSEA Drawing 804-5773931, Rev A, Acoustic and Thermal Insulation For Compartments Installation Details
Page xvii (Rev-4)
PUBLICATIONS TIME COMPLIANCE TECHNICAL ORDER (TCTO), AND ENGINEERING
CHANGE (EC)
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (Series) Coatings and Color Manual, Jun 2006
Coast Guard Technical Publication (TP) 3345, Manufacturer‟s Instruction Books - SWBS Groups 079-259, SWBS 233 Propulsion Internal combustion Engine, Oct 2005
Coast Guard Technical Publication (TP) 3345, Manufacturer‟s Instruction Books - SWBS Groups 079-259, SWBS 259, Exhaust System, Oct 2005
Coast Guard Technical Publication (TP) 3345, Manufacturer‟s Instruction Book - SWBS Group(s) 079-259, SWBS 243 – Propulsion Shafting, Oct 2006
Coast Guard Technical Publication (TP) 3345, Manufacturer‟s Instruction Book - SWBS Group(s) 079-259, SWBS 244 – Propulsion Shaft Bearings, Oct 2006
Coast Guard Technical Publication (TP) 3346- Manufacturer‟s Instruction Book - SWBS Group(s) 302-490 March 2010
Coast Guard Technical Publication (TP) 3347, Manufacturer's Instruction Book – SWBS Group(s) 502-556, (June 1995)
Coast Guard Technical Publication (TP) 3348, Amendment 4, Section A, SWBS 573, Nov 2003
Coast Guard Technical Publication (TP) 4618-551-A Compressed Air System, October
Coast Guard Technical Publication (TP) 4626 Manufacturer's Instruction Book – SWBS Group(s) 302-390, March 2010
Coast Guard Maintenance Procedure Card M00001.0 Replace Hoses 49BUSL-B-01 BUSL Shaft Bearing
49BUSL-A-02 Hot Start Renewal
49BUSL-A-04 HYD Dehumdifying Filter
49BUSL-A-05 Reduction Gear Lubrication Oil Sender
49BUSL-A-06 Replacement of A Frame Balance Valve
49BUSL-A-07 SSDG Pulley
49BUSL-A-08 Amendment1 Hydraulic Case Drain Cooling
49BUSL-B-09 Amendment 1 Intermediate Bearing Installation
Page xviii (Rev-4)
49BUSL-A-10 Time Delay Relay Installation in MDE Start Circuit
49BUSL-A-13 AFFF Extinguisher Installation
49BUSL-A-14 Engine Room Deck Plates
49BUSL-A-15 Engineering Work Shop With Removal
49BUSL-B-16 49' Bouy Deck Configuration
49BUSL-A-18 BUSL Generator Gauge Panel Relocation
49BUSL-B-19 Zinc Anode Upgrade
49BUSL-C-020 Forepeak Scuttle Access
49BUSL-A-021 Main Diesel Engine Mounts
49BUSL-A-022 49' BUSL Life raft Replacement
49BUSL-A-023 Winch Brakes Modification
49BUSL-A-024 Engine Room Exhaust Fan Shut Down Switch
49BUSL-C-027 49' BUSL A-Frame Proximity Switch Replacement
TCTO TN0000.0 Carbon Monoxide Detector
TCTO TM3010.0 Sewage Hose Flushing Valve
TCTO TP0000.1 Anchor Replace (Update)
INDUSTRY STANDARDS
American Society of Mechanical Engineers (ASME), PTC 25, 2001, Pressure Relief Devices
American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2003 Edition, Bronze Gate, Globe, Angle and Check Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves
Page xix (Rev-4)
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 1998, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G- 6032, 1999, Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G- 363, Metric
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2004, Solvent Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 7/NACE No.4, 2004, Brush-Off Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No.5, 2004, Surface Preparation and Cleaning of Steel and Other Hard Materials by High and Ultrahigh Pressure Water Jetting
The Society for Protective Coatings (SSPC)/NACE International (NACE) 2004, Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, Near-White Blast Cleaning
International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50m, Inclusive
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method
Page xx (Rev-4)
List of Government/industrial-furnished Property
The following is a list of property, which the Government/industrial will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY
ESTIMATED
UNIT COST
6 N Freeman Marine Watertight Quick
Acting Hatch 2040-01-F07-1174 1 ea $1922.90
6 N Oval Aluminum Hatch Steel Ring 0031-2226 1 ea $100.00
8 N Duramax 49 BUSL Linerite Dunnage Kit
(complete) 813000044 1 ea $1,986.00
8 N 3 ½” x 3 ½” x 15” long 813000040 1 ea $146.00
8 N 3 ½” x 3 ½” x 45” long 813000043 1 ea $310.00
8 N 3 ½” x 3 ½” x 54” long 813000042 1 ea $336.00
8 N 3 ½” x 3 ½” x 50” long 813000037 1 ea $325.00
8 N 49‟ BUSL Fender Kit (complete) 802031904 1 ea $6,146.68
8 N Forward side fender kit 802101003 2 ea $752.14
8 N Aft side fender kit 802100903 2 ea $827.93
8 N Buoy Deck Fenders 802100803 2 ea ewa
$825.52
8 N Stern fender kit 802100503 1 ea $113.05
8 N Bow nose fender kit 802022504 1 ea $591.01
8 N Stern corner fender kit 802022404 2 ea $315.72
18 N Sea Strainer Hayward Model 72 1 ea $100.00
22 N 24” X 54” Watertight Aluminum Door
LH
2040-01-454-9363 1 ea $7714.32
22 N 24” X 60” Watertight Aluminum Door
RH
2040-01-455-1822 1 ea $4453.00
22 N 24” X 48‟ Watertight Aluminum Door
LH
2040-01-455-1816 1 ea $3714.00
22 N 24” X 24” Watertight Aluminum Hatch 2040-01-455-1312 1 ea $3059.70
22 N 24” Watertight Aluminum Hatch 2040-01-455-0616 1 ea $1922.90
22 N 15” X 24” Watertight Aluminum ER(ER 2040-01-455-0628 1 ea $1379.30
22 N Hatch Hold Open Assembly 0031-2226 1 ea $200.00
24 N WTD 24”x66” LH 2040-01-454-9363 1 ea $1935.00
24 N WTD 24”x60” RH 2040-01-455-1822 1 ea $1935.00
28 Y Engine, Diesel 2815-01-450-5653 1 ea $20,220.00
31 Y Reduction Gear 2010-01-450-5801 1 ea $8,408.22
32 N Flexible Coupling 3010-01-551-3136 1 ea $533.69
33 Y Propeller Shaft 2010-01-458-4612 1 ea $2204.92
34 N Shaft Seal Assembly 2010-01-F04-0256 1 ea $3,577.43
35 N Shaft Razor Line Cutter 02500 1 ea $442.00
37 N Shaft Coupling 3010-01-458-6535 2 ea $398.97
37 N Drive Saver 841193025 2 ea $100.00
37 N Drive Saver Bushing Kit 841193027 2 ea $30.00
39 N Bearing Sleeve 3120-01-366-0506 3 ea $219.16
40 Y Shaft Coupling 3010-01-458-6535 2 ea $398.97
41 Y Right Hand Propeller 2010-01-450-5807 1 ea $1642.00
41 Y Left Hand Propeller 2010-01-450-5805 1 ea $1630.00
44 N Exhaust Muffler, Kit MDE 2990-01-450-5804 1 ea $3,300.00
44 N Exhaust Muffler, Gasket 5330-01-329-4168 1 ea $125.00
49 Y Engine, Diesel Generator Set 6115-01-456-6346 1 ea $23,668.00
50 Y Generator 35MCGBA 1 ea $10,000.00
Page xxi (Rev-4)
53 N Receptacle 5935-01-399-6806 1 ea $436.39
57 N Searchlight 6230-01-461-7591 1 ea $677.00
58 N Horn Replacement Kit 6350-01-F04-0326 1 ea $100.00
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY
ESTIMATED
UNIT COST
59 N Compressor P449-8 1 ea $500.00
59 N Relief Valve 4820-01-019-8943 1 ea $70.19
60 N Horn 6350-01-552-8723 1 ea $100.00
70 N A/C Unit 4120-01-552-9170 1 ea $100.00
66 N 2” Ball, Flange Mount 4820-01-475-0283 3 ea $1,183.00
66 N 2” Flange 4730-00-252-3508 3 ea $49.00
66 N Rubber Sheet, Solid Cloth Insert 5330-00-179-0052 1 ea $38.37
66 N Screw, Cap, Hexagon 5305-00-925-7853 ea
$2.65
66 N Nut, Plain, Hexagon 5310-01-372-2670 ea
$4.86
66 N Washer, Flat 5310-00-187-4129 ea
$4.92
82 N Air Compressor 4310-01-552-8767 1 ay $100.00
81 N Rudder Assembly 2040-01-471-8081 1 ay $5,292.00
81 N Lower Bearing 3120-01-465-0356 1 ea $136.41
81 N Upper Bearing 3120-01-465-0320 1 ea $129.50
81 N Rudder Bearing Seal Applied Industrial
17307H5L16 1 ea $37.83
82 N Thrust Bearing 3120-01-391-1492 1 ea $80.00
Page xxii (Rev-4)
List of Critical Inspection Items
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000_STD, paragraph 3.6.2 (Inspection report particulars)):
The following is a list of work items, which contain Critical Inspection reports, which The Contractor must complete within the first 25% of the availability contract period (see SFLC Standard Specification 0000_STD, paragraph 3.11 (Reports)):
Work Item Title
9 Hull Plating (U/W Body) Ultrasonic Testing, Perform
14 Void (Non-Accessible), Leak Test
Page xxiii (Rev-4)
Specification Feedback
The intent of this section is to inform all users that a spec feedback mechanism is in place, and is located on the MLCA Naval Engineering Division‟s website. Spec feedback is a very important part of our overall continuous improvement process, and is crucial to specification development. It will allow spec writers to capture all specification-related lessons learned, and avoid mistakes or ambiguities in follow-on availabilities. All feedback will be reviewed, evaluated, and responded to in a timely manner.
If you have access to the CGWeb (Intranet), please use the following link, which will connect you to the MLCA(v) Naval Engineering website, for submitting your feedbacks:
http://apps.mlca.uscg.mil/vdiv/surveys/Post_availability/
If you do not have access to the CGWeb (Intranet), you may still submit your feedbacks, using the following web link:
http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp.
http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp
Page xxiv (Rev-4)
PC_41UTB
(07 Jan 2004)
Principal Characteristics
49 FOOT BUSL (BUOY UTILITY STERN LOADING) BOAT
Length Overall 49' 2-1/4"
Beam, maximum 16' 10"
Height of Highest Projection (above DWL), Mast lowered 15‟ (with mast down)
Heightest Unfixed Point (above DWL) 27‟
Full Load Draft 5' 6"
Full Load Displacement 71,690 lbs. (32 LT)
Shore Tie Voltage Requirements 120VAC
PROPULSION
Type Diesel Engine
Number of Units Two, Cummins, Model 6CTA8.3M1 305 hp
PROPELLERS
Number of Propellers 2
Number of Blades per Propeller 4
Diameter of Propeller 31"
Pitch 22" fixed
Shaft Revolutions per Minute (RPM) 2,300
Page 1 (Rev 4)
00000N_BOATS (9 July 2009)
«REC»
General Requirements
1. SCOPE
1.1 Intent. This item describes the general requirements to be followed by the Contractor while conducting this availability«SCOPE».
2. APPLICABLE DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0000_STD, 2009 Edition, General Requirements
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (Series), Jun 2006, Coatings and Color Manual
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in Std Spec 0000_STD and in this item, as applicable, during the performance of this availability.
NOTICE!
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.3 Authorized coating systems. The Contractor shall be aware that all coatings and coating systems authorized for use on Coast Guard cutters and boats are listed in COMDTINST M10360.3, Appendix C; however, the “International Interfine 979” Polysiloxane System is no longer an authorized system.
4. NOTES
4.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may be accessed at the following URL address: www.uscg.mil/directives/default.asp
Page 2 (Rev 4)
4.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 0000_STD to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this item.
Page 3 (Rev 4)
07400_BB_0611_SBPL
WORK ITEM 1: General Welding, Provide
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to provide general welding.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
None.
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual (June 2006)
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements
Surface Forces Logistics Center Standard Specification (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 Welding The Contractor shall provide general welding, including but not limited to, fabrication, brazing, inspection, plate renewal, crack repair, overlay, and associated processes on Coast Guard vessels and equipment in accordance with SFLC Standard Specification 0740 Welding and Allied Processes.
4. NOTES
This section is not applicable to this work item.
Page 4 (Rev 4)
07400_BB_0611_SBPL
WORK ITEM 2: Ultrasonic Testing (UT) Shots, Perform
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to take 100 UT shots at locations designated by the Coast Guard Inspector.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
None.
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual (June 2006)
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements
Surface Forces Logistics Center Standard Specification (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes
OTHER REFERENCES
ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method
3. REQUIREMENTS
3.1 Ultrasonic thickness (UT) measurement. The Contractor shall perform a total of 100 thickness measurements of .140, in locations designated by the Coast Guard Inspector. Submit a CFR.
3.1.1 Ensure that the ultrasonic apparatus, procedure requirements, and report shall be in accordance with ASTM E797, and that the report results shall additionally include the following information for each test point:
Location.
Original metal thickness.
Page 5 (Rev 4)
Measured metal thickness.
Percent deterioration (calculation is based on the original metal thickness).
3.1.2 Perform ultrasonic equipment standardization in accordance with ASTM E797, Section 7 (Standardization of Apparatus) and Section 8 (Technical Hazards).
Page 6 (Rev 4)
11100_3/16”SteelPlate_0210_FLT REC_11100_Steel_FLT_49’ BUSL (0210)
WORK ITEM 3: Hull and Structural Plating - 3/16" Steel Plate , Repair
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew 3/16" hull plating.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 49A BUSL 71-50-5, Rev A, Weather tight Doors
Coast Guard Drawing 49A BUSL 71-50-6, Rev A, Weather tight Doors
Coast Guard Drawing 49A BUSL 130-002, Rev D, Main Deck Plating and Framing
Coast Guard Drawing 49A BUSL 631-001, Rev F, Paint Schedule
Coast Guard Drawing 49A BUSL 635-001, Rev D, Hull Insulation Schedule and Insulation Details
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual, (June 2006)
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements
Surface Forces Logistics Center Standard Specification (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 General. The Contractor shall perform the tasks specified herein, using Coast Guard Drawing as guidance.
NOTE
This item does not address interferences in way of repair work. Cost of interference removal and reinstallation must be negotiated via the Change Request process.
Page 7 (Rev 4)
3.2 Renewal. The Contractor shall renew 3/16” steel hull plating, as designated by the Coast Guard Inspector, up to 4 square feet, using Coast Guard Drawing as guidance.
3.3 Touch-up preservation. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with COMDTINST M10360.3, Appendix A (Cutter and Boat Exterior Painting Systems) and Appendix B (Cutter and Boat Interior Painting Systems), respectively, and as applicable. Abide by all touch-up requirements outlined in SFLC Std Spec 0000, Appendix A (Requirements for Preservation of Ship Structures).
This section is not applicable to this work item
Page 8 (Rev 4)
11100_BB_0611_49BUSL
REC_11100_Steel_FLT_49’ BUSL (0210)
WORK ITEM 4: Hull and Structural Plating - Steel Plate, Repair
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew 5/16”, steel shell plating.
1.2 Government-furnished property
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 49A BUSL 71-50-5, Rev A, Weather tight Doors
Coast Guard Drawing 49A BUSL 71-50-6, Rev A, Weather tight Doors
Coast Guard Drawing 49A BUSL 130-002, Rev D, Main Deck Plating and Framing
Coast Guard Drawing 49A BUSL 631-001, Rev F, Paint Schedule
Coast Guard Drawing 49A BUSL 635-001, Rev D, Hull Insulation Schedule and Insulation Details
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual, (June 2006)
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements
Surface Forces Logistics Center Standard Specification (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor shall perform the tasks specified herein, using Coast Guard Drawings as guidance.
NOTE
Page 9 (Rev 4)
3.2 Renewal. The Contractor shall renew 5/16”, steel plating, as designated by the Coast Guard Inspector, up to 4 square feet, using Coast Guard Drawings as guidance.
3.3 Touch-up preservation. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with COMDTINST M10360.3, Appendix A (Cutter and Boat Exterior Painting Systems) and Appendix B (Cutter and Boat Interior Painting Systems), respectively, and as applicable. Abide by all touch-up requirements outlined in SFLC Std Spec 0000, Appendix A (Requirements for Preservation of Ship Structures).
Page 10 (Rev 4)
11100_3/16”SteelPlate_0210_FLT
REC_11100_Steel_FLT_49’ BUSL (0210)
WORK ITEM 5: Hull and Structural Plating – Degraded Weld (Steel), Repair
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew degraded steel welds.
1.2 Government-furnished property
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 49A BUSL 71-50-5, Rev A, Weather tight Doors
Coast Guard Drawing 49A BUSL 71-50-6, Rev A, Weather tight Doors
Coast Guard Drawing 49A BUSL 130-002, Rev D, Main Deck Plating and Framing
Coast Guard Drawing 49A BUSL 631-001, Rev F, Paint Schedule
Coast Guard Drawing 49A BUSL 635-001, Rev D, Hull Insulation Schedule and Insulation Details
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual, (June 2006)
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements
Surface Forces Logistics Center Standard Specification (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 General. The Contractor shall perform the tasks specified herein, using Coast Guard Drawings as guidance.
Page 11 (Rev 4)
3.2 Renewal. The Contractor shall renew the degraded steel welds designated by the Coast Guard Inspector, up to 10 linear feet in increments of one linear foot.
3.3 Touch-up preservation. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with COMDTINST M10360.3, Appendix A (Cutter and Boat Exterior Painting Systems) and Appendix B (Cutter and Boat Interior Painting Systems), respectively, and as applicable. Abide by all touch-up requirements outlined in SFLC Std Spec 0000, Appendix A (Requirements for Preservation of Ship Structures).
Page 12 (Rev 4)
WORK ITEM 6: Lazarette QAWTH (TCTO TB6010.B), Renew
1. SCOPE
1.1 Intent This work item describes the requirements for the Contractor to Replace the Lazarette Hatch in accordance with TCTO BUSL-49 TB6010.
1.2 Government-furnished property
MTI ITEM DESCRIPTION NSN/PN QTY Estimated Cost
N Freeman Marine Watertight Quick Acting Hatch
2040-01-F07-1174 1 ea $1922.90
N Oval Aluminum Hatch Steel Ring 0031-2226 1 ea $100.00
Note:
Refer to Coast Guard Time Compliance Technical Order TCTO- BUSL-49 TB6010.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 49A BUSL 71-50-5, Rev A, Weather tight Doors
Coast Guard Drawing 49A BUSL 71-50-6, Rev A, Weather tight Doors
Coast Guard Drawing 49A BUSL 130-002, Rev D, Main Deck Plating and Framing
Coast Guard Drawing 49A BUSL 631-001, Rev F, Paint Schedule
Coast Guard Drawing 49A BUSL 635-001, Rev D, Hull Insulation Schedule and Insulation Details
COAST GUARD PUBLICATIONS
Technical Order TCTO- BUSL-49 TB6010
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements
Surface Forces Logistics Center Standard Specification (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes
OTHER REFERENCES
Page 13 (Rev 4)
3. REQUIREMENTS
3.1 Requirements. The Contractor shall complete TCTO- BUSL-49 TB6010 – Replace the Lazarette Hatch in accordance with SFLC Std Spec 0000, SFLC Std Spec 0740, and applicable Coast Guard Drawings.
3.1.1 Reporting The Contractor shall submit a CFR
3.1.2 TCTO-BUSL-49 TB6010 is attached below:
Page 14 (Rev 4)
Page 15 (Rev 4)
Page 16 (Rev 4)
Page 17 (Rev 4)
Page 18 (Rev 4)
Page 19 (Rev 4)
Page 20 (Rev 4)
Page 21 (Rev 4)
WORK ITEM 7: Rub Rail, Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to remove, inspect, and reinstall the rub rail system, and the stern fender system (batter boards).
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
N **Duramax 49 BUSL Linerite Dunnage Kit
PN: 813000044 1 ea. 1,986.00
N **Rub rail side fender kit PN: 802101003 2 ea. 603.00 N **Rub rail side Fender kit PN: 802100903 2 ea. 661.92 N **Rub rail side fender kit PN: 802100803 2 ea. 659.99 N **Stern Fender kit PN: 802100503 1 ea. 65.00 N **Bow nose fender kit PN: 802022504C 1 ea. 896.00 N **Stern corner fender kit PN: 802022404C 2 ea. 448.00
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 49BUSL 114-003, Rev E, Chain Guard and Rub Rails
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual, (June 2006)
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 Requirements The Contractor shall accomplish the following in accordance with the applicable Coast Guard Drawing.
Page 22 (Rev 4)
3.2 Inspections The Contractor shall complete the following tasks:
3.2.1 Clean and visually inspect each section of rub rail, the shell plating in way of the removed rub rail sections, and each mounting fastener (stud and bonded disk, and washer) for damage including but not limited to pitting, corrosion, gouging, fading, cracks, deformation, coating system (if applicable), etc.
3.2.2 Reporting The Contractor shall submit a CFR.
Related work item: Remove and Install Rub Rail Fender.
Page 23 (Rev 4)
11020_BB_0611_49BUSL
WORK ITEM 8: Rub Rail Fender System, Remove and Install
1. SCOPE
1.1 Intent This work item describes the requirements for the Contractor to remove and install the entire rub rail or sections as designated by the Coast Guard Inspector.
1.2 Government-furnished property
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATE
D COST
($/UNIT)
N Duramax 49BUSL Linerite Dunnage Kit (complete) 813000044 1 ea $1,986.00
N 3 ½” x 3 ½” x 15” long 813000040 1 ea $146.00
N 3 ½” x 3 ½” x 45” long 813000043 1 ea $310.00
N 3 ½” x 3 ½” x 54” long 813000042 1 ea $336.00
N 3 ½” x 3 ½” x 50” long 813000037 1 ea $325.00
N 49‟ BUSL Fender Kit (complete) 802031904 1 ea $6,146.68
N Forward side fender kit 802101003 2 ea $752.14
N Aft side fender kit 802100903 2 ea $827.93
N Buoy Deck Fenders 802100803 2 ea $825.52
N Stern fender kit 802100503 1 ea $113.05
N Bow nose fender kit 802022504 1 ea $591.01
N Stern corner fender kit 802022404 2 ea $315.72
Coast Guard Drawing 49A BUSL 114-003, Rev E, Chain Guard and Rub Rails
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual, (June 2006)
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes
Page 24 (Rev 4)
3.1 Requirements The Contractor shall accomplish the following in accordance with the applicable Coast Guard Drawing:
3.1.1 Remove each rub rail section, taking care to avoid damaging them during removal.
3.2 Installation The Contractor shall install each rub rail section using applicable Coast Guard Drawing.
3.3 Government reserves the right to provide new rub rail sections. If the Government exercises this right, the Contractor shall dispose of the old section(s) in accordance with all applicable Federal, state, and local regulations.
3.4 Mounting hardware (stud) renewal. If a Change Request has been authorized and released, the Contractor shall install new Government furnished mounting hardware at designated locations, consisting of a stud and a bonded disk, in accordance with SFLC Standard Spec 0740.
3.5 Government reserves the right to provide new mounting hardware and or sections of rubber bumper. If the Government exercises this right, the Contractor shall dispose of the old hardware and or sections of rubber bumper as directed by the COTR.
Related work item: Inspect Rub Rail Fender.
Page 25 (Rev 4)
11010_BB_BUSL_0310_FLT
REC_11010_UT_FLT_49’ BUSL (ALL) (0110)
10000_BB_0411_49BUSL
WORK ITEM 9: Hull Plating (U/W Body) Ultrasonic Testing, Perform
1 SCOPE
1.1 Intent This work item describes the requirements for the Contractor to take 100 UT shots at locations designated by the Coast Guard Inspector.
1.2 Government-furnished property
None
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 49A BUSL 085-003, Rev A, Docking Plan
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements
Surface Forces Logistics Center Standard Specification (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes
OTHER REFERENCES
ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method
3. REQUIREMENTS
3.1 Ultrasonic thickness measurement. The Contractor shall perform a total of 100 thickness measurements, in locations designated by the Coast Guard Inspector.
3.1.1 Submit a CFR. The ultrasonic apparatus, procedure requirements, and report shall be in accordance with ASTM E797. The report results shall include, the following for each test point:
Location.
Original metal thickness.
Measured metal thickness.
Percent deterioration (calculation is based on the original metal thickness).
Page 26 (Rev 4)
Page 27 (Rev 4)
WORK ITEM 10: Bilges, Inspect
1. SCOPE
1.1 Intent This work item describes the requirements for the Contractor to inspect the vessel‟s bilge…
This is the start of the file's text. The full file is on GovTribe.
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .