55108_DD_TLT_10R0 Spec.pdf
PDF 506 KB Posted
- Attached to
- USCG ANT VENICE (CG 55108) 10 Drydock Repair
- Solicitation number
- HSCG40-10-Q-P30X29
About this file
Specification for USCG ANT VENICE (CG 55108) 10 DD
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT 7 ANB 55108 10 DD.doc | DOC document | |
| Amendment 6 ANB 55108.pdf | ||
| AMENDMENT 5 ANB 55108 10 DD.doc.pdf | ||
| Amendment 4 ANB 55108.pdf | ||
| AMENDMENT 3 ANB 55108 10 DD.pdf | ||
| Amendment 2.pdf | ||
| RFQ 55108.doc | DOC document | |
| AMENDMENT 1 ANB 55108 10 DD.doc | DOC document | |
| RFQ 55108.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCG ANT VENICE (CG 55108)
55 FOOT AIDS TO NAVIGATION BOAT
SPECIFICATIONS FOR DRYDOCK REPAIRS
Developed By:
Thacher Taft
Commander Surface Forces Logistics Command 300 E. Main Street, Suite (600) Norfolk, VA 23510-9102
(03/01/2010 Rev-0)
TABLE OF CONTENTS
Work Item Title Page
List of Sketches iv
Revisions Record v
List of Applicable References vi
List of Government/Industrial-furnished property x
List of Critical Inspection Items xii
Specification Feedback xiii
Principal Characteristics xiv
General Requirements 1
1 Welding Repairs – Flat Plate Renewal (3/16” Aluminum) 8
2 Welding Repairs – Flat Plate Renewal (1/4” Aluminum) 10
3 Welding Repairs – Flat Plate Renewal (5/16” Aluminum) 12
4 Welding Repairs – Flat Plate Renew (3/8” Aluminum) 14
5 Welding Repairs – Overlay (Aluminum) 15
6 Welding Repairs – Crack (Aluminum) 16
7 Welding Repairs – Fill Unused Holes In Buoy Deck Grate Frames <CSMP-2009008> 17
8 Perform Ultrasonic Thickness Measurements – Freeboard & Hull Plating 18
9 Additional Ultrasonic Thickness Measurements – Freeboard & Hull Plating 20
10 Air Test Inaccessible Voids 22
11 Remove, Inspect, and Reinstall Rub Rail System 24
Page i (Rev-0)
12 Renew Fendering System <CSMPs-2009,005,009> 27
13 Renew Shear Bar Rail Section 29
14 Renew Engine Room Insulation <CSMP-2007002> 31
15 Remove, Inspect, and Renew Forepeak Bilge Chocking (Chockfast) <CSMP-2009001> 33
16 Renew Overboard Discharge Piping <CSMP-2009002> 34
17 Realign Main Engine/Reduction Gear to Shaft <CSMP- 2008002> 36
18 Remove, Inspect and Reinstall Propeller Shaft(s) 38
19 Remove and Reinstall Propeller(s) 43
20 Renew Sea Valves <CSMP-2009004> 46
21 Inspect and Overhaul Duplex Sea Strainers 49
22 Renew Fuel Valves 53
23 Clean and Inspect Exhaust Piping System(s) (Renew Mufflers) 55
24 Remove, Inspect, and Reinstall Rudder(s) 58
25 Renew Potable Water Pressure Accumulating Tank and Piping (Preserve and Disinfect) <CSMP- 2008001> 62
26 Clean, Inspect and Disinfect Potable Water Tank 64
27 Preserve Potable Water Tank 67
28 Clean and Inspect Grey Water Holding and Sewage Tanks 70
29 Clean and Inspect Fuel Service Tanks <CSMP-2009006> 73
30 Renew Strut and Stern Tube Bearings 76
31 Routine Drydocking 78
32 Provide Temporary Logistics 81
33 Inspect & Test Air Receiver, Renew Relief Valve 82
Page ii (Rev-0)
34 Preserve Underwater Body – 100% 85
Page iii (Rev-0)
List of Sketches
Work Item Sketch Number Page
This Sketch is not applicable to this document.
Page iv (Rev-0)
Revisions Record
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package.
Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK ITEM# CHANGES MADE
NOTE: All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
Page v (Rev-0)
List of Applicable References
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution. Electronic copies of the latest Editions of MLCA Standard Specifications are available on the Internet and may be accessed at the following Internet Uniform Resource Locator (URL) address:
http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp
Guidance for obtaining copies of all other documents referenced herein is provided in the solicitation.
Order of precedence. In the event of conflicts between text of this specification and the applicable references specified herein, order of precedence shall be in accordance with SFLC Standard Specification 0000_STD, paragraph 3.2.1.1 (Order of Precedence), unless otherwise specified by the Contracting Officer (KO). The Contractor shall immediately notify the KO in writing of any perceived conflicts contained herein. Nothing in these documents, however, supersedes applicable laws and regulations, unless a specific exemption has been obtained.
FEDERAL AND MILITARY SPECIFICATIONS AND STANDARDS
MIL-G-24716A, Apr 1993, Gaskets, Metallic-Flexible Graphite, Spiral Wound
MIL-PRF-24647, Feb 2005, Paint System, Anticorrosive And Antifouling, Ship Hull
Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting
OTHER GOVERNMENT DOCUMENTS, DRAWINGS, AND PUBLICATIONS
DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0000_STD, 2009 Edition, General Requirements
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0740, 2009 Edition, Welding and Allied Processes
Page vi (Rev-0) http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp
Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 1001, 2004 Edition, Temporary Hull Accesses
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 8634, 2009 Edition, Drydocking
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 8635, 2009 Edition, Provide Temporary Logistics
DRAWINGS
Coast Guard Drawing 55-ANB-0103-1 Rev C, Inboard Profile Sections and Arrangements
Coast Guard Drawing 55-ANB-0103-2, Rev M, Outboard Profile, Sections & Arrg (A Class)
Coast Guard Drawing 55-ANB 1101-1, Rev D, Construction Plan & Sections (A Class)
Coast Guard Drawing 55-ANB 2200-2, Rev A, Steering Hydraulic System (A Class)
Coast Guard Drawing 55-ANB 3901-1, Rev A, Insulation Installation (Thermal Type) (A Class)
Coast Guard Drawing 55-ANB 4000-1, Rev D, Machinery Arrangement (A Class)
Coast Guard Drawing 55-ANB 4000-2, Rev B, Machinery Details (A Class)
Coast Guard Drawing 55-ANB 4103-1, Rev B, Main Engine Raw Water & Reduction Gear L/O Piping (A Class)
Coast Guard Drawing 55-ANB 4301-1, Rev A, Forward End Of Propeller Shaft and Propeller Shaft Coupling (A Class)
Coast Guard Drawing 55-ANB 4804-1, Rev A, Fresh Water Tank Access & Cover (A Class)
Coast Guard Drawing 55-ANB-4808-1, Rev B, Drains & Holding Tank Piping (A Class)
Coast Guard Drawing 55-ANB 5500-1, Rev A, Fuel Supply Diagram (A Class)
Page vii (Rev-0)
Coast Guard Drawing 55-ANB-4808-1, Rev B, Drains & Holding Tank Piping (A Class)
Coast Guard Drawing 55-ANB-500-1, Rev A, Lines & Offsets (A Class)
Coast Guard Drawing 55B-ANB 634-1, Rev -, Deck Covering
Coast Guard Drawing 55-ANB-700-1, Rev B, Docking Plan & Profile (A Class)
Coast Guard Drawing 55-ANB-4000-1, Rev D Machinery Arrangement (A Class)
Coast Guard Drawing 55-ANB 4801-1, Rev D, Bilge Piping (A Class)
Coast Guard Drawing 55-ANB 3803-2, Rev A, Air Conditioning System (A Class)
PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (Series), June 2006, Coatings and Color Manual
Coast Guard Technical Publication (TP) 3394, Manufacturer’s Information Book – SWBS Groups 167-261, Jan 2006, SWBS 261 – Fuel Service System
Coast Guard Technical Publication (TP) 2048C, SWBS 233, Rev.
11/75, Diesel Main, V71 Series- Service Manual
Coast Guard Technical Publication (TP) 3394A, SWBS 241, Feb 1976, Propulsion Gear
INDUSTRY STANDARDS
American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2003 Edition, Bronze Gate, Globe, Angle and Check Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves
Page viii (Rev-0)
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
The Society for Protective Coatings (SSPC) Paint Application Specification No. 2 (SSPC-PA Guide 2), 2004, Measurement of Dry Coating Thickness with Magnetic Gages
International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50m, Inclusive
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method
ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates
American Water Works Association (AWWA) C652, 2002, Disinfection of Water-Storage Facilities
Page ix (Rev-0)
List of Government/Industrial-furnished property
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM MTI ITEM DESCRIPTION NSN/PN QTY
ESTIMATED
COST
($/UNIT)
11 N Rub rail (20ft.) NSN: 2040-01-255-3443 6 ea. 501.76
11 N **Batterboard (Duramax) generic or equivalent fender for
55 ANB
10 ea. 80.00
11 N Titanium Mounting Studs NSN: 5307-01-435-0998 40 ea. 61.51
11 N Nut, Plain NSN: 5310-01-435-1001 40 ea. 4.86
11 N Washer, Flat NSN: 5310-01-435-1037 40 ea. 1.09
18 Y Shaft Coupling NSN: 3040-01-135-4315 2 ea. 1,111.69
18 Y **Propeller
Shaft (A Class)
NSN: 0000-XF-C10-7726
http://www.aquanmet.com /contactinfo.nxg
2 ea. 2,200.00
18 Y Shaft Stuffing Box Hose NSN: 4720-01-412-7822 2 ea. 42.03
18 N Shaft Zinc 2-3/4” NSN: 000-XF-C05-8174 4 ea. 40.63
20 Y **Propeller, Right Hand NSN: 2010-01-130-4949 1 ea. 2,687.00
20 Y **Propeller, Left Hand NSN: 2010-01-125-3273 1 ea. 3,740.73
22 Y **2.5” Sea Valves NSN: 4820-01-187-3719 4 ea. 369.69
N
**2 1/2 inch Duplex Strainer
– Main Engine
NSN: 4730-01-033-1285
PN: GROCO VD-2500
2 ea. 1,953.49
23 N **3/4 inch
Duplex Strainer
– Generator &
A/C
PN: GROCO HD-750 2 ea. 687.00
Page x (Rev-0)
25 N **Muffler, Exhaust NSN: N/A 2 ea. 2,687.00
25 Y *Bearings, Strut/Hull NSN: 3120-01-131-3692 4 ea. 77.25
32 Y *Transducer cover plate - 1 ea. $50.00
32 Y **Hull Zinc NSN: 5342-00-290-8243 4 ea. 40.63
34 Y Safety Relief Valve NSN: 1 ea. 86.14
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government/Industrial-furnished property, which is to be supplied by either the vessel, Electronic Systems Support Unit (ESU) or local Electronic Support Detachment
(ESD).
Page xi (Rev-0)
List of Critical Inspection Items
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000_STD, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item Title
8 Perform Ultrasonic Thickness Measurements – Freeboard & Hull Plating
9 Perform Additional Ultrasonic Thickness Measurements – Freeboard & Hull Plating
12 Remove, Inspect, and Reinstall Rub Rail System and Transom Fenders
18 Remove, Inspect, and Reinstall Propeller Shaft(s), 26 Remove, Inspect, and Reinstall Rudder(s)
35 Preserve Underwater Body – 100%
Page xii (Rev-0)
Specification Feedback
The intent of this section is to inform all users that a spec feedback mechanism is in place, and is located on the MLCA Naval Engineering Division’s website. Spec feedback is a very important part of our overall continuous improvement process, and is crucial to specification development. It will allow spec writers to capture all specification-related lessons learned, and avoid mistakes or ambiguities in follow-on availabilities.
All feedback will be reviewed, evaluated, and responded to in a timely manner.
If you have access to the CGWeb (Intranet), please use the following link, which will connect you to the MLCA(v) Naval Engineering website, for submitting your feedbacks:
http://apps.mlca.uscg.mil/vdiv/surveys/Post_availability/ http://apps.mlca.uscg.mil/vdiv/surveys/Post_availability/
If you do not have access to the CGWeb (Intranet), you may still submit your feedbacks, using the following web link:
http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp.
http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp.
Page xiii (Rev-0) http://apps.mlca.uscg.mil/vdiv/surveys/Post_availability/ http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp
Page xiv (Rev-0)
PC_55 ANB
(11 Apr 2006)
Principal Characteristics
55 FOOT AIDS TO NAVIGATION BOAT (ANB)
Length Overall (LOA) 58' 4"
Beam, maximum 16' 9”
Full Load Displacement 74,066 lbs. (33 LT)
Draft at Operating Displacement 5' 0"
Draft at Full Displacement 5' 11-1/8”
Shore Tie Voltage Requirements 120VAC
PROPULSION
Type Diesel Engine
Number of Units Two, Detroit Diesel, Model 12V-71-TA
Total Shaft Horsepower 1,080
PROPELLERS
Number of Propellers 2
Number of Blades per Propeller 3
Diameter of Propeller 38”
Pitch 32” fixed
Shaft Revolutions per minute (RPM) 920
00000N_BOATS (9 July 2009) Project at Contractor Facility
General Requirements
1. SCOPE
1.1 Intent. This item describes the general requirements to be followed by the Contractor while conducting this availability at the Contractor’s facility.
2. APPLICABLE DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0000_STD, 2009 Edition, General Requirements
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (Series), Jun 2006, Coatings and Color Manual
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in Std Spec 0000_STD and in this item, as applicable, during the performance of this availability.
NOTICE!
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Contractor-provided fire watch personnel. The Contractor
shall provide fire watch personnel and equipment.
3.3 Authorized coating systems. The Contractor shall be aware that all coatings and coating systems authorized for use on Coast Guard cutters and boats are listed in COMDTINST M10360.3, Appendix C; however, the “International Interfine 979” Polysiloxane System is no longer an authorized system.
03/01/2010 Page 1 (Rev-0)
4. NOTES
4.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may
be accessed at the following URL address:
http://www.uscg.mil/directives/default.asp
4.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 0000_STD to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this item.
03/01/2010 Page 2 (Rev-0) http://www.uscg.mil/directives/default.asp
03/01/2010 Page 3 (Rev-0)
03/01/2010 Page 4 (Rev-0)
03/01/2010 Page 5 (Rev-0)
03/01/2010 Page 6 (Rev-0)
07400
03/01/2010 Page 7 (Rev-0)
07402O_BOATS (Aug 2009) 55108_DD_TLT (23 Nov 2009)
WORK ITEM 1: Welding Repairs – Flat Plate Renewal (3/16” Aluminum)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform welding repairs – flat plate renewal (3/16” aluminum).
1.2 Government/Industrial-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0740, 2009 Edition, Welding and Allied Processes
3. REQUIREMENTS
3.1 General. The Contractor shall perform all welding and
nondestructive inspection (NDI) in accordance with SFLC Std Spec 0740. This work item includes all welding related activities only and does not include interference removal.
3.2 Electronic equipment protection. The Contractor shall
safeguard electronic equipment before welding to prevent damage from stray current and electromagnetic interference.
Electrically isolate or disconnect ungrounded or sensitive equipment as necessary. Locate all welder ground connections as close to the work as possible.
3.3 Renewal. If a Change Request has been authorized and
released by the KO, the Contractor shall renew the designated flat plate aluminum, up to 10 square feet in increments of 2 square feet.
03/01/2010 Page 8 (Rev-0)
This section is not applicable to this work item.
03/01/2010 Page 9 (Rev-0)
07403O_BOATS (Aug 2009)
WORK ITEM 2: Welding Repairs – Flat Plate Renewal (1/4” Aluminum)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform welding repairs – flat plate renewal (1/4” aluminum).
1.2 Government/Industrial-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0740_STD, 2009 Edition, Welding and Allied Processes
3. REQUIREMENTS
3.1 General. The Contractor shall perform all welding and
nondestructive inspection (NDI) in accordance with SFLC Std Spec 0740. This work item includes all welding related activities only and does not include interference removal.
3.2 Electronic equipment protection. The Contractor shall
safeguard electronic equipment before welding to prevent damage from stray current and electromagnetic interference.
Electrically isolate or disconnect ungrounded or sensitive equipment as necessary. Locate all welder ground connections as close to the work as possible.
3.3 Renewal. If a Change Request has been authorized and
released by the KO, the Contractor shall renew the designated flat plate aluminum, up to 10 square feet in increments of 2
03/01/2010 Page 10 (Rev-0)
03/01/2010 Page 11 (Rev-0)
07403O_BOATS (Aug 2009) 55108_DD_TLT (15 Dec 2009)
WORK ITEM 3: Welding Repairs – Flat Plate Renewal (5/16” Aluminum)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform welding repairs – flat plate renewal (5/16” aluminum).
1.2 Government/Industrial-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0740_STD, 2009 Edition, Welding and Allied Processes
3. REQUIREMENTS
3.1 General. The Contractor shall perform all welding and
nondestructive inspection (NDI) in accordance with SFLC Std Spec 0740. This work item includes all welding related activities only and does not include interference removal.
3.2 Electronic equipment protection. The Contractor shall
safeguard electronic equipment before welding to prevent damage from stray current and electromagnetic interference.
Electrically isolate or disconnect ungrounded or sensitive equipment as necessary. Locate all welder ground connections as close to the work as possible.
3.3 Renewal. If a Change Request has been authorized and
released by the KO, the Contractor shall renew the designated flat plate aluminum, up to 10 square feet in increments of 2
03/01/2010 Page 12 (Rev-0)
03/01/2010 Page 13 (Rev-0)
07405O_BOATS (27 Aug 2009) 55108_TLT (23 Nov 2009)
WORK ITEM 4: Welding Repairs – Flat Plate Renew (3/8” Aluminum)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform welding repairs – flat plate renewal (3/8” aluminum).
1.2 Government/industrial-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0740, 2009 Edition, Welding and Allied Processes
3. REQUIREMENTS
3.1 General. The Contractor shall perform all welding and
nondestructive inspection (NDI) in accordance with SFLC Std Spec 0740. This work item includes all welding related activities only and does not include interference removal.
3.2 Electronic equipment protection. The Contractor shall
safeguard electronic equipment before welding to prevent damage from stray current and electromagnetic interference.
Electrically isolate or disconnect ungrounded or sensitive equipment as necessary. Locate all welder ground connections as close to the work as possible.
3.3 Renewal. If a Change Request has been authorized and
released by the KO, the Contractor shall renew the designated flat plate aluminum, up to 10 square feet in increments of 2 square foot.
4. NOTES
03/01/2010 Page 14 (Rev-0)
07400D_BOATS (12 Feb 2007)
WORK ITEM 5: Welding Repairs – Overlay (Aluminum)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform welding repairs – overlay (aluminum).
1.2 Government/Industrial-furnished property.
None.
2. APPLICABLE DOCUMENTS
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes
3. REQUIREMENTS
3.1 General. The Contractor shall perform all welding and
nondestructive inspection (NDI) in accordance with SFLC Std Spec 0740. This work item includes all welding related activities only and does not include interference removal.
3.2 Electronic equipment protection. The Contractor shall
safeguard electronic equipment before welding to prevent damage from stray current and electromagnetic interference.
Electrically isolate or disconnect ungrounded or sensitive equipment as necessary. Locate all welder ground connections as close to the work as possible.
3.3 Renewal. If a Change Request has been authorized and
released by the KO, the Contractor shall renew the designated overlay aluminum, up to 10 square inches in increments of 2 square inches.
4. NOTES
03/01/2010 Page 15 (Rev-0)
07407O_BOATS (Aug 2009)
WORK ITEM 6: Welding Repairs – Crack (Aluminum)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to repair the cracked aluminum welds.
1.2 Government/Industrial-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0740, 2009 Edition, Welding and Allied Processes
3. REQUIREMENTS
3.1 General. The Contractor shall perform all welding and
nondestructive inspection (NDI) in accordance with SFLC Std Spec 0740_STD. Be aware that this work item includes all welding related activities only and does not include interference removal.
3.2 Repair particulars. If a Change Request has been
authorized and released by the KO, the Contractor shall repair the designated aluminum plate and frame, up to 20 linear feet in increments of one linear foot.
4. NOTES
03/01/2010 Page 16 (Rev-0)
07400O_BOATS (Aug 2009) 55108_DD_DTJ (09 Feb 2010)
WORK ITEM 7: Welding Repairs – Fill Unused Holes In Buoy Deck Grate Frames <CSMP-2009008>
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to repair the cracked aluminum welds.
1.2 Government/Industrial-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0740, 2009 Edition, Welding and Allied Processes
3. REQUIREMENTS
3.1 General. The Contractor shall perform all welding and
nondestructive inspection (NDI) in accordance with SFLC Std Spec 0740_STD. Be aware that this work item includes all welding related activities only and does not include interference removal.
3.2 Repair particulars.
3.2.1 The Contractor shall remove buoy deck grates.
3.2.2 Fill by welding, unused holes in the buoy deck grate
frames up to 30 square inches in increments of 1 square inch as identified by the Coast Guard inspector.
3.2.3 Reinstall buoy deck grates.
4. NOTES
03/01/2010 Page 17 (Rev-0)
11001D_FLT (03 Dec 2008) 55108_DD_TLT (4 Dec 2009)
WORK ITEM 8: Perform Ultrasonic Thickness Measurements – Freeboard & Hull Plating
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform 150 thickness measurements of freeboard hull plating, by ultrasonic methods.
1.2 Government/Industrial-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Drawing 55B ANB 1101-001, Rev B, construction Profile Plan & Sections
ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method
3. REQUIREMENTS
3.1 General.
3.1.1 Critical Inspection Report. The Contractor shall submit a critical inspection report (CIR) for the inspections listed in the following paragraph(s), within 24 hours after inspection completion:
• 3.2 (Thickness measurement particulars).
3.2 Thickness measurement particulars. The Contractor shall
perform a total of 150 ultrasonic thickness measurements of hull and freeboard surfaces, in locations designated by the Coast Guard Inspector using Coast Guard Drawing 55B ANB 1101-001 as a reference. Submit a CIR. Ensure that the ultrasonic apparatus, procedure requirements, and report shall be in accordance with ASTM E797, and the report results shall additionally include the following, for each test point:
03/01/2010 Page 18 (Rev-0)
• Location.
• Original metal thickness.
• Measured metal thickness.
• Percent deterioration (calculation is based on the original metal thickness).
3.3 Apparatus Standardization. The Contractor shall perform
ultrasonic equipment standardization in accordance with ASTM E797, Section 7 (Standardization of Apparatus) and Section 8 (Technical Hazards).
4. NOTES
03/01/2010 Page 19 (Rev-0)
11000O_FLT (03 Dec 2008)
WORK ITEM 9: Additional Ultrasonic Thickness Measurements – Freeboard & Hull Plating
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform 50 thickness measurements of freeboard hull plating, by ultrasonic methods.
1.2 Government/Industrial-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Drawing 55B ANB 1101-001, Rev B, construction Profile Plan & Sections
ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method
3. REQUIREMENTS
3.1 General.
3.1.1 Critical Inspection Report. The Contractor shall submit a critical inspection report (CIR) for the inspections listed in the following paragraph(s), within 24 hours after inspection completion:
• 3.2 (Thickness measurement particulars).
3.2 Thickness measurement particulars. The Contractor shall
perform a total of 50 ultrasonic thickness measurements of hull and freeboard surfaces, in locations designated by the Coast Guard Inspector using Coast Guard Drawing 55B ANB 1101-001 as a reference. Submit a CIR. Ensure that the ultrasonic apparatus, procedure requirements, and report shall be in accordance with ASTM E797, and the report results shall additionally include the following, for each test point:
03/01/2010 Page 20 (Rev-0)
• Location.
• Original metal thickness.
• Measured metal thickness.
• Percent deterioration (calculation is based on the original metal thickness).
3.3 Apparatus Standardization. The Contractor shall perform
ultrasonic equipment standardization in accordance with ASTM E797, Section 7 (Standardization of Apparatus) and Section 8 (Technical Hazards).
03/01/2010 Page 21 (Rev-0)
12300D_55ANB (22 Sep 2009)
WORK ITEM 10: Air Test Inaccessible Voids
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to air test the boat's skeg and transducer void.
1.2 Government/Industrial-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0740, 2009 Edition, Welding and Allied Processes
Coast Guard Drawing 55-ANB 1101-1, Rev D, Construction Plan & Sections (A Class)
3. REQUIREMENTS
3.1 General.
3.2 Air test voids. The Contractor shall air test the
inaccessible voids and skeg shown on Coast Guard Drawing 55B ANB 1101-001 at a pressure of 2 psig for 10 minutes with no allowable leakage in accordance with SFLC Std Spec 0740.
3.2.1 Test Includes:
• Skeg
• Transducer void
3.2.2 Visually inspect any leaks. Submit a CFR.
3.3 Repeat test. The Contractor shall repeat test after
repairing any leaks, (3.2, 3.3) to verify no leaks remain.
3.4 Report. The Contractor shall submit a written condition
found report to COTR within 24 hours after inspection or test.
03/01/2010 Page 22 (Rev-0)
03/01/2010 Page 23 (Rev-0)
11100D_55ANB (23 Sep 2008)
WORK ITEM 11: Remove, Inspect, and Reinstall Rub Rail System
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to remove, inspect, and reinstall the rub rail system.
1.2 Government/Industrial-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED COST
($/UNIT)
N Rub rail (20ft.) NSN: 2040-01-255-3443 6 ea. 501.00
N Titanium Mounting Studs NSN: 5307-01-435-0998 40 ea. 60.29
N Nut, Plain NSN: 5310-01-435-1001 40 ea. 4.86 N Washer, Flat NSN: 5310-01-435-1037 40 ea. 1.09
2. APPLICABLE DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0000, 2009 Edition, General Requirements
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Coatings and Color Manual
Coast Guard Drawing 55-ANB 103-2, Rev M, Outboard Profile, Sections & Arrg (A Class)
Coast Guard Drawing 55-ANB 1101-1, Rev D, Construction Plans and Sections (A Class)
Coast Guard Drawing 55-ANB 1101-2, Rev A, Construction Details (A Class)
03/01/2010 Page 24 (Rev-0)
3. REQUIREMENTS
3.1 Inspection particulars. Using Coast Guard Drawing 55B ANB 103-01 as a guide, the Contractor shall inspect the rub rail system by completing the following:
3.1.1 Interferences. The Contractor shall be aware that
interferences in way of work include, but are not limited to the following:
• Insulation
3.1.2 Remove the rub rail system.
3.1.3 Visually inspect each rub rail and the shell plate in way of the removed rub rail section(s). Submit CIR.
3.2 Preservation. The Contractor shall paint shear bar in
accordance with SFLC Std Spec 0000, paragraph titled “Preservation requirements - general” and COMDTINST M10360.3, Appendix A (Cutter and Boat Exterior Painting Systems).
3.3 Reinstallation. The Contractor shall accomplish the
following:
3.3.1 Reinstall the rub rail system and renew all associated
hardware. The mounting hardware for the rub rail system consists of a 1 ½ inch x 3/16 inch stainless steel flat bar insert and fasteners. A fastener consists of a ½ inch N.C. stud and stainless steel washers and nut.
3.3.2 The contractor shall fabricate and install rub rail end-caps for the aft end of the rub rails. The caps shall be made of the same material as the rub rails.
3.4 Touch-up preservation. Prepare and touch-up coat all
disturbed surfaces to match existing adjacent surfaces, in accordance with SFLC Std Spec 0000_STD, paragraph titled “General preservation requirements” and COMDTINST M10360.3, Appendix A (Cutter and Boat Exterior Painting Systems).
3.5 Rub rail section renewal. If a Change Request has been
released and authorized by the KO, the Contractor shall renew a section of the rub rail system using Government furnished material. The Contractor shall fit designated sections of the rub rail. Use Coast Guard Drawing 55B ANB 103-02 for guidance.
03/01/2010 Page 25 (Rev-0)
3.6 Stud renewal. If a Change Request has been released and
authorized by the KO, the Contractor shall renew designated studs using, government furnished material, to eliminate flat bar insert and fasteners. Weld GFE studs over existing mating holes.
03/01/2010 Page 26 (Rev-0)
11100D_55ANB (23 Sep 2008) 55108_DD_DTJ (08 Feb 2010)
WORK ITEM 12: Renew Fendering System <CSMPs- 2009,005,009>
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew the stern fender sections.
1.2 Government/Industrial-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED COST
($/UNIT)
N Composite Batterboard
(Duramax) generic or equivalent fender for 55
ANB
10 ea. 80.00
2. APPLICABLE DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0000_STD, 2009 Edition, General Requirements
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Coatings and Color Manual
Coast Guard Drawing 55-ANB-0103-1 Rev C, Inboard Profile Sections and Arrangements
Coast Guard Drawing 55-ANB-0103-2, Rev M, Outboard Profile, Sections & Arrg (A Class)
3.1 Inspection particulars. Using Coast Guard Drawing 55B ANB 103-01 as a guide, the Contractor shall inspect the rub rail system and the stern fender sections by completing the following:
03/01/2010 Page 27 (Rev-0)
3.1.2 Remove the stern fender sections to include fendering on the port and starboard quarters. Dispose of removed fendering materials in accordance with federal, state, and local laws and regulations.
3.1.3 Visually inspect the shell plate in way of the removed
fender section(s). Submit CIR.
3.2 Preservation. The Contractor shall preserve shell plating in accordance with SFLC Std Spec 0000, paragraph titled “Preservation requirements - general” and COMDTINST M10360.3, Appendix A (Cutter and Boat Exterior Painting Systems).
3.3 Renewal. The Contractor shall renew the stern fender
sections using new stainless steel mounting hardware and government furnished Linerite II fender material.
NOTICE!
Fendering material provided by the government will be in bulk lengths approximately ten (10) feet in length that will have to be cut to length and drilled for fasteners.
3.4 Touch-up preservation. Prepare and touch-up coat all
disturbed surfaces to match existing adjacent surfaces, in accordance with SFLC Std Spec 0000_STD, paragraph titled “General preservation requirements” and COMDTINST M10360.3, Appendix A (Cutter and Boat Exterior Painting Systems).
03/01/2010 Page 28 (Rev-0)
11100O_55ANB (04 Dec 2008) 55108_DD_TLT (24 Nov 2009)
WORK ITEM 13: Renew Shear Bar Rail Section
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew shear bar rail sections.
1.2 Government/Industrial-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0000, 2009 Edition, General Requirements
Coast Guard Drawing 55-ANB 1101-1, Rev D, Construction Plan & Sections (A Class)
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (Series), Coatings and Color Manual
3. REQUIREMENTS
3.1 Shear rail section renewal. The Contractor shall renew
designated section(s) of up to 86 feet of shear bar rail in one linear foot increments, using Coast Guard Drawing 55B ANB 1101- 001 as guidance.
3.1.1 Interferences. The Contractor shall be aware that
interferences in way of work include, but are not limited to the following:
• Insulation
3.2 Preservation. The contractor shall paint shear rail in
accordance with SFLC Std Spec 0000, paragraph titled “Preservation requirements- General” and COMDTINST M10360.3, Appendix A (Cutter and Boat Exterior Painting Systems).
03/01/2010 Page 29 (Rev-0)
03/01/2010 Page 30 (Rev-0)
63500_55ANB (17 Dec 2009)
WORK ITEM 14: Renew Engine Room Insulation <CSMP- 2007002>
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew engine room overhead and bulkhead insulation in the engine room.
1.2 Government/Industrial-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0000, 2009 Edition, General Requirements
Coast Guard Drawing 55-ANB 3901-1, Rev A, Insulation Installation (Thermal Type) (A Class)
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (Series), Coatings and Color Manual
3. REQUIREMENTS
3.1 General. The Contractor shall renew all engine room
overhead and bulkhead insulation, using Coast Guard Drawing 55- ANB 1101-001 as guidance.
3.1.1 Interferences. The Contractor shall be aware that
interferences in way of work include, but are not limited to the following:
• Light fixtures
• Cable ways
• Electric switches
03/01/2010 Page 31 (Rev-0)
• Expanded metal sheathing
3.2 Insulation renewal: The Contractor shall remove and renew all engine room overhead and bulkhead insulation, using Coast Guard Drawing 55B ANB 1101-001 as guidance.
3.3 Disposal. The Contractor shall dispose of all removed
insulation in accordance with all local, state and Federal requirements.
4. NOTES
4.1 Acoustic insulation (SWBS 635): The overhead and sides of the engine room have acoustic insulation. It consists of a two inch thickness of glass fiber insulation, 1.5 pound density, MIL-I-22023 Type 2, Class 4, against surface to be treated and a layer of lead loaded vinyl sheet, one pound weight per square foot, with a two inch thick layer of glass fiber insulation of
2.25 pound density and vinyl film faced.
03/01/2010 Page 32 (Rev-0)
13000_55ANB (17 Dec 2009) 55108_DD_TLT (17 Dec 2009)
WORK ITEM 15: Remove, Inspect, and Renew Forepeak Bilge Chocking (Chockfast) <CSMP-2009001>
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew forepeak bilge chocking.
1.2 Government/Industrial-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0000, 2009 Edition, General Requirements
Coast Guard Drawing 55-ANB 1101-1, Rev D, Construction Plan & Sections (A Class)
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (Series), Coatings and Color Manual
3. REQUIREMENTS
3.1 General. The Contractor shall remove existing concrete
material, inspect forepeak bilge for water intrusion (submit CFR), and renew Chockfast, using Coast Guard Drawing 55B ANB 1101-001 and manufacturer instructions as guidance.
3.1.1 Interferences. The Contractor shall be aware that
interferences in way of work include, but are not limited to the following:
• Insulation
4. NOTES
03/01/2010 Page 33 (Rev-0)
13000_55ANB (17 Dec 2009)
WORK ITEM 16: Renew Overboard Discharge Piping <CSMP- 2009002>
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew overboard discharge piping.
1.2 Government/Industrial-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0000, 2009 Edition, General Requirements
Coast Guard Surface Forces Logistics Center (SFLC), Standard Specification 0740, 2009 Edition, Welding and Allied Processes
Coast Guard Drawing 55-ANB 4801-1, Rev D, Bilge Piping (A Class)
Coast Guard Drawing 55-ANB 3803-2, Rev A, Air Conditioning System (A Class)
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (Series), Coatings and Color Manual
3. REQUIREMENTS
3.1 General. The Contractor shall remove overboard piping
listed below and renew piping with ¾-inch diameter, 9-inch long 316L stainless steel piping, using Coast Guard Drawing 55-ANB 1101-1, 55-ANB 3803-2 and SFLC Standard Spec 0740 as guidance.
• Forward air conditioning overboard at frame 3.5 in berthing area, starboard side
• Aft air conditioning overboard at frame 6 in ATON shop, starboard side
03/01/2010 Page 34 (Rev-0)
• Sewage overboard discharge at approximately frame 5, port side located behind removable shower wall access under sewage treatment holding tank
3.1.1 Interferences. The Contractor shall be aware that
interferences in way of work include, but are not limited to the following:
• Insulation
• Starboard diesel tank
4. NOTES
03/01/2010 Page 35 (Rev-0)
S23320K_49 BUSL (4 Jun 2007) 23320O_55ANB (27 Oct 2009) 55108_DD_TLT (23 Nov 2009)
WORK ITEM 17: Realign Main Engine/Reduction Gear to Shaft
<CSMP-2008002>
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to realign the designated main diesel engine/marine gear assembly to its corresponding propeller shaft.
1.2 Government/Industrial-furnished property.
None.
2. APPLICABLE DOCUMENTS
Coast Guard Technical Publication (TP) 2048C, SWBS 233 Diesel Main, V71 Series- Service Manual
Coast Guard Technical Publication (TP) 3394A, SWBS 241 Propulsion Gear
Coast Guard Drawing 55-ANB 4000-001, Rev D, Machinery Arrangement (A Class)
Coast Guard Drawing 55-ANB 4301-1, Rev A, Forward End Of Propeller Shaft and Propeller Shaft Coupling (A Class)
3. REQUIREMENTS
3.1 General.
3.1.1 Engine realignment. The Contractor shall reposition the engine/reduction gear set to achieve a satisfactory alignment using Coast Guard Drawing 55B ANB-4301-1 for guidance. Final alignment measurement shall be witnessed by the Coast Guard Inspector. Submit a CFR.
03/01/2010 Page 36 (Rev-0)
3.1.1.1 Final alignment. The Contractor shall conduct final
coupling axial and face to face alignment and align the engine shaft alignment twenty-four hours after being placed back in the water and loaded to at least 80% fuel capacity.
3.2 Operational test. The Contractor shall demonstrate proper operation of the propulsion shafting without binding during sea trials. Inspect and correct any abnormal noise and vibration generated from the shaft or bearings.
4. NOTES
4.1 Personnel qualifications. Alignment of the main
engine/reduction gear to the propulsion shaft shall be done by personnel experienced in and regularly engaged in shaft alignment procedures.
4.2 Equipment operation. Coast Guard personnel will operate
all shipboard machinery and equipment during all operational tests.
03/01/2010 Page 37 (Rev-0)
24310D_55ANB (19 Sep 2008)
WORK ITEM 18: Remove, Inspect and Reinstall Propeller Shaft(s)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to remove, inspect, and reinstall the propeller shafts as designated in the table below and associated components.
PROPELLER SHAFT
Port
Starboard
1.2 Government/Industrial-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY
ESTIMATED
COST
($/UNIT)
Y **Propeller Shaft (A Class) NSN: 0000-XF-C10-7726 2 ea. 2,200.00
Y Shaft Coupling NSN: 3040-01-135-4315 2 ea. 1,111.69
Y Shaft Stuffing Box Hose NSN: 4720-01-412-7822 2 ea. 42.03
2. APPLICABLE DOCUMENTS
Coast Guard Drawing 55-ANB 4301-1, Rev A, Forward End Of Propeller Shaft and Propeller Shaft Coupling (A Class)
Coast Guard Drawing 55-ANB 4000-001, Rev D, Machinery Arrangement (A Class)
Coast Guard Technical Publication (TP) 3394, Jan 2006, Manufacturer’s Information Book – SWBS Groups 167-261, SWBS 245, Section A, Propulsors
Surface Forces Logistics Center Standard Specification 0000 (Std Spec 0000), Jan 2009, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes
03/01/2010 Page 38 (Rev-0)
3.1 General.
3.1.1 Critical Inspection Report. The Contractor shall submit a critical inspection report (CIR) for the inspections listed in the following paragraph(s):
• 3.2.3 (Inspections).
3.2 Work to be accomplished. The Contractor shall accomplish
the following for each designated propeller shaft using the applicable Coast Guard Drawings 55 ANB 4000-001, 55 ANB 4301- 001, and (TP) 3394 for guidance:
3.2.1 Initial tests. Prior to removing shaft, measure initial runout.
3.2.2 Removals.
• Disconnect the propeller shaft from the shaft coupling.
• Mark existing shaft position and match mark shaft coupling to red gear coupling.
• Disassemble and remove the stuffing box, hoses, clamps, and other components as necessary to remove the shaft.
• Remove the shaft and attached components to a suitable repair facility. Ensure shaft is properly protected from the weather and supported at all bearing journals, at all times, until reinstallation.
3.2.3 Inspections. Clean the shaft free of all marine growth, and accomplish the following inspections (Submit CIR):
3.2.3.1 Visually inspect the following components, as
applicable, for excessive or abnormal wear and other mechanical defects such as nicks, cracks, and corrosion, as applicable:
• Shaft surfaces.
• Strut and stern tube bearing and bearing journal surfaces.
• Strut and stern tube bearing housing surfaces.
• All shaft and propeller associated fasteners.
• Couplings.
• Coupling pins (as applicable).
03/01/2010 Page 39 (Rev-0)
• Stuffing box.
• Stern tube.
• Shaft zincs (as applicable).
3.2.3.2 Accomplish the following measurements:
• Measure keys and keyways and/or shear pins.
• Measure all strut and stern tube bearing internal diameters at forward, middle, and aft locations.
• Measure all bearing journal diameters on the shaft at forward, middle, and aft locations.
• Measure runouts for shaft taper, shaft straightness, and coupling end diameters.
• With the coupling fit to shaft, and key in-place, measure the coupling face and bore runouts. The maximum face or bore runout shall be no more than 0.002" TIR.
3.2.3.3 Perform non-destructive inspection of all bearing
sleeves, shaft tapers, coupling bolts, keyways, keys, and welded repair surfaces, in accordance with Std Spec 0740_STD, Appendix C.
3.2.3.4 Perform a straightness inspection of the shaft in a
lathe. Conduct a dial indicator run-out survey at every 20 inches of the shaft. Plot the run-out readings on an appropriate scale to detect any shaft bending.
3.2.4 Reinstallation. Reinstall the propeller shaft to its
original configuration using Coast Guard Drawings 55 ANB 4000- 001, 55 ANB 4301-001 and (TP) 3394 as guidance.
3.2.4.1 Renew the Government/industrial-furnished stuffing box hoses, Contractor-furnished stainless steel clamps and stuffing box packing during reinstallation.
NOTICE!
The boat shall be allowed to sit in the water for a period of 24 hours at operational liquid load prior to performing the face-to-face alignment of the coupling to the drive flange. The Coast Guard
Inspector will be available to answer questions regarding this process on scene.
3.3 Government/industrial-furnished shaft. The Contractor
shall be aware that the Government reserves the right to furnish a spare propeller shaft to be installed in lieu of the one(s) removed. After a Change Request has been released and
03/01/2010 Page 40 (Rev-0) authorized by the Contracting Officer (KO), the Contractor shall transport the new shaft(s) to a suitable inspection facility, and accomplish the following:
3.3.1 Perform the inspections specified in paragraph 3.2.2
(Inspections) and submit a CFR.
3.3.2 Ensure coupling is matched to shaft or is machined to
match.
3.3.3 Package the removed propeller shaft(s) in the delivery
crate of the new propeller shaft(s) and turn over to the Coast Guard Property Administrator as an MTI item.
3.4 Shaft bearings alignment check. If a Change Request has
been authorized and released by the KO, the Contractor shall accomplish the following after the removal of the propeller shaft for the designated shaft system:
3.4.1 Remove the designated strut and stern tube bearings as
shown on Coast Guard Drawings 55 ANB 4301-001, and (TP) 3394.
3.4.2 Perform an alignment check of the stern tube and strut
bearing housing bores relative to the shaft centerline using the optical method. Submit CFR including details on how the shaft centerline was established.
3.4.3 The shaft alignment measurement method shall be performed under the direct supervision of personnel experienced in and regularly engaged in shaft alignment.
3.5 Engine to shaft alignment check. Perform an alignment
check of engine to shaft. Submit CFR including details on how correct alignment was established.
3.6 Shaft zincs replacement. Renew shaft zincs during
reinstallation using Contractor-furnished material.
3.7 Operational test. In the presence of the Coast Guard
Inspector, the Contractor shall thoroughly test and prove the shafting system to be in satisfactory operating condition (see
4.1 (Equipment operation)). Conduct a sea trial to test the propeller shaft in all modes of operation for a minimum of 4 hours. Inspect and correct any excessive leakage, abnormal noise and excessive vibration.
03/01/2010 Page 41 (Rev-0)
4.1 Equipment operation. Coast Guard personnel will operate
all shipboard machinery and equipment during all operational tests.
4.2 Coast Guard presence. The Coast Guard Inspector will be
present during all inspections and measurements specified herein.
4.3 Propeller shaft data. Aquamet 17, 2-3/4" diameter by
approximately 13’ in length.
03/01/2010 Page 42 (Rev-0)
24500D_55 ANB (A, B, C Class) (24 Sep 2008)
WORK ITEM 19: Remove and Reinstall Propeller(s)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to remove and reinstall the propeller(s) designated in the table below.
PROPELLER
Starboard
COST
($/UNIT)
Y **Propeller, Right Hand NSN: 2010-01-130-4949 1 ea. 2,687.00 Y **Propeller, Left Hand NSN: 2010-01-125-3273 1 ea. 2,687.00
2. APPLICABLE DOCUMENTS
Coast Guard Drawing 55-ANB 4000-001, Rev D, Machinery Arrangement (A Class)
Coast Guard Technical Publication (TP) 3394, Jan 2006, Manufacturer’s Information Book – SWBS Groups 167-261, SWBS 245, Section A, Propulsors
International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50m, Inclusive
3. REQUIREMENTS
3.1 Protective and safety measures. The Contractor shall
accomplish the following for the designated propeller(s):
03/01/2010 Page 43 (Rev-0)
• Before removing each designated propeller or propeller nut, fit a shore from the floor of the dock to one propeller blade near the root, to prevent shock transmission to reduction gear, as necessary.
• Protect propeller blade edges and blade roots with suitable covers, at all times until reinstallation, to prevent damage.
3.2 Work to be accomplished. The Contractor shall accomplish
the following for each designated designated propeller, using Coast Guard Drawing 55-ANB 4000-001 and TP-3394 as guidance.
3.2.1 Removal. Remove the propeller and provide to Coast Guard Inspector in exchange for Government/industrial-furnished.
NOTICE!
If it becomes necessary to apply heat to facilitate propeller removal, ensure that the hub temperature never exceeds 500 degrees Fahrenheit; in addition, ensure that gland, packing ring, fill and vent plugs are removed, and the adjacent shafting and canvas under the blade edge guards are protected from flame impingement.
WARNING!
Do not machine the shaft taper.
3.3 Propeller installation.
3.3.1 Cleaning. For the final assembly, the propeller bore and shaft taper surfaces shall be clean and free of bluing, lubricants, dirt, foreign particles, or any other substance, which would hinder moving the propeller along the taper.
Install the propeller with dry metal-to-metal contact to obtain the maximum frictional force for torque transmission. Renew the rubber O-rings and packing before reassembly, if applicable.
3.3.2 Assembly. With the propeller installed on the taper in
the same position as when fitted, install the propeller nut and drive up the propeller until it is advanced forward about 1/16" beyond the inscribed mark as specified in 3.2.4.3 (Location inscription). Lock the nut in place with an appropriate locking device.
NOTICE!
It is prohibited to use grease, oil,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .