ATTACHMENT TO STANDARD FORM 1449 CLINS TERMS AND CONDITIONS.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HSCG40-09-Q-60031
NOTICE FOR FILING AGENCY PROTESTS - United States Coast Guard Ombudsman Program
It is the policy of the United States Coast Guard (USCG) to issue solicitations and make contract awards in a fair and timely manner. The Ombudsman Program for Agency Protests (OPAP) was established to investigate agency protest issues and resolve them without expensive and time-consuming litigation. OPAP is an independent reviewing authority that is empowered to grant a prevailing protester essentially the same relief as the General Accountability Office (GAO).
Interested parties are encouraged to seek resolution of their concerns within the USCG as an Alternative Dispute Resolution (ADR) forum, rather than filing a protest with the GAO or some external forum. Interested parties may seek resolution of their concerns informally or opt to file a formal agency protest with the contracting officer or Ombudsman.
Informal forum with the Ombudsman. Interested parties who believe a specific USCG procurement is unfair or otherwise defective should first direct their concerns to the cognizant contracting officer. If the contracting officer is unable to satisfy the concerns, the interested party is encouraged to contact the USCG Ombudsman for Agency Protests. Under this informal process, the agency is not required to suspend contract award performance. Use of an informal forum does not suspend any time requirement for filing a protest with the agency or other forum. In order to ensure a timely response, interested parties should provide the following information to the Ombudsman: solicitation/contract number, contracting office, contracting officer, and solicitation closing date (if applicable).
Formal Agency Protest with the Ombudsman. Prior to submitting a formal agency protest, protesters must first use their best efforts to resolve their concerns with the contracting officer through open and frank discussions. If the protester’s concerns are unresolved, an independent review is available by the Ombudsman. The protester may file a formal agency protest to either the contracting officer or as an alternative to that, the Ombudsman under the OPAP program. Contract award or performance will be suspended during the protest period unless contract award or performance is justified, in writing, for urgent and compelling reasons or is determined in writing to be in the best interest of the Government. The agency’s goal is to resolve protests in less than 35 calendar days from the date of filing. Protests shall include the information set forth in FAR 33.103. If the protester fails to submit the required information, resolution of the protest may be delayed or the protest may be dismissed. This will not preclude re-filing of the protest to meet the requirement. To be timely, protests must be filed within the period specified in FAR 33.103(e). Formal protests filed under the OPAP program should be submitted to: Department of Homeland Security, United States Coast Guard (CG-9131), Ombudsman Program for Agency Protests, 1900 Half Street, SW, Room 11-0602, Washington, D. C. 20593-0001, FAX: 202.475.3904. The Ombudsman Hotline telephone number is 202.372.3695.
DESCRIPTION
PAGE(S)
Standard Form 1449 (SF1449)
Table of Contents
Addendum to Standard Form 1449:
Blocks 19 – 24, Schedule of Supplies/Services
4-32
Block 15, Packaging and Marking
4-32
Shipping
Block 18A, Additional Payment Information
Contract Administration
33-34 FAR Clause 52.212-4, Contract Terms and Conditions – Commercial Items 34-39 Addendum to FAR Clause 52.212-4, Contract Terms and Conditions –
Commercial Items
39-42 FAR Clause 52.212-5, Contract Terms and Conditions Required to Implement
Statutes or Executive Orders – Commercial Items
42-47 FAR Provision 52.212-1, Instructions to Offerors – Commercial Items
47-51 FAR 52.212-2, Evaluation – Commercial Items
51-53 FAR Clause 52.212-3, Offeror Representations and Certifications – Commercial
Items
53-62 Attachment (1) -Enclosed CD with applicable drawings & specifications referenced in CLINS.
SUPPLIES/SERVICES
The U.S. Coast Guard Engineering Logistics Center intends on awarding a Blanket Purchase Agreement to further reduce the administrative costs of manufacturing of commercial items with three (3) machine shops found to be the lowest price technically acceptable proposals with evaluation factors set forth in this solicitation.
Blanket Purchase Agreements (BPAs) reduce contracting and open market costs such as search for sources, solicitations and the evaluation of offers. The end result is to create a purchasing mechanism for the Government that works better and costs less.
DESCRIPTION OF AGREEMENT
Pursuant to Blanket Purchase Agreements (BPAs), the Contractor agrees to the following terms and conditions of this BPA for the manufacturing of various marine parts for the U.S. Coast Guard Engineering Logistics Center Standard as outlined in the below CLINS.
The BPA shall be issued for a period of five years (one base year and four option years).
Individual delivery orders shall be issued for the supplies outlined in the below CLINS if and when requested by the Contracting Officer (or the authorized representative of the Contracting O fficer). The maximum ordering amount per Delivery Order shall be $100,000.00.
PRICING – BASE YEAR
The contractor shall perform all functions necessary to provide the commercial items described herein. All manufacturing shall be included as per the scope of CLINS with related drawings and specifications, which will be provided on a compact disc (CD) upon request from prospective offeror’s and become incorporated into the BPA upon award. Manufacturing shall comply with all applicable Federal, State, and local laws, regulations, codes and directives.
*Note, unless otherwise stated: All prices on below CLINS shall be a firm fixed price for one year and applicable option years.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0001 |
| 2990 |
| 01-460-0214 |
| 110WPB259-005 ASSY D |
| Flange Exhaust Pipe 18" |
| 001 |
| $ - |
| $ - |
General - 18" Lower Companion Pipe Flange manufactured in accordance with drawing 110WPB 259-005 Rev. C Dated 1/14/02 Assembly D.
Material Certification: Contractor shall provide certifications of material conformance to the Coast Guard QA Representative.
Flange Sealing Surfaces: All flanged sealing surfaces shall be machined to obtain a spiral serrated gasket surface finish (phonographic finish). As a general rule, a 1/16" radius round-nosed tool at a feed of 1/32"for flanges 12" diameter and smaller. Sizes larger than 12" diameter an 1/8" round-nosed tool at a feed of 3/64".
Welder Qualification – Welders shall have a valid qualification record certified by one or more of the following organizations: The American Welding Society, The American Bureau of Shipping or Department of the Navy. This qualification shall be for the same particular service application, filler material type, position of welding, and welding process.
Notifications & Inspections – The contractor shall be responsible for notifying the Contracting Officer no less then seven (7) calendar days prior to the contractor being ready for any Quality Assurance (Q.A.) inspections or testing required herein. Thirty (30) calendar days shall be allowed should the contract be awarded to a foreign contractor.
Inspections & Tests – The inspections & tests required herein are the minimum necessary and are not intended to replace any controls, examinations, or tests normally employed by the contractor to assure the quality of the product. The following will be witnessed by a CG Quality Assurance Representative: a) Material Certifications as required upon request by the Coast Guard Quality Assurance Representative. b) Conformance to dimensional tolerances, surface texture and overall workmanship requirements. c) Overall assembly completeness as required by this statement of work and the drawing. d) Inspection of packaging and marking.
Preservation, Packaging and Marking – Preservation, Packaging and Marking shall be conducted in accordance with USCG ELC SP-PP&M-001 Rev. D Dated 10/01/00.
Bar Coding – Each Flange shall be Bar Coded in accordance with in accordance with ELC specification D-000-100 Rev. G Dated 2/23/06. The Bar Code Label can be applied separately or as part of the marking listed above. Each Flange shall be de-burred to remove all sharp edges.
Calibration System – The Contractor shall be required to maintain a test equipment calibration program in compliance with NCSL Z540-3. The program shall be documented and traceable to the National Institute of Standards (NIST). The calibration system records shall be maintained for inspection for the duration of any contract referencing this item.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0002 |
| 2990 |
| 01-475-9800 |
| 110WPB259-006 ASSY A |
| Flange, Exhaust Pipe 8" |
| 001 |
| $ - |
| $ - |
General - 8" Companion Pipe Flange manufactured in accordance with drawing 110WPB 259-006 Rev. D Dated 3/25/09 Assembly A.
Material Certification: Contractor shall provide certifications of material conformance to the Coast Guard QA Representative.
Flange Sealing Surfaces: All flanged sealing surfaces shall be machined to obtain a spiral serrated gasket surface finish (phonographic finish). As a general rule, a 1/16" radius round-nosed tool at a feed of 1/32"for flanges 12" diameter and smaller. Sizes larger than 12" diameter an 1/8" round-nosed tool at a feed of 3/64".
Welder Qualification – Welders shall have a valid qualification record certified by one or more of the following organizations: The American Welding Society, The American Bureau of Shipping or Department of the Navy. This qualification shall be for the same particular service application, filler material type, position of welding, and welding process.
Notifications & Inspections – The contractor shall be responsible for notifying the Contracting Officer no less then seven (7) calendar days prior to the contractor being ready for any Quality Assurance (Q.A.) inspections or testing required herein. Thirty (30) calendar days shall be allowed should the contract be awarded to a foreign contractor.
Inspections & Tests – The inspections & tests required herein are the minimum necessary and are not intended to replace any controls, examinations, or tests normally employed by the contractor to assure the quality of the product. The following will be witnessed by a CG Quality Assurance Representative: a) Material Certifications as required upon request by the Coast Guard Quality Assurance Representative. b) Conformance to dimensional tolerances, surface texture and overall workmanship requirements. c) Overall assembly completeness as required by this statement of work and the drawing. d) Inspection of packaging and marking.
Preservation, Packaging and Marking – Preservation, Packaging and Marking shall be conducted in accordance with USCG ELC SP-PP&M-001 Rev. D Dated 10/01/00.
Bar Coding – Each Flange shall be Bar Coded in accordance with in accordance with ELC specification D-000-100 Rev. G Dated 2/23/06. The Bar Code Label can be applied separately or as part of the marking listed above. Each Flange shall be de-burred to remove all sharp edges.
Calibration System – The Contractor shall be required to maintain a test equipment calibration program in compliance with NCSL Z540-3. The program shall be documented and traceable to the National Institute of Standards (NIST). The calibration system records shall be maintained for inspection for the duration of any contract referencing this item.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0003 |
| 2990 |
| 01-460-0205 |
| 110WPB259-005 ASSY A |
| Flange Exhaust Pipe 18" |
| 001 |
| $ - |
| $ - |
General – Manufactured in accordance with drawing 110WPB 259-005 Rev. C Dated 1/14/02 Assembly D.
Material Certification: Contractor shall provide certifications of material conformance to the Coast Guard QA Representative.
Flange Sealing Surfaces: All flanged sealing surfaces shall be machined to obtain a spiral serrated gasket surface finish (phonographic finish). As a general rule, a 1/16" radius round-nosed tool at a feed of 1/32"for flanges 12" diameter and smaller. Sizes larger than 12" diameter an 1/8" round-nosed tool at a feed of 3/64".
Welder Qualification – Welders shall have a valid qualification record certified by one or more of the following organizations: The American Welding Society, The American Bureau of Shipping or Department of the Navy. This qualification shall be for the same particular service application, filler material type, position of welding, and welding process.
Notifications & Inspections – The contractor shall be responsible for notifying the Contracting Officer no less then seven (7) calendar days prior to the contractor being ready for any Quality Assurance (Q.A.) inspections or testing required herein. Thirty (30) calendar days shall be allowed should the contract be awarded to a foreign contractor.
Inspections & Tests – The inspections & tests required herein are the minimum necessary and are not intended to replace any controls, examinations, or tests normally employed by the contractor to assure the quality of the product. The following will be witnessed by a CG Quality Assurance Representative: a) Material Certifications as required upon request by the Coast Guard Quality Assurance Representative. b) Conformance to dimensional tolerances, surface texture and overall workmanship requirements. c) Overall assembly completeness as required by this statement of work and the drawing. d) Inspection of packaging and marking.
Preservation, Packaging and Marking – Preservation, Packaging and Marking shall be conducted in accordance with USCG ELC SP-PP&M-001 Rev. D Dated 10/01/00.
Bar Coding – Each Flange shall be Bar Coded in accordance with in accordance with ELC specification D-000-100 Rev. G Dated 2/23/06. The Bar Code Label can be applied separately or as part of the marking listed above. Each Flange shall be de-burred to remove all sharp edges.
Calibration System – The Contractor shall be required to maintain a test equipment calibration program in compliance with NCSL Z540-3. The program shall be documented and traceable to the National Institute of Standards (NIST). The calibration system records shall be maintained for inspection for the duration of any contract referencing this item.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0004 |
| 4810 |
| 01-475-7855 |
| 110CWPB259-003-S |
| Valve, Flapper Assembly |
| 006 |
| $ - |
| $ - |
Butterfly Type Exhaust (Flapper) Valve, 18" Diameter, with electric actuator & solenoid limit (open/close) switches. Manufactured in accordance with Coast Guard drawing 110C WPB 259-003 Rev. E Dated 5/06/2004 and specification no. P-259-0415 Rev. F Dated 7/14/2009. For Starboard side application.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0005 |
| 4810 |
| 01-475-8271 |
| 110CWPB259-003-P |
| Flapper Valve Assembly |
| 005 |
| $ - |
| $ - |
Butterfly Type Exhaust (Flapper) Valve, 18” Diameter with electric actuator and solenoid limit (open/close) switches. Manufactured in accordance with Coast Guard drawing 110CWPB 259-003 Rev. E dated 5/06/2004 and specification P-259-0415 Rev. F Dated 7/14/2009. For Port side application.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0006 |
| 4320 |
| 01-475-8280 |
| 110WPB259-003 ASSEMBLY H |
| Valve, Flapper |
| 001 |
| $ - |
| $ - |
Butterfly valve and spray ring assembly for port side application on Coast Guard 110' WPB "C" Class cutters. manufactured, tested, packaged, packed and marked in accordance with Coast Guard drawing 110CWPB 259-003 Rev. E Dated 5/06/2004, assembly "H" and Coast Guard specification P-259-0414 Rev. E Dated 7/15/2009. Includes upper and lower gaskets, (2) each.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0007 |
| 4320 |
| 01-475-7884 |
| 110WPB259-003 ASSEMBLY J |
| Valve, Flapper |
| 002 |
| $ - |
| $ - |
Butterfly valve and spray ring assembly for starboard side application on Coast Guard 110' WPB Class cutters. Manufactured in accordance with Coast Guard drawing 110C WPB 259-003 Rev. E, Dated 5/06/2004 and Coast Guard specification P-259-0414 Rev. E, Dated 7/15/2009. Assemblies "B", "C" AND "J" in accordance with general note 14 on drawing will complete each assembly.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0008 |
| 3130 |
| 01-442-2863 |
| 5686719 |
| Housing, Bearing Unit, FWD |
| 018 |
| $ - |
| $ - |
Manufacture, Inspect, Package and Mark Bearing Housing IAW attached specification P-161-0417 Rev. B Dated 7/16/2009. Final assembly shall include items 2, 8, 9 and 26 IAW drawing 110CWPB-161-005 Rev. E Dated 4/14/2008.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0009 |
| 2040 |
| 01-486-7595 |
| 110WPB-513-005 |
| Ventillator, Air Circulation |
| 012 |
| $ - |
| $ - |
Lever operated louvered vent that opens and closes. Manufactured IAW Coast Guard drawing 110 WPB-513-005 Rev. C dated 1/14/2002 and manufacturing specification P-513-0486 Change 2 Dated 7/15/2009.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0010 |
| 2990 |
| 01-475-9354 |
| 110WPB259-005-S |
| Exhaust System, Engine |
| 6 |
| $ - |
| $ - |
Starboard 18” Spray Ring Assembly. Manufactured in accordance with Coast Guard specification P-259-0472 Rev. B Change 2 Dated 7/31/2009 and Coast Guard drawing 110WPB 259-005 Rev. C 1/14/2002. In accordance with Note 9 assembly shall include assemblies A, B, C, D and J.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0011 |
| 2990 |
| 01-475-9360 |
| 110WPB259-005-P |
| Exhaust System, Engine |
| 006 |
| $ - |
| $ - |
Port 18” Spray Ring Assembly. Manufactured in accordance with Coast Guard specification P-259-0472 Rev. B Change 2 Dated 7/15/2009 and Coast Guard drawing 110WPB 259-005 Rev C dated 1/14/2002. In accordance with Note 9 assembly shall include assemblies A, B, C, D and H.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0012 |
| 4320 |
| 01-475-8806 |
| 110WPB259-006 ASSEMBLY C |
| Valve, Flapper, Pump |
| 001 |
| $ - |
| $ - |
Flapper Valve Assembly used on the 8” Butterfly Exhaust Valves on the 110’ WPB A, B, and C Class Coast Guard vessels. Manufactured in accordance with USCG drawing 110WPB 259-006 Rev. D, Dated 3/25/2009 and ELC Specification P-259-0438 Rev. C Dated 1/16/2007. Valve encompasses assemblies B and C in accordance with General Note 13.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0013 |
| 4810 |
| 01-475-8648 |
| 110WPB259-006-P |
| Valve, Butterfly |
| 012 |
| $ - |
| $ - |
8” Butterfly Exhaust Valve for use on the Port side of Coast Guard 110’ WPB A, B, and C class cutters. Manufactured in accordance with Coast Guard specification P-259-0437 Rev. D Change 1 Dated 7/20/2009 and Coast Guard drawing 110WPB-259-006 Rev. D dated 3/25/2009.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0014 |
| 4810 |
| 01-475-8415 |
| 110WPB259-006-S |
| Valve, Butterfly |
| 011 |
| $ - |
| $ - |
8” Butterfly Exhaust Valve for use on the Starboard side of Coast Guard 110’ WPB A, B, and C class cutters. Manufactured in accordance with Coast Guard specification P-259-0437 Rev. D Change 1 Dated 7/20/2009 and Coast Guard drawing 110WPB-259-006 Rev. D dated 3/25/2009.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0015 |
| 2990 |
| 01-475-9621 |
| 110WPB259-005 ASSEMBLY H |
| Spray Ring Assembly |
| 001 |
| $ - |
| $ - |
Port 18” Spray Ring Assembly. Manufactured in accordance with Coast Guard specification P-259-0441 Rev. B Change 2 Dated 7/23/2009 and drawing 110WPB 259-005 Rev. C dated 1/14/2002. IAW note 10, assembly includes Assemblies B, C and H. Does not include companion pipe flanges or hardware
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 0016 |
| 2990 |
| 01-475-9620 |
| 110WPB 259-005 ASSEMBLY J |
| Spray Ring Assembly |
| 002 |
| $ - |
| $ - |
Starboard 18" Spray Ring Assembly. Manufacture in accordance with Coast Guard specification P-259-0441 Rev. B Change 2 Dated 7/23/2009 and drawing 110WPB 259-005 Rev. C 1/14/2002. IAW note 10, assembly includes Assemblies B, C and J. Does not include companion pipe flanges or hardware.
PRICING – FIRST OPTION YEAR
The contractor shall perform all functions necessary to provide the commercial items described herein. All manufacturing shall be included as per the scope of CLINS with related drawings and specifications, which will be provided on a compact disc (CD) upon request from prospective offeror’s and become incorporated into the BPA upon award. Manufacturing shall comply with all applicable Federal, State, and local laws, regulations, codes and directives.
*Note, unless otherwise stated: All prices on below CLINS shall be a firm fixed price for one year and applicable option years.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1001 |
| 2990 |
| 01-460-0214 |
| 110WPB259-005 ASSY D |
| Flange Exhaust Pipe 18" |
| 001 |
| $ - |
| $ - |
General - 18" Lower Companion Pipe Flange manufactured in accordance with drawing 110WPB 259-005 Rev. C Dated 1/14/02 Assembly D.
Material Certification: Contractor shall provide certifications of material conformance to the Coast Guard QA Representative.
Flange Sealing Surfaces: All flanged sealing surfaces shall be machined to obtain a spiral serrated gasket surface finish (phonographic finish). As a general rule, a 1/16" radius round-nosed tool at a feed of 1/32"for flanges 12" diameter and smaller. Sizes larger than 12" diameter an 1/8" round-nosed tool at a feed of 3/64".
Welder Qualification – Welders shall have a valid qualification record certified by one or more of the following organizations: The American Welding Society, The American Bureau of Shipping or Department of the Navy. This qualification shall be for the same particular service application, filler material type, position of welding, and welding process.
Notifications & Inspections – The contractor shall be responsible for notifying the Contracting Officer no less then seven (7) calendar days prior to the contractor being ready for any Quality Assurance (Q.A.) inspections or testing required herein. Thirty (30) calendar days shall be allowed should the contract be awarded to a foreign contractor.
Inspections & Tests – The inspections & tests required herein are the minimum necessary and are not intended to replace any controls, examinations, or tests normally employed by the contractor to assure the quality of the product. The following will be witnessed by a CG Quality Assurance Representative: a) Material Certifications as required upon request by the Coast Guard Quality Assurance Representative. b) Conformance to dimensional tolerances, surface texture and overall workmanship requirements. c) Overall assembly completeness as required by this statement of work and the drawing. d) Inspection of packaging and marking.
Preservation, Packaging and Marking – Preservation, Packaging and Marking shall be conducted in accordance with USCG ELC SP-PP&M-001 Rev. D Dated 10/01/00.
Bar Coding – Each Flange shall be Bar Coded in accordance with in accordance with ELC specification D-000-100 Rev. G Dated 2/23/06. The Bar Code Label can be applied separately or as part of the marking listed above. Each Flange shall be de-burred to remove all sharp edges.
Calibration System – The Contractor shall be required to maintain a test equipment calibration program in compliance with NCSL Z540-3. The program shall be documented and traceable to the National Institute of Standards (NIST). The calibration system records shall be maintained for inspection for the duration of any contract referencing this item.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1002 |
| 2990 |
| 01-475-9800 |
| 110WPB259-006 ASSY A |
| Flange, Exhaust Pipe 8" |
| 001 |
| $ - |
| $ - |
General - 8" Companion Pipe Flange manufactured in accordance with drawing 110WPB 259-006 Rev. D Dated 3/25/09 Assembly A.
Material Certification: Contractor shall provide certifications of material conformance to the Coast Guard QA Representative.
Flange Sealing Surfaces: All flanged sealing surfaces shall be machined to obtain a spiral serrated gasket surface finish (phonographic finish). As a general rule, a 1/16" radius round-nosed tool at a feed of 1/32"for flanges 12" diameter and smaller. Sizes larger than 12" diameter an 1/8" round-nosed tool at a feed of 3/64".
Welder Qualification – Welders shall have a valid qualification record certified by one or more of the following organizations: The American Welding Society, The American Bureau of Shipping or Department of the Navy. This qualification shall be for the same particular service application, filler material type, position of welding, and welding process.
Notifications & Inspections – The contractor shall be responsible for notifying the Contracting Officer no less then seven (7) calendar days prior to the contractor being ready for any Quality Assurance (Q.A.) inspections or testing required herein. Thirty (30) calendar days shall be allowed should the contract be awarded to a foreign contractor.
Inspections & Tests – The inspections & tests required herein are the minimum necessary and are not intended to replace any controls, examinations, or tests normally employed by the contractor to assure the quality of the product. The following will be witnessed by a CG Quality Assurance Representative: a) Material Certifications as required upon request by the Coast Guard Quality Assurance Representative. b) Conformance to dimensional tolerances, surface texture and overall workmanship requirements. c) Overall assembly completeness as required by this statement of work and the drawing. d) Inspection of packaging and marking.
Preservation, Packaging and Marking – Preservation, Packaging and Marking shall be conducted in accordance with USCG ELC SP-PP&M-001 Rev. D Dated 10/01/00.
Bar Coding – Each Flange shall be Bar Coded in accordance with in accordance with ELC specification D-000-100 Rev. G Dated 2/23/06. The Bar Code Label can be applied separately or as part of the marking listed above. Each Flange shall be de-burred to remove all sharp edges.
Calibration System – The Contractor shall be required to maintain a test equipment calibration program in compliance with NCSL Z540-3. The program shall be documented and traceable to the National Institute of Standards (NIST). The calibration system records shall be maintained for inspection for the duration of any contract referencing this item.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1003 |
| 2990 |
| 01-460-0205 |
| 110WPB259-005 ASSY A |
| Flange Exhaust Pipe 18" |
| 001 |
| $ - |
| $ - |
General – Manufactured in accordance with drawing 110WPB 259-005 Rev. C Dated 1/14/02 Assembly D.
Material Certification: Contractor shall provide certifications of material conformance to the Coast Guard QA Representative.
Flange Sealing Surfaces: All flanged sealing surfaces shall be machined to obtain a spiral serrated gasket surface finish (phonographic finish). As a general rule, a 1/16" radius round-nosed tool at a feed of 1/32"for flanges 12" diameter and smaller. Sizes larger than 12" diameter an 1/8" round-nosed tool at a feed of 3/64".
Welder Qualification – Welders shall have a valid qualification record certified by one or more of the following organizations: The American Welding Society, The American Bureau of Shipping or Department of the Navy. This qualification shall be for the same particular service application, filler material type, position of welding, and welding process.
Notifications & Inspections – The contractor shall be responsible for notifying the Contracting Officer no less then seven (7) calendar days prior to the contractor being ready for any Quality Assurance (Q.A.) inspections or testing required herein. Thirty (30) calendar days shall be allowed should the contract be awarded to a foreign contractor.
Inspections & Tests – The inspections & tests required herein are the minimum necessary and are not intended to replace any controls, examinations, or tests normally employed by the contractor to assure the quality of the product. The following will be witnessed by a CG Quality Assurance Representative: a) Material Certifications as required upon request by the Coast Guard Quality Assurance Representative. b) Conformance to dimensional tolerances, surface texture and overall workmanship requirements. c) Overall assembly completeness as required by this statement of work and the drawing. d) Inspection of packaging and marking.
Preservation, Packaging and Marking – Preservation, Packaging and Marking shall be conducted in accordance with USCG ELC SP-PP&M-001 Rev. D Dated 10/01/00.
Bar Coding – Each Flange shall be Bar Coded in accordance with in accordance with ELC specification D-000-100 Rev. G Dated 2/23/06. The Bar Code Label can be applied separately or as part of the marking listed above. Each Flange shall be de-burred to remove all sharp edges.
Calibration System – The Contractor shall be required to maintain a test equipment calibration program in compliance with NCSL Z540-3. The program shall be documented and traceable to the National Institute of Standards (NIST). The calibration system records shall be maintained for inspection for the duration of any contract referencing this item.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1004 |
| 4810 |
| 01-475-7855 |
| 110CWPB259-003-S |
| Valve, Flapper Assembly |
| 006 |
| $ - |
| $ - |
Butterfly Type Exhaust (Flapper) Valve, 18" Diameter, with electric actuator & solenoid limit (open/close) switches. Manufactured in accordance with Coast Guard drawing 110C WPB 259-003 and specification no. P-259-0415. For Starboard side application.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1005 |
| 4810 |
| 01-475-8271 |
| 110CWPB259-003-P |
| Flapper Valve Assembly |
| 005 |
| $ - |
| $ - |
Butterfly Type Exhaust (Flapper) Valve, 18” Diameter with electric actuator and solenoid limit (open/close) switches. Manufactured in accordance with Coast Guard drawing 110CWPB 259-003 and specification P-259-0415. For Port side application.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1006 |
| 4320 |
| 01-475-8280 |
| 110WPB259-003 ASSEMBLY H |
| Valve, Flapper |
| 001 |
| $ - |
| $ - |
Butterfly valve and spray ring assembly for port side application on Coast Guard 110' WPB "C" Class cutters. manufactured, tested, packaged, packed and marked in accordance with Coast Guard drawing 110CWPB 259-3, assembly "H" and Coast Guard specification P-259-0414. Includes upper and lower gaskets, (2) each.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1007 |
| 4320 |
| 01-475-7884 |
| 110WPB259-003 ASSEMBLY J |
| Valve, Flapper |
| 002 |
| $ - |
| $ - |
Butterfly valve and spray ring assembly for starboard side application on Coast Guard 110' WPB Class cutters. Manufactured in accordance with Coast Guard drawing 110C WPB 259-003 Rev. E, Dated 5/6/2004 and Coast Guard specification P-259-0414 Rev. D, Change 2, Dated 12/31/2008. Assemblies "B", "C" AND "J" in accordance with general note 14 on drawing will complete each assembly.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1008 |
| 3130 |
| 01-442-2863 |
| 5686719 |
| Housing, Bearing Unit, FWD |
| 018 |
| $ - |
| $ - |
Manufacture, Inspect, Package and Mark Bearing Housing IAW attached specification P-161-0417 Rev. B Dated 7/16/2009. Final assembly shall include items 2, 8, 9 and 26 IAW drawing 110CWPB-161-005 Rev. E Dated 4/14/2008.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1009 |
| 2040 |
| 01-486-7595 |
| 110WPB-513-005 |
| Ventillator, Air Circulation |
| 012 |
| $ - |
| $ - |
Lever operated louvered vent that opens and closes. Manufactured IAW Coast Guard drawing 110 WPB-513-005 Rev. C dated 1/14/2002 and manufacturing specification P-513-0486 Change 2 Dated 7/15/2009.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1010 |
| 2990 |
| 01-475-9354 |
| 110WPB259-005-S |
| Exhaust System, Engine |
| 6 |
| $ - |
| $ - |
Starboard 18” Spray Ring Assembly. Manufactured in accordance with Coast Guard specification P-259-0472 and Coast Guard drawing 110WPB 259-005. In accordance with Note 9 assembly shall include assemblies A, B, C, D and J.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1011 |
| 2990 |
| 01-475-9360 |
| 110WPB259-005-P |
| Exhaust System, Engine |
| 006 |
| $ - |
| $ - |
Port 18” Spray Ring Assembly. Manufactured in accordance with Coast Guard specification P-259-0472 and Coast Guard drawing 110WPB 259-005 Rev. In accordance with Note 9 assembly shall include assemblies A, B, C, D and H.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1012 |
| 4320 |
| 01-475-8806 |
| 110WPB259-006 ASSEMBLY C |
| Valve, Flapper, Pump |
| 001 |
| $ - |
| $ - |
Flapper Valve Assembly used on the 8” Butterfly Exhaust Valves on the 110’ WPB A, B, and C Class Coast Guard vessels. Manufactured in accordance with drawing 110WPB 259-006 Rev. D, Dated 3/25/2009. Valve encompasses assemblies B and C in accordance with General Note 13.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1013 |
| 4810 |
| 01-475-8648 |
| 110WPB259-006-P |
| Valve, Butterfly |
| 012 |
| $ - |
| $ - |
8” Butterfly Exhaust Valve for use on the Port side of Coast Guard 110’ WPB A, B, and C class cutters. Manufactured in accordance with Coast Guard specification P-259-0437 and Coast Guard drawing 110WPB-259-006.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1014 |
| 4810 |
| 01-475-8415 |
| 110WPB259-006-S |
| Valve, Butterfly |
| 011 |
| $ - |
| $ - |
8” Butterfly Exhaust Valve for use on the Starboard side of Coast Guard 110’ WPB A, B, and C class cutters. Manufactured in accordance with Coast Guard specification P-259-0437 and Coast Guard drawing 110WPB-259-006.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1015 |
| 2990 |
| 01-475-9621 |
| 110WPB259-005 ASSEMBLY H |
| Spray Ring Assembly |
| 001 |
| $ - |
| $ - |
Port 18” Spray Ring Assembly. Manufactured in accordance with Coast Guard specification P-259-0441 and drawing 110WPB 259-005. IAW note 10, assembly includes Assemblies B, C and H. Does not include companion pipe flanges or hardware
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 1016 |
| 2990 |
| 01-475-9620 |
| 110WPB 259-005 ASSEMBLY J |
| Spray Ring Assembly |
| 002 |
| $ - |
| $ - |
Starboard 18" Spray Ring Assembly. Manufacture in accordance with Coast Guard specification P-259-0441 and drawing 110WPB 259-005 . IAW note 10, assembly includes Assemblies B, C and J. Does not include companion pipe flanges or hardware.
PRICING – SECOND OPTION YEAR
The contractor shall perform all functions necessary to provide the commercial items described herein. All manufacturing shall be included as per the scope of CLINS with related drawings and specifications, which will be provided on a compact disc (CD) upon request from prospective offeror’s and become incorporated into the BPA upon award. Manufacturing shall comply with all applicable Federal, State, and local laws, regulations, codes and directives.
*Note, unless otherwise stated: All prices on below CLINS shall be a firm fixed price for one year and applicable option years.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2001 |
| 2990 |
| 01-460-0214 |
| 110WPB259-005 ASSY D |
| Flange Exhaust Pipe 18" |
| 001 |
| $ - |
| $ - |
General - 18" Lower Companion Pipe Flange manufactured in accordance with drawing 110WPB 259-005 Rev. C Dated 1/14/02 Assembly D.
Material Certification: Contractor shall provide certifications of material conformance to the Coast Guard QA Representative.
Flange Sealing Surfaces: All flanged sealing surfaces shall be machined to obtain a spiral serrated gasket surface finish (phonographic finish). As a general rule, a 1/16" radius round-nosed tool at a feed of 1/32"for flanges 12" diameter and smaller. Sizes larger than 12" diameter an 1/8" round-nosed tool at a feed of 3/64".
Welder Qualification – Welders shall have a valid qualification record certified by one or more of the following organizations: The American Welding Society, The American Bureau of Shipping or Department of the Navy. This qualification shall be for the same particular service application, filler material type, position of welding, and welding process.
Notifications & Inspections – The contractor shall be responsible for notifying the Contracting Officer no less then seven (7) calendar days prior to the contractor being ready for any Quality Assurance (Q.A.) inspections or testing required herein. Thirty (30) calendar days shall be allowed should the contract be awarded to a foreign contractor.
Inspections & Tests – The inspections & tests required herein are the minimum necessary and are not intended to replace any controls, examinations, or tests normally employed by the contractor to assure the quality of the product. The following will be witnessed by a CG Quality Assurance Representative: a) Material Certifications as required upon request by the Coast Guard Quality Assurance Representative. b) Conformance to dimensional tolerances, surface texture and overall workmanship requirements. c) Overall assembly completeness as required by this statement of work and the drawing. d) Inspection of packaging and marking.
Preservation, Packaging and Marking – Preservation, Packaging and Marking shall be conducted in accordance with USCG ELC SP-PP&M-001 Rev. D Dated 10/01/00.
Bar Coding – Each Flange shall be Bar Coded in accordance with in accordance with ELC specification D-000-100 Rev. G Dated 2/23/06. The Bar Code Label can be applied separately or as part of the marking listed above. Each Flange shall be de-burred to remove all sharp edges.
Calibration System – The Contractor shall be required to maintain a test equipment calibration program in compliance with NCSL Z540-3. The program shall be documented and traceable to the National Institute of Standards (NIST). The calibration system records shall be maintained for inspection for the duration of any contract referencing this item.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2002 |
| 2990 |
| 01-475-9800 |
| 110WPB259-006 ASSY A |
| Flange, Exhaust Pipe 8" |
| 001 |
| $ - |
| $ - |
General - 8" Companion Pipe Flange manufactured in accordance with drawing 110WPB 259-006 Rev. D Dated 3/25/09 Assembly A.
Material Certification: Contractor shall provide certifications of material conformance to the Coast Guard QA Representative.
Flange Sealing Surfaces: All flanged sealing surfaces shall be machined to obtain a spiral serrated gasket surface finish (phonographic finish). As a general rule, a 1/16" radius round-nosed tool at a feed of 1/32"for flanges 12" diameter and smaller. Sizes larger than 12" diameter an 1/8" round-nosed tool at a feed of 3/64".
Welder Qualification – Welders shall have a valid qualification record certified by one or more of the following organizations: The American Welding Society, The American Bureau of Shipping or Department of the Navy. This qualification shall be for the same particular service application, filler material type, position of welding, and welding process.
Notifications & Inspections – The contractor shall be responsible for notifying the Contracting Officer no less then seven (7) calendar days prior to the contractor being ready for any Quality Assurance (Q.A.) inspections or testing required herein. Thirty (30) calendar days shall be allowed should the contract be awarded to a foreign contractor.
Inspections & Tests – The inspections & tests required herein are the minimum necessary and are not intended to replace any controls, examinations, or tests normally employed by the contractor to assure the quality of the product. The following will be witnessed by a CG Quality Assurance Representative: a) Material Certifications as required upon request by the Coast Guard Quality Assurance Representative. b) Conformance to dimensional tolerances, surface texture and overall workmanship requirements. c) Overall assembly completeness as required by this statement of work and the drawing. d) Inspection of packaging and marking.
Preservation, Packaging and Marking – Preservation, Packaging and Marking shall be conducted in accordance with USCG ELC SP-PP&M-001 Rev. D Dated 10/01/00.
Bar Coding – Each Flange shall be Bar Coded in accordance with in accordance with ELC specification D-000-100 Rev. G Dated 2/23/06. The Bar Code Label can be applied separately or as part of the marking listed above. Each Flange shall be de-burred to remove all sharp edges.
Calibration System – The Contractor shall be required to maintain a test equipment calibration program in compliance with NCSL Z540-3. The program shall be documented and traceable to the National Institute of Standards (NIST). The calibration system records shall be maintained for inspection for the duration of any contract referencing this item.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2003 |
| 2990 |
| 01-460-0205 |
| 110WPB259-005 ASSY A |
| Flange Exhaust Pipe 18" |
| 001 |
| $ - |
| $ - |
General – Manufactured in accordance with drawing 110WPB 259-005 Rev. C Dated 1/14/02 Assembly D.
Material Certification: Contractor shall provide certifications of material conformance to the Coast Guard QA Representative.
Flange Sealing Surfaces: All flanged sealing surfaces shall be machined to obtain a spiral serrated gasket surface finish (phonographic finish). As a general rule, a 1/16" radius round-nosed tool at a feed of 1/32"for flanges 12" diameter and smaller. Sizes larger than 12" diameter an 1/8" round-nosed tool at a feed of 3/64".
Welder Qualification – Welders shall have a valid qualification record certified by one or more of the following organizations: The American Welding Society, The American Bureau of Shipping or Department of the Navy. This qualification shall be for the same particular service application, filler material type, position of welding, and welding process.
Notifications & Inspections – The contractor shall be responsible for notifying the Contracting Officer no less then seven (7) calendar days prior to the contractor being ready for any Quality Assurance (Q.A.) inspections or testing required herein. Thirty (30) calendar days shall be allowed should the contract be awarded to a foreign contractor.
Inspections & Tests – The inspections & tests required herein are the minimum necessary and are not intended to replace any controls, examinations, or tests normally employed by the contractor to assure the quality of the product. The following will be witnessed by a CG Quality Assurance Representative: a) Material Certifications as required upon request by the Coast Guard Quality Assurance Representative. b) Conformance to dimensional tolerances, surface texture and overall workmanship requirements. c) Overall assembly completeness as required by this statement of work and the drawing. d) Inspection of packaging and marking.
Preservation, Packaging and Marking – Preservation, Packaging and Marking shall be conducted in accordance with USCG ELC SP-PP&M-001 Rev. D Dated 10/01/00.
Bar Coding – Each Flange shall be Bar Coded in accordance with in accordance with ELC specification D-000-100 Rev. G Dated 2/23/06. The Bar Code Label can be applied separately or as part of the marking listed above. Each Flange shall be de-burred to remove all sharp edges.
Calibration System – The Contractor shall be required to maintain a test equipment calibration program in compliance with NCSL Z540-3. The program shall be documented and traceable to the National Institute of Standards (NIST). The calibration system records shall be maintained for inspection for the duration of any contract referencing this item.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2004 |
| 4810 |
| 01-475-7855 |
| 110CWPB259-003-S |
| Valve, Flapper Assembly |
| 006 |
| $ - |
| $ - |
Butterfly Type Exhaust (Flapper) Valve, 18" Diameter, with electric actuator & solenoid limit (open/close) switches. Manufactured in accordance with Coast Guard drawing 110C WPB 259-003 and specification no. P-259-0415. For Starboard side application.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2005 |
| 4810 |
| 01-475-8271 |
| 110CWPB259-003-P |
| Flapper Valve Assembly |
| 005 |
| $ - |
| $ - |
Butterfly Type Exhaust (Flapper) Valve, 18” Diameter with electric actuator and solenoid limit (open/close) switches. Manufactured in accordance with Coast Guard drawing 110CWPB 259-003 and specification P-259-0415. For Port side application.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2006 |
| 4320 |
| 01-475-8280 |
| 110WPB259-003 ASSEMBLY H |
| Valve, Flapper |
| 001 |
| $ - |
| $ - |
Butterfly valve and spray ring assembly for port side application on Coast Guard 110' WPB "C" Class cutters. manufactured, tested, packaged, packed and marked in accordance with Coast Guard drawing 110CWPB 259-3, assembly "H" and Coast Guard specification P-259-0414. Includes upper and lower gaskets, (2) each.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2007 |
| 4320 |
| 01-475-7884 |
| 110WPB259-003 ASSEMBLY J |
| Valve, Flapper |
| 002 |
| $ - |
| $ - |
Butterfly valve and spray ring assembly for starboard side application on Coast Guard 110' WPB Class cutters. Manufactured in accordance with Coast Guard drawing 110C WPB 259-003 Rev. E, Dated 5/6/2004 and Coast Guard specification P-259-0414 Rev. D, Change 2, Dated 12/31/2008. Assemblies "B", "C" AND "J" in accordance with general note 14 on drawing will complete each assembly.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2008 |
| 3130 |
| 01-442-2863 |
| 5686719 |
| Housing, Bearing Unit, FWD |
| 018 |
| $ - |
| $ - |
Manufacture, Inspect, Package and Mark Bearing Housing IAW attached specification P-161-0417 Rev. B Dated 7/16/2009. Final assembly shall include items 2, 8, 9 and 26 IAW drawing 110CWPB-161-005 Rev. E Dated 4/14/2008.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2009 |
| 2040 |
| 01-486-7595 |
| 110WPB-513-005 |
| Ventillator, Air Circulation |
| 012 |
| $ - |
| $ - |
Lever operated louvered vent that opens and closes. Manufactured IAW Coast Guard drawing 110 WPB-513-005 Rev. C dated 1/14/2002 and manufacturing specification P-513-0486 Change 2 Dated 7/15/2009.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2010 |
| 2990 |
| 01-475-9354 |
| 110WPB259-005-S |
| Exhaust System, Engine |
| 6 |
| $ - |
| $ - |
Starboard 18” Spray Ring Assembly. Manufactured in accordance with Coast Guard specification P-259-0472 and Coast Guard drawing 110WPB 259-005. In accordance with Note 9 assembly shall include assemblies A, B, C, D and J.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2011 |
| 2990 |
| 01-475-9360 |
| 110WPB259-005-P |
| Exhaust System, Engine |
| 006 |
| $ - |
| $ - |
Port 18” Spray Ring Assembly. Manufactured in accordance with Coast Guard specification P-259-0472 and Coast Guard drawing 110WPB 259-005 Rev. In accordance with Note 9 assembly shall include assemblies A, B, C, D and H.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2012 |
| 4320 |
| 01-475-8806 |
| 110WPB259-006 ASSEMBLY C |
| Valve, Flapper, Pump |
| 001 |
| $ - |
| $ - |
Flapper Valve Assembly used on the 8” Butterfly Exhaust Valves on the 110’ WPB A, B, and C Class Coast Guard vessels. Manufactured in accordance with drawing 110WPB 259-006 Rev. D, Dated 3/25/2009. Valve encompasses assemblies B and C in accordance with General Note 13.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2013 |
| 4810 |
| 01-475-8648 |
| 110WPB259-006-P |
| Valve, Butterfly |
| 012 |
| $ - |
| $ - |
8” Butterfly Exhaust Valve for use on the Port side of Coast Guard 110’ WPB A, B, and C class cutters. Manufactured in accordance with Coast Guard specification P-259-0437 and Coast Guard drawing 110WPB-259-006.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2014 |
| 4810 |
| 01-475-8415 |
| 110WPB259-006-S |
| Valve, Butterfly |
| 011 |
| $ - |
| $ - |
8” Butterfly Exhaust Valve for use on the Starboard side of Coast Guard 110’ WPB A, B, and C class cutters. Manufactured in accordance with Coast Guard specification P-259-0437 and Coast Guard drawing 110WPB-259-006.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2015 |
| 2990 |
| 01-475-9621 |
| 110WPB259-005 ASSEMBLY H |
| Spray Ring Assembly |
| 001 |
| $ - |
| $ - |
Port 18” Spray Ring Assembly. Manufactured in accordance with Coast Guard specification P-259-0441 and drawing 110WPB 259-005. IAW note 10, assembly includes Assemblies B, C and H. Does not include companion pipe flanges or hardware
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 2016 |
| 2990 |
| 01-475-9620 |
| 110WPB 259-005 ASSEMBLY J |
| Spray Ring Assembly |
| 002 |
| $ - |
| $ - |
Starboard 18" Spray Ring Assembly. Manufacture in accordance with Coast Guard specification P-259-0441 and drawing 110WPB 259-005 . IAW note 10, assembly includes Assemblies B, C and J. Does not include companion pipe flanges or hardware.
PRICING – THIRD OPTION YEAR
The contractor shall perform all functions necessary to provide the commercial items described herein. All manufacturing shall be included as per the scope of CLINS with related drawings and specifications, which will be provided on a compact disc (CD) upon request from prospective offeror’s and become incorporated into the BPA upon award. Manufacturing shall comply with all applicable Federal, State, and local laws, regulations, codes and directives.
*Note, unless otherwise stated: All prices on below CLINS shall be a firm fixed price for one year and applicable option years.
| CLIN |
| FSC |
| NIIN |
| P/N |
| DESCRIPTION |
| EST. Annual QTY |
| UNIT PRICE |
| TOTAL PRICE |
| 3001 |
| 2990 |
| 01-460-0214 |
| 110WPB259-005 ASSY D |
| Flange Exhaust Pipe 18" |
| 001 |
| $ - |
| $ - |
General - 18" Lower Companion Pipe Flange manufactured in accordance with drawing 110WPB 259-005 Rev. C Dated 1/14/02 Assembly D.
Material Certification: Contractor shall provide certifications of material conformance to the Coast Guard QA Representative.
Flange Sealing Surfaces: All flanged sealing surfaces shall be machined to obtain a spiral serrated gasket surface finish (phonographic finish). As a general rule, a 1/16" radius round-nosed tool at a feed of 1/32"for flanges 12" diameter and smaller. Sizes larger than 12" diameter an 1/8" round-nosed tool at a feed of 3/64".
Welder Qualification – Welders shall have a valid qualification record certified by one or more of the following organizations: The American Welding Society, The American Bureau of Shipping or Department of the Navy. This qualification shall be for the same particular service application, filler material type, position of welding, and welding process.
Notifications & Inspections – The contractor shall be responsible for notifying the Contracting Officer no less then seven (7) calendar days prior to the contractor being ready for any Quality Assurance (Q.A.) inspections or testing required herein. Thirty (30) calendar days shall be allowed should the contract be awarded to a foreign contractor.
Inspections & Tests – The inspections & tests required herein are the minimum necessary and are not intended to replace any controls, examinations, or tests normally employed by the contractor to assure the quality of the product. The following will be witnessed by a CG Quality Assurance Representative: a) Material Certifications as required upon request by the Coast Guard Quality Assurance Representative. b) Conformance to dimensional tolerances, surface texture and overall workmanship requirements.
This is the start of the file's text. The full file is on GovTribe.