RDLEREVISESOW.doc
DOC document 35 KB Posted
- Attached to
- RENTAL OF BARGE
- Solicitation number
- HSCG3716QDTF803
About this file
RDLEREVISESOW
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF-1449BARGERENTAL.doc | DOC document | |
| FARCLAUSESSUPPLYCOMMERCIAL(noel).pdf | ||
| RDLESOWFORBARGERENTAL.pdf | ||
| FARCLAUSESSUPPLYCOMMERCIAL(noel).pdf | ||
| SF-1449BARGERENTAL.doc | DOC document | |
| SF-1449BARGERENTAL.doc | DOC document | |
| SOWFORBARGERENTAL.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Logistical Support Platform for Diving Operations
1. Background: Coast Guard dive team requires a barge to support Aids to Navigations (AToN) diving operations in the Virginia Inside Passage. Coast Guard organic assets are unable to support logistical challenges and depth limitations within the locations listed in enclosure (1), which are scheduled for removal.
2. Scope: To provide a commercial shallow draft platform capable of navigating the Virginia Inside Passage and supporting up to fifteen Coast Guard members using surface supplied dive capabilities with underwater hydraulic tools.
3. Objective: Safely support Coast Guard team in positions from enclosure (1), for the removal of derelict AToN structures that pose a hazard to navigation from July 11, 2016 to July 22, 2016.
4. Tasks: The contractor shall provide the following:
4.1. Minimum 600 sq ft solid deck barge, capable of maneuvering within the Virginia Inside Passage. Needs to be able to set and recover two or more point anchor or spud from opposite end of barge, in positions and depths listed in enclosure (1) for duration of daily diving operations. Additionally needs to be capable of remaining at positions overnight, with or without crew.
4.2. Tug and or pusher boat capable of maneuvering with barge as a unit within the Virginia Inside Passage in vicinity of positions listed in enclosure (1).
4.3. Captain and deckhand rated and licensed for operating badge and tug and or pusher boat.
4.4. Vessel capable of transporting Captain, deckhand and Coast Guard team, at the start and end of each work period, to and from barge platform.
4.5. Secure weather tight storage affixed to deck of barge, accessible by Coast Guard team with minimum dimensions of 108”W X 88”L X 91.35”H.
4.6. Temporary or installed head facilities for both male and female members.
4.7. Period of work from 0800 – 1700 EST, Monday through Friday, July 11, 2016 – July 22, 2016.
4.8. Transportation and mooring of barge and dive equipment in close proximity to aids listed in Enclosure (1) line 2-14 (5525, 5531, 5535, 5540, 5545, 5547, 5615, 5620, 5625, 5630, 5635, 5640).
4.9. Once completion of task 4.6, contractor and Coast Guard team will coordinate transit and moorings for remaining positions in enclosure (1), for remainder of period of work.
5. Delivery: Contractor shall provide a final report within 3 days of end of contracted period of performance.
6. Government Furnished Property: There is no Government furnished property (GFP) anticipated; however, the Government may in the course of this repair require GFP. If GFP is required, it will be incorporated via contract modification.
7. Security Requirement: Base access may be required. Contractors shall have a valid driver’s license and be able to produce it upon request. A Coast Guard representative will act as a sponsor and escort contractors while on Base.
8. Place of performance: Virginia Inside Passage, positions as listed in enclosure (1).
9. Period of performance: 11 July 16 - 22 July 16, Monday through Friday 0800-1700 EST.