SOW.pdf
PDF 18 KB Posted
- Solicitation number
- HSCG31-16-Q-PQQ042
About this file
Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_No._1.pdf | ||
| 5_Page_Drawings_(Amend._No._1).pdf | ||
| Wage_Determination.pdf | ||
| Solicitation_Provisions_-_Sections_B-M.pdf | ||
| SF_1442_-_Template.pdf | ||
| REQUEST_FOR_INFORMATION_(RFI)_FORM.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
REMOVAL OF RIDGE CAP VENT
INSTALLATON OF SEALED RIDGE CAP
BUILDING 5A
COAST GUARD ISLAND
1. Scope
1.1 Contractor shall provide all necessary permits, labor, materials, equipment and supervision necessary to remove existing ridge cap vent and replace with a sealed ridge cap on building 5A and adjoining breezeway, 1 Eagle Road, Coast Guard Island, Alameda, CA, 94501.
2. Security Requirements
2.1 Vehicles must have valid registration and insurance. All vehicle operators must a have valid driver license.
2.2 Contractors shall notify Point of Contact a minimum of 7 calendar days prior to starting work which will require the blocking of any parking spaces on Coast Guard Island.
3. Technical Point of Contact Designation
The POC for this task is:
DCCS Chris Garcia Office: (510) 437-5361 Cell: (415 599-6814 E-mail: Christopher.t.garcia@uscg.mil
4. Description of Work – Building 5A
4.1 Building 5A currently has a vented ridge cap installed. This current configuration allows for rain and debris to enter this sensitive electronics space. The vented ridge cap also degrades the installed clean agent flooding fire suppression system by allowing the fire suppression agent to vent out reducing agent concentration within the protected space.
4.2 Work will take place on the roof of building 5A and within a secured gated area.
4.3 The contractor shall remove the existing ridge cap vent on top of building 5A and the adjoining breezeway.
4.4 The contractor shall replace the removed sections with a weather/watertight sealed ridge cap.
4.5 Newly installed ridged cap shall be painted to match existing roof components.
4.6 Contractor shall take all necessary precautions, without interrupting operation, to protect electronic equipment within building 5A from weather and debris during demolition/construction.
4.7 All work shall commence between the hours of 0700-1600 Monday thru Friday.
5. Coast Guard Furnished Material
5.1 None.
6. Coast Guard Furnished Equipment
6.1 None.
7. Travel Requirements
7.1 All costs associated with travel to complete this task are included within the
Contractor’s proposal.
8. Transportation of Equipment/Material
8.1 All costs associated with transportation of equipment/materials are included within the Contractor’s proposal.
9. Data Deliverables
9.1 The contractor shall complete the project no later than 30 days after receipt of the task order from the Contract Officer.
10. Acceptance Plan
10.1 Completion of work under this contract will be monitored and accepted by Coast
Guard Technical POC(s), DCCS Chris Garcia.
STATEMENT OF WORK