Text version

Statement of Work (SOW) Fabricate SPQ-9B waveguides CGC WAESCHE

A. GENERAL INFORMATION

Title of Project: Fabricate SPQ-9B waveguides CGC WAESCHE PR 2116316PFJ006

1. Background: USCGC WAESCHE experienced a casualty with its AN/SPQ-9B waveguide which is a critical component necessary to maintain operational readiness.

2. Scope of Work:

The contractor shall provide labor and materials to fabricate two new sections of AN/SPQ-9B waveguide out of aluminum in accordance with the attached diagram and parts list. Vendor shall test both sections of waveguide for voltage standing wave ratio (VSWR) to assure they are free of obstructions that will cause performance problems after installation. The waveguide is made from M85/1-077 and the flanges are M3922/54-088 and M5922/54-014. Diagram is attached; this work is item 182 and 183 located on page 19 of 23. General notes are on Page 1 and parts list is page 17 of 23.

B. GOVERNMENT RESPONSIBILITIES

The government will provide all diagrams and specifications needed to accurate fabricate the requested item

D. DELIVERY OR DELIVERABLES

Contractor shall commence work within two (2) calendar days of contract award and complete all work no more than FOURTY FIVE (45) calendar days after contract award

E. TECHNICAL REPRESENTATIVE (TR)

Mr. Dale Smith (757) 686-4160 email:Dale.R.Smith@uscg.mil The TR will ensure that the Government’s technical objectives are met, provide necessary information and coordination. The TR is not authorized to change any of the terms and conditions of this contract, nor authorize any additional direction beyond the scope of work. Changes in the scope of work will be made by the Contracting Officer (KO), only by properly written modifications to the contract.

****In order for a contractor to receive award, they must have an active registration in the System for Award Management (SAM), www.sam.gov.

File details come from the government source that posted it. Updated .