QUESTIONS.pdf
PDF 16 KB Posted
- Attached to
- Commercial Fishing Vessel Safety Training
- Solicitation number
- HSCG2308QMMC265
About this file
Initial Questions and Answers on combined synopsis/solicitation HSCG23-08-Q-MMC265
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Applicable Provisions and Clauses.doc | DOC document | |
| Performance Work Statement.doc | DOC document | |
| Contract Line Items.doc | DOC document | |
| rev CFVS FY09 PWS 22MAY08 FINAL.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Note: Any questions regarding this synopsis/solicitation are due no later than 12:00p.m. 9 September 2008.
2. QUESTIONS:
Question: Do we have to submit a proposal on all of the deliverables?
Answer: Your proposal should include all deliverables. See Contract Line Items.
Question: Do we have to include copies of the FAR Clauses we follow or can we just note in our proposal that we will “follow all applicable clauses and requirements”?
Answer: It is acceptable to note in your proposal that we will follow all applicable clauses and requirements.
Question: How soon is the contract being awarded?
Answer: The anticipated award date is 29 September 2008.
Question: Once the contract is awarded, how soon does the CG expect the first class to start? i.e., 3rd Qtr of FY09?
Answer: 1ST Quarter of FY-2009. As soon as the contractor and COTR are in agreement on the curriculum, instructors, materials, location and ODC’s.
Question: What is the turn around time on payments & reimbursable travel costs? Also, the payment divided over 12 months period or lump sum?
Answer: An invoice is typically paid approximately 30 days after the submission of a proper invoice. We anticipate that the payments will be divided over a 12 month period.
Question: Is there an actual funding currently in place or is this going to be a line item in the FY 09 Budget?
Answer: Funding is currently in place for 12 months.
Question: Is the project going to continue and move forward even if there is a continuing resolution on CG's budget or stop until the budget is passed?
Answer: Funding is currently in place for 12 months.
Question: How detailed is the draft "project plan?" Also, is it possible to get a sample project plan?
Answer: The project plan should be as detailed as possible (See 1.11 of the PWS). We do not have a sample project plan available at this time.