HSCETC-14-R-00003 TeleRadiology Services Attachment 1b Transition In Interim Service Plan
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TeleRadiology Attachment 1b Roll Out Plan
SERVICES
Transition In & Interim
Services Plan
NTP + 30 Calendar
Days
NTP + 60 Calendar
Days
NTP + Calendar
PHASE - I PHASE - II PHASE - III
LOCATIONS
IHSC STAFF FACILITIES
Alexandria PHASE - 2
El Centro PHASE - 1
El Paso PHASE - 1
Elizabeth PHASE - 3
Eloy PHASE - 1
Florence PHASE - 1
Houston PHASE - 1
Jena PHASE - 2
Krome PHASE - 3
LA Staging PHASE - 1
Pearsall PHASE - 2
Port Isabel PHASE - 2
San Diego PHASE - 1
Santa Ana PHASE - 1
Stewart PHASE - 3
Tacoma PHASE - 1
Taylor PHASE - 2
Varick PHASE - 3
York PHASE - 3
Suggested Transition In &
Interim Support Plan by
Locations
* Facilities for each phase choosen by geographic proximity to each other
*The Incumbent Contractor will be directed to leave the facilities according to the negotiated Transition In schedule. The process will begin immediately after the the PostAward Conference.
The PostAward Conference will be held not later than 10 working days after the
Contract Award.
TeleRadiology Attachment 1b Roll Out Plan
*The Overall Transition In &
Interim Service Support must be accomplished within 90 calendar days.