This document outlines specifications for work to be accomplished on two 8-meter Rigid Hull Inflatable Boats (RHIBs). The specifications cover overhaul and repair of the RHIBs and their trailers, including replacement of engines, electrical systems, and other components. Work includes surface preparation, painting, and preservation of the vessels. The Navy seeks repair of structural defects, pitting, cracks, and previous repairs across the hulls, decks, and other areas. Bidders must meet standards for welding, non-destructive testing, pressure testing repaired areas, and conducting trials upon completion. The specifications provide detailed requirements for individual aspects of the overhaul from removal and replacement of parts to cleaning, inspection, and operational testing of systems.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
HRMC (NMD)
LOGSU-8 (RMC 55457)
SPECIFICATIONS FOR WORK TO BE ACCOMPLISHED
SPECIFICATION NUMBER: HRMC-014-24
INCLUDES ALL CHANGES THROUGH 11/3/2023
DRAFT
INDEX
SHIP: LOGSU-8 (RMC 55457) HRMC-014-24
ITEMS THAT ARE STRUCK OUT IN THIS INDEX DO NOT APPLY TO THIS CONTRACT.
CATEGORY I. FY-24 STANDARD ITEMS APPLICABLE TO THIS JOB ORDER WITHOUT FURTHER REFERENCE.
ITEM_NO. TITLE CHANGE DATE CHANGE
009-01 General Criteria; accomplish 09/27/2022 Original
009-02 Environmental Compliance Report for Material Usage; accomplish 09/27/2022 Original
009-03 Toxic and Hazardous Substance; control 09/27/2022 Original
009-04 Quality Management System; provide 09/27/2022 Original
009-05 Temporary Access; accomplish 09/27/2022 Original
009-06 Maintaining Protection and Cleanliness from Non-Radioactive Operations;
accomplish
09/27/2022 Original
009-07 Confined Space Entry, and Certification; accomplish 09/27/2022 Original
009-08 Shipboard Fire Protection and Fire Prevention; accomplish 02/28/2023 CH-1
009-10 Asbestos-Containing Material (ACM); control 09/27/2022 Original
009-18 Mine Warfare Ships Magnetic Material; control 09/29/2022 Original
009-19 Provisioning Technical Documentation (PTD); provide 09/27/2022 Original
009-20 Government Property; control 09/27/2022 Original
009-21 Logistics and Technical Data; provide 09/27/2022 Original
009-23 Interference; remove and install 09/29/2022 Original
009-24 Authorization, Control, Isolation, Blanking, Tagging, and Cleanliness; accomplish 09/27/2022 Original
009-34 Fire Protection of Unmanned Vessel at Contractor Facility; accomplish 09/27/2022 Original
009-39 Technical Manual Contract Requirement (TMCR) for a New Technical Manual for
Commercial Equipment/Component; accomplish
09/27/2022 Original
009-40 Contractor Crane, Multi-Purpose Machine and Material Handling Equipment at a
Naval Facility; provide
09/27/2022 Original
009-60 Schedule and Associated Reports for CNO Availabilities; provide and manage 09/30/2022 Original
009-61 Shipboard Use of Fluorocarbons; control 09/27/2022 Original
009-67 Integrated Total Ship Testing; manage 09/27/2022 Original
009-69 Heavy Weather/Mooring Plan; provide 09/27/2022 Original
009-70 Confined Space Entry, Certification, Fire Protection, Fire Prevention and
Housekeeping for Unmanned Vessels; accomplish
09/27/2022 Original
009-72 Physical Security at a Private Contractor Facility; accomplish 09/30/2022 Original
009-73 Shipboard Electrical/Electronic Cable Procedure; inspect, test, install, remove, and repair
09/30/2022 Original
009-74 Occupational, Safety and Health Plan; accomplish 09/30/2022 Original
009-80 Ship Facilities; maintain 09/27/2022 Original
009-81 Compartment Closeout; accomplish 09/30/2022 Original
009-82 Installation of Equal Component Vice Specified Component; report 09/27/2022 Original
009-84 Threaded Fastener Requirements; accomplish 09/30/2022 Original
009-88 Collection, Holding and Transfer (CHT) and Motor Gasoline (MOGAS) Tanks, Spaces, and Piping, including Sewage or MOGAS-Contaminated Tanks, Spaces, and Piping; certify
09/27/2022 Original
009-93 Emergency Planning and Community Right-to-Know Act (EPCRA) and Pollution
Prevention Act (PPA) Information; provide
09/27/2022 Original
009-99 Ship Departure Report; provide 09/27/2022 Original
ITEM_NO. TITLE CHANGE DATE CHANGE
009-100 Ship's Stability; maintain 09/30/2022 Original
009-101 Ship Transit and Berthing; accomplish 09/27/2022 Original
009-106 Work Authorization Form Coordinator (WAFCOR); provide 09/27/2022 Original
009-109 Non-SUBSAFE Work on SUBSAFE-Certified Vessel; accomplish 09/27/2022 Original
009-110 Non-Nuclear Work on a Nuclear Vessel; accomplish 09/27/2022 Original
009-111 Schedule and Associated Reports for non-CNO Availabilities; provide and manage
09/30/2022 Original
009-117 Combat Systems, Light-Off Suport; provide 09/30/2022 Original
009-118 CG Deck Loading; accomplish 09/27/2022 Original
009-120 Fact Finding and Critique of Unplanned Event; manage 09/30/2022 Original
009-122 Temporary Padeye; install and remove 09/30/2022 Original
009-125 Boats Less Than 65 Feet Long; accomplish 10/25/2022 Original
099-01PH Waste Generated on Government Property, including Satellite Accumulation area (SAA), Managing and Disposing of Hazardous Waste (HW) and non-HW;
accomplish
01/20/2023 Original
099-02PH Dry Dock Requirement; accomplish 01/20/2023 Original
099-03PH Additional Environmental Requirements; accomplish 01/20/2023 Original
099-04PH Industrial Wastewater/Oily Wastewater Disposal; accomplish 01/20/2023 Original
099-007PH Radiological Fallout Controls; accomplish 07/13/2023 CH-3
099-08PH Safety of Ship Requirement; provide 01/17/2023 Original
099-40PH Additional Requirements for Contractor Cranes, Multi-Purpose machine, and
Material Handling Equipment at Joint Base Pearl Harbor Hawaii; accomplish
01/17/2023 Original
099-69PH Pier Laydown for Pearl Harbor Naval Shipyard & IMF (PHNSY & IMF)
Availability; accomplish
07/06/2023 CH-2
CATEGORY II. FY-24 STANDARD ITEMS WHICH MAY BE INVOKED IN THE WORK ITEMS OF THIS JOB ORDER.
TITLE CHANGE DATEITEM NO. CHANGE
009-12 Weld, Fabricate, and Inspect; accomplish 09/27/2022 Original
009-25 Structural Boundary Test; accomplish 09/29/2022 Original
009-32 Cleaning and Painting Requirements; accomplish 09/29/2022 Original
009-90 Technical Representative; provide 09/27/2022 Original
ITEM NO. TITLE
Hazardous Waste Produced on Naval Vessels; control077-00-001
RHIB Workskiff Outboard Engines; replace236-11-001
RHIB Workskiff Electrical System; replace321-11-001
Vessel and Trailer Custody Transfer; accomplish583-31-001
RHIB Workskiff; repair583-31-002
RHIB Workskiff; repair and preserve631-11-001
SHIP: LOGSU-8 (RMC 55457) ITEM NO: 077-00-001
COAR: 26 PCN: SERV-L107
SERV-L106
CMP:
PLANNER:
NONE
SSP: HRMC-014-24 1 of 4 ITEM NO: 077-00-001
1. SCOPE:
1.1 Title: Hazardous Waste Produced on Naval Vessels; control
1.2 Location of Work:
1.2.1 Throughout the Ship
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 Resource Conservation and Recovery Act (RCRA)
2.2 49 U.S.C. 5103, Federal Hazardous Materials Transportation Act
2.3 Applicable Hazardous Waste Manifest Form
2.4 10 U.S.C. 7311
3. REQUIREMENTS:
3.1 Manage and dispose of all hazardous waste listed in 3.5 in accordance with 2.1 and 2.2.
3.1.1 When a Navy generator number is required by this Work Item, submit the original of 2.3 to the SUPERVISOR for assignment of Environmental Protection Agency (EPA) or delegated state environmental agency identification number.
3.1.2 Manage and transport for Navy disposal, Navy-generated
hazardous waste listed in 3.5 in accordance with 2.1 and 2.2, as designated by the SUPERVISOR.
3.1.3 Submit one legible copy of 2.3 signed by the owner or operator of the disposal facility to the SUPERVISOR within 48 hours of receipt from owner or operator of disposal facility.
3.2 Complete documentation required by 2.1 and 2.2, using EPA or delegated state environmental agency identification number in accordance with 2.4.
3.3 If the contractor, while performing work at a Government facility, cannot obtain a separate generator identification number from the state in which the availability will be performed, the contractor shall notify the SUPERVISOR within three business days of receipt of written notification by the state. After obtaining approval of the SUPERVISOR, the contractor shall use the Navy site generator identification number and insert in the remarks block the contractor generator identification number issued for the site where his main facilities are located.
3.4 If, for availabilities at a contractor-owned or controlled facility, the Navy cannot obtain a separate generator identification number for use at a contractor facility, the Navy shall notify the contractor within three business days of receipt of notification by the state. The contractor shall dispose of hazardous waste in accordance with 2.1, 2.2, and 3.2.3.
SHIP: LOGSU-8 (RMC 55457)
SSP: HRMC-014-24 2 of 4 ITEM NO: 077-00-001
3.5 Hazardous waste, as identified in 2.1, expected to be produced during performance of this Job Order:
AMOUNT
TYPE NAVY CO-GENERATED CONTRACTOR
Acid Solutions (may include _____ ____________ __________ spent sulfamic, citric, chromic, nitric, sulfuric, hydrochloric, etc.)
Ethylene Glycol (Antifreeze) _____ ____________ __________
Sodium Hydroxide _____ ____________ __________
Cleaning Solvents _____ ____________
Sodium Phosphates (Tri, Bi, _____ ____________ or Mono)
Fluorocarbons _____ ____________ __________
Morpholine _____ ____________ __________
Sodium Chromates _____ ____________ __________
Hydrazine _____ ____________ __________
Methyl Ethyl Ketone _____ ____________ __________
Spent Abrasive Blast Material _____ ____________ __________
(contaminated with a known hazardous waste)
Trichloroethane _____ ____________ __________
Miscellaneous Chemicals _____ ____________ __________
(Ignitable)
Miscellaneous Chemicals _____ ____________
(Corrosive)
Miscellaneous Chemicals _____ ____________ __________
(TCLP Toxic)
Miscellaneous Chemicals _____ ____________ __________
(Reactive)
Oil (Synthetic) _____ ____________ __________
Paints (Enamel, Latex, _____ ____________ __________
Epoxy, thinners, oil based, rubber paint, nonskid, lacquer, remover, varnishes)
Paints (May include lead, _____ ____________ __________ cadmium, or chrome)
SSP: HRMC-014-24 3 of 4 ITEM NO: 077-00-001
Paint Strippers (phenols, _____ ____________ __________ lead, chromium)
Sludge (Contaminated with _____ ____________ a known hazardous waste)
Waste Water w/ Detergent _____ ____________
Ventilation Debris/Residue
(heavy metals, e.g., cadmium, chromium) _____ ____________ __________
3.5.1 Provide 0 dollars for managing and disposing of all hazwaste listed in 3.5. Total cost greater or less than dollar amount when authorized will be the subject of an equitable adjustment.
3.6 Notify the SUPERVISOR at least one working day prior to shipment of hazardous waste for disposal.
3.7 Submit one legible copy, in approved transferrable media, of a report identifying type, amount, and disposal cost of waste listed in 3.5 that was removed during the performance of this Job Order to the
SUPERVISOR.
3.7.1 The report shall include analysis or other method used to identify the waste and state whether each listed waste was hazardous (with generator assignment), non-hazardous, or did not exist.
3.7.1.1 Chemical analysis shall be accomplished by laboratories with state or EPA approved quality assurance programs.
3.7.2 The contractor shall make an effort to minimize hazardous waste generation by reducing the volume or toxicity by neutralizing, recycling, or otherwise removing it from the requirements of Subtitle C of 2.1 and include a description of such efforts in the report.
3.8 Nothing contained in this Work Item shall relieve the contractor from complying with applicable federal, state, and local laws, codes, ordinances, and regulations, including the obtaining of licenses and permits in connection with hazardous waste handling and disposal in the performance of this contract.
4. NOTES:
4.1 The waste listed in 3.5 is based on the best information available at the time of preparation of the solicitation. Hazardous waste generated during the actual performance of the work may vary in type or amount from waste listed in 3.5 which may result in renegotiation for credit or increase pursuant to Paragraph (b) of 2.4. The contractor is expected to use best management practice to identify and dispose of all hazardous waste. Some of the substances listed in 3.5 may be neutralized, recycled, or otherwise removed from the requirements of Subtitle C of 2.1. Inclusion of these substances in the waste listed in
3.5 does not preclude the contractor from taking action consistent with
2.1 to reduce or eliminate the hazardous constituents of any waste required to be disposed of under the contract in accordance with 2.2.
Processes that add hazardous constituents to the bilges may require that bilge water be disposed of as a hazardous waste.
4.1.1 The types and amounts of wastes listed in 3.5 are estimates of waste to be disposed of under this contract as required by 2.4. They
SSP: HRMC-014-24 4 of 4 ITEM NO: 077-00-001 are not estimates of the amount of the work involved in generating that waste. The work requirements of each individual Work Item specify the actual work to be accomplished.
4.2 Hazardous wastes are determined by one or more of the following methods:
4.2.1 Chemical analysis which shows that the material
characteristics of ignitability, corrosivity, reactivity, and/or toxicity (Toxicity Characteristic Leachate Procedure - TCLP) exceed the limits for that material in 40 CFR 261.20 Subpart C.
4.2.2 Reference to a Material Safety Data Sheet (MSDS).
4.2.3 Applying knowledge of the hazardous characteristics of the waste in light of the materials or the process used.
4.3 Asbestos, bilge water, oil/water including sludge, debris and other contaminants, sludge which includes solids and sludge from ballast tanks, CHT tanks, voids, oily waste tanks, fuel ballast tanks, fuel oil tanks, skegs (West coast), PCB's (Maryland), etc., apply only in those states listing them as hazardous waste. When an availability is to be performed in a state where these items are hazardous waste, an estimate of the amount to be generated shall be included in 3.5.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.
SHIP: LOGSU-8 (RMC 55457) ITEM NO: 236-11-001
COAR: 26 PCN: SERV-L109
SERV-L108
CMP:
PLANNER:
NONE
SSP: HRMC-014-24 1 of 7 ITEM NO: 236-11-001
1. SCOPE:
1.1 Title: RHIB Workskiff Outboard Engines; replace
1.2 Location of Work:
1.2.1 Throughout Vessel
1.3 Identification:
1.3.1 Quantity (one EA), 8 Meter RHIB, (OPEN), Hull Identification Number: 8MSC1703
1.3.2 Quantity (one EA), 8 Meter RHIB, (OPEN), Hull Identification Number: 8MSC1704
2. REFERENCES:
2.1 Standard Items, (FY-24 CH-1)
2.2 300-5107858 Rev A, Standard Electrical Installation Requirements and Nomenclature
2.3 MIL-STD-2003, Electric Plant Installation Standard Methods for Surface Ships and Submarines
2.4 TO300-AU-SPN-010 Rev A, Fabrication, Welding, and Inspection of Small Boats and Craft, Aluminum Hulls
2.5 Evinrude E-Tech, BRP Service Manual
2.6 WS28F-00001, Master Tech Data Drawing Index
2.7 WS28F-00002, Cage Code List
2.8 WS28F-00003, Outboard Plan and Profiles
2.9 WS28F-00004, Inboard Plan and Profiles
2.10 WS28F-00005, General Arrangement
2.11 WS28F-00006, Canopy Arrangement
2.12 WS28F-00007, Fuel System Arrangement
2.13 WS28F-00008, Fuel Tank Arrangement
2.14 WS28F-00009, Bilge Pump Arrangement
2.15 WS28F-00011, Control System
2.16 WS28F-00012, Navigation-Display Arrangement
2.17 WS28F-00013, Collar System Arrangements Mounting Plates
2.18 WS28F-00014, Structural Arrangement
2.19 NSW8MTR-BAT-T-TOP-001, Battery System
2.20 NSW8MTR-CKTS-T-TOP-001, Circuits
2.21 NSW8MTR-FUEL-T-TOP-001, Fuel Gage
2.22 NSW8MTR-PNL-T-TOP-001, 12 VDC House Service
SSP: HRMC-014-24 2 of 7 ITEM NO: 236-11-001
2.23 NSW8MTR-STEER-T-TOP-001, Power Assisted Steering
2.24 NSW8MTR-SW-T-TOP-001, Switch Panels
2.25 NSW8MTR-VSM-T-TOP-001, VSM Meter and Breaker Wiring
2.26 Suzuki Engine Manual, K13-DF250AP-300AP-99011-98J20-03BEN
2.27 Suzuki DF250AP-300AP, Set up manual
2.28 SeaStar-Hydraulic Assist Pump, Installation and Owner's Manual
2.29 SeaStar Liquid Alignment/Tiebar Valve, Installation and Owner's Manual
2.30 Systems and Specifications, SSPC Painting Manual, Volume 2
2.31 DOL, OSHA STD 29 CFR 1915, Occupational Safety and Health Standards for Shipyard Employment
3. REQUIREMENTS:
3.1 All removed fasteners shall be replaced with new corrosion resistant steel (CRES), ASTM A276, Type 316 fasteners, unless otherwise specified.
All nuts shall be self-locking type, unless otherwise specified. One CRES washer shall be used under each bolt head and under each nut. Bolt/stud length shall not exceed less than 1-1/2 threads or more than 5 threads beyond the nut with full thread engagement for each vessel listed in 1.3.
3.1.1 Apply anti-seize compound, Loctite 34026 marine grade anti-seize or equal to all stainless-steel threaded fasteners.
3.2 All equipment mounted to aluminum shall have corrosion protection tape (3M Scotchrap #51) installed between the mating surfaces unless otherwise noted for each vessel listed in 1.3.
3.3 Accomplish an operational test and inspection of each existing engine for the vessels identified in 1.3 prior to removal. An authorized Evinrude technician shall perform diagnostic testing and resolve any service codes in accordance with 2.5.
3.3.1 Accomplish an operational and technical inspection of each engine to include gear case and identify any additional items recommended for repair or replacement. Repair or replacement items include, but are not limited to propellers, knobs, handles, switches, cylinders, valves, pumps, bearings and gears, etc.
3.3.2 The operational and technical inspection shall be performed to sufficiently determine additional items needing repair or replacement not covered in paragraphs 3.3.3 to 3.3.23 in order to return the unit to a reliable, operational condition that meets OEM specifications.
3.3.3 Accomplish 500 hour maintenance in accordance with OEM
Inspection and maintenance schedule.
3.3.4 Verify starter output voltage is 55 volts as per OEM
specifications.
3.3.5 Accomplish an Engine Management Module (EMM) function test.
3.3.6 Accomplish engine cylinder dry and wet compression tests.
3.3.7 Accomplish engine cylinder leak down test.
3.3.8 Accomplish an inspection of the reed block.
3.3.9 Remove existing engine zinc anodes and install with new engine
SSP: HRMC-014-24 3 of 7 ITEM NO: 236-11-001 zinc anodes.
3.3.10 Remove existing corroded engine fittings and replace with new engine fittings.
3.3.11 Remove existing Evinrude front engine cover and install new front engine cover (Evinrude part number 0357604) on port engine of vessel listed in 1.3.1.
3.3.12 Remove existing and install new port and starboard propellers (Evinrude part numbers 763990 and 763991).
3.3.13 Clean and preserve spray plate mounted to bottom of swivel assembly.
3.3.14 Accomplish base metal repair (clad weld) and to forward part of lower unit skegs.
3.3.15 Open and inspect the lower unit internal components, order and replace all wearable/broken items to include gaskets/seals and any rotating or sliding component showing signs of excessive wear or damage.
3.3.16 Remove existing water pump, thermostat and thermostat gasket from the engine cooling system and install new cooling system water pump, thermostat and thermostat gasket.
3.3.17 Remove existing engine water inlet screens and install new high flow water inlet screens part number 5010501.
3.3.18 Accomplish a pressure and vacuum test of the gear case.
3.3.19 Remove existing engine gear case oil and plug gasket and install new gear case oil and plug gasket.
3.3.20 Accomplish Trim and Tilt system service in accordance with procedures starting on page 323 of 2.5 BRP Service Manual to include replacing filters and O-rings.
3.3.21 Ensure all existing Evinrude engine mounting brackets, wiring, hoses and assemblies are removed prior to installation of new port and starboard Suzuki engines for each vessel listed in 1.3.
3.3.22 Remove existing Evinrude remote oil tanks, oil level
converter kits and senders, system hoses, associated fittings, hose clamps, and engine oil in the remote tanks for each vessel listed in 1.3.
3.3.23 Ensure overhauled Evinrude engines are placed in long term storage in accordance with manufacturer’s recommendations. Place each engine in a crate suitable for long term storage and deliver to LOGSU8 local point of contact.
3.3.23.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.3.1 through 3.3.23 to the SUPERVISOR.
3.3.23.2 Reports shall include all discrepancies, diagnostic
results, recommendations and material required to repair any discrepancies.
3.4 Retain all removed items for instructions by SUPERVISOR. At the discretion of SUPERVISOR, box all removed items for turnover upon vessel/trailer turnover for each vessel listed in 1.3.
SSP: HRMC-014-24 4 of 7 ITEM NO: 236-11-001
3.5 Accomplish the requirements of 009-90 of 2.1 for Suzuki engine installation, setup and to verify all engine related work.
3.6 Install new port and starboard Suzuki engines (Suzuki part number DF250APXX0) for each vessel listed in 1.3 in accordance with 2.26 and
2.27. NOTE: Engines will be provided by the Government.
3.6.1 Install new Seastar Tournament Series Adjustable tie bar kit for 15” to 20.5” (part number TFX HO6821) for each vessel listed in 1.3.
3.6.2 Install new Suzuki Watergrip 3x16x18.5 port and starboard propellers (Suzuki part number 990C0-0081L-185 and 990C0-00810-185), and two (2) propeller hub kits (Suzuki part number 57630-92L00).
NOTE: Propellers will be provided by the Government.
3.6.3 Remove existing port and starboard engine cable protective hoses and procure and install new port and starboard engine cable protective hoses. Template exact size, length, configuration and location from existing boat conditions using 2.26 and 2.27 for guidance.
3.6.4 An authorized Suzuki dealer shall setup and verify all engine related work listed in Paragraph 3.6 through 3.6.3 in accordance with 2.26, 2.27 and 009-90 of 2.1. Contractor shall estimate two separate setups, one per craft.
3.7 Remove existing engine and trim control cables, binnacle, gauges, engine harnesses, engine GPS Antenna, and associated hardware.
3.7.1 Install new 21’ Harness (Suzuki part number 36620-98L00), Panel assembly, main switch (Suzuki part number 37100-98L10), 2’ Harness extension (Suzuki part number 990C0-88104), Wire Comp Gauge Adapter (Suzuki part number 36667-96L40), Multifunction Gauge (Suzuki part number 34011-96L42), 2’ N2K cable (Suzuki part number 990C0- 88L00-KIT), Backbone T (Suzuki part number 990C0-88110), Fluid Level Sensor (Suzuki part number 990C0-88217), GPS Module (Suzuki part number 990C0-88122), Battery Isolator Lead Set (Suzuki part number 33830-98J11), and all additional cabling and hardware in accordance with the manufacturer’s instructions for installing the Suzuki DF250APXX engines. GPS Module antenna shall be installed on the starboard side of the hardtop, outboard of the radar scanner.
Contractor is responsible to install all components necessary to convert boat to Suzuki DF250APXX engines in accordance with manufacturer specifications. NOTE: Dual Engine SPC 2.0 Kit (Suzuki part number 67000-98L20) will be provided by the Government.
3.7.2 Contractor is responsible to install all components necessary to convert each vessel to Suzuki DF250APXX engines in accordance with manufacturer specifications.
3.8 Remove the existing ignition switch, kill switch and Evinrude dual switch panel assembly and associated cabling and install new ignition switch (Honeywell part number 1TL1-2D), kill switch (Sierra part number MP40970-1), dual switch panel assembly (Suzuki part number 37100-98J21), and cabling in accordance with manufacturer’s instructions. The new ignition switches, kill switch, and dual switch panel assembly shall be connected to the new Suzuki system. Connect switches to the new engine wiring harness using Deutsch connectors vice cutting the harness.
3.8.1 All harnesses installed shall be procured in accordance with
SSP: HRMC-014-24 5 of 7 ITEM NO: 236-11-001 appropriate length for each vessel. No connections shall take place in bilge bottom.
3.8.2 Technical Representative shall update the display software to the current version.
3.9 Remove the existing steering system in its entirety to include steering wheel, tilt helm pump, power assist pump, and hydraulic lines and install new steering wheel, steering wheel cap, steering wheel knob, tilt helm pump (Teleflex part number HH6543), power assist pump (Teleflex part number PA1200-2), port and starboard steering cylinders (Teleflex part number HC6845), Hardware mounting kit (Teleflex part number HA6804), 3FT steering hose (8 EA), 6FT steering hose (2 EA), and 32FT Steering hose (3 EA), through fittings class 3000 aluminum Coupling ¼" (4 EA) (McMaster part number 3867T61), Compression fittings straight (18 EA) (Seastar part number HF5528), Compression fittings elbow (8 EA)(Seastar part number HF5529), T fittings (Seastar part number HF5530), Alignment Valve (SeaStar part number HA5471-2, and 8FT steering hose (SeaStar part number HO7508) in accordance 2.28, 2.29 and manufacturer’s instructions.
Template exact size, length, configuration and location from existing boat conditions. New hydraulic lines shall be routed to new port and starboard engine in accordance with manufacturer’s instructions.
3.9.1 Fill and bleed the hydraulic steering system and refill to proper level with new steering fluid using 2.28, 2.29 and manufacturer’s instructions as guidance.
3.9.2 A certified Suzuki technician ensure the display and engine software is the current version.
3.9.3 An authorized Suzuki dealer shall setup and verify all
controls and steering related work listed in paragraphs 3.9 through
3.9.2 in accordance with 2.27.
3.10 Dress and secure all engine and steering control system
hoses/cables throughout the vessel, including chaffing protection at all penetrations for each vessel listed in 1.3.
3.11 Drain, clean, ventilate, certify gas free, and inspect fuel tank on each vessel listed in 1.3, in accordance with the requirements of 2.31.
3.11.1 Clean interior surfaces free of loose rust, dirt, grease, lint and other foreign matter.
(V)(G) "CLEANLINESS INSPECTION"
3.12 Accomplish a visual inspection after cleaning of interior surfaces of each fuel tank cleaned in 3.11 Method for inspection shall be visual and by use of a borescope. Accept criteria for cleanliness shall be in accordance with paragraph 3.11.1
3.12.1 Submit one legible copy, in hard copy or approved
transferable media, of a report listing the results of 3.12 to the
SUPERVISOR.
(V)(G) "PRELIMINARY FUEL TANK PRESSURE TEST"
3.13 Accomplish a pressure test of the fuel tank for each vessel listed in 1.3, within the first 10 days of the start of the availability. Test pressure shall be 2 PSI, holding pressure for 10 minutes. Pressure shall not exceed 2.5 PSI. Allowed pressure drop: NONE. Apply a soapy solution
SSP: HRMC-014-24 6 of 7 ITEM NO: 236-11-001 that is non-corrosive and nontoxic solution to inspect for leakage.
Inspect all seams and attachments for leakage. Record results.
3.13.1 Upon completion of the preliminary tank test, blank all tank openings until final installation of fuel system fittings, hoses and hardware to prevent foreign object entry.
3.13.2 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing the results of 3.13 and
3.13.1 to the SUPERVISOR. Report shall include type, extent and locations of defects found.
3.14 Remove existing and install new fuel system, lines, valves, fittings, filters, gauges, gaskets, and filter housings using the same size and type of that removed for each vessel listed in 1.3, in accordance with 2.12 and 2.13. This includes but not limited to fuel fill cap, fuel fill cap with key and sounding rod, fuel vent, fuel supply, fuel fill hoses, hose clamps, cable clams, fuel gaskets, fuel and water filter separator housings and filters, fuel shut-off valves, gauges, and fuel tank fittings.
3.14.1 Do not procure and install in-line fuel ball pumps.
3.15 Double CRES 316 stainless steel hose clamps shall be installed at any hose to fitting connection for the oil and fuel system for each vessel listed in 1.3.
3.16 Dress and secure all fuel and oil system hoses throughout the vessel, including chaffing protection at all penetrations for each vessel listed in 1.3.
3.17 All fuel and oil hoses shall be templated from existing, shall meet appropriate length for vessel and continuous from fitting to fitting for each vessel listed in 1.3. No connections shall take place in bilge bottom.
(V)(G) "FINAL FUEL TANK PRESSURE TEST"
3.18 After fuel tank installations are complete, accomplish a final pressure test for each vessel listed in 1.3. Pressure test fuel tank to 2 PSI, holding pressure for 10 minutes. Pressure shall not exceed 2.5 PSI.
Allowable Pressure drop: NONE. Apply a soapy solution that is non-corrosive and non-toxic solution to inspect for leakage. Inspect all seams and attachments for leakage. Record test results.
3.18.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.18 and 3.18.1 to the SUPERVISOR.
(V)(G) "FINAL VISUAL INSPECTION"
3.19 Completion walk thru with the SUPERVISOR prior to accomplishing Customer waterborne trials, for each vessel listed in 1.3. Contractor shall have all work and discrepancy work list compete, all electrical/electronic, and steering, propulsion equipment and safety systems tested satisfactory prior to waterborne Customer Trials. Provide a complete list of equipment that has been successfully tested prior to waterborne trials to the SUPERVISOR.
3.19.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements
SSP: HRMC-014-24 7 of 7 ITEM NO: 236-11-001 of 3.19 to the SUPERVISOR within 3 days of waterborne trials.
3.19.2 Contractor shall turn over all warranty and registration documentation at the end of the availability for the newly installed engines.
(V)(G) "WATERBORNE TRIALS"
3.20 Provide qualified personnel to operate each vessel listed in 1.3.
Provide 250 gallons of fuel for each vessel prior to waterborne trials.
Accomplish a two-hour waterborne trial for each vessel to test engines, all electrical and mechanical equipment. The Contactor shall conduct independent waterborne trials prior to customer acceptance trials to verify all work has been accomplished successfully and all systems/components are operating properly. The contractor shall top off the fuel tank between each waterborne trial.
3.20.1 Contractor shall provide a QA inspection report certifying each waterborne trial completion, and work completion, including any discrepancies identified during each waterborne trial.
3.20.2 Submit one legible copy, in approved transferrable media, of a report listing results of the requirements of 3.20 and 3.20.1 to the SUPERVISOR within 2 days of each waterborne trial completion.
3.21 Clean and degrease the bilge of each vessel listed in 1.3.
Thoroughly wash-down each vessel and bilge with soap and fresh water, rinse the seawater from all components after each waterborne trial has been performed.
3.22 Flush engine cooling system with freshwater after each waterborne trial has been performed. NO WATER IS TO BE LEFT IN THE BILGES. CLEANING
IS TO BE ACCOMPLISHED AFTER ALL TRIALS AND PRIOR TO FINAL ACCEPTANCE.
3.23 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface for each vessel listed in 1.3.
4. NOTES:
4.1 Work in conjunction with 8SC1703 and 8MSC1704 work items 321-11-001, 583-31-002 and 631-11-001
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
SHIP: LOGSU-8 (RMC 55457) ITEM NO: 321-11-001
COAR: 26 PCN: SERV-L111
SERV-L110
CMP:
PLANNER:
NONE
SSP: HRMC-014-24 1 of 7 ITEM NO: 321-11-001
1. SCOPE:
1.1 Title: RHIB Workskiff Electrical System; replace
1.2 Location of Work:
1.2.1 Throughout Vessel
1.3 Identification:
1.3.1 Quantity (One EA), 11 Meter RHIB, (OPEN), Hull Identification Number: 8MSC1703
1.3.2 Quantity (One EA), 11 Meter RHIB, (OPEN), Hull Identification Number: 8MSC1704
1.3.3 Quantity (One EA), 8 Meter RHIB Trailer, Trailer Serial Number: 42XBK273XHB115833
1.3.4 Quantity (One EA), 8 Meter RHIB Trailer, Trailer Serial Number: 42XBK2737HB115837
2. REFERENCES:
2.1 Standard Items, (FY-24 CH-1)
2.2 300-5107858 Rev A, Standard Electrical Installation Requirements and Nomenclature
2.3 MIL-STD-2003, Electric Plant Installation Standard Methods for Surface Ships and Submarines
2.4 TO300-AU-SPN-010 A, Fabrication, Welding and Inspection of Small Boats and Craft, Aluminum Hulls
2.5 WS28F-00001, Master Tech Data Drawing Index
2.6 WS28F-00003, Outboard Plan and Profiles
2.7 WS28F-00004, Inboard Plan and Profiles
2.8 WS28F-00005, General Arrangement
2.9 WS28F-00006, Canopy Arrangement
2.10 WS28F-00007, Fuel System Arrangement
2.11 WS28F-00008, Fuel Tank Arrangement
2.12 WS28F-00009, Bilge Pump Arrangement
2.13 WS28F-00011, Control Systems
2.14 WS28F-00012, Navigation Display Arrangement
2.15 WS28F-00013, Collar System Arrangements Mounting Plates
2.16 WS28F-00014, Structural Arrangement
2.17 NSW8MTR-T-TOP-001, Battery System
2.18 NSW8MTR-CKTS-T-TOP-001, Circuits
2.19 NSW8MTR-FUEL-T-TOP-001, Fuel Gauge
SSP: HRMC-014-24 2 of 7 ITEM NO: 321-11-001
2.20 NSW8MTR-PNL-T-TOP-001, 12 VDC House Service
2.21 NSW8MTR-STEER-T-TOP-001, Power Assisted Steering
2.22 NSW8MTR-SW-T-TOP-001, Switch Panels
2.23 NSW8MTR-VSM-T-TOP-001, VSM Meter and Breaker Wiring
2.24 BOATMASTER, Operation and Maintenance Manual Trailer: WS8M-180
2.25 Suzuki Engine Manual, K13-DF250AP-300AP-990111-98J20-03BEN
2.26 Suzuki DF250P-300AP, Set up manual
2.27 Underwater Light, Mounting Plates
2.28 8M RIB, Console Cracking Fix
3. REQUIREMENTS:
(I) "PRELIMINARY ELECTRICAL INSPECTION AND OPERATIONAL TEST"
3.1 Accomplish a complete inspection, and an operational test of all installed mechanical and electrical equipment, including each electrical component, lighting, navigational equipment, wiring/cabling, pump, piping, hose and label plate, using 2.2 through 2.28 as guidance, for each vessel listed in 1.3, and the location identified in 1.2. Record results.
3.1.1 Submit one legible copy, in approved transferable media, of a report listing the results of the inspection and testing requirements of 3.1 to the SUPERVISOR, within 5 days of testing.
3.1.1.1 The report shall include electrical/mechanical component item number, as identified on its associated reference, reference number, component location, condition, and the testing results of each component tested.
3.2 Prior to component removal, record each component name, as identified on its associated reference, reference number, location, and electrical connection (Disconnect Log) for each vessel listed in 1.3.
3.2.1 Retain all removed items, the SUPERVISOR shall determine disposition. At the discretion of SUPERVISOR, box each item removed for turnover upon vessel/trailer turnover to the GOVERNMENT.
3.2.1.1 Submit one legible copy, in approved transferable media, of a report listing the results of the requirements of 3.2 to the
SUPERVISOR.
3.3 All new electrical installations shall meet the electrical installation requirements of 2.2, 2.3, 2.8, 2.10 thru 2.14, and 2.17 thru
2.28 for each vessel listed in 1.3.
3.3.1 No electrical connection shall take place in the bilge bottom.
3.3.2 All new electrical connections shall have heat shrink style connections or shall have heat-shrink tubing installed on terminal ends to weatherize.
3.3.3 All new battery and main power connections shall have
protective boots installed.
3.3.4 All new equipment, electrical components, label plates, cable markers, and wire markers, shall be installed, and wire ways and cableways shall be strapped and installed in accordance with 2.2, SSP: HRMC-014-24 3 of 7 ITEM NO: 321-11-001
2.3, 2.8, 2.10 thru 2.14, and 2.17 thru 2.28 prior to operational testing.
3.3.4.1 All new cabling shall be labeled to include circuit
identification at each end.
3.3.4.2 All new wiring shall be labeled to include component
identification on each wire connection/termination point.
3.3.5 Remove corrosion on existing and lightly coat all new and existing electrical terminals and connections, including, battery switch terminals, engine positive and negative terminals, battery connection terminals, gauge terminals, positive and negative terminal blocks, negative bus terminals, circuit breaker connections, switch connections, reset push buttons, receptacles, connectors using No-Ox (NSN 8030-00-598-5915). Ensure all electrical connections are tight.
3.3.6 Groom, dress, and secure all existing and new cabling and wiring to ensure wire/cable runs do not interfere with access to components that are removable.
3.3.7 Install chafe protection to existing and new wires/cables entering cableways and/or where chafing may occur.
3.3.8 Split Conduit shall be installed for each cableway, where previously installed.
3.3.9 Ensure all cable penetration are packed properly throughout each vessel in accordance with manufacturer’s instructions.
3.3.10 Ensure all exterior electrical connections are properly weatherproofed in accordance with 2.2 and 2.3.
3.4 All new equipment mounted to aluminum shall have corrosion protection tape (3M Scotchrap #51) installed between each mating surface unless otherwise noted.
3.5 Each new threaded fastener shall be corrosion resistant steel (CRES), ASTM A276, Type 316, unless otherwise specified. Each nut shall be self-locking, unless otherwise specified. One CRES washer shall be used under each bolt head and under each nut. Bolt/stud thread protrusion shall not extend less than 1-1/2 threads or more than 5 threads beyond the nut with full thread engagement.
3.5.1 Apply anti-seize compound, Loctite 34026 marine grade anti-seize or equal to each new stainless-steel threaded fastener.
3.6 Remove existing and install new batteries in accordance with 2.17.
Install new battery connection hardware using standard nuts and lock washers.
3.7 Install new full enclosure type battery boxes for all new batteries.
3.8 Accomplish the requirements of 009-90 of 2.1, for replacement of the Furuno Navigation System components, for each vessel listed in 1.3, in accordance with 2.14 and manufacturer’s instructions.
3.8.1 Remove existing Furuno navigation system, all associated equipment/cabling and install a new Furuno navigation system to include NavNet TZTouch display (Furuno part number TZTL12F), remote control (Furuno part number MCU002), 24” radome (Furuno part number DRS4DL+), radome power supply (Furuno part number PSU017), (2 EA) NMEA 2000 micro cables (Furuno part number 001-105-800-10), GPS receiver (Furuno part number GP-330B), GPS flush mount kit (Furuno
SSP: HRMC-014-24 4 of 7 ITEM NO: 321-11-001 part number 001-037-630), heading sensor (Furuno part number PG700), transducer (Furuno part number SS60-20-10F) and all associated equipment to include console control pad, cabling and hardware in accordance with manufacturer’s instructions to convert boat to new navigation system. Contractor is responsible to install all components necessary to convert boat to new navigation system.
3.8.1.1 Install latest version of software and charts on Furuno navigation system in accordance with manufacturer’s instructions.
3.8.1.2 Ensure navigation system is electrically connected to the VHF Marine Band Radio at the existing NMEA terminal strip in order to display position data at radio, installation shall be in accordance with manufacturer’s instructions.
3.8.1.3 GPS receiver shall be mounted on the port side of the radar mast, outboard of the radar scanner and connected directly to the NMEA 2000 backbone in the console, in accordance with the manufacturer’s instructions.
3.8.1.4 Install four (4 EA) new spare label plates at the NMEA terminal strip inside the console for removed heading output wiring using the same size and type of that removed.
3.8.1.5 Navigation system shall be connected to the new Suzuki system in accordance with manufacturer’s instructions in order to display engine information.
3.8.1.6 Remove existing and replace with new NMEA 2000 backbone in accordance with 2.13 and manufactures instructions.
(Q)(G) "VISUAL INSPECTION"
3.8.1.7 An authorized Furuno technician shall verify
installation and calibration of all navigation related work.
3.8.2 Install new bus extender (Maretron Part Number NBE100) in the console in order to separate the engine NMEA 2000 from the Furuno NMEA 2000 in accordance with the manufacturer’s instructions.
3.9 Remove existing and install new forward and aft bilge pump system, including, bilge pumps, float switches, NEMA boxes, label plates, associated cabling, hoses, hose clamps and overboard thru-hull fittings using the same size and type of that removed in accordance with 2.12 and 2.13.
3.9.1 Double CRES316 stainless steel hose clamp shall be installed at each hose to fitting connection.
3.9.2 Dress and secure each bilge system hose throughout the vessel, including chaffing protection at each penetration.
3.9.3 All bilge hoses installed shall be templated from existing, ensuring appropriate length for the vessel and continuous from fitting to fitting.
(V)(G) "VISUAL INSPECTION"
3.9.4 Perform manual/auto function bilge test to ensure the float switch operated properly.
3.10 Remove existing and install new fuel sending unit in the fuel tank using the same size and type of that removed in accordance with 2.10, SSP: HRMC-014-24 5 of 7 ITEM NO: 321-11-001
2.11, 2.17 thru 2.19, 2.22 and manufacturer’s instructions.
3.11 Remove existing and install new fuel gauge in accordance with 2.11, 2.13, 2.17 thru 2.20 and manufacturer’s instructions.
3.12 Install (2 EA) new underwater lights (OceanLED part number 012305B), cable (LSDSGU-9) and splices in accordance with 2.2 and manufacturer’s instructions. Underwater lighting circuit must be connected to 12VDC Distribution Panel, 12-P-16 5A, SPARE circuit for power. Connect the underwater lights to power using the upper right “SPARE” On/Off switch on the switch panel located on the port side of the steering wheel. Fabricate and install new U/WTR Lights label plate for switch. Fabricate and install new underwater lights label plate at 12VDC House Service Panel using existing “SPARE” label plate as a template.
New underwater lights must be located on the port and starboard side of the engine bracket in accordance with 2.27. Buoyancy foam must be notched out for light and cable installation and reinstalled inside engine bracket.
3.13 Install (37 EA) new appropriately sized toggle switch boots on all switches located on the console at 12VDC House Service Panel, Switch Panel 1 and Switch Panel 2 for each vessel listed in 1.3.
3.14 Remove existing and install new FWD search light receptacle with dust cap and lanyard on each vessel listed in 1.3, using the same size and type of that removed and in accordance with 2.18.
3.15 Remove existing and install new handheld search light and mount for each vessel listed in 1.3 using the same size and type as that removed and in accordance with 2.18.
3.16 Remove existing and install new AFT search light receptacle with dust cap and lanyard located on the aft deck transom for each vessel listed in 1.3, using the same size and type of that removed and in accordance with 2.18.
3.17 Remove existing and install new Port and Stbd console search light receptacles with dust caps and lanyards for each vessel listed in 1.3, using the same size and type of that removed and in accordance with 2.18.
3.18 Remove existing and install new Port and Stbd console 12 VDC receptacles with dust caps for each vessel listed in 1.3, using the same size and type of that removed and in accordance with 2.18.
3.19 Remove existing and install new forward, aft bilge, and fuel tank vent blower indicator lights on the console for each vessel listed in 1.3, in accordance with 2.18.
3.20 Remove existing and install new hailer control head on each vessel listed in 1.3, in accordance with manufacturer’s instructions and in accordance with 2.18.
3.21 Remove existing and install new Whelen microphone and microphone clip (Whelen part number 01-026D286-06) for each vessel listed in 1.3, in accordance with manufacturer’s instructions and in accordance with 2.11.
3.22 Remove existing and install new Whelen loud hailer speaker for each vessel listed in 1.3, using the same type and size as that removed and in accordance with 2.18.
3.23 Remove existing and install new loud hailer amplifier for each vessel listed in 1.3 in accordance with 2.18.
SSP: HRMC-014-24 6 of 7 ITEM NO: 321-11-001
3.24 Remove existing and install new navigation horn for each vessel listed in 1.3, using the same size and type as that removed and in accordance with 2.18.
3.25 Remove existing and install new AFT deck light for the vessel listed in 1.3.2 using the same size and type of that removed and in accordance with 2.18.
3.26 Disconnect and pull back the existing nineteen (19 EA) cables that run up to the hardtop in order to perform weld repairs in accordance with Paragraph 2.18, and 2.28. Install new cable clams using the same size and type of that removed. After completion of weld repairs, reinstall cables using disconnect sheets.
3.27 Remove existing and install new circuit breakers on 12VDC House Service Panel, Switch Panel 1 and Switch Panel 2 for each vessel listed in 1.3, in accordance with 2.18. Ensure new breaker labels listed in Para
3.12 are incorporated into new distribution panel.
3.28 Remove existing and install new VSM system monitor Blue Seas System part number 1850 for each vessel listed in 1.3, using same type and size as that removed in accordance with 2.23.
3.29 Remove existing and install new Tiger Communications headset helmet jack and dust covers Port and Starboard side of console for each vessel listed in 1.3, using the same size and type as that removed.
3.30 Remove existing and install new console overhead dome light Port and Starboard for each vessel listed in 1.3 and in accordance with manufacturer’s instructions and in accordance with 2.18.
3.31 Remove existing and install new Restricted In Ability to Maneuver (RIAM) lights and wiring for mast on each vessel listed in 1.3 using the same size and type of that removed and in accordance with 2.18.
3.32 Remove existing and install new cable ties in console interior for each vessel listed in 1.3, using the same size and type as that removed in accordance with 2.18.
3.33 Install new port Tiger Communications yellow PTT pushbutton cover Port and Starboard for each vessel listed in 1.3, using the same size and type as that removed.
3.34 Remove existing and install new negative bus bar in starboard transom compartment for each vessel listed in 1.3 in accordance with 2.18.
3.35 Remove existing and install new console interior bus bars for the vessel listed in 1.3.1, using the same size and type as that removed in accordance with 2.18.
3.36 Remove existing and install new Port running light for the vessel listed in 1.3.1, using the same size and type as that removed in accordance with 2.18.
3.37 Remove existing and install new forward deck lights for vessel listed in 1.3.2, using the same size and type as that removed in accordance with 2.18.
3.38 Remove existing and install new Infrared (IR) lights for the vessel listed in 1.3.2, using the same size and type as that removed in accordance with 2.18.
3.39 Remove existing and install new seven-way flat pin, round cable
SSP: HRMC-014-24 7 of 7 ITEM NO: 321-11-001 harness for each trailer listed in 1.3, in accordance with 2.24. Cable harness shall be spliced in accordance with 2.2.
3.40 Remove existing and install new port and starboard taillights for each trailer listed in 1.3, using the same size and type of that removed in accordance with manufacturer’s instructions and 2.24.
3.41 Remove existing and install new aft center light for each trailer listed in 1.3, using the same size and type of that removed in accordance with manufacturer’s instructions and 2.24.
(V)(G) "TRAILER LIGHTS OPERATIONAL TEST"
3.42 Operationally test each trailer light to ensure they are functioning properly.
3.42.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing the operational testing results of 3.42 within 3 days of test completion.
(V)(G) "ELECTRICAL EQUIPMENT OPERATIONAL TEST"
3.43 Coordinate with ships force and accomplish an Operational Test of each piece of newly installed electrical equipment, each electrical device, and each newly installed component for each vessel listed in 1.3.
Testing shall be in accordance with 2.2 through 2.2x and the manufacturer's instructions.
3.43.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing the operational testing results of 3.43.
3.44 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface for each vessel listed in 1.3.
4. NOTES:
4.1 Work in conjunction with 8MSC1703 and 8MSC1704 work items 236-11- 001, 583-31-002 and 631-11-001.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
SHIP: LOGSU-8 (RMC 55457) ITEM NO: 583-31-001
COAR: 26 PCN: SERV-L104
SERV-L105
CMP:
PLANNER:
NONE
SSP: HRMC-014-24 1 of 2 ITEM NO: 583-31-001
1. SCOPE:
1.1 Title: Vessel and Trailer Custody Transfer; accomplish
1.2 Location of Work:
1.2.1 Contractor's Facility
1.3 Identification:
1.3.1 Quantity (One EA), 8 Meter RHIB, (OPEN), Hull Identification Number: 8MSC1703
1.3.2 Quantity (One EA), 8 Meter RHIB, (OPEN), Hull Identification Number: 8MSC1704
1.3.3 Quantity (One EA), 8 Meter RHIB Trailer, Trailer Serial Number: 42XBK273XHB115833
1.3.4 Quantity (One EA), 8 Meter RHIB Trailer, Trailer Serial Number: 42XBK2737HB115837
2. REFERENCES:
2.1 Standard Items, (FY-24 CH-1)
2.2 Attachment (A), Boat and Trailer Custody Form
3. REQUIREMENTS:
3.1 The Government will deliver custody of each vessel and trailer listed in 1.3 to the contractor at the place designated in the specifications, and upon completion of availability will pick-up and accept custody of the vessel and trailer at the place designated in the specifications.
3.1.1 The contractor shall be responsible for each vessel and trailer from the time of delivery to the contractor, to the return of the vessels and trailers to the GOVERNMENT.
3.2 Upon receiving custody of the vessels and trailers listed in 1.3 from the activity, complete Part A of 2.2. Submit one copy, in approved transferrable media, of 2.2 to the SUPERVISOR within 24 hours after delivery of the vessels.
3.3 After returning custody of the vessels and trailers listed in 1.3 to the activity, complete Part B of 2.2. Submit one copy, in approved transferrable media, of 2.2 to the SUPERVISOR, within 24 hours after redelivery of the vessels.
4. NOTES:
4.1 None.