HQ072718R0002_Questions_and_Responses_001.pdf
PDF 94 KB Posted
- Attached to
- Landscaping Services
- Solicitation number
- HQ072718R0002
- Issued by
-
Defense Microelectronics Activity
About this file
Responses to questions
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HQ072718R0002-0001_Amend.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers from the site visit held at DMEA on 15 Nov 2017
1‐ Are there any areas that need hand watering if yes where are those areas located?
Answer – Unknown, refer to section 3.2.9 of the PWS
2‐ Will there be any clean up done prior to new contract start or will the awarded contractor be paid additional for clean‐ up costs?
Answer – Contractor will assume site in existing condition. Government does not guarantee the condition of the site prior to award. Contractor should include any costs associated or bringing into compliance with the PWS in the CLIN(s) provided.
3‐ Will the irrigation system be evaluated and repaired prior to new contract start or will the awarded contractor be paid additional for repairs?
Answer – Irrigation will not be evaluated prior to award. At this time, it is in working order. See section 3.2.9 of the PWS. After award and prior to commencement of work, the COR and contractor will evaluate all systems.