HQ003417R0127_PPML_Q_and_A's_04_AUG_17.docx

DOCX document 20 KB Posted

Attached to
PPML Software Development Services
Solicitation number
HQ003417R0127
Issued by

About this file

Questions and Answers

View the file

Other files

File Type Posted
PPML_PWS_Final_v2_Aug022017.docx DOCX document
HQ003417R0127_Amendment_02.docx DOCX document
HQ003417R0127_Amendment_02_Conformed_Copy_of_the_Solicitation.docx DOCX document
HQ003417R0127_Amendment_01.docx DOCX document
HQ003417R0127_Amendment_01_Conformed_Copy_of_the_Solicitation.docx DOCX document
HQ003417R0127_PPML_Q_and_A's_01_AUG_17.docx DOCX document
PPML_RFP_Past_Performance_Questionnaire.docx DOCX document
HQ003417R0127_PPML_Solicitation_07132017.docx DOCX document
PPML_CDRL_Entries_16_Jun_2017.xlsx XLSX spreadsheet
Presolicitation_Q_and_A_HQ003417R0127.pdf PDF
A03_PPML_PWS_Final.docx DOCX document
PPML_PWS_v9_6_JUN_17.docx DOCX document
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNCLASSIFIED // FOR OFFICIAL USE ONLY

PPML Software Development Services Solicitation # HQ0034-17-R-0127 Questions and Answers Amendment 02

Question #
Question / Comment
Government Response
1.
The requirement reads in part "The Government will have unlimited rights to any contractor-developed software funded under the contract." If however the contractor is using open source software and needs to modify the code for the software, the terms of the open source license may require that such code be contributed to the open source community. Will the Government modify the requirement to allow contribution of code to the open source community when is it required by the open source license terms?
The Government's unlimited rights pursuant to DFARS 252.227-7013, 252.227-7014 and 252.227-7015 does not impact Contractor's ability to comply with the terms of the open source license.
2.
Please advise if the Government will consider additional terms and conditions proposed by the Offeror?
No.
3.
The 'CLIN' column in PWS Section 8 does not align with the CLIN table in Section B. For example, the Draft Conceptual Design Report is listed as CLIN 1001 in the PWS, but under CLIN 0001 in the Solicitation. Similarly the Final Coneptual Design Report is listed in the PWS as CLIN 1002, but appears under CLIN 0001 in the solicitation. Similar discrepancies exist for all the CLINS listed. Recommend the Government align the two tables to make it clear which deliverables are associated with milestone payments under each CLIN.
The misalignment has been addressed by revising the PWS dated August 2, 2017.
4.
Reference Page 15 of 56. Small Business Subcontracting Plan (FAR 52.219-9 and DFAR 252.219-7003) are incorporated in the solicitation. Is the Offeror required to submit a subcontracting plan?
Yes. The solicitation has been adjusted accordingly. The updates can be found in Sections L and M of the conformed copy of Amendment 02.