The document is a Statement of Objectives (SOO) for the US Coast Guard Cutter HICKORY's Fuel Oil Purifier (FOP) Diagnosis and Repair. The Coast Guard is seeking a certified technical representative to provide two days of on-site assistance to diagnose and identify repair parts for a malfunctioning Alpha Laval WHPX-405-TGD-24-60 Fuel Oil Purifier system. The current system is experiencing critical operational issues, including oil discharge through the water outlet, no product outlet discharge, and a suspected broken oil/water seal.

The solicitation (70Z08525Q12824) requires a contractor who is specifically certified to work on Alpha Laval equipment, with performance timing flexible based on the cutter's operational schedule. The work will be conducted at CGC Hickory, located at 4000 Coast Guard Boulevard in Portsmouth, VA, with primary points of contact being Brandon W. Seitz and LTJG Christopher Lansing. Technical references include SFLC Standard Specifications for general requirements, welding processes, auxiliary machine systems, and fire prevention, indicating a comprehensive approach to equipment repair and maintenance.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Objectives for USCGC HICKORY Fuel Oil Purifier

Points of Contact:

CGC Hickory 4000 Coast Guard Boulevard

Portsmouth, VA, 23703

231-944-2157 Email: brandon.w.seitz@uscg.mil Product Line Support:

LTJG Christopher Lansing 443-764-4921

Christopher.g.lansing@uscg.mil Description of Problem:

CGC Hickory has had significant issues operating their Fuel Oil Purifier (FOP) system and have exhausted organic support on troubleshooting and identifying necessary repairs. They are requesting two days off on site to support to identify necessary parts to replace to effect repairs. They are currently experiencing FOP discharges oil through the water outlet, no discharge through the product outlet. Small knick seen on sealing face of sliding bowl body. Replaced O-rings and seals following the intermediate service kit. Systems point to broken oil/water seal during separation process.

Tech Rep Requirements:

Contractor will be certified to work on Alpha Laval specific equipment and systems.

Fuel Oil Purifier Info:

WHPX-405-TGD-24-60

Work to be performed:

Two days of on site technical assistance and identification of necessary parts to purchase to affect repairs.

Desired Period of performance Windows:

Flexible based on the operational schedule of the cutter Technical references:

SFLC Std Spec 0000
General Requirements
SFLC Std Spec 0740
Welding and Allied Processes
SFLC Std Spec 5000
Auxiliary Machine Systems
SFLC Std Spec 5550
Fire Prevention and Response