HEATING SCOPE.docx

DOCX document 63 KB Posted

Attached to
Heating Baseboards, 6262 Morris Road Marcy NY
Solicitation number
2140247
Issued by
Oneida County, New York

About this file

This is a project scope document for a heating baseboard installation project at the Morris Road Integrated Residential Alternative (IRA) Facility located at 6262 Morris Road, Marcy, New York 13403. The project involves adding hydronic baseboards and extending existing heating infrastructure throughout the residential facility. The work includes baseboard extensions of approximately 5 to 7 feet in the entryway and three bedrooms, and new baseboard cover installations in the bathroom and closet. All work must comply with local codes and manufacturer specifications, utilize Haydon 750 Series Hydronic Baseboard or an approved equal, and be completed within 30 days of award. The project is classified as a New York State Public Works project requiring prevailing wage compensation under Project Reference Code 2026028739. A site visit is referenced but specific dates and times are not populated in the document. The point of contact is Jim Bell at 315-281-7760.

The bid price must include all materials, labor, disposal fees, and site cleanup costs. The contractor is responsible for verifying all field dimensions and conditions, protecting adjacent finishes, performing daily cleanup, and removing all debris upon completion. Mechanical and piping work includes extending and reconnecting copper piping to the existing boiler system, purging air from heating lines, and testing and balancing the system for proper operation. Work is restricted to Monday through Friday during specified hours in an occupied residential facility, requiring coordination with the House Director and project manager. The contractor must secure all tools, materials, and equipment daily and is held liable for any lawn or property damage caused during work execution. No specific bid due date, site visit date, or award date is provided in the document.

View the file

Other files

File Type Posted
Floor Plan for work to be done.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT SCOPE

Facility:

Morris Rd. IRA Facility Address:

6262 Morris Rd. Marcy N.Y.13403

Point of Contact:

Jim Bell Contact Phone Number:

315-281-7760

Project Title:

Heating Project Summary of Work:

Add base board in areas where needed.

DESCRIPTION:

(Short description of project). The vendor shall provide all labor and materials necessary to complete the work in a professional manner according to scope of work and architectural drawings if supplied. Work is to be completed within 30 days of award, unless modified below. This is a NYS Public Works project and prevailing wages are to be paid (PRC 2026028739). Refer to attached specification for the following scope of work. Site must be cleaned and all materials secured at the end of each work day. Absolutely no scraps, especially fasteners, are to be left unsecured. Upon completion of (project item), before removal of equipment and scaffolding, contractor is to schedule a quality control and quality assurance inspection with project manager.

SCOPE OF WORK includes, but is not necessarily limited to the following:

The Contractor shall perform the following work

General Conditions Contractor must verify all dimensions and field conditions before work begins.

All work shall comply with applicable local codes and manufacturer installation requirements.

Contractors shall protect adjacent finishes and cleanup work areas daily.

All debris and scrap materials shall be removed from the site upon completion.

System should be tested, purged of air, and verified for proper operation before project closeout.

Baseboard Replacement and Extension Baseboard Type: Haydon 750 Series Hydronic Baseboard (or approved equal).

Entryway Extend existing hot water baseboard approximately 5 feet, install new baseboard cover with matching end caps.

Bedroom 1 Extend existing hot water baseboard approximately 5 feet, install new baseboard cover with matching end caps.

Bedroom 2 Extend existing hot water baseboard approximately 5 feet, install new baseboard cover with matching end caps.

Bedroom 3 Extend existing hot water baseboard approximately 7 feet, install new baseboard cover with matching end caps.

Bathroom Install new baseboard cover with matching end caps.

Closet Install new baseboard cover with matching end caps.

Mechanical & Piping Work Extend and reconnect all copper piping as needed to feed new baseboard sections.

Reconnect all supply and return lines to existing boiler piping, both upstairs and in the basement.

Purge all air from heating lines and ensure full circulation through the affected zone.

Test and verify proper operation of the boiler and this specific heating zone.

Adjust system for proper temperature and flow balance as required.

GENERAL REQUIREMENTS:

0. Bid price is to include all materials, labor, disposal of materials fees and site clean-up. Final acceptance of completed job will be provided by the appropriate Maintenance Supervisor.

Work is to be done between the hours of ___ and ___, Monday through Friday. Contractor is advised that this is an occupied home and may be occupied during these times.

All tools must be controlled at all times and debris, tools and materials secured and stored at the end of each work day.

Any unforeseen conditions that may alter the established price are to be reported to the Plant Superintendent listed above immediately upon discovery.

Smoking is prohibited by contractors at all residential and program sites owned by OPWDD.

Prior to the commencement of the work, there shall be a meeting with DDSO Operations and Maintenance staff to discuss specific safety requirements needed to be adhered to during the work period.

Safety Data Sheets as applicable will be provided to the Plant Superintendent prior to the start of work and a copy maintained at the property.

All applicable environmental testing associated with this work will be provided to the contractor prior to start of work.

SITE VISIT

A site visit (is or is not) mandatory. The site visit date is scheduled for DATE AND TIME at the project site. All prospective bidders are encouraged to attend.

A. Lawn Damage/Property Damage

· If the delivery of materials or any other work necessitates the contractor, his suppliers, or sub-contractors to drive on the lawn for ANY reason, the contractor shall be held responsible for the repair of the lawn.

· Personal vehicles are not to be parked on the grass.

· Any property damage caused by work performed is to be corrected to the condition existing prior to start of the job.

B. Continuity of Work/Communication/Scheduling

· Once the job has begun, it is to be worked on continuously until completed.

· If there are any delays, even if due to inclement weather, a Work Control Representative MUST be contacted.

· Work must be completed within ___ days of receiving the purchase order.

C. House Safety

· The residence will be occupied during the job.

· The contractor must take all reasonable care to safeguard the residents and the staff.

· The contractor shall ensure all tools, materials and other items are picked up, removed or stored and are safely secured at the end of each workday.

· Any ladders, scaffolding or lifts used in conjunction with this job are to be stored to the satisfaction of the House Director at the end of the day.

· The work as indicated above shall be scheduled as not to interfered with other functions of the residence. All work performed as part of this job is to be coordinated with the House Director and project manager above.

image1.emf

File details come from the government source that posted it. Updated .