HDEC03-18-R-0001
Amendment 2
Program Management Assistance Contract (PMAC)
Questions and Answers #1
1. Question: Would you kindly confirm if this is an entirely new effort or is there an incumbent currently providing the services? If so, can you please provide the incumbent contract details?
Answer: The incumbent is Jacobs Engineering Group 911 Central Parkway North, Ste 425 San Antonio, TX 78232-5065. POC: Mike Brandt, Michael.brandt@jacobs.com, 210-403-6324.
2. Question: Is this a SBA 8a set aside opportunity to partner on this opportunity?
Answer: No, this is not an 8(a) set aside acquisition.
3. Question: Are covers, tabs, and SF330 Part II forms included in the maximum 60-page double-sided count? Are cover letters or compliance matrices included in the page count?
Answer: Cover protective sheets and tabs are not part of the 60 double sided pages.
Cover letters and compliance matrices are included in the page count.
4. Question: Is the maximum page count 30 double sided sheets (for 60 total pages) or is it 60 double sided sheets (for 120 total pages)?
Answer: It is 60 double sided sheets (for 120 total pages).
5. Question: Can commendation letters or Past Performance Questionnaires be placed in an Appendix and NOT be included in the page count?
Answer: No, they will be included in the page count.
6. Question: Under “Required Submittals,” it is stated “A-E Firms will provide a single-page narrative discussion for each of the six (6) criteria stated above.” This is unclear since there are only 5 Evaluation Criteria listed. Please clarify.
Answer: There are only 5 evaluation criteria.
7. Question: Are the one-page resumes also limited to 3 example project descriptions?
mailto:Michael.brandt@jacobs.com
Answer: Resumes are referenced in Factor 3. The 3 example project descriptions are referenced in Factor 1.
8. Question: You have requested an organizational chart in Factor 4 – Firm’s A-E Capacity, which is duplicative of org chart in Section D of the SF330. Instead of repeating our org chart in our response to Factor 4, may we reference our organization chart back in Section D?
Answer: Yes