Question and Answer F2i 2023 .docx
DOCX document 16 KB Posted
- Attached to
- DISA's Forecast to Industry 2023
- Solicitation number
- HC1047-23-R-0002
- Issued by
-
Defense Information Systems Agency
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HC104723R0002AMD02.pdf | ||
| HC104723R002AMD01.pdf | ||
| Wage Determination 2015-4265.pdf | ||
| HC1047-23-R-0002.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation # HC1047-23-R-0002 DISA’s Forecast to Industry (F2i) 2023
Question and Response
| Question # |
| Questions / Comments |
| RFP Reference |
| Government Response |
| RFP Change Required (Y/N) |
| Location of Change |
| 1 |
| Box #8 on page 1 of the RFQ and SAM.gov indicate that the due date for responses to the RFQ is 4:00 PM on 20 April 2023. However, on page 7, paragraph #10 indicates that the due date for responses is 3:00 PM on 20 April 2023. Can you please advise which time of day, 3:00 or 4:00 PM EST is correct? |
| Page 7, paragraph #10 of the RFQ. |
| Formal responses to the RFQ are due at 4:00 PM EST on 20 April 2023. |
| Y |
| Page 7, paragraph #10 of the RFQ. |