m2P1_J_6_Transition_Support_tasks_FINAL_8JUL2016.docx

DOCX document 219 KB Posted

Attached to
milCloud 2 Phase 1
Solicitation number
HC1028-16-R-0020
Issued by

About this file

Attachment J-6 Transition Support Tasks

View the file

Other files

File Type Posted
Amendment_0009_m2P1_RFP_Questions_and_Answers_1_to_188.pdf PDF
Amendment_0009_m2P1_-_Att_j_3_08SEP2016.xlsx XLSX spreadsheet
Amendment_0009_HC102816R0020_SF_30.pdf PDF
Amendment_0009_m2P1_Attachment_M-1.pdf PDF
Amend_0008_-_Questions_and_Answers_for_m2P1_(_186)_2SEP16.pdf PDF
Amend_0008_HC102816R0020_2SEP16.pdf PDF
Amendment_0008_m2P1_-_Att_j_3_02SEP2016.xlsx XLSX spreadsheet
HC102816R0020_Amd_0007_SF_30.pdf PDF
Amendment_0007_m2P1_Section_L-1.pdf PDF
Amendment_0006_m2P1_Atch_J-6_Transition_Support_Tasks_M2P1.pdf PDF
Amendment_0006_m2P1_RFP_Questions_and_Answers_1_to_185.pdf PDF
Amendment_0006_m2P1_-_Att_j_3_30AUG2016.xlsx XLSX spreadsheet
Amendment_0006_m2P1_Atch_J-1_PWS_m2P1.pdf PDF
Amendment_0006_m2P1_Section_Atch_L-1.pdf PDF
SF_30_HC102816R0020_Amendment_0006.pdf PDF
Amendment_0006_m2P1_Section_Atch_M-1.pdf PDF
Amendment_0005_m2P1_Section_L.pdf PDF
Amendment_0005_m2P1_Atch_J-1_PWS.pdf PDF
Amendment_0005_SF_30.pdf PDF
Amendment_0005_m2P1_DD254_Revised.pdf PDF
Amendment_0005_m2P1_RFP_Questions_and_Answers_1_to_155.pdf PDF
Amendment_0004_m2P1_Section_L.pdf PDF
Amendment_0004_m2P1_Section_M.pdf PDF
Amendment_0004_m2P1_Atch_J-1_PWS.pdf PDF
HC102816R0020_Amendment_0004_Conformed_Copy.pdf PDF
Amendment_0004_m2P1_Atch_J-6_Transition_Support_Tasks.pdf PDF
Amendment_0004_m2P1_RFP_Questions_and_Answers_1_to_147.pdf PDF
Amendment_0004_m2P1_-_Att_J_3_22AUG2016.xlsx XLSX spreadsheet
Amendment_0004_m2P1_Att_j_5_Labor_Category_Descriptions.pdf PDF
Amendment_0004_SF_30_with_Summary_of_Changes.pdf PDF
HC102816R0020_Amend_0003_Ext_Prop_Due_Date_to_31AUG16.pdf PDF
m2P1_Section_M_for_Amend_0002.pdf PDF
HC102816R0020_Amendment_0002.pdf PDF
m2P1_Section_L_for_Amend_0002.pdf PDF
m2P1_RFP_Questions_and_Answers_Amendment_0002_July_29.pdf PDF
m2P1_Section_M_Amend_0001_12JUL16.pdf PDF
m2P1_Section_L_Amend_0001_12JUL16.pdf PDF
RFP_Q A__1_for_MilCloud_2_0_12JUL16.pdf PDF
Amend_0001_HC102816R0020_12JUL16.docx DOCX document
m2P1_-_DD254_Signed.pdf PDF
HC102816R0020_m2P1_RFP_Final_8JUL16.docx DOCX document
m2P1_-_Att_J_3_FIINAL_8JUL16_(2).xlsx XLSX spreadsheet
m2P1_PWS_FINAL_8JUL16.doc DOC document
m2P1_Draft_PWS_Questions__Answers_28_Jun_2016.pdf PDF
m2PI_Industry_Site_Visit_Participant_Listing.xlsx XLSX spreadsheet
DECC_Montgomery_Site_Visit_QA_Final_16_Jun_2016.doc DOC document
MILCLOUD_2_Industry_Day_Script_Jun_2016.docx DOCX document
MilCloud_2.0_Site_Visit.docx DOCX document
m2P1_Draft_PWS_Q A_template.doc DOC document
m2P1_DRAFT_PWS_for_posting_23_May_2016.doc DOC document
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment J-6 Transition support tasks The Tasks 1 and 2 are notional sample tasks of potential workloads for migration to allow the Offeror to provide an estimated cost for transition support a Basis of Estimate (BOE) for each task for evaluation. The Government will evaluate the technical approach and cost factors shown in the BOEs. Tasks 3 through 7 are actual existing milCloud workloads that are scheduled to be transitioned to milCloud 2.0 as part of the Initial Operating Capability (IOC). The Offeror will provide a BOE for each task with estimated level of effort including the proposed number of labor hours by labor category required to perform a successful transition for each task from the current state to the proposed cloud environment. Note that the existing systems are subject to change in detail as the systems evolve, and the identified systems are also subject to replacement upon contract award. Fully burdened firm fixed prices by labor category will be established in the contract. Actual task orders for transition of IOC workloads will negotiated with the successful offeror after contract award.

If the offeror feels that some or all of the labor should be performed at the Consumer’s current location, they will define the hours for the tasks which must be performed at the Consumer’s location, and the hours that should be performed at the Offeror’s location or the DISA Cloud Hosting location.

The Offeror will also include in each BOE a priced list of CLINs/SLINs to meet the IaaS capacity required to support the systems in each task to include all compute, storage and required services.

Travel to the Consumer location will be performed using cost-reimbursable ODCs in accordance with standards identified in FAR Part 31 (aka the JTR). Offeror will identify the estimated travel by identifying the quantity of FTE/Days required for completeness and reasonableness evaluation purposes only. There shall be no travel required or funded for work performed at the DISA Cloud Hosting site, or Offeror’s location.

The Offeror shall propose intermediate level or grade support personnel to support the defined categories. Labor descriptions and skill levels are described in Attachment J-9 for reference. The Offeror may propose different labor categories or experience levels instead of, or in addition to those listed.

Each task description will define the current environment. If additional data would be required from the Consumer, the Offeror will make an assumed answer, and document the assumptions with the response. The Transition Support Task Order Response will provide a description of the work to be performed and the tools and methodology to be used, plus an estimate to perform the following tasks (if required):

A. Technical Analysis - Analyze the current environment to include network connectivity, server performance, virtualization requirements and application design B. Transition Program Plan - Develop plan to transition to cloud environment including resource capacity, funding assessment, architectural support, mitigation of workload or data portability issues, testing, risk planning, recommended server sizes, OS and application changes related to the target environment C. Virtualize - Transition all physical and virtual servers to images suitable for the target virtual format.

D. Extract, Transform and Load (ETL) of data stores, for migration to the infrastructure services, when applicable E. Migrate - Transport all images and data to the infrastructure services F. Import - Import or Export images and data into the Consumer’s purchased infrastructure services G. Turn-over - Ensure connectivity for Consumer management personnel to target servers H. Testing of DoD Consumer mission capabilities after migration I. Aid in understanding the use of service APIs, CLIs, and infrastructure service management consoles J. Support in using operational features such as machine image snapshotting and image libraries K. Support in Consumer IA accreditation efforts for their transitioned workloads L. Additional tasks as defined by the Offeror

Task 1 (Notional) Legacy application with physical servers This is an Notional example of an existing DoD legacy project with staff with a low level of technical knowledge. They will require Transition support for all phases of the transition. The application has a Private (.mil only) facing web tier containing two small Red Hat 6.x servers. The application must be available 24/7/365, and is not designed for elasticity. There are two application servers running Windows Server 2008 R2, and two clustered database servers running red Hat 6.x and using a shared database. All servers are currently rack mounted physical servers operating at the Consumer location. The application operates at a single site, with no COOP or failover to an external site. Standard backup is required to provide 24 Hour RTO, and 24 Hour RPO for all storage. Privileged administrative users are at a combination of .mil DoD and .com contractor sites.

Task 1

Existing Physical Servers

Server
CPU Cores
Mem GB
OS and App Storage Disk - (Usable GB)
Additional Tier 1 Data Storage (Usable GB)
Object Store (Usable GB)
Web 01 - Red Hat
1
2
75
0
Web 02 - Red Hat
1
2
75
0
App 01 - Windows
2
12
75
100
App 02 - Windows
2
12
75
100
DB 01 - Red Hat
8
32
75
1000
DB 02 - Red Hat
8
32
75
0

Object Storage

Task 1 Support Labor

Year 1 SLIN
Function
Offeror Location
DISA Cloud Hosting Site
Consumer Location
Trips
Travel Days Required
003TAT
Travel
003TAA
Windows SA
003TAB
Linux SA
003TAC
DBA
003TAD
Network Engineer
003TAE
Virtualization Specialist
003TAF
Cloud Specialist
003TAG
Project Manager
003TAH
Cybersecurity Analyst

Task 2 (Notional) Virtualized Legacy System Task 2 is an Air Force legacy system operating on Microsoft Hyper-V. It is in a small center on an Air Force base. The personnel are knowledgeable about virtualization and their application. They will require some support on all aspects of the transition. The application must be available 24/7. The developers want to add the ability to horizontally expand the Web and App tiers which is a capability of the application. This is to meet expected increased demand for the application during business hours, and to allow for surge processing in the event of a deployment. The Consumer wants to manage their own backup of the database. Failing servers will be restored from existing templates for OS and Application software. The Consumer plans to provide their own services including logging, VPN, CND and scanning from their existing datacenter via a lobe extension. The lobe extension will exist in the COLO (co-located network devices) at the site of the milCloud 2.0 instance. The COLO will be DISA designed and managed. Privileged administrative users are at .mil DoD sites. The application is impact level 5, and requires internal failover, and RPO and RTO of no more than 8 hours.

Task 2 Virtualized Legacy System

Server
CPU Cores
Mem GB
OS and App Storage Disk - (Usable GB)
Additional Tier 1 Data Storage (Usable GB)
Tier 2 Storage (Usable GB)
Tier 3 Storage (Usable GB)
Object Store (Usable GB)
Web 01 - Windows
1
4
75
0
Web 02 - Windows
1
4
75
App 01 - Windows
2
10
75
100
App 02 - Windows
2
10
75
100
DB 01 - Windows
8
32
75
1000
DB 02 - Windows
8
32
75
0

Task 2 Support Labor

Year 1 SLIN
Function
Offeror Location
DISA Cloud Hosting Site
Consumer Location
Trips
Travel Days Required
003TAT
Travel
003TAA
Windows SA
003TAB
Linux SA
003TAC
DBA
003TAD
Network Engineer
003TAE
Virtualization Specialist
003TAF
Cloud Specialist
003TAG
Project Manager
003TAH
Cybersecurity Analyst

Task 3 (IOC) IRIS Test System in RACE IRIS is a DISA Test system that recently transitioned from DISA’s RACE environment to milCloud 1.0. The following is a System Requirements Form (SRF) that was extracted from their transition request. IRIS has two servers.

Part 1 - Project Overview Project Identification

1. System/Application Name
2. Mission Partner
3. Project Title
4. Service Provider Tracking Number
5. Priority

IRIS Legacy RACE Dev

DISA
IRIS
3914
Normal
6. Designated Hosting Site
tbd
7. Managing Site
Tbd

8. Project Description – Describe project details, dependencies, and constraints below. Attach any relevant design specifications or documentation to this section.

The Mission Partner requested an estimate to detail the total cost support services provided with the milCloud Plus service offering rate for the legacy RACE PLD environment. The Mission Partner would order through the milCloud portal two (2) milCloud Central Processing Units (CPUs), 4 gigabytes (GB) of Random Access Memory (RAM) and 200 GBs of usable storage. The IRIS environment consists of two (2) development Virtual Operating Environments (VOEs)

9. System/Application Description

Test systems for DITCO

10. Operational Impact

Development System

11. CIC/ASC/BAN
12. MAC Level
13. Confidentiality Level
14. DoD Network
III
|X| Public

|_| Classified |_|Sensitive |X| NIPRNet |_| SIPRNet |_| Mission Partner DAA Accredited Enclave (CDAE)

15. System DAA (Name, Title, Org, Email, Phone)
DISA AO
16. Accreditation Status
17. If System/Application is NOT accredited, what is Mission Partner’s plan for achieving accreditation?

|X| IATT

|_| IATO

|_| ATO

|_| Not Accredited

18. Accrediting Agency
19. Accreditation Expiration
20. System DITPR Number

DISA

21. Accreditation Repository
22. Residual Risk
23. VMS Registration
|_| eMASS |_| Other
|_| Yes |_| No
|_| Yes |_|No Program Name:
24. PPSM ID Number
25. PPS Utilized
26. Application Development Environment
TBD
|_| Standard |_| Non-Standard
|_| STIG’d |_| Non-STIG’d
27. Critical Plans (select all that exist)
28. Reviews/Assessments (select all that exist)

|_| Configuration Management Plan |_| Risk Management Plan |_| Vulnerability Management Plan |_| Patch Management Plan |_| Incident Response Plan |_| Continuity of Operations Plan |_| Disaster Recovery Plan |_| DoD 8500.2 IA Control Review Location of Review:

|_| Application Security and Development Review Location of Review:AFNIC |_| Privacy Impact Assessment Location of Assessment:AFMC/A6 XI

29. Tool Compatibility

HBSS |X| Yes |_| No |_| Unknown ESM Software |_| Yes |_| No |_| Unknown

30. Open Source Software
|_| Yes |_| No |_| Unknown

CDSP - DoDD O-8530.01 and in support of CJCSI 6510.01F and CJCSI 6211.02D, require all DoD information systems and networks that process, store, transmit, display, or receive DoD information to be aligned in writing to an accredited Tier II CDSP. The Mission Partner is required to obtain/maintain compliance with this requirement. DISA is able to provide this service or another provider can be used. In the case that another CDSP provider is chosen, a copy of the current SLA must be provided so that DISA analysts are able to provide TIPPER notifications the chosen CDSP.

31. Will the information system/application/network process, store, transmit, display, receive or disseminate DoD information
|_| Yes |X| No
32. Will the Mission Partner system connect to a DECC infrastructure?
|_| Yes |X| No
33. Does the Mission Partner intend to leverage the DISA DECC Network Infrastructure?
|X| Yes |_| No
34. Does the Mission Partner intend to align to DISA for CDSP services?
|X| Yes |_| No
35. If not aligned to DISA CDSP, provide name of other CDSP. Please also provide SLA to <insert applicable DISA office here> AND letterkenny.re.list.cdsp-requests@mail.mil
Mission Partner CDSP

CDSP POC

CDSP Email

Special Compliance Information (select all that apply)

36. PII
37. HIPAA
38. Financial System/ Application
39. Nuclear Information
|_| Yes |X| No
|_| Yes |X| No
|_| Yes |X| No
|_| Yes |X| No
40. Data Access
41. CAC Enabled (Restricted/Private)

|_| Unrestricted (unauthenticated) |_| Restricted (authenticated .com) |_| Private (access from .mil only) |_| Yes |_| No

42. Cyber Compliance

|_| Yes |_| No

Special Audits, Inspections, Assessments, and Tests (select all that apply)

43. SSAE 16
44. FISCAM
45. PCI
46. C&A
|_| Yes |X| No
|_| Yes |X| No
|_| Yes |X| No
|_| Yes |X| No
47. Incident Response
48. Penetration Testing
|_| Yes |X| No
|_| Yes |X| No
49. Points of Contact
Name
Office and Physical Address
Phone
Email
Mission Partner Program POC
Barbara Biebl

Mission Partner Technical POC

Mission Partner Financial POC

Mission Partner IA POC

Service Provider Team Lead

Service Provider Project Manager

Service Provider Technical Lead

Service Provider Customer Account Rep (CAR)

Service Provider IA Technical Advisor

Service Provider Network Lead

Service Provider Software Engineer

Target Dates Initial Operation Environment (IOE) Date – date that Operating Environments (OEs) are turned over to the application administrators for application load Initial Operating Capability (IOC) Date – date that OEs are configured for production users

50. Target Letter Estimate Date
51. Target Funding Date
52. Target IOE Date
53. Target IOC Date

Risk Assessment Note: IA risk can only be determined by the IA Technical Advisor

54. Technical
55. Schedule
56. IA

|_| High |_| Medium |X| Low |_| High |_| Medium |X| Low |_| High |_| Medium |X| Low

57. Enter Details of Any “High” or ‘Medium” Risks Noted:

N/A

Part 2 - Implementation and Cutover Support Requirements

1. Implementation Contacts

Role
Name and Contact Information

Mission Partner Lead Technical POC

Mission Partner Lead Management POC (Authority to approve changes)

Vendor or Integrator SME

Other Implementation POC (specify)

2. Migration Requirements

OE/File System Name
Size of File(s) or Image Being Migrated (usable storage in GB)
Type

(e.g., DB Export, Flat File, OVA Image) File Transmission Method (Offline Copy, Online Copy (SFTP), Array-to-Array Replication, Application Replication) Migration Method (Import, Overlay, Mirror, OVA)

N_RUJ03R_70_131
100
N_RUJ03R_70_163
100

3. Cutover Requirements

Describe the cutover window in terms of length and timing constraints:

Describe the Mission Partner, integrator, and vendor resources necessary to support cutover:

Describe any system-specific post-cutover acceptance criteria:

Describe any post-cutover parallel processing requirements:

4. Performance Metrics

Provide any performance metrics that must be attained for systems migrating to the Service Provider:

5. Global Service Desk Level 1 Support Information

Approximate number of concurrent end-users:

Approximate Service Desk contact volume and frequency:

Part 3 - Technical Requirements

1. Mission Partner Disposition – Which of these statements best describes the Partner’s view of their technical requirements?

The Mission Partner is providing a detailed specification for computing infrastructure that they expect to deliver without modification.

The Mission Partner is providing detailed technical requirements based on an existing environment but acknowledges the design may not be optimal for Cloud hosting and is willing to engage the Cloud Service Provider to explore design alternatives.

The Mission Partner is providing general technical description and requires the Cloud Service Provider technical assistance to define technical requirements.

Other (fill in here):

Server Name (hostname or unique identifier if not known)
Server Function (e.g., web, database, app)
Environment (Production, Test, COOP)
Estimated Availability Requirement (Metered Billing)
OS
OS Version
32-bit or 64-bit
# of vCPUReq
Req RAM (GB)

N_RUJ03R_70_131

DEV
24/7/365
Windows
2008
64
1
2

N_RUJ03R_70_163

DEV
24/7/365
Windows
2008
64
1
2

2. OE Storage Requirements – Specify the storage that is required by each OE (usable storage in GB)

Server Name and Function
Allocation for Application
Allocation for Database
Allocation for Logs
Allocation for Flat Files
Desired Storage Tier Or performance Level
Total (GB)
N_RUJ03R_70_131
100
Tier 1
100
N_RUJ03R_70_163
100
Tier 1
100

Object Storage – Not tied to specific server

Total Usable Storage Required (in GBs):

3. Web Interfaces – Identify URLs required and their attributes Public – Any service intended to provide unclassified and non-sensitive information accessible from outside the NIPRNet, to include anonymous access.

Restricted – Any service intended to be accessible from the Internet and serves sensitive information to a limited set of users. Access controls are in place to limit the user set who can access the service.

Private – Any service meant to be accessed only from the NIPRNet or SIPRNet, respectively (.mil only).

URL Name
Application
Public/Restricted/Private

(see definitions above) Load-balanced to Multiple Web Servers (Yes/No)

4. External System Communication Requirements – List the OEs that require communication with any external system. Specify the ports and protocols used by each. This does not include external access for administration by privileged users.

Internal Server or Enclave Name
Function
External Server or System Name and Domain
Party Initiating Communication
Ports
Protocols
Notes

NA

5. Internal System Communication Requirements – List the OEs that require communication with other OEs within the enclave. Specify the ports and protocols used by each.

Internal Server
Function
Target Internal Server
Party Initiating Communication
Ports
Protocols
Workload Characterization

tbd

6. Software Requirements – List all application software, tools and accessories. Do not include Cloud Service Provider-provided Enterprise Systems Management (ESM) software.

Server Name
Software Vendor
Software Name
Detail Version Information
Software License Provided/Procured by
Licensing or Acquisition Notes

tbd

7. Open Source Software Requirements – List all open source software used. For open source, indicate whether or not the software has been DAA-approved. List additional information (i.e. licensing, vendor support, etc.) in the Notes column.

Software Vendor Software Name Version Information

DAA-Approved
Licensing, Acquisition, Support Notes

Yes |_| No|_|

Yes |_| No|_|

Yes |_| No|_|

Yes |_| No|_|

Yes |_| No|_|

8. User Authentication Requirements

Does user authentication / authorization require access to a remote resource (e.g., LDAP, AD)? |_| Yes |_| No

If Yes, who will manage the authentication / authorization database? .

9. Networking & Security

Describe any specific data protection requirements (e.g., data at rest) specified by the data owner.

N/A

Describe any interconnection requirements among DoD applications operating at different classification levels (e.g., SIPRNet to NIPRNet or vice versa).

Describe any system-to-system interfaces with government agencies, commercial companies, foreign countries, etc.

N/A

Are any network VPNs required to secure system-to-system interfaces?
|_| Yes |_| No
If Yes, network VPNs required, remote sites are:
|_| .com |_| .mil |_| .gov

Characterize anticipated aggregate bandwidth requirements (data center inbound/outbound).

Load Balancing: Describe any local or global application and/or server load balancing requirements.

10. Local High Availability Requirements – Does the system require any specific local high availability feature for any specific OEs or functions (e.g., clustering, Oracle RAC)?

|_| Yes |X| No

If Yes, please elaborate on the requirement (if possible identify the OEs to be clustered and the type of clustering required, e.g., active, passive, RAC) below:

11.

Remote or Second Site High Availability Requirements – Does the system require remote or second site high availability feature for any specific OEs or functions (e.g., remote failover, clustering, Oracle RAC)?

|_| Yes |X| No

If Yes, please elaborate on the requirement (if possible identify the OEs to be clustered and the type of clustering required, e.g., synchronous, asynchronous, RAC) below:

Part 4 - Standard and Optional Rate-Based Services

1. Core Services – Every workload hosted in milCloud 2.0 is based on the amount of Compute capacity.

Compute
Compute is the basic Infrastructure as a Service capability provided by the CSP. This include virtual CPU, Memory and storage at the rates identified by the CSP. This also includes a Client OS license for a supported OS.

Describe any requested deviations from these core services:

2. Optional CSP Services –The below services may be acquired from the CSP These may have prerequisites in terms of connectivity and root control of the OS. Review and check any requested optional services:

|_|
Automated Patch Management – Automated Patch Management provides an automated patching service for supported client OS’s. This service may be limited to security and system patching and may include prerequisite levels of system access and scheduling.

3. Optional Value Add Services –The below services may be acquired from DISA. These may have prerequisites in terms of connectivity and root control of the OS. These may include any of the “Optional” service shown below. Review and check any requested optional services:

|_|
milCloud Plus – milCloud Plus includes System Administration (on-site support during normal business hours (8x5) with two-hour on-call response outside of normal hours), Security, Facilities Support, Standard OE (SOE) core software, Power, and Communications (local infrastructure/shared communications), and Level II Service Desk services. Level 1 and Level 3 services are not provided in Basic Services. Basic Services is assessed by OE.
|_|
Application Support – Tier 2 Service Desk support of a dedicated application. Examples include running special jobs on behalf of users, re-running aborted jobs, loading new releases of functional-user software, etc. If application support is selected, it will be applied to all OEs associated with a Mission Partner’s workload except for Service Provider-provided or Web Administration OEs.
|_|
Database Administration – Includes the labor to provide Database Administration support and to ensure databases comply with security guidelines. It only applies to Database servers.
|_|
Oracle Grid Control – Provides the Service Provider standard web based database monitoring and management interface to Mission Partner DBAs. It is included if the Mission Partner is paying for Database Administration, but can be selected as an option by those Mission Partners who elect to perform their own DBA support. It is billed at 10 percent of the Database administration rate.
|_|
Database Software Maintenance – Maintenance of Oracle database software. Costs associated with this include the software maintenance and not the license itself. Note: DB Software Maintenance is a required service if the Service Provider provides Oracle licenses.
|_|
24 x 7 System Administration – Provides seven days a week, 24 hours a day (24x7), full system administration support. Standard system administration support is part of Basic Services.
|_|
24 x 7 Application Support –Provides seven days a week, 24 hours a day (24x7), full application support. Select this option if the standard 8x5 with two hour after-hours response time is insufficient.
|_|
24 x 7 Database Administration – Provides seven days a week, 24 hours a day (24x7) full database administration support. Select this option if the standard 8x5 with two-hour after-hours response time is insufficient.

Include any comments or relevant information related to the selected optional services above:

4. Conditional Services – Conditional services may be required depending upon the optional services selected. Review and check any applicable conditional services that apply:

|_|
Web Administration – Web Administration is another type of application support and it utilizes the Application Support rate. This service supports the labor to administer a web server and its associated software. If a web server uses Microsoft's Internet Information Services (IIS), the Service Provider will install the feature and support static content at no additional charge, as this is included in the standard Basic Services rate.
|_|
Database Security –Includes the labor associated with ensuring database servers comply with security guidelines (e.g., consultative services on the STIG, handling STIG findings, database scans, and VMS entry and validation) and applies to those database servers for which the Mission Partner retains the DBA function themselves. It is billed at 10 percent of the optional Database Administration rate. Database security is included for those database servers that the Mission Partner selects Database Administration.
|_|
Capacity Planning Reporting – Mission Partners who maintain their own hardware and do not pay the Hardware Services rate may elect to receive capacity planning reports billed at 10 percent of the Hardware Services rate.

Include any comments or relevant information related to the selected conditional services above:

5. Service Continuity – If remote site COOP support is required, please select one of the options below. Descriptions ar ebased on DISA service levels for reference. These services may be application dependent depending on the level of automation required:

|_|
Shared COOP – Referred to as “Remote Recovery Combination 1” in the DISA Service Catalog

(RTO = 5 days, RPO = 7 days) – MAC III applications only

|_|
Shared COOP w/Replication Option – Referred to as “Remote Recovery Combination 1.2” in the DISA Service Catalog

(RTO = 5 days, RPO = 8 hours) – MAC III applications only

|_|
Dedicated COOP – Referred to as “Remote Recovery Combination 2” in the DISA Service Catalog

(RTO = 24 hours, RPO = 8 hours)

|_|
Dedicated COOP – Referred to as “Remote Recovery Combination 3” in the DISA Service Catalog

(RTO and RPO = 8 hours)

|_|
High-Availability COOP – Referred to as “Remote Recovery Combination 4” in the DISA Service Catalog

(RTO = 30 minutes, RPO = 1 Sec)

|_|
Custom – (Failover, T&D, Mission Partner-managed COOP, etc.)
|_|
No Service Provider-provided COOP

Note any special considerations related to your Service Continuity requirement here and provide more detailed specifications in the Non-Standard Requirements section, if applicable:

Is the detailing of production and COOP locations in the same documentation authorized?
|_| Yes |_| No

Part 5 - Non-Standard Requirements Fulfillment of non-standard requirements are generally not included in the Service Provider’s published server and storage rates and entail additional design and integration efforts, special considerations/approvals (waivers), and/or long procurement lead times.

1. Non-Standard Configurations or Mission Partner-Provided Items – Specify non-standard or Mission-Partner-provided hardware that must be deployed at a DECC in support of this system.

Item Name or Description
Item Type (Server, storage, network, software, other)
Purpose
Justification (explain why standard components will not work)
Source
Acquired by
Maintenance Arrangement if Mission-Partner Provided (contract number, vendor, expiration date)
Will the Service Provider Pick Up Maintenance Upon Current Contract Expiration?

|_| Yes |_| No

|_| Yes

|_| Yes

|_| Yes

|_| Yes

|_| Yes

2. Non-Standard Support Requirements – Explain any non-standard operations or support requirements. (e.g., any SME labor or non-standard support functions.

3. Non-Standard Communications or Network Requirements – Explain any non-standard network or communications requirements. (e.g., any deviation from the Service Provider enclave designs, exceptional bandwidth, latency or access requirements, etc. Include diagrams if available.)

4. Non-Standard Other – Explain any non-standard unusual, unique or exceptional requirements that do not fit into the previous categories.

5. Additional Documentation – Attach and identify in the space below any documents that support the specification of non-standard requirement(s) noted in this section:

Task 3 IRIS Support Labor

Year 1 SLIN
Function
Offeror Location
DISA Cloud Hosting Site
Consumer Location
Trips
Travel Days Required
003TAT
Travel
003TAA
Windows SA
003TAB
Linux SA
003TAC
DBA
003TAD
Network Engineer
003TAE
Virtualization Specialist
003TAF
Cloud Specialist
003TAG
Project Manager
003TAH
Cybersecurity Analyst

Task 4 (IOC) PSD Development and Test Systems PSD is two environments, Development and Test, that have recently transitioned from RACE to two separate VDCs in milCloud 1.0. The data below has been extracted from their transition requests. There are separate support teams for each environment, and they are billed separately. Transition may be billed on a single Task Order.

Part 1 - Project Overview Project Identification

58. System/Application Name
59. Mission Partner
60. Project Title
61. Service Provider Tracking Number
62. Priority

PSD Legacy RACE Dev and Test

DITCO
PSD
3912 and 3913
Normal
63. Designated Hosting Site
tbd
64. Managing Site
Tbd

65. Project Description – Describe project details, dependencies, and constraints below. Attach any relevant design specifications or documentation to this section.

The Mission Partner requested an estimate to detail the total cost of support services provided with the milCloud Plus service offering rate for the PSD Legacy Applications. The Mission Partner would order through the milCloud portal seven (7) milCloud Central Processing Units (CPUs), 18 gigabytes (GB) of Random Access Memory (RAM) and 1220 GBs of usable storage. The PSD Legacy Applications Development environment consists of three (3) development Virtual Operating Environments (VOEs). To meet the requirements of this request, the Service Provider would provide the services outlined in Enclosure 1 with the milCloud Plus service rate to three (3) development VOEs The Mission Partner requested an estimate to detail the total cost support services provided with the milCloud Plus service offering rate for the PSD Legacy Test RACE/milCloud environment. The Mission Partner would order through the milCloud portal 12 milCloud Central Processing Units (CPUs), 26 gigabytes (GB) of Random Access Memory (RAM) and 2,600 GBs of usable storage. The PSD Legacy Test environment consists of five (5) test and development Virtual Operating Environments (VOEs). To meet the requirements of this request, the Service Provider would provide the services outlined in Enclosure 1 with the milCloud Plus service rate to five (5) test and development VOEs

66. System/Application Description

Development and Test enclaves

67. Operational Impact

Development and Test Systems

68. CIC/ASC/BAN
69. MAC Level
70. Confidentiality Level
71. DoD Network
III
|X| Public

|_| Classified |_|Sensitive |X| NIPRNet |_| SIPRNet |_| Mission Partner DAA Accredited Enclave (CDAE)

72. System DAA (Name, Title, Org, Email, Phone)
DISA AO
73. Accreditation Status
74. If System/Application is NOT accredited, what is Mission Partner’s plan for achieving accreditation?

|_| IATT

|_| IATO

|_| ATO

|X| Not Accredited Development system – VPN access only

75. Accrediting Agency
76. Accreditation Expiration
77. System DITPR Number
78. Accreditation Repository
79. Residual Risk
80. VMS Registration
|_| eMASS |_| Other
|_| Yes |_| No
|_| Yes |_|No Program Name:
81. PPSM ID Number
82. PPS Utilized
83. Application Development Environment
TBD
|_| Standard |_| Non-Standard
|_| STIG’d |_| Non-STIG’d
84. Critical Plans (select all that exist)
85. Reviews/Assessments (select all that exist)

|_| Configuration Management Plan |_| Risk Management Plan |_| Vulnerability Management Plan |_| Patch Management Plan |_| Incident Response Plan |_| Continuity of Operations Plan |_| Disaster Recovery Plan |_| DoD 8500.2 IA Control Review Location of Review:

|_| Application Security and Development Review Location of Review:AFNIC |_| Privacy Impact Assessment Location of Assessment:AFMC/A6 XI

86. Tool Compatibility

HBSS |X| Yes |_| No |_| Unknown ESM Software |_| Yes |_| No |_| Unknown

87. Open Source Software
|_| Yes |_| No |_| Unknown

CDSP - DoDD O-8530.01 and in support of CJCSI 6510.01F and CJCSI 6211.02D, require all DoD information systems and networks that process, store, transmit, display, or receive DoD information to be aligned in writing to an accredited Tier II CDSP. The Mission Partner is required to obtain/maintain compliance with this requirement. DISA is able to provide this service or another provider can be used. In the case that another CDSP provider is chosen, a copy of the current SLA must be provided so that DISA analysts are able to provide TIPPER notifications the chosen CDSP.

88. Will the information system/application/network process, store, transmit, display, receive or disseminate DoD information
|_| Yes |X| No
89. Will the Mission Partner system connect to a DECC infrastructure?
|_| Yes |X| No
90. Does the Mission Partner intend to leverage the DISA DECC Network Infrastructure?
|X| Yes |_| No
91. Does the Mission Partner intend to align to DISA for CDSP services?
|X| Yes |_| No
92. If not aligned to DISA CDSP, provide name of other CDSP. Please also provide SLA to <insert applicable DISA office here> AND letterkenny.re.list.cdsp-requests@mail.mil
Mission Partner CDSP

Special Compliance Information (select all that apply)

93. PII
94. HIPAA
95. Financial System/ Application
96. Nuclear Information
|_| Yes |X| No
|_| Yes |X| No
|_| Yes |X| No
|_| Yes |X| No
97. Data Access
98. CAC Enabled (Restricted/Private)

|_| Unrestricted (unauthenticated) |_| Restricted (authenticated .com) |_| Private (access from .mil only) |_| Yes |_| No

99. Cyber Compliance

|_| Yes |_| No

Special Audits, Inspections, Assessments, and Tests (select all that apply)

100. SSAE 16
101. FISCAM
102. PCI
103. C&A
|_| Yes |X| No
|_| Yes |X| No
|_| Yes |X| No
|_| Yes |X| No
104. Incident Response
105. Penetration Testing
|_| Yes |X| No
|_| Yes |X| No
106. Points of Contact
Name
Office and Physical Address
Phone
Email
Mission Partner Program POC
Cora Benriquez

Mission Partner Technical POC

Mission Partner Financial POC

Mission Partner IA POC

Service Provider Team Lead

Service Provider Project Manager

Service Provider Technical Lead

Service Provider Customer Account Rep (CAR)

Service Provider IA Technical Advisor

Service Provider Network Lead

Service Provider Software Engineer

Target Dates Initial Operation Environment (IOE) Date – date that Operating Environments (OEs) are turned over to the application administrators for application load Initial Operating Capability (IOC) Date – date that OEs are configured for production users

107. Target Letter Estimate Date
108. Target Funding Date
109. Target IOE Date
110. Target IOC Date

Risk Assessment

111. Technical
112. Schedule
113. IA

|_| High |_| Medium |X| Low |_| High |_| Medium |X| Low |_| High |_| Medium |X| Low

114. Enter Details of Any “High” or ‘Medium” Risks Noted:

N/A

6. Implementation Contacts

Role
Name and Contact Information

Mission Partner Lead Technical POC

Mission Partner Lead Management POC (Authority to approve changes)

Vendor or Integrator SME

Other Implementation POC (specify)

7. Migration Requirements

OE/File System Name
Size of File(s) or Image Being Migrated (usable storage in GB)
Type

(e.g., DB Export, Flat File, OVA Image) File Transmission Method (Offline Copy, Online Copy (SFTP), Array-to-Array Replication, Application Replication) Migration Method (Import, Overlay, Mirror, OVA)

N_DIT01R_65_131
120
N_DIT01R_65_165
100

N_DIT01R_65_196

1,000

N_DIT02R_78_195
300
N_DIT02R_78_227
1200
N_DIT02R_78_162
300
N_DIT02R_78_194
300
N_DIT02R_78_226
500

8. Cutover Requirements

Describe the cutover window in terms of length and timing constraints:

Describe the Mission Partner, integrator, and vendor resources necessary to support cutover:

Describe any system-specific post-cutover acceptance criteria:

Describe any post-cutover parallel processing requirements:

9. Performance Metrics

Provide any performance metrics that must be attained for systems migrating to the Service Provider:

10. Global Service Desk Level 1 Support Information

Approximate number of concurrent end-users:

Approximate Service Desk contact volume and frequency:

12. Mission Partner Disposition – Which of these statements best describes the Partner’s view of their technical requirements?

The Mission Partner is providing a detailed specification for computing infrastructure that they expect to deliver without modification.

The Mission Partner is providing detailed technical requirements based on an existing environment but acknowledges the design may not be optimal for Cloud hosting and is willing to engage the Cloud Service Provider to explore design alternatives.

The Mission Partner is providing general technical description and requires the Cloud Service Provider technical assistance to define technical requirements.

Other (fill in here):

Server Name (hostname or unique identifier if not known)
Server Function (e.g., web, database, app)
Environment (Production, Test, COOP)
Estimated Availability Requirement (Metered Billing)
OS
OS Version
32-bit or 64-bit
# of vCPUReq
Req RAM (GB)

N_DIT01R_65_131

Dev
24/7/365
Windows
2008
64
2
8

N_DIT01R_65_165

Dev
24/7/365
Windows
2008
64
1
2

N_dit01r_65_196

Dev
24/7/365
Windows
2008
64
4
8

N_DIT02R_78_195

Test
24/7/365
Windows
2008
64
2
4

N_DIT02R_78_227

Test
24/7/365
Windows
2008
64
2
4

N_DIT02R_78_162

Test
24/7/365
Windows
2008
64
2
4

N_DIT02R_78_194

Test
24/7/365
Windows
2008
64
2
6

N_DIT02R_78_226

Test
24/7/365
Windows
2008
64
4
8

13. OE Storage Requirements – Specify the storage that is required by each OE (usable storage in GB)

Server Name and Function
Allocation for Application
Allocation for Database
Allocation for Logs
Allocation for Flat Files
Desired Storage Tier Or performance Level
Total (GB)
N_DIT01R_65_131
120
Tier 1
120
N_DIT01R_65_165
100
Tier 1
100
N_dit01r_65_196
1000
Tier 1
1,000
N_DIT02R_78_195
300
Tier 1
300
N_DIT02R_78_227
1200
Tier 1
1200
N_DIT02R_78_162
300
Tier 1
300
N_DIT02R_78_194
300
Tier 1
300
N_DIT02R_78_226
500
Tier 1
500

Object Storage – Not tied to specific server

Total Usable Storage Required (in GBs):

14. Web Interfaces – Identify URLs required and their attributes Public – Any service intended to provide unclassified and non-sensitive information accessible from outside the NIPRNet, to include anonymous access.

Restricted – Any service intended to be accessible from the Internet and serves sensitive information to a limited set of users. Access controls are in place to limit the user set who can access the service.

Private – Any service meant to be accessed only from the NIPRNet or SIPRNet, respectively (.mil only).

URL Name
Application
Public/Restricted/Private

(see definitions above) Load-balanced to Multiple Web Servers (Yes/No)

15. External System Communication Requirements – List the OEs that require communication with any external system. Specify the ports and protocols used by each. This does not include external access for administration by privileged users.

Internal Server or Enclave Name
Function
External Server or System Name and Domain
Party Initiating Communication
Ports
Protocols
Notes

NA

16. Internal System Communication Requirements – List the OEs that require communication with other OEs within the enclave. Specify the ports and protocols used by each.

Internal Server
Function
Target Internal Server
Party Initiating Communication
Ports
Protocols
Workload Characterization

tbd

17. Software Requirements – List all application software, tools and accessories. Do not include Cloud Service Provider-provided Enterprise Systems Management (ESM) software.

Server Name
Software Vendor
Software Name
Detail Version Information
Software License Provided/Procured by
Licensing or Acquisition Notes

tbd

18. Open Source Software Requirements – List all open source software used. For open source, indicate whether or not the software has been DAA-approved. List additional information (i.e. licensing, vendor support, etc.) in the Notes column.

Software Vendor Software Name Version Information

DAA-Approved
Licensing, Acquisition, Support Notes

Yes |_| No|_|

Yes |_| No|_|

Yes |_| No|_|

Yes |_| No|_|

Yes |_| No|_|

19. User Authentication Requirements

Does user authentication / authorization require access to a remote resource (e.g., LDAP, AD)? |_| Yes |_| No

If Yes, who will manage the authentication / authorization database? .

20. Networking & Security

Describe any specific data protection requirements (e.g., data at rest) specified by the data owner.

N/A

Describe any interconnection requirements among DoD applications operating at different classification levels (e.g., SIPRNet to NIPRNet or vice versa).

Describe any system-to-system interfaces with government agencies, commercial companies, foreign countries, etc.

N/A

Are any network VPNs required to secure system-to-system interfaces?
|_| Yes |_| No
If Yes, network VPNs required, remote sites are:
|_| .com |_| .mil |_| .gov

Characterize anticipated aggregate bandwidth requirements (data center inbound/outbound).

Load Balancing: Describe any local or global application and/or server load balancing requirements.

21. Local High Availability Requirements – Does the system require any specific local high availability feature for any specific OEs or functions (e.g., clustering, Oracle RAC)?

|_| Yes |X| No

If Yes, please elaborate on the requirement (if possible identify the OEs to be clustered and the type of clustering required, e.g., active, passive, RAC) below:

22.

Remote or Second Site High Availability Requirements – Does the system require remote or second site high availability feature for any specific OEs or functions (e.g., remote failover, clustering, Oracle RAC)?

|_| Yes |X| No

If Yes, please elaborate on the requirement (if possible identify the OEs to be clustered and the type of clustering required, e.g., synchronous, asynchronous, RAC) below:

6. Core Services – Every workload hosted in milCloud 2.0 is based on the amount of Compute capacity.

Compute
Compute is the basic Infrastructure as a Service capability provided by the CSP. This include virtual CPU, Memory and storage at the rates identified by the CSP. This also includes a Client OS license for a supported OS.

Describe any requested deviations from these core services:

7. Optional CSP Services –The below services may be acquired from the CSP These may have prerequisites in terms of connectivity and root control of the OS. Review and check any requested optional services:

|_|
Automated Patch Management – Automated Patch Management provides an automated patching service for supported client OS’s. This service may be limited to security and system patching and may include prerequisite levels of system access and scheduling.

8. Optional Value Add Services –The below services may be acquired from DISA. These may have prerequisites in terms of connectivity and root control of the OS. These may include any of the “Optional” service shown below. Review and check any requested optional services:

|_|
milCloud Plus – milCloud Plus includes System Administration (on-site support during normal business hours (8x5) with two-hour on-call response outside of normal hours), Security, Facilities Support, Standard OE (SOE) core software, Power, and Communications (local infrastructure/shared communications), and Level II Service Desk services. Level 1 and Level 3 services are not provided in Basic Services. Basic Services is assessed by OE.
|_|
Application Support – Tier 2 Service Desk support of a dedicated application. Examples include running special jobs on behalf of users, re-running aborted jobs, loading new releases of functional-user software, etc. If application support is selected, it will be applied to all OEs associated with a Mission Partner’s workload except for Service Provider-provided or Web Administration OEs.
|_|
Database Administration – Includes the labor to provide Database Administration support and to ensure databases comply with security guidelines. It only applies to Database servers.
|_|
Oracle Grid Control – Provides the Service Provider standard web based database monitoring and management interface to Mission Partner DBAs. It is included if the Mission Partner is paying for Database Administration, but can be selected as an option by those Mission Partners who elect to perform their own DBA support. It is billed at 10 percent of the Database administration rate.
|_|
Database Software Maintenance – Maintenance of Oracle database software. Costs associated with this include the software maintenance and not the license itself. Note: DB Software Maintenance is a required service if the Service Provider provides Oracle licenses.
|_|
24 x 7 System Administration – Provides seven days a week, 24 hours a day (24x7), full system administration support. Standard system administration support is part of Basic Services.
|_|
24 x 7 Application Support –Provides seven days a week, 24 hours a day (24x7), full application support. Select this option if the standard 8x5 with two hour after-hours response time is insufficient.
|_|
24 x 7 Database Administration – Provides seven days a week, 24 hours a day (24x7) full database administration support. Select this option if the standard 8x5 with two-hour after-hours response time is insufficient.

Include any comments or relevant information related to the selected optional services above:

9. Conditional Services – Conditional services may be required depending upon the optional services selected. Review and check any applicable conditional services that apply:

|_|
Web Administration – Web Administration is another type of application support and it utilizes the Application Support rate. This service supports the labor to administer a web server and its associated software. If a web server uses Microsoft's Internet Information Services (IIS), the Service Provider will install the feature and support static content at no additional charge, as this is included in the standard Basic Services rate.
|_|
Database Security –Includes the labor associated with ensuring database servers comply with security guidelines (e.g., consultative services on the STIG, handling STIG findings, database scans, and VMS entry and validation) and applies to those database servers for which the Mission Partner retains the DBA function themselves. It is billed at 10 percent of the optional Database Administration rate. Database security is included for those database servers that the Mission Partner selects Database Administration.
|_|
Capacity Planning Reporting – Mission Partners who maintain their own hardware and do not pay the Hardware Services rate may elect to receive capacity planning reports billed at 10 percent of the Hardware Services rate.

Include any comments or relevant information related to the selected conditional services above:

10. Service Continuity – If remote site COOP support is required, please select one of the options below. Descriptions ar ebased on DISA service levels for reference. These services may be application dependent depending on the level of automation required:

|_|
Shared COOP – Referred to as “Remote Recovery Combination 1” in the DISA Service Catalog

(RTO = 5 days, RPO = 7 days) – MAC III applications only

|_|
Shared COOP w/Replication Option – Referred to as “Remote Recovery Combination 1.2” in the DISA Service Catalog

(RTO = 5 days, RPO = 8 hours) – MAC III applications only

|_|
Dedicated COOP – Referred to as “Remote Recovery Combination 2” in the DISA Service Catalog

(RTO = 24 hours, RPO = 8 hours)

|_|
Dedicated COOP – Referred to as “Remote Recovery Combination 3” in the DISA Service Catalog

(RTO and RPO = 8 hours)

|_|
High-Availability COOP – Referred to as “Remote Recovery Combination 4” in the DISA Service Catalog

(RTO = 30 minutes, RPO = 1 Sec)

|_|
Custom – (Failover, T&D, Mission Partner-managed COOP, etc.)
|_|
No Service Provider-provided COOP

Note any special considerations related to your Service Continuity requirement here and provide more detailed specifications in the Non-Standard Requirements section, if applicable:

Is the detailing of production and COOP locations in the same documentation authorized?
|_| Yes |_| No

Fulfillment of non-standard requirements are generally not included in the Service Provider’s published server and storage rates and entail additional design and integration efforts, special considerations/approvals (waivers), and/or long procurement lead times.

6. Non-Standard Configurations or Mission Partner-Provided Items – Specify non-standard or Mission-Partner-provided hardware that must be deployed at a DECC in support of this system.

Item Name or Description
Item Type (Server, storage, network, software, other)
Purpose
Justification (explain why standard components will not work)
Source
Acquired by
Maintenance Arrangement if Mission-Partner Provided (contract number, vendor, expiration date)
Will the Service Provider Pick Up Maintenance Upon Current Contract Expiration?

|_| Yes

|_| Yes

|_| Yes

|_| Yes

|_| Yes

|_| Yes milCloud 2.0 SRF Template Version FY16.0 – Jun 2016

7. Non-Standard Support Requirements – Explain any non-standard operations or support requirements. (e.g., any SME labor or non-standard support functions.

8. Non-Standard Communications or Network Requirements – Explain any non-standard network or communications requirements. (e.g., any deviation from the Service Provider enclave designs, exceptional bandwidth, latency or access requirements, etc. Include diagrams if available.)

9. Non-Standard Other – Explain any non-standard unusual, unique or exceptional requirements that do not fit into the previous categories.

10. Additional Documentation – Attach and identify in the space below any documents that support the specification of non-standard requirement(s) noted in this section:

Task 4 Support Labor for PSD Development and Test Systems

Year 1 SLIN
Function
Offeror Location
DISA Cloud Hosting Site
Consumer Location
Trips
Travel Days Required
003TAT
Travel
003TAA
Windows SA
003TAB
Linux SA
003TAC
DBA
003TAD
Network Engineer
003TAE
Virtualization Specialist
003TAF
Cloud Specialist
003TAG
Project Manager
003TAH
Cybersecurity Analyst

Task 5 (IOC) CMIS Development and Test Systems Task 5 is for the CMIS program Development and Test systems that were recently implemented in milCloud 1.0. Development and Test systems are in a single VDC in milCloud, but are logically separated except as noted in the following SRF document.

Part 1 - Project Overview Project Identification

115. System/Application Name
116. Mission Partner
117. Project Title
118. Service Provider Tracking Number
119. Priority
CMIS
DISA SD2
CMIS milCloud T&D
3915
Normal
120. Designated Hosting Site
tbd
121. Managing Site
Tbd

122. Project Description – Describe project details, dependencies, and constraints below. Attach any relevant design specifications or documentation to this section.

Move the existing CMIS basic milCloud VDC (0280u) to the milCloud 2.0 service

123. System/Application Description

Test system for CMIS

124. Operational Impact

CMIS is the only tool that DISA uses to track human resources management information to include security, training, travel, and facilities information.

125. CIC/ASC/BAN
126. MAC Level
127. Confidentiality Level
128. DoD Network
III
|_| Public

|_| Classified |X|Sensitive…