- HC101324QA284-0004.v1.pdf
PDF 14 KB Posted
- Attached to
- AWARD NOTICE.
- Solicitation number
- HC101324QA284
- Issued by
-
Defense Information Systems Agency
About this file
This is an administrative amendment (0004) to solicitation HC101324QA284 that extends the quote due date to January 6, 2025 4:00 PM CST, updates testing specifications, and revises evaluation criteria. The Defense Information Systems Agency (DISA) seeks quotes to provide, install, and maintain an unprotected, transparent leased OTU-2 DISA IE1 backbone trunk between Offutt AFB, NE (Bldg 1000) and Fargo, ND (Bldg 110).
The service requires totally diverse end-to-end engineering with physical paths separated by at least 50 meters from TSR SG09APR248890, including separate manholes, conduit, and fiber builds. Technical requirements include ITU-T G.709 compliance, 10GB SR1 SMF signal, LC connectors, and specific testing parameters for bit error rate and overhead transparency. The service date is March 17, 2025. Vendors must provide color PowerPoint drawings showing routes from commercial demarcs to supporting facilities, including total fiber miles and round trip delay, as well as detailed circuit/path connectivity diagrams in KMZ/KML format identifying all points of presence.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HC101324QA284-0004.v1.pdf | ||
| HC101324QA284-0001_v0.zip | ZIP file | |
| HC101324QA284_v1.zip | ZIP file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IQO INQUIRY
FM: PL8211
TO: Contractors
DATE (MM/DD/YYYY): 12/23/2024
SUBJECT: HC101324QA284-0004 Amend: 0004
A. TYPE ACTION: ADMIN AMEND
1. PURPOSE: HC101324QA284-0004 ISSUED TO EXTEND THE QUOTE DUE DATE TO 06 JAN
24, UPDATE TESTING SPECIFICATIONS, AND UPDATED EVALUATION CRITERIA.
2. SUBMIT A QUOTE TO PROVIDE, INSTALL, AND MAINTAIN A UNPROTECTED,
TRANSPARENT LEASED OTU-2 DISA IE1 BACKBONE TRUNK BETWEEN THE DISA IE1
PROVIDED CIENA RECONFIGURABLE OPTICAL ADD-DROP-MUX (URDWHEC070) AT BLDG
1000, ROOM 222, FL SL1, 900 SAC BLVD, OFFUT AFB, NE AND BLDG 110, ROOM 201, 1400
32ND AVENUE NORTH, FARGO, ND 58102. THIS REQUIREMENT MUST BE ENGINEERED
AND PROVISIONED TOTALLY DIVERSE END TO END TO GOVERNMENT'S SERVICE
DELIVERY POINTS (SDP'S), MEANING THAT PHYSICAL PATHS ARE TOTALLY SEPARATE
INCLUDING MANHOLES, CONDUIT, (CENTRAL OFFICE LOCATIONS), AND FIBER BUILDS.
ADDITIONALLY, AS A MINIMUM THERE MUST BE A 50 METER PHYSICAL SEPARATION FROM
TSR SG09APR248890.
3. CONTRACTORS ARE RESPONSIBLE FOR READING AND ADDRESSING ALL TECHNICAL
REQUIREMENTS OF THIS SOLICITATION, READING AND AGREEING WITH THE DITCO
ADDITIONAL TEXTS, PROVIDE PRICE QUOTATION IN ACCORDANCE WITH DITCO
ADDITIONAL TEXT 4, AND MEET THE REQUESTED SERVICE DATE.
4. THE SERVICE DATE TO BE MET IS: 17 MAR 2025 (SIP) TO COMPLY WITH PROCUREMENT
ACQUISITION LEAD TIME (PALT) FOR THIS TIPE OF SERVICE. THE GOVERNMENT ASSUMES
THAT CONTRACTORS HAVE CONSIDERED ALL ISSUES THAT MAY DELAY THE DELIVERY
OF SERVICE ON REQUESTED SERVICE DATE AND MAY CANCEL, TERMINATE, OR REQUEST
CONSIDERATION IAW DITCO ADDITIONAL TEXT 42 FOR FAILURE TO MEET CONTRACTUAL
SERVICE DATE OR COMPLY WITH ANY CONTRACT TERMS OR CONDITIONS.
5. CONTRACTORS MUST ENSURE THAT QUOTES SHALL INCLUDE SUFFICIENT DETAIL
FOR EFFECTIVE EVALUATION AND SHOULD NOT SIMPLY REPHRASE OR RESTATE THE
GOVERNMENT REQUIREMENTS. RATHER, CONTRACTORS MUST PROVIDE CONVINCING
RATIONALE TO ADDRESS HOW THEY INTEND TO MEET THE REQUIREMENT.
6. QUOTES MUST BE UPLOADED TO IDEAS. GOVERNMENT IS NOT RESPONSIBLE FOR
MISSING OR OVERLOOKED QUOTES.
M. ADDITIONAL INFORMATION:
3. TSR NUMBER: SG09APR248874B
4. CCSD: DWDX6QY9
Z. DITCO CONTACT:
HC101324QA284-0004
Maxwell Jones
667-891-1196 maxwell.s.jones.civ@mail.mil
Dale L. Rupright
DITCO Contracting Officer
Unless otherwise specified, all other terms and conditions are unchanged.
Paragraph M.10.TESTING REQUIREMENTS change from:
TEST & ACCEPTANCE INSTRUCTIONS:
1. OTU-2 TESTING PARAMETERS:
A. THE OTU-2 MUST COMPLY WITH THE ITU-T G.709 STANDARDS
B. THE SIGNAL IS OTU-2, 10GB (SR1), SMF
C. FEC BASED ON ITU-T G.709 RS-8
D CONNECTOR TYPE: LC
2. DETAILED TESTING PARAMETERS:
TEST & ACCEPTANCE INSTRUCTIONS: A. OTM2 FORMAT:
(1) FEC ITU-T G.709 RS-8
(2) PHYSICAL INTERFACE SR-1
(3) OPTICAL POWER -1 DBM TO -6 DBM
(4) THE SIGNAL IS OTU-2, 10GN (SR1),SMF
(5) CONNECTOR TYPE: LC
B. BIT ERROR RATE (BER)
(1) BETTER THAN 1E-12 LESS THAN 2 SES IN A MONTH
(2) ZERO (0) LOS/LOF/SEFS IN 72 HOURS
3. CIENA OVERHEAD TRANSPARENCY (OTU-2):
A. GCC0 = OPTIONALLY TRANSPARENT; VENDOR SHALL DECLARE WHETHER
THE BYTE IS END TO END TRANSPARENT.
B. GCC1 = TRANSPARENT; VENDOR SHALL DECLARE WHETHER THE BYTE IS
END TO END TRANSPARENT.
C. GCC2 = TRANSPARENT; VENDOR SHALL DECLARE WHETHER THE BYTE IS
END TO END TRANSPARENT.
D. TCM1, TCM2, TCM3, TCM4, TCM5, TCM6 = AT LEAST TWO OF THE
LISTED TCM BYTES REQUIRED TO BE TRANSPARENT.
E. R4C9 AND R4C10 = OPTIONALLY TRANSPARENT; VENDOR SHALL DECLARE
WHETHER THE BYTE IS END TO END TRANSPARENT.
F. R4C11, R4C12, R4C13, R4C14, R4C15 = TRANSPARENT
G. R1C16 = VENDOR SHALL REPORT COLUMN 16, ROW 1 BYTE STATUS
H. R2C15 = TRANSPARENT
I. R2C16 = VENDOR SHALL REPORT COLUMN 16, ROW 2 BYTE STATUS
J. R3C15 = TRANSPARENT
K. R3C16 = VENDOR SHALL REPORT COLUMN 16, ROW 3 BYTE STATUS
L. R4C15 = TRANSPARENT
M. R4C16 = VENDOR SHALL REPORT COLUMN 16, ROW 4 BYTE STATUS
4. LATENCY: ROUND TRIP DELAY (RTD) WILL BE
MEASURED IN
MILLISECONDS FROM THE CUSTOMER'S SDP SITE-A TO THE CUSTOMER'S
SDP SITE-Z. THE RTD SHALL BE LESS THAN OR EQUAL TO 10
MILLISECONDS TO EFFECTIVELY SUPPORT THE GOVERNMENT'S MISSION.
FOR THE LOCATIONS THAT HAVE AN ESTIMATED TOTAL FIBER ROUTE
DISTANCE OVER 600 MILES (ONE-WAY), WHERE THE 10 MILLISECONDS
RTD SPECIFICATION CANNOT REASONABLY BE MET, THE RTD SHALL BE
LESS THAN OR EQUAL TO 10 MILLISECONDS PER 350 MILES MEASURED
To:
TEST & ACCEPTANCE INSTRUCTIONS:
1. OTU-2 TESTING PARAMETERS:
A. THE OTU-2 MUST COMPLY WITH THE ITU-T G.709 STANDARDS
B. THE SIGNAL IS OTU-2, 10GB (SR1), SMF
C. FEC BASED ON ITU-T G.709 RS-8
D CONNECTOR TYPE: LC
2. DETAILED TESTING PARAMETERS:
TEST & ACCEPTANCE INSTRUCTIONS: A. OTM2 FORMAT:
(1) FEC ITU-T G.709 RS-8
(2) PHYSICAL INTERFACE SR-1
(3) OPTICAL POWER -1 DBM TO -6 DBM
(4) THE SIGNAL IS OTU-2, 10GN (SR1),SMF
(5) CONNECTOR TYPE: LC
B. BIT ERROR RATE (BER)
(1) BETTER THAN 1E-12 LESS THAN 2 SES IN A MONTH
(2) ZERO (0) LOS/LOF/SEFS IN 72 HOURS
3. CIENA OVERHEAD TRANSPARENCY (OTU-2):
A. GCC0 = OPTIONALLY TRANSPARENT; VENDOR SHALL DECLARE WHETHER
THE BYTE IS END TO END TRANSPARENT.
B. GCC1 = TRANSPARENT; VENDOR SHALL DECLARE WHETHER THE BYTE IS
END TO END TRANSPARENT.
C. GCC2 = TRANSPARENT; VENDOR SHALL DECLARE WHETHER THE BYTE IS
END TO END TRANSPARENT.
D. TCM1, TCM2, TCM3, TCM4, TCM5, TCM6 = AT LEAST TWO OF THE
LISTED TCM BYTES REQUIRED TO BE TRANSPARENT.
E. R4C9 AND R4C10 = OPTIONALLY TRANSPARENT; VENDOR SHALL DECLARE
WHETHER THE BYTE IS END TO END TRANSPARENT.
F. R4C11, R4C12, R4C13, R4C14, R4C15 = TRANSPARENT
G. R1C16 = VENDOR SHALL REPORT COLUMN 16, ROW 1 BYTE STATUS
H. R2C15 = TRANSPARENT
I. R2C16 = VENDOR SHALL REPORT COLUMN 16, ROW 2 BYTE STATUS
J. R3C15 = TRANSPARENT
K. R3C16 = VENDOR SHALL REPORT COLUMN 16, ROW 3 BYTE STATUS
L. R4C15 = TRANSPARENT
M. R4C16 = VENDOR SHALL REPORT COLUMN 16, ROW 4 BYTE STATUS
4. LATENCY: ROUND TRIP DELAY (RTD) WILL BE
MEASURED IN
MILLISECONDS FROM THE CUSTOMER'S SDP SITE-A TO THE CUSTOMER'S
SDP SITE-Z. THE RTD SHALL BE LESS THAN OR EQUAL TO 10
MILLISECONDS TO EFFECTIVELY SUPPORT THE GOVERNMENT'S MISSION.
FOR THE LOCATIONS THAT HAVE AN ESTIMATED TOTAL FIBER ROUTE
DISTANCE OVER 600 MILES (ONE-WAY), WHERE THE 10 MILLISECONDS
RTD SPECIFICATION CANNOT REASONABLY BE MET, THE RTD SHALL BE
LESS THAN OR EQUAL TO 10 MILLISECONDS PER 350 MILES MEASURED
CIRCUIT SPECIFICATIONS: CONUS OTU-2
1) VENDOR MUST DELIVER OTU-2 SERVICE (UNPROTECTED) FROM LOCATION
STATED IN PARAGRAPH 3.
2) REQUEST VENDOR PROVIDE LIGHT LEVEL READINGS (DB LOSS) ON
EXTENSION FROM THE COMMERCIAL POP TO THE GOVERNMENT SERVICE
DELIVERY POINT (SDP) AT BOTH LOCATIONS.
3) VENDOR MUST CONDUCT WALK-THROUGH SITE SURVEY PRIOR TO
INSTALLATION AT ALL TERMINATING GOVERNMENT LOCATIONS. VENDOR MUST
COORDINATE SITE VISIT WITH POC'S 72 HOURS IN ADVANCE PRIOR TO
REQUIRING ACCESS TO FACILITIES AT BOTH USER LOCATIONS.
4) VENDOR MUST CONTACT IMPLEMENTATION ASSISTANCE TO ESTABLISH THE
COORDINATION AND ACTIVATION PROCESS FOR TURN-UP OR ANY SITE
CONTACT ISSUES.
5) INSTALLATION AND MAINTENANCE: IAW THE UNIQUE INSTALLATION
FACTORS IN PARAGRAPH 3
Paragraph U.EVALUATION CRITERIA change from:
To:
THE TELECOM PROVIDER MUST PROVIDE DITCO COLOR POWERPOINT DRAWINGS FOR TECHNICAL REVIEW
SHOWING THE ROUTE FROM THE COMMERCIAL DEMARCS TO THE SUPPORTING CENTRAL OFFICES AND/OR
WIRING CENTERS. DRAWINGS MUST INCLUDE TOTAL FIBER MILES AND ROUND TRIP DELAY (RTD).
ADDITIONALLY, THE VENDOR IS TO PROVIDE DITCO WITH DETAILED CIRCUIT/PATH CONNECTIVITY DIAGRAMS, IN
KMZ OR KML FORMAT, IDENTIFYING ALL POINTS OF PRESENCE (POP) FOR PROPOSAL EVALUATION AND AS A
FINAL RECORD OF THE INSTALLED PATH.
Paragraph V.QUOTE DUE DATE AND TIME change from:
Dec 16, 2024 4:00:00 PM CST
Jan 6, 2025 4:00:00 PM CST
Location A, UNIQUE INSTALLATION FACTORS change from:
(1) FIBER CABLE X-CONNECT, IN-HOUSE, INSIDE WIRE,
SINGLE-MODE, 1310NM, TELCO.
(2) COMMERCIAL FIBER POINT OF PRESENCE (COMMERCIAL CARRIER
SYSTEM)
AMPLIFYING INFO:
A. VENDOR IS RESPONSIBLE FOR INSTALLATION AND MAINTENANCE
OF SINGLE MODE FIBER FROM THE LINE SIDE OF THE DISA IE1
PROVIDED FIBER TERMINATING PATCH PANEL INSTALLED IN THE
ROADM SUITE (URDWHEC070) BLDG 110, ROOM 201 TO THE DROP
SIDE OF THE COMMERCIAL FIBER POINT OF PRESENCE FIBER
DISTRIBUTION PANEL (FDP) BLDG 110, ROOM 201. "LC" TO "LC"
CONNECTORS.
B. VENDOR MUST PROVIDE FIBER STRANDS FROM THE ROADM SUITE
LOCATION TO THE COMMERCIAL DEMARC WITHOUT SPLICING AND OR
USE OF CONNECTORS TO CONNECT 2 OR MORE FIBER STRANDS
MEANING THE FIBER CANNOT BE BROKEN IN THE MIDDLE MUST BE
CONTINUOUS.
C. THE CIRCUIT MUST BE TAGGED WITH THE VENDOR'S CIRCUIT ID
AS APPLICABLE AT THE DROP SIDE OF THEIR POINT OF PRESENCE
(FIBER DISTRIBUTION PANEL) BLDG 110, ROOM 201.
ADDITIONALLY, VENDOR MUST SHOW SITE PERSONNEL LISTED ON
THIS ORDER THE EXACT TERMINATION POINT WHEN INSTALLATION IS
COMPLETE.
D. VENDOR MUST SCHEDULE/COORDINATE WITH THE POC'S LISTED ON
THIS ORDER 72 HOURS IN ADVANCE PRIOR TO SITE SURVEYS OR
INSTALLATIONS.
Location B, UNIQUE INSTALLATION FACTORS change from:
A. VENDOR IS RESPONSIBLE FOR INSTALLATION AND MAINTENANCE
OF SINGLE MODE FIBER FROM THE DROP SIDE OF THE COMMERCIAL
FIBER POINT OF PRESENCE FIBER DISTRIBUTION PANEL (FDP) BLDG
1000, ROOM 222 TO THE LINE SIDE OF THE DISA IE1 PROVIDED
FIBER TERMINATING PATCH PANEL INSTALLED IN THE ROADM SUITE
(URDWOFF030) BLDG 1000, ROOM 222. TERMINATE WITH "LC"
CONNECTORS TO DISA PROVIDED FIBER TERMINATING PATCH PANEL.
B. VENDOR MUST PROVIDE FIBER STRANDS FROM THEIR POINT OF
PRESENCE TO THE ROADM SUITE WITHOUT SPLICING AND OR USE OF
CONNECTORS TO CONNECT 2 OR MORE FIBER STRANDS MEANING THE
FIBER CANNOT BE BROKEN IN THE MIDDLE AND MUST BE
CONTINUOUS.
C. THE CIRCUIT MUST BE TAGGED WITH THE VENDOR'S CIRCUIT ID
AS APPLICABLE AT THE DROP SIDE OF THEIR POINT OF PRESENCE
(FIBER DISTRIBUTION PANEL) BLDG 1000, ROOM 222.
ADDITIONALLY, VENDOR MUST SHOW SITE PERSONNEL LISTED ON
THIS ORDER THE EXACT TERMINATION POINT WHEN SERVICE IS
COMPLETE.
D. VENDOR MUST SCHEDULE/COORDINATE WITH THE POC'S LISTED ON
THIS ORDER 72 HOURS IN ADVANCE PRIOR TO SITE SURVEYS OR
INSTALLATIONS.
File details come from the government source that posted it. Updated .