Text version
IQO INQUIRY
FM: PL8211
TO: Contractors
DATE (MM/DD/YYYY): 10/19/2022
SUBJECT: HC101322QA501-0001 Amend: 0001
A. TYPE ACTION: ADMIN AMEND
1. PURPOSE: ****AMEND0001 IS TO:****
1. EXTEND QUOTE DUE DATE TO 31 OCT 22
2. CHANGE SERVICE DATE TO 16 FEB 23
**ALL ELSE REMAINS THE SAME**
1. SUBMIT A QUOTE TO PROVIDE, INSTALL, AND MAINTAIN A 1GB ETHERNET SERVICE
ON THE IQO (BULLETIN BOARD) LEASE BETWEEN (BLDG) 241; (RM) SERVER; (FLR) 8TH;
241 18TH ST. SUITE 800, CRYSTAL CITY, VA 22202 (CRYSLML1/CCI) AND (BLDG) 2521; (RM)
COMPUTER CENTER; 2521 SOUTH CLARK STREET, CRYSTAL CITY, ARLINGTON, VA 22202
(CRYSTLCY/CCI).
- THE PROPOSED AND APPROVED RTD SHALL BE NO GREATER THAN 13MS ONE-WAY
WITHIN THE 48 CONTINENTAL STATES. ANY APS SWITCHOVER SHALLTAKE LESS THAN 50
MILLISECONDS MONTHLY AVAILABILITY SHALL BE NO LESS THAN 99.5% TO EFFECTIVELY
SUPPORT THE GOVERNMENT'S MISSION. THE GOVERNMENT ACCEPTING AUTHORITY WILL
CONFIRM THE RTD DURING THE TURN-UP AND TEST PHASE AND IF IT DOES NOT ALIGN
WITH THE CONTRACTORS PROPOSAL, DISA IE161 WILL NOTIFY DITCO IMMEDIATELY IN
WRITING. ANY CHANGES TO THE RTD AFTER AWARD ARE NOT ACCEPTABLE..
- SEE UNIQUE INSTALL FACTS
- CUSTOMER REQUESTS SOONER IF POSSIBLE SERVICE DATE (SIP)
- VENDOR QUOTE MUST INCLUDE THE A LOC AND Z LOC LEC’S ALONG WITH THE
VENDOR’S SUB-CONTRACTOR/LONG-HAUL PROVIDER/CARRIERS FOR THE SERVICE
-VENDOR QUOTES MUST INDICATE IF LEC’S ARE CURRENTLY ON-NET OR IF A BUILD IS
REQUIRED TO COMPLETE THE SERVICE.
- IF A BUILD IS REQUIRED TO COMPLETE THE SERVICE, VENDOR MUST INDICATE THE
SCOPE OF THE BUILD (LENGTH, BURIED/AERIAL, TRENCHING/DIRECTIONAL BORING, NEW
CONDUIT, ETC), AND VENDOR MUST INDICATE IF THE SITE HAS GRANTED PERMISSION
FOR VENDOR TO BUILD INTO THE SITE (MUST ALSO PROVIDE THE SITE POC’S NAME THAT
GRANTED PERMISSION) AND HAS SUFFICIENT SPACE, POWER AND HVAC CAPACITY TO
SUPPORT THE VENDOR EQUIPMENT AND CABLING.
HC101322QA501-0001
2. CONTRACTORS ARE RESPONSIBLE FOR READING AND ADDRESSING ALL TECHNICAL
REQUIREMENTS OF THIS INQUIRY/SOLICITATION, READING AND AGREEING WITH THE
STANDARD PROVISIONS, PROVIDE PRICE QUOTATION IN ACCORDANCE WITH STANDARD
PROVISION 4, AND MEET THE REQUESTED SERVICE DATE.
3. THE SERVICE DATE TO BE MET IS: 06 FEB 23 (SIP) TO COMPLY WITH PROCUREMENT
ACQUISITION LEAD TIME (PALT) FOR THIS TYPE OF SERVICE. ANY CHANGES TO THE
ORIGINAL SERVICE DATE WILL BE NOTIFIED VIA AMENDMENT TO THE SOLICITATION AND
POSTED TO FBO. THE GOVERNMENT ASSUMES THAT CONTRACTORS HAVE CONSIDERED
ALL ISSUES THAT MAY DELAY THE DELIVERY OF CIRCUIT ON REQUESTED SERVICE
DATE. THE GOVERNMENT MAY CANCEL, TERMINATE, OR REQUEST CONSIDERATION IAW
STANDARD PROVISION 42 FOR FAILURE TO MEET CONTRACTUAL SERVICE.
4. CONTRACTORS MUST ENSURE THAT QUOTES SHALL INCLUDE SUFFICIENT DETAIL
FOR EFFECTIVE EVALUATION AND SHOULD NOT SIMPLY REPHRASE OR RESTATE THE
GOVERNMENT REQUIREMENTS. RATHER, CONTRACTORS MUST PROVIDE CONVINCING
RATIONALE TO ADDRESS HOW THEY INTEND TO MEET THE REQUIREMENT. IN RESPONSE
TO THIS SOLICITATION, NO TERMS OR CONDITIONS PLACED UPON THE GOVERNMENT,
NOR ASSUMPTIONS WILL BE ACCEPTED. CONTRACTORS ARE INSTRUCTED TO SUBMIT
QUESTIONS AND REQUEST CLARIFICATIONS OF THE REQUIREMENT (S) BEFORE
SUBMITTING QUOTES. QUOTES MUST BE UPLOADED TO IDEAS.
5. THIS REQUIREMENT MUST BE WORKED IN CONJUNCTION WITH SOLICITATION
HC101322QA500/TSR DM02SEP227704 AND MUST BE ENGINEERED AND PROVISIONED
TOTALLY DIVERSE END TO END FROM THE GOVERNMENT SERVICE DELIVERY POINTS
(SDP) FROM TSR DM02SEP227704 MEANING THE PHYSICAL PATHS ARE TOTALLY
SEPARATE INCLUDING MANHOLES, CONDUIT, CENTRAL OFFICE LOCATIONS, AND FIBER
BUILDS. IN ADDITION AS A MINIMUM MUST HAVE 50 METERS / 164 FEET PHYSICAL
SEPARATION FROM TSR DM02SEP227704.
6. AWARDS OF DIVERSE REQUIREMENTS WILL ONLY BE SPLIT BETWEEN TWO
CONTRACTORS IF THE DIVERSITY, RTD, SERVICE DATE AND LOWEST PRICE
REQUIREMENTS ARE PRESERVED. DITCO WILL ATTEMPT TO AWARD BOTH
REQUIREMENTS TO THE SAME VENDOR, BUT TO DETERMINE THE AWARDEE(S) OF
DIVERSE REQUIREMENTS, THE GOVERNMENT WILL FIRST EVALUATE THE LOWEST
PRICED SOLUTION FOR EACH SOLICITATION. IF THOSE TWO SOLUTIONS ARE DIVERSE
FROM EACH OTHER AND MEET ALL REQUIREMENTS, AWARD WILL BE MADE TO THE
CONTRACTOR OR CONTRACTORS THAT PROPOSED THE TWO SOLUTIONS. IF THE
TWO LOWEST PRICED SOLUTIONS ARE NOT AWARDABLE BECAUSE THEY ARE NOT
DIVERSE FROM EACH OTHER OR DO NOT MEET REQUIREMENTS, THE GOVERNMENT WILL
EVALUATE THE NEXT LOWEST PRICED COMBINATION FOR BOTH SOLICITATIONS UNTIL
IT DETERMINES THE LOWEST PRICED COMBINATION THAT MEETS ALL REQUIREMENTS.
AWARDS WILL BE MADE AS A PAIR TO ONE CONTRACTOR ONLY OR SPLIT THE AWARD
BETWEEN TWO CONTRACTORS THAT MEET ALL TECHNICAL REQUIREMENTS, REQUESTED
SERVICE DATE AND PROPOSE THE LOWEST PRICE.
7. CONTRACTOR SHALL PROVIDE COLOR POWERPOINT DRAWINGS SHOWING THE ROUTES
FROM THE COMMERCIAL DEMARKS TO THE SUPPORTING CENTRAL OFFICES AND/OR
WIRING CENTERS, ENSURING THE PHYSICAL END TO END DIVERSITY REQUIREMENTS ARE
BEING MET. DRAWINGS MUST INCLUDE SEPARATION DISTANCES, TOTAL FIBER MILES
AND ROUNDTRIP DELAY BASED ON ACTUAL DISTANCE IN MILES. REFER TO STANDARD
PROVISION 39 FOR SPECIFIC DOCUMENTATION REQUIREMENTS. SAMPLE DRAWINGS
INCLUDED WITH INQUIRY/SOLICITATION SHALL BE FOLLOWED IN ORDER TO PROVIDE THE
REQUIRED TECHNICAL INFORMATION. MAPS AND DRAWINGS WITH ERRORS, MISMATCH
INFORMATION, MISSING RTD, AND NOT ENOUGH DETAIL TO DETERMINE DIVERSITY
THROUGHOUT THE FIBER PATH WILL BE FOUND TECHNICALLY DEFICIENT AND WILL NOT
BE ACCEPTED.
8. PRE AWARD SITE SURVEYS ARE AUTHORIZED (AT CONTRACTOR EXPENSE) AND
SHOULD BE CONDUCTED IN COORDINATION WITH LOCAL POCS AT EACH GOVERNMENT
SITE. IT IS HIGHLY RECOMMENDED THAT AT A MINIMUM, CONTRACTORS CONDUCT PHONE
SURVEYS TO ADEQUATELY ASSESS THE MAGNITUDE OF THE WORK TO BE PERFORMED IN
DETERMINING THEIR PRICE STRATEGY.
9. CONTRACTORS MUST ADDRESS IN QUOTES COMPLIANCE WITH TESTING AND
ACCEPTANCE REQUIREMENTS..
10. TESTING & ACCEPTANCE REQUIREMENTS MUST BE COORDINATED WITH CUSTOMER
ACCEPTANCE AUTHORITY BEFORE NOTICE OF COMPLETION IS SUBMITTED TO DITCO.
FOR DISA REQUIREMENTS THE TESTING AND ACCEPTING AUTHORITY IS:
DISA DSCC IE Mailbox DCP Commercial Activation
11. THIS IS A REAWARD OF A CURRENT SERVICE, CSA CAST000012EBM IF THE INCUMBENT
QUOTE IS EVALUATED AS THE LOWEST PRICE TECHNICAL ACCEPTABLE, THE CURRENT
CSA WILL BE ADMINISTRATIVELY DISCONTINUED USING THE DATE PRIOR TO THE START
DATE OF NEW CSA.
FAILURE TO READ AND ADDRESS ANY OF THE TECHNICAL REQUIREMENTS AND SERVICE
DATE REQUESTED IN THIS INQUIRY SHALL RENDER THE QUOTE NON-COMPLIANT AND
RESULT IN IT BEING EXCLUDED FROM EVALUATION AND AWARD.
M. ADDITIONAL INFORMATION:
3. TSR NUMBER: DM09SEP227705
4. CCSD: SVI6HT91
Z. DITCO CONTACT:
Karen Pakosta
Not Applicable karen.s.pakosta.civ@mail.mil
Robert E Spencer
DITCO Contracting Officer
Unless otherwise specified, all other terms and conditions are unchanged.
Paragraph E.SERVICE DATE change from:
Feb 6, 2023
To:
Feb 16, 2023
Paragraph V.QUOTE DUE DATE AND TIME change from:
Oct 21, 2022 4:00:00 PM CDT
To:
Oct 31, 2022 4:00:00 PM CDT