Text version
IQO INQUIRY
FM: PL8211
TO: Contractors
DATE (MM/DD/YYYY): 3/15/2023
SUBJECT: HC101322QA096-0001 Amend: 0001
A. TYPE ACTION: AMEND
1. PURPOSE: AMENDMENT IS ISSUED TO:
1. UPDATE THE TSP TO TSPM94N9-11: 2. REMOVE THE REFERENCE "LATENCY WILL BE
MEASURED WILL BE ACCORDING TO THE FOLLOWING MAXIMUM TRANSMISSION DELAY
FOR ANY CIRCUIT UP TO 500 MILES AIR-MILES IN LENGTH SHALL BE NO GREATER THAN
13MS ONE-WAY AND ANY POINT-TO-POINT CIRCUIT LONGER THAN 500 AIR-MILES SHALL
BE NO GREATER THAN 50MS ONE WAY WITHIN THE 48 CONTINENTAL STATES. ANY APS
SWITCHOVER SHALL TAKE LESS THAN 50 MILLISECONDS MONTHLY AVAILABILITY SHALL
BE NO LESS THAN 99.5%". 3. INFORM THAT THIS REQUIREMENT IS ISSUED TO REPLACE
CSA ABI000036EBM. 4. QUOTES DUE DATE IS CHANGED TO 31 MAR 23. 4. SERVICE DATE
CHANGES TO 14 AUG 23 SIP.
SUBMIT A QUOTE TO PROVIDE, INSTALL, AND MAINTAIN A A SECOND DEDICATED
WHEELHOUSE SERVICE AT 10 MB OVER THE IQO CONTRACT FROM SITE R, BLUE
RIDGE SUMMIT, PA 17214/CCI TO SITE R, BLUE RIDGE SUMMIT, PA 17214/CCI.
THIS REQUIREMENTS IS TO REPLACE EXISTING ATT TECHNOLOGY FOR CURRENT
WHEELHOUSE CIRCUITS AND MAINTAIN THE SAME LEVEL OF PERFORMANCE.
2. CIRCUIT MUST BE ABLE TO PROVIDE VIRTUAL PRIVATE NETWORK (VPN) CONNECTION.
A NETWORK-BASED MPLS VPN TO LINK LOCATIONS AND EFFICIENTLY TRANSMIT
APPLICATIONS SUCH AS VOICE, DATA, AND VIDEO OVER A SINGLE CONNECTION USING
VARIOUS ACCESS TECHNOLOGIES.
3. ANY TESTING & ACCEPTANCE REQUIREMENTS MUST BE COORDINATED WITH
GOVERNMENT POC.
4. CONTRACTORS ARE RESPONSIBLE FOR READING AND ADDRESSING ALL TECHNICAL
REQUIREMENTS OF THIS SOLICITATION, READING AND AGREEING WITH THE STANDARD
PROVISIONS, PROVIDE PRICE QUOTATION IN ACCORDANCE WITH STANDARD PROVISION 4,
AND MEET THE REQUESTED SERVICE DATE.
5. THE SERVICE DATE TO BE MET IS: 11 MAY 2023(SIP).
6. CONTRACTORS MUST CONSIDER ALL ISSUES THAT MAY DELAY THE DELIVERY OF
CIRCUIT ON APPROVED SERVICE DATE. THE GOVERNMENT MAY CANCEL, TERMINATE,
OR REQUEST CONSIDERATION IAW STANDARD PROVISION 42 FOR FAILURE TO MEET
CONTRACTUAL SERVICE.
7. QUOTES MUST INCLUDE NAME AND INFORMATION ABOUT SUB-CONTRACTOR/LONG
HAUL PROVIDER/OTHER CARRIER INSTALLING CIRCUIT IS ON NET/OFF NET.
8. ESTABLISH TSP: TSP0LCJTK-02
HC101322QA096-0001
9. MAXIMUM TRANSMISSION DELAY FOR ANY CIRCUIT UP TO 500 MILES AIR-MILES IN
LENGTH SHALL BE NO GREATER THAN 13MS ONE-WAY AND ANY POINT-TO-POINT CIRCUIT
LONGER THAN 500 AIR-MILES SHALL BE NO GREATER THAN 50MS ONE WAY WITHIN THE 48
CONTINENTAL STATES. ANY APS SWITCHOVER SHALL TAKE LESS THAN 50 MILLISECONDS
MONTHLY AVAILABILITY SHALL BE NO LESS THAN 99.5%.
M. ADDITIONAL INFORMATION:
3. TSR NUMBER: JS30NOV215391
4. CCSD: CUED72VU
Z. DITCO CONTACT:
Aaron Fuehne aaron.j.fuehne.civ@mail.mil
Dale L. Rupright
DITCO Contracting Officer
Unless otherwise specified, all other terms and conditions are unchanged.
Paragraph C.TSP AUTHORIZATION CODE/RESTORATION CODE change from:
TSP0LCJTK-02
To:
TSPM94N9-11
Paragraph E.SERVICE DATE change from:
May 11, 2023
Aug 14, 2023
Paragraph M.3.TSR NUMBER change from:
JS30NOV215391B
JS30NOV215391
Paragraph V.QUOTE DUE DATE AND TIME change from:
Feb 10, 2023 4:00:00 PM CST
Mar 31, 2023 4:00:00 PM CDT