HC101320QA475-0002.v0.pdf
PDF 9 KB Posted
- Solicitation number
- HC101320QA475
- Issued by
-
Defense Information Systems Agency
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HC101320QA475-0001.v0.pdf | ||
| HC101320QA475.v0.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IQO INQUIRY
FM: PL8211
TO: Contractors
DATE (MM/DD/YYYY): 4/6/2020
SUBJECT: HC101320QA475-0002 Amend: 0002
A. TYPE ACTION: AMEND
1. PURPOSE: THE PURPOSE OF AMENDMENT 0002 IS AS FOLLOWS:
1. UPDATE 3.B AND 3.C INSIDE WIRE TO SHOW "CPIWI-NO/CPIWM-NO," VICE "CPIWI-YES/
CPIWM-NO"
2. EXTEND QUOTE DUE DATE TO 06 MAY 20 FOR COMPETITION/QUOTE.
3. EXTEND SERVICE DATE TO 07 AUG 20.
**************OTHER AMENDMENT***********
THE PURPOSE OF AMENDMENT 0001 IS TO CORRECT LOC A ADDRESS TO SHOW "8601
ODELL RD," VICE "8601 LAUREL RD".
**********ORIGINAL SOLICITATION*********
1. SUBMIT A QUOTE TO PROVIDE, INSTALL, AND MAINTAIN A NEW 100MB ETHERNET LEASE
BETWEEN: (BLDG) 8601; (RM) 88; B FL; 8601 LUAREL ROAD; LAUREL, MD, 20708/CCI, AND
BLDG 6910, (RM) C3F14, CER ROOM; (FL) 3RD; 6910 COOPER AVENUE, FT GEORGE G
MEADE, MD 20755/CC5.
-SEE UNIQUE INSTALL FACTORS
- CUSTOMER REQUESTS AND WILL ACCEPT SOONER IF POSSIBLE
2. EACH CONTRACTOR IS RESPONSIBLE FOR READING AND COMPLYING WITH ALL
TECHNICAL ASPECTS OF THIS SOLICITATION, TO INCLUDE READING AND AGREEING
WITH THE STANDARD PROVISIONS, ATTACHMENTS LISTING SPECIFIC TECHNICAL
REQUIREMENTS, PRICE QUOTE REQUIREMENTS, AND REQUESTED SERVICE DATE.
FAILURE TO READ AND ADHERE TO ANY PORTION OF THE INQUIRY SHALL RENDER
THE QUOTE NON-COMPLIANT AND RESULT IN IT BEING EXCLUDED FROM EVALUATION AND
AWARD.
3. THE SERVICE DATE TO BE MET IS: 10 JUL 20 (SIP). THE GOVERNMENT ASSUMES THAT
CONTRACTORS HAVE CONSIDERED ALL ISSUES THAT MAY IMPACT THE SERVICE DATE.
THE GOVERNMENT MAY CANCEL, TERMINATE, OR REQUEST CONSIDERATION IAW
STANDARD PROVISION 42 FOR FAILURE TO MEET CONTRACTUAL SERVICE DATE OR
COMPLY WITH ANY CONTRACT TERMS OR CONDITIONS.
HC101320QA475-0002
4. CONTRACTORS SHALL SUBMIT QUOTES IAW STANDARD PROVISION 04. QUOTES SHALL
INCLUDE SUFFICIENT DETAIL FOR EFFECTIVE EVALUATION AND SHOULD NOT SIMPLY
REPHRASE OR RESTATE THE GOVERNMENT REQUIREMENTS. QUOTE MUST PROVIDE
CONVINCING RATIONALE TO ADDRESS HOW THE CONTRACTOR INTENDS TO MEET THE
REQUIREMENT. IN RESPONSE TO THIS SOLICITATION, NO TERMS OR CONDITIONS PLACED
UPON THE GOVERNMENT, NOR ASSUMPTIONS WILL BE ACCEPTED. CONTRACTORS
ARE ENCOURAGED TO SUBMIT QUESTIONS AND REQUEST CLARIFICATION OF THE
REQUIREMENT(S) BEFORE SUBMITTING QUOTES. QUESTIONS SHALL BE SUBMITTED TO
CONTRACT SPECIALIST AND CONTRACTING OFFICER DURING THE SOLICITATION PHASE
ONLY, AND RESPONSES FOR ALL INTERESTED PARTIES WILL BE POSTED TO BETA.SAM.
5. QUOTES MUST BE UPLOADED TO IDEAS.
FAILURE TO READ AND ADHERE TO ANY PORTION OF THE SOLICITATION SHALL RENDER
THE QUOTE NON-COMPLIANT AND RESULT IN IT BEING EXCLUDED FROM EVALUATION AND
AWARD.
M. ADDITIONAL INFORMATION:
3. TSR NUMBER: XA19DEC196251
4. CCSD: UPNG7GTL
Z. DITCO CONTACT:
Catherine Haake
618-418-6097 catherine.a.haake.civ@mail.mil
KEVIN L. KNOWLES
DITCO Contracting Officer
Unless otherwise specified, all other terms and conditions are unchanged.
Paragraph E.SERVICE DATE change from:
Jul 25, 2020
To:
Aug 7, 2020
Paragraph M.3.TSR NUMBER change from:
XA19DEC196251A
XA19DEC196251
Paragraph V.QUOTE DUE DATE AND TIME change from:
Apr 9, 2020 4:00:00 PM CDT
May 6, 2020 4:00:00 PM CDT
Location A, INSIDE WIRE INSTALLATION / MAINTENANCE REQUIRED change from:
CPIWI-YES/CPIWM-NO
CPIWI-NO/CPIWM-NO
Location B, INSIDE WIRE INSTALLATION / MAINTENANCE REQUIRED change from:
CPIWI-YES/CPIWM-NO
CPIWI-NO/CPIWM-NO
Delete the Following:
STANDARD PROVISION - 13 - END-TO-END SERVICE - AUG 2015
This telecommunications service shall be provided on an end-to-end basis, to include all facilities required to extend this service from Contractor provided commercial communications interface point to termination location (i.e., inside wire, etc.). Installation, provision, and maintenance of such service extensions shall be provided as firm fixed prices, and be included in Contractor’s quote as non-recurring charge (NRC) and/or monthly recurring charge (MRC), as applicable. Such service extension charges will be considered in the evaluation of quotes. Quotes containing other than firm fixed price charges for installation, provision, and maintenance of service extensions may be excluded from consideration for award. The U.S. Government shall not be obligated to pay charges which are not specified in the quote and authorized in resultant Order. Contractor receiving this contract shall have total responsibility for end-to-end technical sufficiency (i.e., end-to-end provisioning and restoral/maintenance) for entire telecommunication service.
ACCEPTABLE CONTRACTOR RESPONSE: The acceptable Contractor response to Standard Provision – Thirteen is
“UNDERSTAND,” and provide separately itemized service extension NRC and/or MRC in quote.
File details come from the government source that posted it. Updated .