(A) FIBER TERMINATION: SINGLE-MODE INTERFACE REQUIREMENT/INTERFACE DATA RATE: LINE CODING, FRAME FORMAT, PHYSICAL CONNECTOR, 2.5 GBPS, NRZ, SCRAMBLED PER ANSI T1.104-1991 (R2003). ALL OPTIONS DEFINED SC CONNECTOR, SINGLE-MODE FIBER PER ANSI T1.105.06-2002 (SR-0, SR-1, IR-1, IR-2, LR-1, LR-2, LR-3).

(B) LINE MUST REMAIN FULLY OPERATIONAL AND AVAILABLE TO USERS 24 HOURS A DAY, SEVEN DAYS PER WEEK, AT LEAST 99.5% OR BETTER.

(C) ONE-HOUR RESPONSE TIME TURN-AROUND MUST OCCUR TO REPAIR ONCE TROUBLE-CALL HAS BEEN REPORTED.

(D) GFE CLOCKING: VENDOR ESFU (OR EQUIVALENT) NOT TO BE ENGINEERED INTO CIRCUIT.

(E) SINGLE MODE FIBER TERMINATIONS "SC" CONNECTORS

(F) NO NETWORK INTERFACE UNIT.

(G) DEDICATED PATH.

(H) CARRIER REQUIRED TO HAVE CIRCUIT VISIBILITY TO ASSIST IN ANY CIRCUIT OUTAGES.

(I) THE VENDOR MUST CONDUCT A 72 HOUR SATISFACTORY END TO END TEST ON THE 2.5 WAVE SERVICE IAW ITU STANDARD M.2101. ADDITIONALLY, THE VENDOR TEST SET/SETS MUST HAVE THE ABILITY TO PRINT THE TEST RESULTS AND THOSE RESULTS MUST BE EMAILED TO THE ACCEPTING AUTHORITY FOR REVIEW.

(J) VENDOR MUST HAVE A 24X7 NETWORK OPERATIONAL CENTER OF THIS 2.5GB WAVE SERVICE.

(K) THE COMMERCIAL CIRCUIT WILL BE ACCEPTED ON BEHALF OF THE GOVERNMENT BY THE CONUS GNOSC: PRI POC: CONTACT: MIKE REEVES (C) 618-418-8973 (D) 418-8973 ALT POC: CONTACT: DON NORDENHOLT (C) 618-418-8643 (D) 418-8643 ALT POC: CONTACT: AARON SMITH (C) 618-418-9820 (D) 418-9820 ALT POC: CONTACT: BOB RISKY (C) 618-418-8632 (D) 418-8632 ALT POC: ORGANIZATIONAL NUMBER (C) 618-418-8691 (D) 418-8691

(L) THE VENDOR MUST PROVIDE: 1) THE LONG HAUL CIRCUIT NUMBER AND THE 1-800 TROUBLE REPORT NUMBER TO THE ACCEPTING AUTHORITY PRIOR TO THE GOVERNMENT ACCEPTING SERVICE. INSIDE WIRING MUST BE COMPLETED AND TESTED PROPERLY IAW THE ORDER PRIOR TO TURNUP TO THE GOVERNMENT.

2. VENDOR IS RESPONSIBLE FOR INSTALLATION AND MAINTENANCE OF 2.5GB WAVE SERVICE IAW UNIQUE INSTALLATION FACTORS.

3. FOR UNSATISFACTORY SERVICE OR TO REPORT EQUIPMENTAND/OR CIRCUIT PROBLEMS INVOLVING DISA PROVIDED TRANSPORT AND/OR EQUIPMENT, PLEASE CONTACT THE DISN CUSTOMER CONTACT CENTER (DCCC) SCOTT AFB, IL. TOLL FREE: 1-855-868-9500 COML: 618-418-9500 DSN: 312-418-9500 7. DD FORM 1368 WILL BE SUBMITTED ON THIS TRUNK IAW DISAC-DITCO 350-135-1 BY RNSOC, SCOTT AFB, IL.

SPECIFIC FORMAT TO BE USED IS:

LINE RATE: 2.5GB.

LINE CODE: NRZ

FRAME FORMAT: SCRAMBLED IAW ANSI T1.104-1991 (R2003)

1. TEST AND ACCEPTANCE: FIBER OPTIC 2.5GB WAVE CIRCUITS SHALL PASS A FULLY DOCUMENTED SATISFACTORY SOAK TEST BY THE CONUS GNOSC AT SCOTT AFB, IL. PRIMARY: (C) 618-418-8691 (D) 418-8691

2. THE WAVELENGTH TRANSMISSION SERVICE PROVIDED SHALL MEET THE FOLLOWING PERFORMANCE REQUIREMENTS ON A MONTHLY BASIS. PERFORMANCE REQUIREMENT/PERFORMANCE SPECIFICATION: NON-DIVERSE/NON-PROTECTED AVAILABILITY: GREATER THAN OR EQUAL TO 99.5% OR BETTER. MONTHLY SHORT INTERRUPTION EVENT COUNT (SEIC): LESS THAN OR EQUAL TO 9% ERRORED SECONDS (ES): LESS THAN OR EQUAL TO 0.005% SEVERELY ERRORED SECONDS (SES): LESS THAN OR EQUAL TO 0.00035 BACKGROUND BLOCK ERROR RATIO (BBER): LESS THAN OR EQUAL TO 5 X 10-6 BIT COUNT INTEGRITY (BCI)/PATTERN SLIP (PAT SLIP): LESS THAN OR EQUAL TO 1 PER 72 HOURS JITTER SEE NOTE 1 (JITTER) BER: LESS THAN OR EQUAL TO 1X10-12 DELAY (ONE WAY): * LESSER OF 10 MSEC OR (0.01 X D MSEC) * WHERE "D" IS THE SDP TO SDP TRANSMISSION DISTANCE, MEASURED SHORTEST GREAT CIRCLE, IN KILOMETERS.

3. ROUND TRIP DELAY (RTD): RTD SHALL BE MEASURED OVER THE 2.5GB WAVE CIRCUIT AND SHALL BE LESS THAN OR EQUAL TO 22 MILLISECONDS TO EFFECTIVELY SUPPORT THE GOVERNMENT'S MISSION. THE GOVERNMENT RESERVES THE RIGHT TO ACCEPT A HIGHER RTD ONLY IF SUPPORTED BY ACTUAL PHYSICAL FIBER DISTANCE BETWEEN THE TWO END LOCATIONS. ADDITIONALLY THE GOVERNMENT RESERVES THE RIGHT TO REJECT A PROPOSED PATH IF DEEMED EXCESSIVELY LONG WITHOUT WRITTEN JUSTIFICATION IN THE PROPOSAL. JUSTIFICATION FOR EXCESSIVE FIBER MILEAGE COULD BE DIVERSITY/AVOIDANCE REQUIREMENTS, LIMITED INFRASTRUCTURE, AVAILABLE PROVIDERS, GEOGRAPHIC AND PHYSICAL LIMITATION. THE GOVERNMENT ACCEPTING AUTHORITY WILL CONFIRM THE RTD DURING THE TURN-UP AND TEST PHASE AND IF IT DOES NOT ALIGN WITH THE CONTRACTORS PROPOSAL DISA IE161 WILL NOTIFY DITCO IMMEDIATELY IN WRITING.THE CIRCUIT MUST BE TAGGED WITH THE CIRCUIT ID AT THE LINE SIDE OF THE DISA IE1 PROVIDED FIBER TERMINATING PATCH PANEL BLDG 1082, ROOM 1 (SWITCH ROOM). ADDITIONALLY, VENDOR MUST SHOW SITE PERSONNEL LISTED ON THIS ORDER THE EXACT TERMINATION POINT WHEN SERVICE IS COMPLETED.