ADDITIONAL REQUIREMENTS FOR HC101318QA683

***ATTENTION WHITE SANDS LOCATION***

1. TELECOMM PROVIDER MUST PROVIDE DITCO COLOR POWERPOINT

DRAWINGS FOR TECHNICAL REVIEW SHOWING THE ROUTES FROM

THE COMMERCIAL DEMARCS TO THE SUPPORING CENTRAL

OFFICES AND OR WIRING CENTERS. DRAWINGS ALSO TO

INCLUDE TOTAL FIBER MILES AND ROUND TRIP DELAY (RTD).

2. VENDOR MUST DELIVER OC-48C SERVICE 2W (UNPROTECTED)

FROM THE COML DEMARC TO THE GOVERNMENT SERVICE

DELIVERY POINT AT BOTH LOCATIONS.

3. REQUEST VENDOR PROVIDE LIGHT LEVEL READINGS (DB LOSS)

ON EXTENSION FROM THE COMMERCIAL POP TO THE GOVERNMENT

SERVICE DELIVERY POINT (SDP) AT BOTH LOCATIONS PRIOR

TO CIRCUIT TURN UP TO THE GOVERNMENT ENSURING

OPERATIONAL SERVICE DATE: 310800Z JUL 18 SIP

ANY ADDRESSEE ON THE TSO WILL NOTIFY ALL

ADDRESSEES IMMEDIATELY BY MESSAGE IDENTIFYING ANY ISSUES,

PROBLEMS, OR SITUATIONS WHICH MAY PREVENT OR DELAY THE

IMPLEMENTATION OF THIS TELECOMMUNICATIONS SERVICE ORDER (TSO).

ALL STATIONS WILL REVIEW THE CONFIGURATION, EQUIPMENT, CONTACT

NUMBERS AND ADDRESSES CONTAINED IN THIS TSO AND PROVIDE UPDATES

TO ORIGINATOR OF TSO ANY ERRORS SO THAT SUBSEQUENT TSOS MAY BE

UPDATED. THE LEVELS ARE WITHIN SPECS. LIGHT LEVELS MUST

BE ADJUSTED TO -5 TO -13.

***VENDOR MUST TERMINATE OC-48C SERVICE AT THE JUNIPER SUITE

LOCATIONS IAW UNIQUE INSTALLATION FACTORS.***

4. VENDOR MUST CONDUCT WALK-THROUGH SITE SURVEY PRIOR TO

INSTALLATION AT BOTH LOCATIONS.

5. VENDOR MUST CONTACT CONUS IP BACKBONE ENGINEERING AND

IMPLEMENTATION GROUP UPON RECEIPT OF A VALID TSO TO ESTABLISH THE

COORDINATION AND ACTIVATION PROCESS. (C) 618-220-8843 (D)

770-8843

6. VENDOR MUST CONDUCT A SATISFACTORY 72 HOUR END TO END TEST

PRIOR TO TURN OVER TO THE GOVERNMENT FOR ACCEPTANCE TESTING.

7. THE OC-48C SERVICE MUST PASS A DOCUMENTED SATISFACTORY 72

HOUR END TO END TEST IAW ITU STANDARD M.2101 PRIOR TO TURN UP TO

THE GOVERNMENT.

REMARKS:

1. CIRCUIT REQUIRES THE FOLLOWING PARAMETERS:

(A) FIBER TERMINATION: FRAME FORMAT: STS-48C, 1310NM

RATE: PLUS OR MINUS 20 PPM USER PROVIDED STS-48C FRAMING FROM

GOVT JUNIPER SWITCH

(B) NO CHANNELIZATION REQUIRED.

(C) LINE MUST REMAIN FULLY OPERATIONAL AND AVAILABLE TO USERS 24

HOURS A DAY, SEVEN DAYS PER WEEK, AT LEAST 99.5% OR BETTER.

(D) REQUEST ONE-HOUR RESPONSE TIME TURN-AROUND TO REPAIR ONCE

TROUBLE-CALL HAS BEEN REPORTED.

(E) GFE CLOCKING: VENDOR ESFU (OR EQUIVALENT) NOT TO BE

ENGINEERED INTO CIRCUIT.

(F) SINGLE MODE FIBER TERMINATIONS SC/SC CONNECTORS

(G) NO NETWORK INTERFACE UNIT.

(H) DEDICATED PATH.

(I) VENDOR REQUIRED TO HAVE CIRCUIT VISIBILITY TO ASSIST IN ANY

CIRCUIT OUTAGES.

(J) VENDOR MUST TEST THE CIRCUIT END TO END FOR 72 HOURS

UTILIZING A 2E23 TEST PATTERN.

(K) VENDOR MUST HAVE A 24X7 NETWORK OPERATIONS CENTER.

(L) THE COMMERCIAL CIRCUIT WILL BE ACCEPTED ON BEHALF OF THE

GOVERNMENT BY THE CONUS IP BACKBONE ENGINEERING AND

IMPLEMENTATION GROUP, SCOTT AFB, IL. (C) 618-220-8843 (D)

770-8843

(M) VENDOR MUST PROVIDE: 1) THE LONG HAUL CIRCUIT NO. AND LEC

CKT ID. PRIOR TO TURN UP TO THE GOVERNMENT.

2. VENDOR WINNING AWARD IS RESPONSIBLE FOR INSTALLATION AND

MAINTENANCE OF OC-48C SERVICE IAW THE UNIQUE INSTALLATION

FACTORS.

3. INSIDE WIRING IS AUTHORIZED IAW WITH THE UNIQUE INSTALLATION

FACTORS.

4. VENDOR MUST COORDINATE SITE VISIT WITH POC'S 72 HOURS IN

ADVANCE PRIOR TO REQUIRING ACCESS TO FACILITIES AT BOTH USER

LOCATIONS. IF UNABLE TO REACH SITE POC'S CONTACT KEN DIEF OR RAY

BURKE IMMEDIATELY FOR ASSISTANCE AT: (301) 225-2416/2550

5. ALL EQUIPMENT AND CIRCUIT PROBLEMS WILL BE REPORTED BY PHONE

TO THE CONUS IP BACKBONE ENGINEERING AND IMPLEMENTATION GROUP,

SCOTT AFB, IL. PRIMARY: (C) 618-220-9950(D) 770-9950 TOLL FREE:

855-868-9950

6. DD FORM 1368 WILL BE SUBMITTED ON THIS TRUNK IAW DISAC-DITCO

350-135-1 BY RNSOC, SCOTT AFB, IL. GUIDANCE ON SUBMISSION IS

AVAILABLE AT

<HTTP://WWW.DITCO.DISA.MIL/ASP/PUBLICATIONS.ASP>.

CLICK ON "DISA-DITCO CIRCULAR, 350-135-1, DEFENSE COMMERCIAL

COMMUNICATIONS ACQUISITION PROCEDURES."

MINIMUM TECHNICAL SPECIFICATIONS:

SPECIFIC FORMAT TO BE USED IS:

LINE RATE: OC-48C/ 20 PPM.

LINE CODE: OPTIC

FRAME FORMAT: SONET/STS-48C

1. TEST AND ACCEPTANCE: FIBER OPTIC OC-48C CIRCUITS SHALL PASS A

FULLY DOCUMENTED SATISFACTORY 72 HOUR SOAK TEST BY THE CONUS AT

SCOTT AFB, IL. PRIMARY: (C) 618-229-8691 (D) 779-8691

2. TESTING PARAMETERS AND THRESHOLDS: THE FOLLOWING TESTING

PARAMETERS SHALL BE MEASURED DURING TEST AND ACCEPTANCE TESTING.

ERROR PERFORMANCE (AVAILABILITY, SES, DM, EFS) AND LOSS OF BIT

COUNT INTEGRITY SHALL BE MEASURED AND RECORDED OVER THE DURATION

OF THE CONTIGUOUS 72 HOUR TESTING INTERVAL AND SHALL BE MEASURED

AND RECORDED PER DEFINITION IN ITU

RECOMMENDATION G.826 AND M.2100.

3. ERROR PERFORMANCE: ERROR PERFORMANCE SHALL BE BETTER THAN THE

FOLLOWING PARAMETER THRESHOLDS TO BE ACCEPTABLE:

AVAILABILITY SHALL BE GREATER THAN 99.5% OR BETTER SEVERELY

ERRORED SECONDS (SES) SHALL BE LESS THAN 0.02% DEGRADED MINUTES (DM) SHALL BE LESS THAN 0.2% ERROR FREE SECONDS (EFS) SHALL BE GREATER THAN 99%

4. LOSS OF BIT COUNT INTEGRITY (LBCI): LOSS OF BIT

COUNT INTEGRITY SHALL BE MONITORED ONLY BY THE

FOLLOWING METHOD: USING TEST EQUIPMENT WHICH CAN

DETECT AND MEASURE THE OCCURRENCE OF THE INSERTION

OR DELETION OF ONE OR MORE BITS INTO THE DIGITAL

BIT STREAM, ON MANY MANUFACTURERS BERT TEST

EQUIPMENT THIS IS MONITORED USING THE "PATTERN

SLIP" PARAMETER WHERE EVERY OCCURRENCE OF A PATTERN

SLIP "EVENT" MARKS THE OCCURRENCE OF A LBCI (RATHER

THAN THE RAW TOTAL NUMBER OF PATTERN SLIPS

ACCUMULATED OVER A TESTING INTERVAL)

5. MEAN TIME TO LOSS OF BIT COUNT INTEGRITY (MTTLBCI)

SHALL BE GREATER THAN 24 HOURS.

6. ROUND TRIP DELAY (RTD): RTD SHALL BE MEASURED OVER THE

OC-48C CIRCUIT AND SHALL BE LESS THAN OR EQUAL TO

(10) MILLISECONDS.

CISCO ASR-9010 ROUTER (GFE)(DISA IE1 PROVIDED)

OPTICAL INTERFACE CARD (SPA-2XOC48POS/RPR)

(GFE)(DISA IE1 PROVIDED)

RACK/SHELF/SLOT/PORT - TBD

FIBER TERMINATING PATCH PANEL (GFE)(DISA IE1 PROVIDED)

RACK/SHELF/PORT - TBD

(1) CISCO ASR-9010 ROUTER (GFE)(DISA IE1 PROVIDED)

NODE ID: UJEWKEL030

(2) OPTICAL INTERFACE CARD (SPA-2XOC48POS/RPR)

(GFE)(DISA IE1 PROVIDED)

RACK/SHELF/SLOT/PORT - TBD

(3) FIBER CABLE X-CONNECT, IN-HOUSE, INSIDE WIRE,

SINGLE-MODE, 1310NM, DISA IE4

(4) FIBER TERMINATING PATCH PANEL (GFE)(DISA IE1 PROVIDED)

RACK/SHELF/PORT - TBD

(5) FIBER CABLE X-CONNECT, IN-HOUSE, INSIDE WIRE,

SINGLE-MODE, 1310NM, TELCO

AMPLIFYING INFO:

A. DISA IE4 IS RESPONSIBLE FOR INSTALLATION AND GSM-O

FOR MAINTENANCE OF THE CISCO ASR-9010 ROUTER, OPTICAL

INTERFACE CARD BLDG 200, COMPUTER ROOM #2.

B. DISA IE4 IS RESPONSIBLE FOR INSTALLATION AND GSM-O OF

SINGLE MODE FIBER FROM THE OPTICAL INTERFACE CARD

INSTALLED IN THE CISCO ASR-9010 ROUTER TO THE DROP

SIDE OF THE DISA IE1 PROVIDED FIBER TERMINATING PATCH

PANEL INSTALLED IN THE CISCO ASR-9010 SUITE. TYPE

CONNECTORS TBD.

C. VENDOR IS RESPONSIBLE FOR INSTALLATION AND MAINTENANCE

OF SINGLE MODE FIBER FROM THE LINE SIDE OF THE DISA

PROVIDED FIBER TERMINATING PATCH PANEL INSTALLED IN THE

CISCO ASR-9010 ROUTER SUITE (UJEWKEL030) BLDG 200,

COMPUTER ROOM #2 TO THE DROP SIDE OF THE COMMERCIAL

FIBER POINT OF PRESENCE FIBER DISTRIBUTION PANEL BLDG

200, COMPUTER ROOM #2. COORDINATE TYPE OF CONNECTORS

FOR TERMINATION TO THE DISA PROVIDED PATCH PANEL.

D. THE LENGTH OF SINGLE MODE FIBER JUMPERS REQUIRED

WILL BE BASED ON THE LOCATION OF THE VENDOR'S FIBER

MUX/FIBER DISTRIBUTION PANEL.

E. THE CIRCUIT MUST BE TAGGED WITH THE LOCAL CIRCUIT ID

AND LONG HAUL CIRCUIT NO. AT THE LINE SIDE OF THE DISA

PROVIDED FIBER TERMINATING PATCH PANEL BLDG 200,

COMPUTER ROOM #2 AND AT THE DROP SIDE OF THE VENDOR'S

FIBER DISTRIBUTION PANEL INSTALLED IN THEIR SONET

EQUIPMENT SUITE. ADDITIONALLY, VENDOR MUST SHOW SITE

PERSONNEL LISTED ON THIS ORDER THE EXACT TERMINATION

POINT WHEN SERVICE IS COMPLETE.

(** ADDITIONAL PROVISIONING INFORMATION **) (ORG ACCT) DISA

(DISN IP ROUTER NETWORK BACKBONE AND BACKBONE HOSTS)(CONUS

AND OCONUS)

R. REMARKS CONTINUED: FUNDING TCO APL: (** ON BEHALF OF **) DEFENSE

INFORMATION SYSTEMS AGENCY