Harbor Management Plan RFP Addendum 1.pdf
PDF 399 KB Posted
- Solicitation number
- 9-28-2026
- Issued by
- New London County, Connecticut
About this file
This Addendum 1 document clarifies key terms for the City of Groton's Request for Proposals (RFP) 9-28-2026 regarding professional consulting services for a Harbor Management Plan update, with proposals due October 20, 2026. The City will work with the selected consultant to finalize the project schedule, including start date, duration, and target completion date based on the consultant's proposed timeline. The Harbor Management Commission will play an active role in providing project direction, coordinating with the consultant, and reviewing work products, while the City will provide relevant existing documents, information, and GIS layers to support the project. The consultant will be responsible for completing all work and deliverables specified in the RFP in coordination and collaboration with the Harbor Management Commission.
The City of Groton has not disclosed a specific budgeted amount for the project and encourages proposers to develop proposals based on the scope and deliverables outlined in the RFP, with cost-effectiveness being a key evaluation criterion. All vendors are eligible to respond with no set-asides or preferences indicated. The addendum clarifies that the City will only accept proposals from individual entities, with any other entities involved required to serve as sub-contractors rather than joint venture partners. No estimated contract value or incumbent information is specified in the available documentation.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF GROTON
REQUEST FOR PROPOSALS
FOR PROFESSIONAL CONSULTING SERVICES
FOR CITY OF GROTON
HARBOR MANAGEMENT PLAN UPDATE
BID PROPOSAL# 9-28-2026
DUE: OCTOBER 20, 2026
ADDENDUM 1
Harbor Management Plan Update Proposal # 9-28-2026
Addendum 1 Q&A
Q: Do you have a budget in mind for this project and, if so, are you able to share that?
A: The City currently does not have an exact budgeted amount for this project that we are able to share. We encourage proposers to develop their proposals based on the scope and deliverables outlined in the RFP. The City will carefully consider the proposed cost in evaluating submissions and seeks the most cost-effective proposal that meets the City's requirements.
Q: Do you have an estimated/desired start date and project duration that you can share?
A: The City will work with the selected consultant to finalize the project schedule, including the start date, duration, and target completion date, based on the schedule proposed by the consultant.
Q: To what extent will the City be involved in the effort? For example, will the Harbor Management Commission play a significant role? Will the City be providing GIS layers and other data to inform the process?
A: The Harbor Management Commission will play an active role in providing project direction, coordinating with the consultant, and reviewing work products. The Commission will also utilize other City resources to generate the GIS maps needed for the Harbor Management Plan update. The City will provide relevant existing documents and information available to support the project. The consultant will be responsible for completing the work and deliverables specified in the RFP, in coordination and collaboration with the Harbor Management Commission.
Q: Can you please clarify what is meant by "If the project is a joint venture…each joint venture shall execute the proposal"?
A: This statement was an oversight when issuing the RFP. The City of Groton will only accept proposals from an individual entity. The entity submitting the proposal shall be the contractor, and any other entities involved shall be deemed sub-contractors.