This Request for Proposal is issued by YES Prep Public Schools for a construction project at Gulfton Secondary Campus located at 6565 DeMoss Drive, Houston, Texas. The project involves converting an existing second-floor office into a Teacher's Workroom and constructing a separate Lactation Room within that space. The scope encompasses architectural modifications, millwork installation, electrical work, plumbing work, and mechanical modifications as detailed in project drawings and specifications. An optional bid walk is scheduled for December 2, 2026, with inquiries directed to adenete.fariasanders@yesprep.org. The selected contractor must provide all labor, materials, equipment, supervision, and coordination necessary to deliver complete and functional spaces. No specific response date, due date, award date, or contract term is specified in the document provided.
The document does not contain explicit pricing terms, set-asides, incumbent information, or funding amounts and sources. The contractor is required to submit a complete proposed construction schedule with a critical path from mobilization to turnover and must provide 48-hour advance notice of any utility interruptions. Key requirements include establishing a dust mitigation program, maintaining OSHA-compliant site safety practices, performing all work after regular campus hours, maintaining clear communications with the YES Prep Construction Coordinator, and providing a comprehensive closeout package including warranties and operational manuals. The contractor bears full responsibility for validating all information provided for takeoffs and bidding, with any miscalculations in materials, fixtures, or labor costs being the sole responsibility of the responding contractor.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project: Teacher Lounge Conversion – Gulfton Secondary Campus
Project Overview: YES Prep is soliciting competitive proposals from qualified contractors to convert an existing second-floor office into a Teacher’s Workroom and construct a separate Lactation Room within that space at Gulfton Secondary, located at 6565 DeMoss Drive, Houston, TX 77074. The project includes architectural modifications, millwork, electrical and plumbing work, and associated mechanical modifications as indicated in the project drawings and specifications. The selected contractor shall provide all labor, materials, equipment, supervision, and coordination necessary to deliver complete and functional spaces.
A Optional Bid Walk will take place on 12/02/2026. Email adenete.fariasanders@yesprep.org for further details.
Scope of Work:
The selected contractor will be responsible for the following:
• Verifying existing conditions, dimensions, utilities, and access requirements before starting work, and notifying YES Prep of any discrepancies or concealed conditions affecting the scope.
• Performing all construction work after regular campus hours, as coordinated with YES Prep. Work areas must be left clean, safe, and ready for use before campus operations resume each day.
• Performing selective demolition and removals required to accommodate the new layout, while protecting existing construction and utilities to remain.
• Constructing and finishing partitions to create the Lactation Room, including doors, frames, hardware, and associated components as indicated in the drawings.
• Furnishing and installing millwork, cabinetry, countertops, and associated accessories as specified.
• Completing plumbing work, including fixtures, water supply, drainage, and connections as indicated in the drawings.
mailto:adenete.fariasanders@yesprep.org
• Completing electrical work, including lighting, switches, receptacles, circuits, and connections as indicated in the drawings.
• Completing mechanical modifications required by the drawings to serve the renovated spaces.
• Repairing and restoring affected walls, floors, ceilings, and finishes to provide a complete, finished installation.
• Coordinating construction activities, deliveries, utility shutdowns, and work hours with YES Prep to minimize disruption to campus operations.
• Maintaining safe and clean work areas, including appropriate barriers, dust control, protection of adjacent spaces, and regular removal of construction debris.
• Including sufficient time in the construction schedule for an initial walkthrough with YES Prep, punch list completion, and a follow-up walkthrough.
• Testing installed systems, completing final cleaning, and providing applicable warranties, operating information, and closeout documentation before final acceptance.
Appendix:
• Contractor shall establish and submit a complete proposed construction schedule detailing a full critical path from mobilization to turn over. Any changes, alterations, or deviations from this critical path after approval shall be with the consultation and acceptance of the YES Prep Construction Coordinator.
• Contractor shall provide a minimum 48hr advance notice of any service utility interruptions to the owner. Shutdown notices shall detail the span of “no service lapse” with “estimated time of reconnection.”
• Contractor shall establish and maintain a dust mitigation program and take measures throughout the build to protect, secure and isolate “as needed” all emergency medical, safety and fire monitoring devices. And return those devices to full operational function at the end of every working shift.
• Contractor acknowledges responsibility for trash collection & removal from building site. The contractor agrees to establish and maintain a daily wrap-up routine; cleaning areas of scope as well as any other areas affected by the build Scope. The contractor shall not utilize any YES Prep trash receptacles for construction debris unless expressly approved by the owner. Roll-off and staging locations areas are to be approved by the owner.
• All Employees shall remain within the designated areas of work with no engagements with YES Prep students, parents, faculty, or staff. Construction personnel are not to utilize any campus facilities, tools, or equipment without written approval from the owner.
• Contractor agrees to establish and maintain an OSHA compliant site safety plan for the full duration of the project.
• Contractor shall provide labor inclusive of management, supervision, laborer, administrative services, and installation. Contractor shall supply all required tools and equipment to implement the entire scope of services.
• Contractor shall secure all lifts, scaffolding, or ladders at the end of each workday by placing this equipment in areas that are not accessible by the public and have been coordinated and agreed upon by the Owner. An acceptable alternative is to remove the equipment from the Premises except during working hours.
• Contractor shall take special precautions to ensure that floors are not damaged by equipment used to complete installation. The contractor shall provide proposed plans for protecting flooring, walls, and ceilings in buildings.
• Contractor agrees to provide Yes Prep with a closeout project package including but not limited to: All warranties, references, operational usage manuals, etc. at or before project closeout.
• Contractor acknowledges and agrees that scope of work shall not be considered 100% completed until final review/ orientation of Yes Prep team with all outstanding items of punch completed and a written “Project completed with no punch/housekeeping items outstanding” letter issued by the Yes Prep construction coordinator.
• Contractor agrees to establish and fully maintain clear and perpetual communications with the YES Prep Construction coordinator on job status from bid acceptance to turnover. Including but not limited to texts, emails, calls, progress reports and photos.
• Contractor acknowledges full responsibility to maintain, repair, or replace damages to any/all rated wall assemblies caused by or related to the scope in which he/she has been commissioned to fulfill.
Including but not limited to stud spacing, Fire stop Collars, rated gypsum, rated insulation etc. Any penetrations in rated assemblies shall be repaired in compliance with current IBC/IFC approved methods of rated wall penetration repair for the classification of the building in which scope is performed.
• Contractor shall fully & immediately report to the YES Prep construction team any/all issues actual, potential, or perceived which are or may affect contractors’ ability to fulfill his/her production at any phase of the critical path schedule.
• Photography, filming, audio/video recording, and/or capturing of images of any kind in areas occupied by students, faculty, or staff @ any phase of the project is strictly prohibited. Any request to record/photograph work performed may be submitted in writing to the YES Prep construction coordinator and may proceed only under the provisions granted allotted to.
• Contactor responsibilities: All plans, schematics, renderings, measurements, and elevations provided within this solicitation are the most recent reference materials available for the projects’ scope at the time of its issuing. Any additions, addendums or alterations added post initial publication will be updated online for all vendors participating in this exercise to view.
• Participation in this solicitation is voluntary. The contractor acknowledges responsibility to validate any & all information provided which he/she will utilize for take-offs, bidding, and resource procurement.
Miscalculations in fixtures, fittings, finishing materials or labor due to errors in tabulations, insufficient scope review or failure to validate job site conditions; is the sole, full & complete responsibility of the contractor responding to this solicitation.