GTC_for_Cnstruction_5316.docxo.docx

DOCX document 73 KB Posted

Attached to
Camarillo Center Water Damage Repair/Replace
Solicitation number
C5814BAK
Issued by
Ventura County, California

About this file

This is a General Terms and Conditions document for Construction contracts issued by the California Conservation Corps (CCC). The document outlines comprehensive contractual requirements covering project administration, contractor responsibilities, subcontracting, payments, disputes, insurance, and bonds. Key operational requirements include the contractor maintaining proper documentation, following safety protocols, providing progress schedules, and completing work according to specifications. The contractor must also comply with state labor laws, maintain appropriate insurance coverage, and follow specified procedures for changes and disputes.

The document requires contractors to maintain commercial general liability insurance of $1 million per occurrence, automobile liability of $1 million per accident, and workers' compensation coverage. A payment bond is required for contracts exceeding $25,000, though a performance bond is not required since progress payments will not be made. The contractor must comply with Disabled Veteran Business Enterprise (DVBE) participation requirements and certify participation levels upon completion. The document also specifies retention of 5% of the estimated value of completed work, with provisions for securities in lieu of retention under Public Contract Code 10263.

View the file

Other files

File Type Posted
Camarillo_Water_Damage.docx DOCX document
IMG_7270.JPG JPG image

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GENERAL TERMS and CONDITIONS OF THE CONTRACT FOR CONSTRUCTION

Table of Articles

1. GENERAL PROVISIONS

1.1 Definitions

1.2 Execution. Correlation and Intent

1.3 Use of the State’s Drawings, Project Manual and other Documents

1.4 Capitalization

1.5 Conflicts in the Contract Documents

2. ADMINISTRATION OF THE CONTRACT

2.1 Information and/or Services Required of the State

2.2 Administration of the Contract

2.3 Breaches, Defaults and Termination for Cause

2.4 Termination for the State’s Convenience

2.5 Suspension by the State for Convenience

3. CONTRACTOR

3.1 Review of Contract Documents and Field Conditions by the Contractor

3.2 Supervision and Construction Procedures

3.3 Labor and Materials

3.4 Nondiscrimination Clause

3.5 Guarantee

3.6 Taxes

3.7 Permits, Fees and Notices

3 8 Allowances

3.9 Superintendent

3.10 Contractor’s Progress Schedule

3.11 Documents and Samples at the Project Site

3.12 Shop Drawings, Product Data and Samples (Submittals)

3.13 Tests and Inspections

3.14 Use of Project Site

3.15 Cutting and Patching

3.16 Cleaning Up

3.17 Access to Work

3.18 Royalties and Patents

3.19 Indemnification

3.20 Air Pollution

3.21 Certification by Contractor of Recycled Content

3.22 Unfair Business Practices

3.23 Child Support Compliance Act

3.24 Contractor Required Notification of Changes

4. SUBCONTRACTORS

4.1 Subletting and Subcontracting

4.2 Sub contractual Relations

4.3 Disabled Veteran Business Enterprise Program

4.4 Contract Assignments

5. CONSTRUCTION BY THE STATE OR BY SEPARATE CONTRACTORS

5.1 State’s Right to Perform Construction and to Award Separate Contracts

5.2 Mutual Responsibility

5.3 State’s Right to Clean Up

6. CHANGES IN THE WORK

6.1 General

6.2 Change Order

6.3 Acceptance of Change Orders

6.4 Effect on Sureties

7. TIME

7.1 Notice to Proceed

7.2 Contract Time

7.3 Liquidated Damages

7.4 Time Extensions

7.5 Delays in Completion of the Work

7.6 Acceleration

8. PAYMENTS AND COMPLETION

8.1 Schedule of Values

8.2 Timeliness of Payments

8.3 Retentions

8.4 Assignment of Contract Funds

8.5 Occupancy by the State Prior to Completion of the Work

8.6 Acceptance of the Work and Final Payment

8.7 Interest

9. DISPUTES AND CLAIMS

9.1 Dispute and Claim Procedures

9.2 Audit and Access to Records

10. PROTECTION OF PERSONS AND PROPERTY

10.1 Safety of Persons and Property

10.2 Emergencies

10.3 Drug-Free Workplace

11. INSURANCE AND BONDS

11.1 Contractor's Insurance

11.2 No Personal Liability

11.3 Performance Bond and Payment Bond

12. UNCOVERING AND CORRECTION OF WORK

12.1 Uncovering and Correction of Work

12.2 Correction of Work

12.3 Acceptance of Nonconforming Work

13. MISCELLANEOUS PROVISIONS

13.1 Governing Law

13.2 Successors and Assigns

13.3 Written Notice

13.4 Contractor’s Use of Computer Software

13.5 Independent Contractor

13.6 Unenforceable Provisions

13.7 Expatriate Corporations

13.8 Domestic Partners

13.9 Air or Water Pollution Violation

13.10 Certification by Contractor of Disabled Veteran Business Enterprise/Small Business Participation

ACRONYMS

CBSCCalifornia Building Standards Code
CCCCalifornia Conservation Corps
CCRCalifornia Code of Regulations
DFEHDepartment of Fair Employment and Housing
DVBEDisabled Veterans Business Enterprise
GCGovernment Code
LCLabor Code
M&VCMilitary and Veterans Code
PCCPublic Contract Code
StateState of California

ARTICLE 1 - GENERAL PROVISIONS

1.1 DEFINITIONS: When the following terms appear in the Contract, they shall have the following meaning:

Acceptance of the Work: Written acceptance of the Work by the Director of the California Conservation Corps (CCC), State of California (State), or the Director’s designee.

Act of God: An Act of God shall include only the following occurrences or conditions and effects:

1. Earthquakes in excess of a magnitude of 3.5 on the Richter scale; or

2. Tidal waves.

Addendum (Addenda): A document issued by the State during the bidding period which modifies, supersedes or supplements the Contract Documents.

Alternative: Refer to Approved Equal and Substitution.

Applicable Codes: Include, but are not limited to, applicable laws, statutes, regulations, rules, building and other codes, ordinances, rulings, and lawful orders of all public authorities having jurisdiction over the State, the Contractor, Subcontractors, or the execution of the Work.

Approved Equal: Material, equipment, or method approved by the State for use in the Work, as being acceptable as an equivalent in essential attributes to the material, equipment, or method specified in the Contract Documents.

Agreement: The written and executed document known as the Contract Agreement.

Beneficial Occupancy: Occupancy and use by the State of all, or part, or parts, of the Work as selected by the State, prior to Completion.

Bidder: Any individual, partnership, corporation, association, joint venture, or any combination thereof, submitting a Bid Form for the Work.

Change Order: A written order issued by the State used to determine adjustments in the Contract based on:

1. a change in the Work,

2. The amount of the adjustment in the Contract Sum, and

3. the extent of the adjustment in the Contract Time.

Claim: An unresolved Dispute arising under or relating to the performance of the Contract which can only be filed after acceptance of the Work and the final statement to the Contractor.

Completion: When the entire Work has been performed in accordance with the Contract requirements as delineated in the Contract Documents and Project Manual. Completion of the Work occurs when the State’s final inspection has been made and all construction, services and deliverables have been fully executed as determined by the State’s Representative, including but not limited to completion of all punch-list items and delivery of as-built drawings, operation & maintenance manuals, guaranties, warranties, spare parts, reports and certifications, warranties, spare parts, reports and certifications as noted in the Project Manual, Contract: The Contract Documents from the Contract for Construction. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. The Contract may be amended or modified by a Change Order. The Contract Documents shall not be construed to create a contractual relationship of any kind between any persons or entities other than the State and the Contractor.

Contract Documents: The Contract Documents consist of the Agreement between the CCC and Contractor, Payment and Performance Bonds; the Conditions of the Contract, including General, Supplementary and other Conditions; Drawings, Specifications, Addenda and Change Orders.

Contract Sum: The Contract Sum is stated in the Agreement and, including authorized adjustments by Change Order, is the total amount payable by the State to the Contractor for performance of the Work under the Contract Documents.

Contract Time: The Contract Time is the period of time, from the Start Date to the date of Completion of the Work, including authorized adjustments, allotted in the Contract.

Contractor: The individual, partnership, corporation, association, joint venture, or any combination thereof, who has entered into a contract with the State, identified as such in the Agreement, and referred to throughout the Contract as if singular in number. The term "Contractor" means the Contractor or the Contractor's representative.

Day: Calendar day, unless otherwise specifically defined.

Department: The California Conservation Corps (CCC), State of California.

Director: The Director of the CCC, State of California, or the Director's designee.

Dispute: A demand during performance of the Work seeking adjustment or interpretation of Contract terms, payment of money, extension of time or other relief with respect to the terms of the Contract. A Dispute is not a Claim.

Drawings: The graphic and pictorial portions of the Contract Documents, illustrating the design, location and dimensions of the Work, generally including but not limited to, plans, elevations, sections, details, schedules and diagrams.

Emergency: A sudden, unexpected occurrence that poses a clear and imminent danger, requiring immediate action to prevent or mitigate the loss or impairment of life, health, property, or essential public services.

General Notes: The written instructions, provisions, conditions or other requirements appearing on the Drawings, and so identified thereon, which pertain to the performance of the Work.

Guarantee: The Contractor's assurance that the Project complies with the requirements of the Contract Documents.

Official Progress Schedule: The Contractor's baseline schedule and updates accepted by the State.

Or Equal: Refer to Approved Equal.

Owner: The State of California.

Product Data: Illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work.

Project: The total construction of which the Work performed under the Contract may be the whole or a part.

Project Manual: The volume(s) assembled for the Work which includes the Introductory Information, Bidding Requirements, Contracting Requirements, Specifications, and other information as may be listed in the Project Manual Table of Contents.

Retention: A percentage of the Contract Sum held back upon completion of the Work, or any portion of the Work, to cover outstanding liabilities, contingencies, and the like, as specified in the Contract Documents.

Samples: Physical examples which illustrate materials, equipment or workmanship and establish standards by which the Work will be judged.

Schedule of Values: A document furnished by the Contractor to the State reflecting the portions of the Contract sum allotted for the various parts of the Work, and used as the basis for reviewing the Contractor's applications for payment request.

Shop Drawings: Drawings, diagrams, schedules, and other data specially issued for the Work by the Contractor or a Subcontractor, Sub-subcontractor, and material suppliers to illustrate some portion of the Work.

Specifications: The portion of the Contract Documents consisting of the written requirements for materials, standards, equipment, construction systems, and standards of workmanship for the Work, and performance of related services.

State: The State of California acting through the CCC.

State Construction Supervisor/Inspector: The person(s) authorized by the State to provide inspection services, field coordination and quality control during construction.

State Contract Act: The act which is set forth in the California Public Contract Code (PCC), §10100, et seq.

State's Representative: Person(s) authorized by the State to act on behalf of the State for the Project.

Subcontractor: An individual, partnership, corporation, association, joint venture, or any combination thereof, who has a direct contract with the Contractor to perform work or labor or render service in or about the Work. The term "Subcontractor" is referred to as if singular in number and means a Subcontractor or a representative of the subcontractor. The term "Subcontractor" shall not include those who supply materials only or a separate contractor or subcontractors of a separate contractor.

Sub-subcontractor: A person or entity who has a direct or indirect contract with a Subcontractor to perform a portion of the work. The term "Sub-subcontractor" is referred to as if singular in number and means a Sub-subcontractor or a representative of the Sub-subcontractor.

Substitution: A material and/or process offered by the Contractor in lieu of the specified material and/or process, and accepted by the State in writing as being equivalent (equal) to the specified material and/or process.

Warranty: A Contractor's, manufacturer's or material supplier's assurance that products and services provided meet the requirements of the Contract Documents.

Work: Construction, services and deliverables required by the Contract Documents and Project Manual, including labor, materials, equipment, services, and documents provided or to be provided by the Contractor to fulfill the Contractor’s obligations under the Contract, including but not limited to requirements such as; completion of punch-list items, as-built drawings, operation & maintenance manuals, guaranties, warranties, spare parts, reports, and certifications.

1.2 EXECUTION, CORRELATION AND INTENT

The Contract shall not be binding on the State until appropriately endorsed by the State's legal Representative, in accordance with Public Contract Code (PCC) § 10220.

Execution of the Contract by the Contractor is a representation that the Contractor is familiar with the methodology under which the work is to be performed and has correlated personal observations with requirements of the Contract Documents.

The intent of the Contract Documents is to include items necessary for completion of the Work by the Contractor. The Contract Documents are complementary, and what is required by one shall be as binding as if required by all. Performance by the Contractor shall be required only to the extent consistent with the Contract Documents and reasonably inferable from them as being necessary to produce the intended results.

Organization of the Specifications into Groups, Divisions, Subgroups, Sections and Articles, and arrangement of Drawings shall not be the basis that Contractor utilizes in dividing the work among Subcontractors, nor in establishing the extent of work to be performed by any trade.

When standards of the Federal Government, trade societies, or trade associations are referred to in the Contract Documents by specific date of issue, these shall be considered as part of the Contract Documents. When such references do not bear date of issue, current published edition at the date of the first Invitation to Bid shall be considered as part of the Contract Documents.

Unless otherwise stated in the Contract Documents, words and terms which have well-known or commonly accepted technical or construction industry meanings shall be used in the Contract Documents in accordance with such recognized meanings.

Every part of the Work shall be accomplished in workmanship-like manner by workers, laborers, or mechanics especially skilled in the class of work required. Any person the State may deem incompetent or disorderly shall be promptly removed from the project by the Contractor upon written notice from the State, and shall not be re-employed on this Project.

1.3 USE OF THE STATE'S DRAWINGS, PROJECT MANUAL AND OTHER DOCUMENTS:

The Drawings, and other documents issued by the State, and copies furnished to the Contractor, are for use solely with respect to this Project. They are not to be used by the Contractor or any Subcontractor, Sub-subcontractor or material or equipment supplier on other projects, nor for additions to this Project outside the scope of the Work without the specific written consent of the State. The Contractor, Subcontractors, Sub-subcontractors and material or equipment suppliers are granted a limited license to use and reproduce applicable portions of the Drawings, Project Manual and other documents issued by the State appropriate to, and for use in, the execution of their work under the requirements of the Contract Documents.

1.4 CAPITALIZATION

Terms capitalized in the General Conditions of the Contract for Construction include those which are:

1. Specifically defined; or

2. Titles of numbered Articles; or

3. References to Paragraphs, Subparagraphs and Clauses; or

4. Titles of other documents.

1.5 CONFLICTS IN THE CONTRACT DOCUMENTS

In the event of conflict in the Contract Documents, the following priorities shall govern:

1. Addenda shall govern over other Sections of the Contract Documents to the extent specifically noted; subsequent Addenda shall govern over prior Addenda only to the extent specified.

2. These General Conditions of the Contract for Construction shall govern over Drawings and Specifications except for specific modifications stated in the Supplementary Conditions, and except for Addenda.

3. In case of conflict between the Drawings and the Specifications, the Specifications shall govern unless the requirement(s) in the Drawings is/are more stringent and/or of higher quality and/or of higher quantity.

4. In the case of conflict within the Drawings, the following shall govern:

a) Schedules, when identified as such, shall govern over all other portions of the Drawings.

b) Specific notes shall govern over other notes and all other portions of the Drawings, except schedules described in the preceding Clause.

c) Larger scale Drawings shall govern over smaller scale Drawings.

d) Detail Drawings shall govern over standard plates.

e) Figured or numerical dimensions shall govern over dimensions obtained by scaling.

Omissions: If the Contract Documents are not complete as to any minor detail or required construction system or with regard to the manner of combining or installing of parts, materials, or equipment, but there exists accepted trade standard for good and workmanlike construction, such detail shall be deemed to have been implied by the requirements of the Contract Documents in accordance with such standard.

1. "Minor Detail” shall include the concept of substantially identical components, where price of each such component is small even though aggregate cost or Importance is substantial, and shall include a single component which is incidental, even though its cost or importance may be substantial. Quality and quantity of parts or material so supplied shall conform to trade standards and be compatible with type, composition, strength, size and profile of parts or materials otherwise set forth in the Contract Documents.

ARTICLE 2 - ADMINISTRATION OF THE CONTRACT

2.1 INFORMATION AND/OR SERVICES REQUIRED OF THE STATE

Information and/or services under the State's control shall be furnished by the State within a mutually agreed upon response time so as to avoid delay in the orderly progress of the Work.

The Contractor will be furnished Drawings as specified in the Contract Documents.

2.2 ADMINISTRATION OF THE CONTRACT

The State will provide administration of the Contract as described in the Contract Documents during construction, until final payment is due, during the correction period and throughout the guarantee period.

The State will visit the Project site appropriate to the stage of construction to become familiar with the progress and quality of the completed work and to determine if the Work is in accordance with the Contract Documents.

Unless so specified in the Contract Documents, the State will not have control over construction means, methods, techniques, sequences or procedures, or safety precautions and programs in connection with the Work. The State will not be responsible for the Contractor's failure to carry out the Work in accordance with the requirements of the Contract Documents. The State will not be responsible for acts, errors, or omissions of the Contractor, a Subcontractor, or anyone directly or indirectly employed by any of them, or of any other persons performing portions of the Work.

Communications Facilitating Contract Administration: Communications by and with the State's consultants shall be through the State. Communications by and with Subcontractors, Sub-subcontractors and material suppliers shall be through the Contractor. Communications by and with separate contractors shall be through the State.

If the State observes work that appears to not comply with the requirements of the Contract Documents, the State will have the authority to reject the Work. Whenever the State considers it necessary or advisable for implementation of the intent of the Contract Documents, the State will require additional inspection or testing of the Work, in accordance with Article 3.13, whether or not such work is fabricated, installed or completed.

The State will review and take action upon the Contractor's submitted Shop Drawings, Product Data and Samples, but only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents. Review of submittals is not conducted for the purpose of determining the accuracy and completeness of other details, such as dimensions and quantities, nor for substantiating instructions for installation or performance of equipment or systems, which remain the responsibility of the Contractor.

Substitutions and Approved Equals: Alternative material(s), article(s), or equipment that are of equal quality and of required characteristics for the purpose intended may be proposed by the Contractor. The State will examine proposed alternatives for compliance with the Contract Documents. The proposed material(s), article(s), or equipment, will be reviewed for comparative quality, suitability, and performance against the product(s) specified in the Contract Documents. Refer to Article 3.12, for Substitution procedures. If Contractor’s substitution is accepted, the Contractor shall be responsible for the costs of any changes resulting from the substitution, including, but not limited to redesign costs of the Project.

The State will conduct inspections to determine the Contractor’s compliance with the Contract Documents and the date of Completion; will receive, for review and record, written warranties and related documents required by the Contract Documents and assembled by the Contractor; and will issue a final Payment Authorization upon compliance with the requirements of the Contract Documents and Acceptance of the Work.

2.3 BREACHES, DEFAULTS AND TERMINATION FOR CAUSE

If the Director deems that the Contractor has failed to supply an adequate working force, or material of proper quality, or has failed to comply with PCC § 10262, or has failed in any other respect to prosecute the Work with the diligence and force specified by the Contract, the Director may:

1. after written notice of at least 5 days to the Contractor, specifying the defaults to be remedied, provide any such labor or materials and deduct the cost from any money due or to become due to the Contractor under the Contract; or

2. if the Director considers that the failure is sufficient ground for such action, the Director may give written notice of at least 5 days to the Contractor and the Contractor's sureties, that if the defaults are not remedied, the Contractor's control over the Work will be terminated.

Should the State exercise its rights to terminate, the State may, without prejudice to any other rights or remedies of the State and subject to any prior rights of the Surety:

1. Terminate employment of the Contractor;

2. Take possession of the Project site, materials, equipment, tools, appliances, and construction equipment and machinery owned by the Contractor;

3. Accept assignment of Subcontractor Agreements pursuant to Article 4.4; and/or

4. Finish the Work by whatever method(s) the State may deem expeditious and appropriate.

When the State terminates the Contract for reasons provided in Article 2.3, the Contractor shall not be entitled to receive any further payment until Completion of the Work. If the costs incurred by the State because of termination under Article 2.3 exceed the unpaid balance, the Contractor shall pay the difference to the State.

2.4 TERMINATION FOR THE STATE'S CONVENIENCE

The State reserves the right to terminate this Contract or any part thereof, due to an Act of God or for its sole convenience. In the event of such termination, the Contractor shall immediately stop hereunder and shall immediately cause its Subcontractors, Sub-subcontractors and material suppliers at any tier, to immediately stop work, leaving the site in a safe and secured condition. The Contractor shall not be paid for any work performed or costs incurred after the termination date that could have been avoided.

The Contractor shall be paid in accordance with the provisions of Article 8.6; except that the amount due the Contractor shall be based upon the State's final estimate of the Work completed, or acceptable materials furnished but not used, to the date of suspension of the Work, less any amounts required to be withheld pursuant to Article 8.6, and less any prior payment(s) made to, or on the account of the Contractor.

2.5 SUSPENSION BY THE STATE FOR CONVENIENCE

The State may, by written notice, order the Contractor to suspend, delay or interrupt the Work, in whole or in part, for such period of time as the State may determine.

An adjustment may be claimed by the Contractor in accordance with Article 6 and Article 7 for changes in the Work, caused by a suspension, delay or interruption. No adjustment will be made to the extent:

1. that Contractor’s performance of the Work, is, was or would have been so suspended, delayed or interrupted by another cause for which the Contractor is responsible; or

2. that an equitable adjustment is made or denied under another provision of the Contract.

ARTICLE 3 – CONTRACTOR

3.1 REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY THE CONTRACTOR

The Contractor shall carefully study and compare the Contract Documents with each other and shall report to the State, in writing, any errors, inconsistencies or omissions discovered. If the Contractor performs any work knowing it involves a recognized error, inconsistency or omission in the Contract Documents, without such notice to the State the Contractor shall assume responsibility for such performance and shall bear the cost for correction.

The Contractor shall take field measurements and verify field conditions and shall compare such field measurements, conditions and other related information known to the Contractor with the Contract Documents before proceeding.

The Contractor shall promptly, and before such conditions are disturbed, notify the State in writing of:

1. Sub-surface or latent physical conditions at the site differing materially from those indicated, or

2. Unknown physical conditions at the site of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in this Contract.

3. Hazardous materials.

The State will promptly investigate the conditions, and if the State finds that such conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performance of any part of the Work, whether or not changed as a result of such conditions, a Change Order will be issued in accordance with Article 6.

3.2 SUPERVISION AND CONSTRUCTION PROCEDURES

The Contractor shall supervise and direct the Work. The Contractor shall be responsible for, and have control over, construction means, methods, techniques, sequences, procedures, safety precautions and programs in connection with the Work, and for coordinating the Work under the Contract; unless otherwise noted or specified in the Contract Documents.

The Contractor shall be responsible to the State for acts and omissions of the Contractor's employees, Subcontractors, Sub-subcontractors or material suppliers and their agents and employees, and other persons performing portions of the Work under a contract with the Contractor.

The Contractor shall be responsible for the actions or inaction of Subcontractors, Sub-subcontractors or material suppliers, at all tiers, regardless of whether they are a Disabled Veterans Business Enterprise (DVBE) firm or are stipulated suppliers or sole sourced. No claim, request for equitable adjustment or Change Order request shall be submitted to the State for any action of any Subcontractor, Sub-subcontractor or material supplier, at any tier, unless the Contractor can demonstrate that the State is the proximate cause of the change or delay alleged in such request.

The State will not accept any responsibility or liability for any action or inaction of any Subcontractor, Sub-subcontractor or material supplier, at any tier, except to the extent that the State is the proximate cause of the change or delay.

The Contractor shall not be relieved of obligations to perform the Work in accordance with the Contract Documents, either by activities or duties of the State, the State's administration of the Contract, or by tests, inspections or approvals required or performed by persons other than the Contractor.

The Contractor shall be responsible for inspections of portions of the Work already completed under the Contract to determine that such portions are in proper condition to receive subsequent work. If the Contractor determines that some work performed on the Project does not comply with the requirements of the Contract Documents, the Contractor shall repair or replace such defective work at the Contractor's sole expense.

Until Acceptance of the Work, the Contractor shall have the charge and care thereof, and shall bear risk of injury or damage to any part of the Work by action of the elements (except for an Act of God, or natural disaster as proclaimed by the State or Federal Government), or from any other reason except for such damages as are directly caused by acts of the Federal or State Government and the public enemy, except as provided in Article 8.5.

3.3 LABOR AND MATERIALS

Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation, and other facilities and services necessary for proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work. Materials, articles and equipment furnished by the Contractor for incorporation into the Work shall be new unless otherwise specified in the Contract Documents.

Hours of Labor: Workers are limited and restricted to 8 hours during any one calendar day, and 40 hours during any one calendar week except that pursuant to Labor Code (LC) § 1813 & §1815, any work performed in excess of 8 hours per day and 40 hours during any one week, shall be permitted upon compensation for hours worked in excess of 8 hours per day at not less than 1-1/2 times the basic rate of pay. The Contractor shall pay the State $25 as a penalty for each worker for each calendar day worked in violation of the above limitations and restrictions.

Prevailing Wage: The Contractor shall comply with LC, § 1774 and §1775. Pursuant to § 1774, the Contractor and any subcontractors, regardless of tier, shall pay not less than the specified prevailing wage rates to all workers employed in the execution of the Contract. In accordance with LC § 1775, the Contractor and any subcontractor under the Contractor shall forfeit to the State not more than $50 for each calendar day, or portion thereof, for each worker paid less than the prevailing wage rates for the work or craft, in which the worker is employed for any work executed under the Contract by the Contractor or by any subcontractor in violation of the provisions of the Labor Code; and, in particular, LC, § 1770 to §1780, inclusive. In addition to such forfeiture, the difference between such stipulated prevailing wage rates and the amount paid to each worker for each day, or portion thereof, shall be paid to each underpaid worker by the Contractor or subcontractor. This provision shall not apply to properly registered apprentices.

1. Pursuant to LC, § 1770, the Director of the Department of Industrial Relations(DIR) has ascertained the general prevailing rate of per diem wages and a general prevailing rate for legal holiday and overtime work for each craft required for execution of the Contract. The Contractor shall obtain copies of the prevailing rate of per diem wages from the Department of Industrial Relations, Division of Labor Statistics & Research, PO Box 420603, San Francisco, CA 94142-0603, (415) 703-4780; or wage rates may be accessed on the internet at http://www.dir.ca.gov/DLSR/statistics_research.html.The Contractor is responsible to read, understand and comply with all the guidelines, including the fine print in the prevailing wage determinations; and shall post a copy of the prevailing wage rates, specific to the Project, at the Project site.

2. Wage rates set forth are the minimum that may be paid by the Contractor. Nothing herein shall be construed as preventing the Contractor from paying more than the minimum rates set. No extra compensation will be allowed by the State due to the inability of the Contractor to hire labor at minimum rates, nor for necessity for payment by the Contractor of subsistence, travel time, overtime, or other added compensations, all of which possibilities are elements to be considered and ascertained to the Contractor's own satisfaction in preparing the Bid Form.

3. If it becomes necessary to employ crafts other than those listed in the General Prevailing Wage Rate booklet, the Contractor shall contact the Division of Labor Statistics and Research as noted above. The rates thus determined shall be applicable as minimum for the contract and incorporated in the bid. When the wage determination shows an expiration date (noted by a double asterisk**), to expire during the term of the contract, the Contractor must call or write the DIR to obtain the new rates and incorporate them in the bid to be applicable for the term of the contract.

4. The Contractor and each subcontractor, regardless of tier, shall keep an accurate payroll record showing the names, addresses, social security numbers, work classifications, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by the Contractor and/or subcontractor in connection with the Work.

5. Payroll records shall be certified and shall be on forms provided by the Division of Labor Standards Enforcement, or shall contain the same information as those forms. The Contractor's and subcontractor's certified payroll records for each employee shall be submitted with each payment request, covering the period of the payment request.

Travel and Subsistence Payments: The Contractor shall pay travel and subsistence payments to persons required to execute the Work as such travel and subsistence payments are defined in applicable collective bargaining agreements filed with the DIR, pursuant to LC, § 1773.1 and §1773.9.

Apprentices: Properly registered apprentices may be employed in the execution of the Work. Every apprentice shall be paid the standard wage paid to apprentices under the regulations of the craft or trade at which the apprentice is employed, and shall be employed only at the work of the craft or trade to which the apprentice is registered.

The Contractor and each Subcontractor shall comply with the requirements of LC, §1777.5, and any related regulations regarding the employment of registered apprentices.

3.4 NONDISCRIMINATION CLAUSE

Contract Specifications:

1. Administrator: The Administrator, Office of Compliance Programs (OCP), California Department of Fair Employment and Housing (DFEH), or any person to whom the Administrator delegates authority.

2. Minority includes:

a) Black (all persons having primary origins in any of the Black racial groups of Africa, but not of Hispanic origin); or

b) Hispanic (all persons of primary culture or origin in Mexico, Puerto Rico, Cuba, Central or South America, or other Spanish derived culture or origin regardless of race); or

c) Asian/Pacific Islander (all persons having primary origins in any of the original peoples of the Far East, Southeast Asia, the Indian Subcontinent or the Pacific Islands); or

d) American Indian/Alaskan Native (all persons having primary origins in any of the original peoples of North America and who maintain culture identification through tribal affiliation or community recognition).

Whenever the Contractor or any Subcontractor subcontracts a portion of the Work, it shall physically include in each subcontract of $5,000 or more, the Nondiscrimination Clause in the Contract directly or through incorporation by reference. Any subcontract for work involving a construction trade shall also include the Standard California Construction Contract Specifications, either directly or through incorporation by reference.

The Contractor shall implement the specific nondiscrimination standards provided in Article 3.4.

Neither the provisions of any collective bargaining agreement, nor the failure by a union with whom the Contractor has a collective bargaining agreement, to refer either minorities and/or women shall excuse the Contractor's obligations under these specifications, Government Code(GC), § 12990, or the regulations promulgated pursuant thereto.

In order for the nonworking training hours of apprentices and trainees to be counted, such apprentices and trainees shall be employed by the Contractor during the training period, and the Contractor shall have made a commitment to employ the apprentices and trainees upon the completion of their training, subject to the availability of employment opportunities. Trainees shall be trained pursuant to training programs approved by the U.S. Department of Labor or the DIR.

The Contractor shall take specific actions to implement the Contractor's nondiscrimination program. The evaluation of the Contractor's compliance with these specifications shall be based upon the Contractor's effort to achieve maximum results from the Contractor's actions. The Contractor shall be able to demonstrate fully the Contractor's efforts under Steps 1. through 5. below:

1. Ensure and maintain a working environment free of harassment, intimidation, and coercion at all sites and at all facilities at which the Contractor's employees are assigned to work. The Contractor, whenever possible, shall assign two or more women to each construction project. The Contractor shall specifically ensure that all leadsperson’s, superintendents, and other on-site supervisory personnel are aware of and carry out the Contractor's obligations to maintain such a working environment, with specific attention to minority and/or female individuals working at such sites or in such facilities.

2. Provide written notification within 7 days to the Director of DFEH when the union(s) with which the Contractor has a collective bargaining agreement(s) has not referred to the Contractor a minority person and/or woman sent by the Contractor, or when the Contractor has other information that the union(s) referral process has impeded the Contractor's efforts to meet the Contractor's obligations.

3. Disseminate the Contractor's equal employment opportunity policy by providing notice of the policy to unions and training, recruitment and outreach programs and requesting their cooperation in assisting the Contractor to meet the Contractor's obligations; and by posting the company policy on bulletin boards accessible to all employees at each location where construction work is performed.

4. Ensure all personnel making management and employment decisions regarding hiring, assignment, layoff, termination, conditions of work, training, rates of pay or other employment decisions, including all supervisory personnel, superintendents, general lead persons, on-site lead persons, etc., are aware of the Contractor's equal employment opportunity policy and obligations, and discharge their responsibilities accordingly.

5. Ensure that seniority practices, job classifications, work assignments and other personnel practices, do not have a discriminatory effect by continually monitoring all personnel and employment related activities to ensure that the equal employment opportunity policy and the Contractor's obligations under these specifications are being carried out.

Contractors are encouraged to participate in voluntary associations which assist in fulfilling their equal employment opportunity obligations. The efforts of a contractor association, joint contractor-union, contractor-community, or other similar group of which the Contractor is a member and participant, may be asserted as fulfilling any one or more of the Contractor's obligations under these specifications provided that the Contractor actively participates in the group, makes every effort to assure that the group has a positive impact on the employment of minorities and women in the industry, ensures that the concrete benefits of the program are reflected in the Contractor's minority and female work-force participation, and can provide access to documentation which demonstrates the effectiveness of actions taken on behalf of the Contractor. It is the Contractor's obligation to comply.

The Contractor is required to provide equal employment opportunity for all minority groups, both male and female, and all women, both minority and non-minority. Consequently, the Contractor may be in violation of the Fair Employment and Housing Act (GC, § 12990 et seq.) if a particular group is employed in a substantially disparate manner.

Establishment and implementation of a bona fide affirmative action plan pursuant to § 8104(b) of Title 2, California Code of Regulations (CCR), shall create a rebuttable presumption that the Contractor is in compliance with the requirements of GC, § 12990, and its implementing regulations.

The Contractor shall not use the nondiscrimination standards to discriminate, harass or allow harassment against any person because of race, color, religion, sex, national origin, ancestry, physical disability (including HIV and AIDS), mental disability, medical condition (cancer), marital status, or age over 40, denial of family and denial of family care leave.

The Contractor shall not enter into any subcontract with any person or firm decertified from State contracts pursuant to GC, § 12990.

The Contractor shall carry out such sanctions and penalties for violation of these specifications and the Nondiscrimination Clause, including suspension, termination and cancellation of existing subcontracts as may be imposed or ordered pursuant to GC, § 12990 and its implementing regulations by the awarding agency. Any Contractor who fails to carry out such sanctions and penalties shall be in violation of these specifications and GC, § 12990.

The Contractor shall designate a responsible official to monitor all employment-related activity to ensure that the company's equal employment opportunity policy is being carried out, to submit reports relating to the provisions herein as may be required by OCP, and to keep records. Records shall at least include for each employee the name, address, telephone number, construction trade, union affiliation, if any, employee identification number when assigned, social security number, race, sex, status (e.g., mechanic, apprentice trainee, helper or laborer), dates of changes in status, hours worked per week in the indicated trade, rate of pay, and locations at which the work is performed. Records shall be maintained in any easily understandable and retrievable form; however, to the degree that existing records satisfy this requirement, the Contractor shall not be required to maintain separate records.

3.5 GUARANTEE

The Contractor unconditionally guarantees the Work will be completed in accordance with the requirements of the Contract Documents, and will remain free of defects in workmanship and materials for a period of 1 year from the date of Completion of the Work of the Project, unless a longer guarantee period is specifically called for in the Contract Documents. The Contractor shall repair or replace work, or adjacent work, or both, that may have been damaged or displaced, which was not in accordance with the requirements of the Contract Documents, or that may be defective in its workmanship or material within the guarantee period specified in the Contract Documents, without any expense whatsoever to the State; ordinary wear and tear and abuse excepted.

The Contractor further agrees, within 14 days after being notified in writing by the State, of work not in accordance with the requirements of the Contract Documents or defects in the Work, that the Contractor shall commence and execute, with due diligence, work necessary to fulfill the terms of the guarantee. If the State finds that the Contractor fails to perform the work under the guarantee, the State will proceed to have the work completed at the Contractor's expense and the Contractor will pay costs of the work upon demand. The State will be entitled to all costs, including attorney's fees necessarily incurred upon the Contractor's refusal to pay the above costs.

Notwithstanding the foregoing Subparagraph, in the event of an emergency constituting an immediate hazard to health or safety of State employees, property, or licensees, the State may undertake, at the Contractor's expense and without prior notice, work necessary to correct such hazardous condition(s) when it is caused by work of the Contractor not being in accordance with the requirements of the Contract Documents.

3.6 TAXES:

The Contractor shall pay all applicable taxes for the Work, or portions thereof provided by the Contractor, which were legally enacted as of the bid date, whether or not yet effective or merely scheduled to go into effect.

3.7 PERMITS, FEES AND NOTICES

The Contractor shall secure and pay for required permits, governmental fees, licenses and inspections necessary to complete the Work, unless otherwise provided in the Contract Documents.

The Contractor shall comply with and give notices required by laws, ordinances, rules, regulations and lawful orders of public authorities bearing on the performance of the Work.

If the Contractor observes that portions of the Contract Documents are at variance with applicable laws, statutes, ordinances, building codes, and rules and regulations, the Contractor shall promptly notify the State in writing. If the Contractor performs work known to be contrary, or should have known to be contrary to laws, statutes, ordinances, building codes, and rules and regulations without prior notice to the State, the Contractor shall assume full responsibility for the Work and shall bear the attributable costs.

The Contractor is not subject to municipal, county, or district laws, rules, or regulations pertaining to building permits or regulating the design or construction of buildings upon State property, except as specified in the Contract Documents.

The Contractor may be subject to federal, state, municipal, county, local or district laws, rules, or regulations pertaining to off-site work, such as utility connections, fire protection systems and encroachment upon federal, state, private, city or county property, including, but not limited to storm water pollution prevention plans.

All construction work shall comply with CCR, Title 24, California Building Standards Code (CBSC), and other Applicable Codes, current edition, as of the bid date or as specified in the Specifications.

3.8 ALLOWANCES

The Contractor shall include in the Contract Sum, Allowances in accordance with the requirements of the Specifications.

3.9 SUPERINTENDENT

The Contractor shall employ a competent Superintendent and assistants who shall be in attendance at the Project site during performance of the Work. The Superintendent, or the Contractor’s duly appointed representative, shall be the person in charge of the construction of the Work and shall represent the Contractor. Communications given to the Superintendent shall be as binding as if given directly to the Contractor. All communications shall be confirmed in writing by the Contractor. Should the State deem the Superintendent to be incompetent, the State has the authority to request the Contractor to replace this person.

Should the Contractor decide to replace the Superintendent, the Contractor shall notify the State in writing, no fewer than 14 calendar days prior to the replacement. The Contractor shall submit the name and resume of the new Superintendent with the letter.

At any other time when the Superintendent is absent from the Project site because no Work is being performed, the Superintendent shall nevertheless keep the State advised of the Superintendent's whereabouts so that the Superintendent may readily be reached and available for consultation at the Project site at any time.

3.10 CONTRACTOR'S PROGRESS SCHEDULE

Within the time frame specified in the specifications and prior to the first payment request, the Contractor shall submit to the State a Progress Schedule, including submittal schedules, prepared in accordance with the Specifications, Division 01. The Progress Schedule shall show the order in which the Contractor proposes to execute the Work, dates on which the Contractor will start each major subdivision of the Work, and projected dates of completion of each such subdivision in accordance with the requirements of the Contract Documents. The Contractor shall submit adjusted Progress Schedules, including submittal schedules, to reflect changed conditions in accordance with the requirements of the Contract Documents with each payment request.

The Contractor shall, unless otherwise specified in the Contract Documents, or directed by the State in writing, show in the schedule that physical construction of the Work will start within 10 calendar days of the start date stipulated in the Notice to Proceed, and show execution to Completion, in accordance with the specified schedule, subject to adjustment in accordance with the requirements of the Contract Documents.

The Contractor shall provide an adequate work force, materials of proper quality, and equipment to properly execute the Work and to ensure completion of each part in accordance with the Progress Schedule and within the Contract Time specified.

The Contractor shall submit to the State a Schedule of Values consistent with the Progress Schedule and Article 8. The Schedule of Values will be used as a basis for payment in accordance with Article 8.

The State's review and acceptance of the Progress Schedule is for compliance with the requirements of the Contract…