About this file

Amend 3

View the file

Other files

File Type Posted
Amendment 04 Documents.doc DOC document
Amendment 02.zip ZIP file
Attendee's List.pdf PDF
Division 2 Spec Sections.zip ZIP file
Amend01.doc DOC document
Division 1 Spec Sections.zip ZIP file
PreBid Conference and RFIs.docx DOCX document
DOCUMENTS SUMMARY.docx DOCX document
NDA.doc DOC document
0010 8a.zip ZIP file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTINUATION OF SF 30: AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

GS11P10MMC0010, RECOVERY

Amendment No. 2

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE

GS11P10MMC0010

PAGE OF

PAGES

2. AMENDMENT/MODIFICATION NO.

Amendment 03

3. EFFECTIVE DATE

08/06/2010

REQUISITION/PURCHASE REQ. NO.

PROJECT NO. (If applicable)

6. ISSUED BY
CODE
MM000
7. ADMINISTERED BY (If other than Item 6)
CODE
MM000

GSA, NCR, PBS,

Campus Development Team (WP) 301 7th Street, SW Room 4606 Washington, DC 20407

GSA, NCR, PBS,

Campus Development Team (WP)

301 7th Street, SW Room 4606

Washington, DC 20407

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

9.A. AMENDMENT OF SOLICITATION NO.

(X)
GS11P10MMC0010 RECOVERY

To All Prospective Offerors

9B. DATED (SEE ITEM 11)

07/16/2010

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE
FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers FORMCHECKBOX is extended, FORMCHECKBOX is not extended

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning. copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegraph which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS

IT MODIFIES THE CONTRACT/ORDER NO. DESCRIBED IN ITEM 14.

(x)
A.

THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

c.

THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D.

OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor FORMCHECKBOX is not FORMCHECKBOX is required to sign this document and return ________ copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible).

The solicitation is hereby amended as follows:

The following changes, clarifications, additions and supplements are hereby incorporated into this SOLICITATION in their entirety as submitted. Continued on Page 2 of this Amendment

Except as provided herein, all terms and conditions of the document reference in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print) Bonnie Echoles, Contracting Officer

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED
16B. UNITED STATES OF AMERICA

BY

Bonnie Echoles .

(Signature of Contracting Officer)

16C. DATE SIGNED

08/06/2010

NSN 7540-01-152-8070

PREVIOUS EDITION UNUSABLE

30-105

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

COMPETITION IS LIMITED TO ELIGIBLE 8(A) FIRMS REGISTERED AND CERTIFIED BY THE U.S. SMALL BUSINESS ADMINISTRATION.

RECOVERY: GS11P10MMC0010, SELECTIVE DEMOLITION AND ABATEMENT OF BUILDINGS 31, 33, 34, 37, 49, 52, 21, 77, 78, 70 & 71, ST. ELIZABETHS WEST CAMPUS CONSOLIDATION PROGRAM, Washington, DC

ITEM A:

THE PROPOSAL RECEIPT is UNCHANGED as follows:

AUGUST 16, 2010 by 2:00 PM, EST. Place of receipt as follows:

GSA, NCR, ROB – Bid Room 301 7th Street, SW, Room 1065 Washington, DC 20407 Phone: (202)708-5961

ITEM B:

Section I.C Period of Performance is hereby modified as follows:

I.C Period of Performance

I.C.1 Commencement. The Contractor shall commence performance of the Work within 10 days after the Contractor receives the Notice to Proceed (NTP).

Contractor shall have 90 calendar days from the NTP to complete the project.

I.C.2 Substantial Completion. The Contractor shall achieve Substantial Completion of the Work, as that term is defined in this Agreement, in buildings 31, 33, 34 and 37 no later than 45 calendar days from issuance of Notice to Proceed (NTP) and buildings 49, 52, 21, 77, 78, 70 & 71 no later than 90 calendar days from issuance of Notice to Proceed (NTP).

I.C.3 Contract Completion. The Contractor shall achieve Contract Completion, as the term is defined in this Agreement, within 30 calendar days of Substantial Completion.

ITEM C:

E-Verify and Executive Order 12989 Amendment

On June 11, 2008, President George W. Bush amended Executive Order 12989 to direct all executive departments and agencies to require contractors to electronically verify employment authorization of employees, new and existing, performing work under qualifying federal contracts.

U.S. law requires companies to employ only individuals who may legally work in the United States – either U.S. citizens, or foreign citizens who have the necessary authorization. This diverse workforce contributes greatly to the vibrancy and strength of our economy, but that same strength also attracts unauthorized employment.

E-Verify is an Internet-based system that allows businesses to determine the eligibility of their employees to work in the United States. E-Verify is fast, free and easy to use – and it’s the best way employers can ensure a legal workforce.

The attached clause – FAR 52.222-54 – Employment Eligibility Verification (JAN 2009) is hereby included and incorporated into this RFP:

ITEM D:

The attached Demo & Abatement RFI Log 1 is hereby included and incorporated in its entirety in this solicitation.

ITEM E:

Bidders must acknowledge receipt of this amendment on bid form, giving number and date.

Attachments:

FAR 52.222-54 - Employment Eligibility Verification (Jan 2009)

Demo & Abatement RFI Log 1

END OF AMENDMENT NO. THREE (3)

FAR 52.222-54 - Employment Eligibility Verification (Jan 2009)

(a) Definitions. As used in this clause—

“Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply that is—

(i) A commercial item (as defined in paragraph (1) of the definition at 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 (46 U.S.C. App. 1702), such as agricultural products and petroleum products. Per 46 CFR 525.1 (c)(2), “bulk cargo” means cargo that is loaded and carried in bulk onboard ship without mark or count, in a loose unpackaged form, having homogenous characteristics. Bulk cargo loaded into intermodal equipment, except LASH or Seabee barges, is subject to mark and count and, therefore, ceases to be bulk cargo.

“Employee assigned to the contract” means an employee who was hired after November 6, 1986, who is directly performing work, in the United States, under a contract that is required to include the clause prescribed at 22.1803. An employee is not considered to be directly performing work under a contract if the employee—

(1) Normally performs support work, such as indirect or overhead functions; and

(2) Does not perform any substantial duties applicable to the contract.

“Subcontract” means any contract, as defined in 2.101, entered into by a subcontractor to furnish supplies or services for performance of a prime contract or a subcontract. It includes but is not limited to purchase orders, and changes and modifications to purchase orders.

“Subcontractor” means any supplier, distributor, vendor, or firm that furnishes supplies or services to or for a prime Contractor or another subcontractor.

“United States”, as defined in 8 U.S.C. 1101(a)(38), means the 50 States, the District of Columbia, Puerto Rico, Guam, and the U.S. Virgin Islands.

(b) Enrollment and verification requirements.

(1) If the Contractor is not enrolled as a Federal Contractor in E-Verify at time of contract award, the Contractor shall—

(i) Enroll. Enroll as a Federal Contractor in the E-Verify program within 30 calendar days of contract award;

(ii) Verify all new employees. Within 90 calendar days of enrollment in the E-Verify program, begin to use E-Verify to initiate verification of employment eligibility of all new hires of the Contractor, who are working in the United States, whether or not assigned to the contract, within 3 business days after the date of hire (but see paragraph (b)(3) of this section); and

(iii) Verify employees assigned to the contract. For each employee assigned to the contract, initiate verification within 90 calendar days after date of enrollment or within 30 calendar days of the employee’s assignment to the contract, whichever date is later (but see paragraph (b)(4) of this section).

(2) If the Contractor is enrolled as a Federal Contractor in E-Verify at time of contract award, the Contractor shall use E-Verify to initiate verification of employment eligibility of—

(i) All new employees.

(A) Enrolled 90 calendar days or more. The Contractor shall initiate verification of all new hires of the Contractor, who are working in the United States, whether or not assigned to the contract, within 3 business days after the date of hire (but see paragraph (b)(3) of this section); or

(B) Enrolled less than 90 calendar days. Within 90 calendar days after enrollment as a Federal Contractor in E-Verify, the Contractor shall initiate verification of all new hires of the Contractor, who are working in the United States, whether or not assigned to the contract, within 3 business days after the date of hire (but see paragraph (b)(3) of this section); or

(ii) Employees assigned to the contract. For each employee assigned to the contract, the Contractor shall initiate verification within 90 calendar days after date of contract award or within 30 days after assignment to the contract, whichever date is later (but see paragraph (b)(4) of this section).

(3) If the Contractor is an institution of higher education (as defined at 20 U.S.C. 1001(a)); a State or local government or the government of a Federally recognized Indian tribe; or a surety performing under a takeover agreement entered into with a Federal agency pursuant to a performance bond, the Contractor may choose to verify only employees assigned to the contract, whether existing employees or new hires. The Contractor shall follow the applicable verification requirements at (b)(1) or (b)(2) respectively, except that any requirement for verification of new employees applies only to new employees assigned to the contract.

(4) Option to verify employment eligibility of all employees. The Contractor may elect to verify all existing employees hired after November 6, 1986, rather than just those employees assigned to the contract. The Contractor shall initiate verification for each existing employee working in the United States who was hired after November 6, 1986, within 180 calendar days of—

(i) Enrollment in the E-Verify program; or

(ii) Notification to E-Verify Operations of the Contractor’s decision to exercise this option, using the contact information provided in the E-Verify program Memorandum of Understanding (MOU).

(5) The Contractor shall comply, for the period of performance of this contract, with the requirements of the E-Verify program MOU.

(i) The Department of Homeland Security (DHS) or the Social Security Administration (SSA) may terminate the Contractor’s MOU and deny access to the E-Verify system in accordance with the terms of the MOU. In such case, the Contractor will be referred to a suspension or debarment official.

(ii) During the period between termination of the MOU and a decision by the suspension or debarment official whether to suspend or debar, the Contractor is excused from its obligations under paragraph (b) of this clause. If the suspension or debarment official determines not to suspend or debar the Contractor, then the Contractor must reenroll in E-Verify.

(c) Web site. Information on registration for and use of the E-Verify program can be obtained via the Internet at the Department of Homeland Security Web site: http://www.dhs.

HYPERLINK "http://www.dhs.gov/E-Verify"gov/E-Verify.

(d) Individuals previously verified. The Contractor is not required by this clause to perform additional employment verification using E-Verify for any employee—

(1) Whose employment eligibility was previously verified by the Contractor through the E-Verify program;

(2) Who has been granted and holds an active U.S. Government security clearance for access to confidential, secret, or top secret information in accordance with the National Industrial Security Program Operating Manual; or

(3) Who has undergone a completed background investigation and been issued credentials pursuant to Homeland Security Presidential Directive (HSPD)-12, Policy for a Common Identification Standard for Federal Employees and Contractors.

(e) Subcontracts. The Contractor shall include the requirements of this clause, including this paragraph (e) (appropriately modified for identification of the parties), in each subcontract that—

(1) Is for—

(i) Commercial or noncommercial services (except for commercial services that are part of the purchase of a COTS item (or an item that would be a COTS item, but for minor modifications), performed by the COTS provider, and are normally provided for that COTS item); or

(ii) Construction;

(2) Has a value of more than $3,000; and

(3) Includes work performed in the United States. (End of clause)

8/6/2010
Selective Demolition and Abatement RFI Log 1
Solicitation No. GS11P10MMC0010
Question
Response
1
Specification Section 111321 - Scissors Dock Lifts Will a forklifts be used on this scissors lift?
This question is not applicable to this project.
2
Section 111321 2.3 G. is calling for a 12" deep X 96" wide bridge. Is this bridge for transition or for unloading trucks? The bridge is to wide for offloading trucks.
This question is not applicable to this project.
3
Could you please furnish the building sizes for buildings 70,71,77 and 78.

Also, per the revised scope of work, option #8 is supposed to be the cost for the complete abatement of asbestos containing roofing materials on buildings 21,71, 77 and 78. Per the hazardous material survey report, the roof of building 21 was not surveyed for asbestos at the government’s request, neither is the amount of asbestos containing roofing material given.

For buildings 71, 77 and 78 please scale the AD series drawings. For building 70 refer to the drawings in the Hazmat report and scale.

There is not an Option #8 in the solicitation and amendments. We believe you are actually referring to Option #3. If this is the case, bidders should assume the entire roof of building 21 is covered in asbestos containing roof materials.

4
Does the government intend that all substrates to remain will be abated free of

lead base paint?

Yes. All work must be performed in accordance with the project documents issued in the solicitation and amendments.

All windows are excluded. It is expected that the lead based paint will remain at the windows.