A/E SCOPE OF WORK
02/25/2016
PROJECT:
Truck Exit Lane Paving and Pothole Repairs
LOCATION:
Lynden Land Port of Entry
Lynden, Washington I. Project Scope: Work includes, but is not restricted to, the following items:
A.
Remove asphalt paving in truck lane and replace with new (see Sketch 1). Remove existing asphalt down to crushed surfacing top course. Provide additional top course material and compact in preparation for new asphalt. New asphalt shall conform to Detail 2/C1, Section – Roadway & Parking Area.
B.
Provide eight (8) asphalt patches (see Sketch 1). Remove 3 foot by 3 foot section of existing asphalt down to crushed surfacing top course. Compact top course and provide patch to conform to Detail 2/C1, Section – Roadway & Parking Area. Note – exact locations will be located with paint by GSA.
II. Project Schedule: The LPOE is open and operational 7 days a week from 6:00 AM – 12:00 Mid-Night. All on-site Work shall be performed between 12:00 Mid-Night and 6:00 AM. The entire LPOE must be fully available for operation by 6:00 AM each day.
Truck Exit Lane Paving & Pothole Repairs