- Replace air-cooled chiller, Carson City FB Federal contract opportunity
- Solicitation number
- GS-09P-09-KSC-0049
About this file
Amendment 1 - adds requirement for electrical assessment of chiller # 2, and clarifies bid bond requirement.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| GS09P09KSC0049 Amendment 2.pdf | ||
| GS09P09KSC0049 SOLICITATION.PDF | ||
| GS09P09KSC0049 CC CHILLER DAVIS-BACON.txt | TXT text file | |
| Document Security Agreement.doc | DOC document | |
| Chiller Replacement Summary and Intent.pdf | ||
| PBS Order 3490.1 - Bldg Doc Security.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATiON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED
(SEE
ITEM
11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
| IDCode: |
| EffDate: MAR 31, 2009 |
| ReqNo: 9PM-06-2038 |
| ProjNo: |
| IssuedBy: GSA, PBS, REAL PROPERTY PROGRAMS |
TECHNICAL SECTION, 9PM-FT
450 GOLDEN GATE AVE, 4TH FLOOR EAST
SAN FRANCISCO CA 94102
AdminBy: GSA, FACILITIES MGT & SVCS PROGRAMS DIV
450 GOLDEN GATE AVE, 4TH FL EAST (9PME)
SAN FRANCISCO CA 94102
| NoCopies: |
| Amended: Yes |
| ChgeOrder: |
| Modify: Off |
| SuppAuth: |
| OthrSpec: |
| Require: Off |
| Copies: |
| Descript: FB & USPO, CARSON CITY, ROOFTOP CHILLER REPLACEMENT (RCA00021) |
Requirement is added for Contractor to provide an analysis and letter report assessing whether chiller #2 (the chiller not replaced by this project) meets Maximum Overload Protection (MOP) requirements. Electrical work to improve electrical service to chiller #2 is NOT included in this contract, but may at the discretion of GSA be subsequently added for a negotiated price adjustment.
Clause 52.228-1 "Bid Guarantee" omitted the required percentage of bid price for bid bonds. Bid bonds must be submitted for 20% of the offeror's bid price. Offerors may use either Standard Form 24, or an alternative form that provides the same assurance as SF 24.
| SignName: |
| SignTitl: |
| ContDate: |
| CODate: |
| OffrExt: Off |
| OffrNoEx: No |
| ChgeOrd: Off |
| SuppAgre: Off |
| ModOthr: Off |
| NoReq: Off |
| ContractorCode: |
| FacCode: |
| ContractorPOC: |
| AwdChg: Off |
| SolChg: Yes |
| SolNo: GS-09P-09-KS-C-0049 |
| SolDate: MAR 05, 2009 |
| AwdNo: |
| IssuedByCode: 9PM-FT |
| AdminByCode: 9PME |
| ContrOfficerInfo: |
| DocNo: 01 |
| AwdDate: |
| text1: 10B. DATED (SEE ITEM 13) |
| block 14: 14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.) |
| pageblock: PAGE OF PAGES |
| block13: 13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14. |
| Contractor: |
| ContratorInfo: |
| ModAmount: |