VMO00166_SF30_Amend3_pgs4.pdf

PDF 230 KB Posted

Attached to
VMO00166 R6_RAY Bldg_DB Seismic Retrofit Federal contract opportunity
Solicitation number
GS-06P-15-GZ-C-002
Issued by
General Services Administration Public Buildings Service Region 6

About this file

VMO00166 AMEND 3_pgs4

View the file

Other files for this federal contract opportunity

Other files attached to VMO00166 R6_RAY Bldg_DB Seismic Retrofit, newest first.
File Type Posted
VMO00166_Phase_2_Notification.pdf PDF
AMEND_4_Phase_1.pdf PDF
VMO00166_Amend_2_General_Notice.pdf PDF
VMO00166_Amend_1_Phase_1_SF30.pdf PDF
VMO00166_SOW_Phase_1_FINAL_2015.01.13.pdf PDF
VMO00166_Questionnaire_Phase_1_FINAL_2015.01.13.pdf PDF
C301_Dec_2014.pdf PDF
VMO00166_DB_Phase_I_solicitation_FBO_2015.01.13.pdf PDF
VMO00166_Pre_Solicitation_Synopsis_2014.12.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CONTRACT ID CODE PAGE OF PAGES

AMENDMENT OF SOLICITATION 1 | 4

2. AMENDMENT NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If Applicable)

3 VMO00166

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

General Services Administration, PBS Acquisition Management Division 1500 E. Bannister Road 6PQW Kansas City, MO 64131-3009 For information contact:

Audra Harrison 816 823 2591

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.

X 9B. DATED (SEE ITEM 11)

Seismic Renovation Robert A. Young Federal Building 10A. MODIFICATION OF CONTRACT/ORDER

1222 Spruce Street NO.

St. Louis, MO

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, x is not ex-tended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDG-

MENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT

IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CON-

TRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b)

C. THIS SUPPLEMENT AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT (Organized by UCP section headings, including solicitation/contract subject matter where feasible.)

See Attached supplement to Amend 3.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Michael Flanigan

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (Rev. 10-83)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

FAR (48 CFR) 53.243

02/03/15

GS-06P-15-GZ-C-002

1/14/2015

3:00pm 02/18/15

Robert A. Young Federal Building Seismic Renovation

GS-06P-15-GZ-C-0002

VMO00166

Supplement to Amendment 3

February 3, 2015

GENERAL QUESTIONS

1. What is the RFP time for Phase 2?

ANSWER: 90 days

2. Would you consider accepting electronic proposals?

ANSWER: We considered it and had to decide against it due to the current Phased Move of R6 GSA Headquarters and the file size structure would be too big to ensure proper electronic delivery.

3. Will Site visits be allowed?

ANSWER: During Phase 2 site visits will be allowed.

4. Is there an existing set of structural drawings, and can these be made available to Offerors during the phase 1 proposal period?

ANSWER: Existing structural drawings will be provided in Phase 2.

5. Is there an existing/recent geotechnical investigation of the site, and can the findings be made available to Offerors during the phase 1 proposal period?

ANSWER: The geotechnical report will be provided in Phase 2.

6. Can the seismic evaluation report on the structure be made available to Offerors during the phase 1 proposal period?

ANSWER: The Seismic study will be provided in Phase 2.

7. The Scope of Work document mentioned some items that are in the appendix and a BIM model, can these be made available to Offerors during the phase 1 proposal period?

ANSWER: The BIM model will be provided in Phase 2.

8. In several instances, the Phase 1 Solicitation SOW references the "Appendix" (see attached for examples). Is the Appendix available for review at this time? Or, will the Appendix only be issued to those contractors who are short listed for the Phase 2 solicitation.

ANSWER: During Phase 2 the appendix will be provided.

SOLICITATION CLARIFICATIONS:

9. Are Offerors required to submit a SF 1442 with the phase 1 proposal?

ANSWER: Yes, There is no price associated with Phase 1, however the 1442 provides for amendment acknowledgement and formalizes the offerors Request for Qualifications (RFQ).

Robert A. Young Federal Building Seismic Renovation

GS-06P-15-GZ-C-0002

VMO00166

Supplement to Amendment 3

February 3, 2015

10. Is the Sensitive But Unclassified (SBU) Documents Request form required to be submitted with the phase 1 proposal (reference page 22 of 24 in the Phase I solicitation)?

ANSWER: No, this form is for the offeror to keep track of who they may disseminate SBU documents to during phase 1 RFQ. The offeror is required to update this form at the end of Phase 1 as the Government may request all SBU documents to be destroyed for those offerors not moving onto Phase 2.

11. Factor 3b in the Phase I solicitation states “Provide a list of all claims submitted by the Offeror’s member teams with the last five years. For each claim briefly describe the claim and the final resolution, if already resolved.” Please clarify if this requirement applies to the Offeror and design subcontractors, or just the Offeror. If design subcontractors are required to submit claims information, please confirm the design subcontractors may provide this information directly to GSA rather than in the Offeror’s proposal.

ANSWER: This requirement applies to the Offerors Team which is inclusive of the Design firm(s).

12. Factor 3a in the Phase I solicitation states "...the Offeror may submit projects that demonstrate the work of either the designer or constructor or both." Please verify that the total number of projects submitted in response to Factor 3a is (3), and can be any combination of designer or constructor projects.

ANSWER: Correct

13. On page 8 of the RFQ, Factors 2c and 2d appear to be asking for the same information. Factor 2c (second sentence) indicates that the "Offerors shall provide its means, methods, and processes used to manage clients, trade subcontractors, consultants, and other entities during Design Phase Services and Construction Phase Work." Factor 2d (first sentence) indicates that "Offerors shall provide a written narrative that describes its means, methods, and processes used to manage clients, trade subcontractors, consultants, and other entities." Our assumption is that this information should reside in Factor 2d (Coordination). Please confirm if this information should be provided only in Factor 2d, or in both sections as written.

ANSWER: Factor 2c asks for offerors to depict Resource Capacity and Factor 2d asks offerors to depict management/coordination of those resources.

14. Factor 3a of the proposal requires that we have one (1) reliable reference complete the Questionnaire for each project submitted in accordance with the Instructions for the Questionnaire. Regarding the Questionnaire Form itself, Page 2 indicates that the Company/Contractor and Project Name is to be "completed by the GSA". Since we are to send the Questionnaire directly to our customers, please confirm that this information is actually to be provided by the Offeror (prior to sending to the Evaluator) and not the GSA.

ANSWER: Page 2 of the Questionnaire 1. AND 2. Shall be completed by GSA. As offeror please fill in:

Name of Offeror:

Name of Contact:

Company:

ATTACHMENTS:

Pre Proposal Agenda from 1/22/15

Pre-Proposal Conference Agenda January 22, 2015 1:00 PM

Robert A. Young Federal Building Seismic Renovation GS-06P-15-GZ-C-002 Project Number VMO 00166

Disclaimer: Statements made during this conference do not change the term and conditions of the issued solicitation. An amendment will be issued at a later date to capture changes to the solicitation.

FAR Clause 52.215-1 Instructions to Offerors—Competitive Acquisition Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).

1. Introductions - Welcome CO, CS Attendance taken

2. Project Description and Scope of Work PM

3. Contract and Proposal Process CO, CS

Overview: This procurement is being conducted using the two phase selection process found in FAR 36.3. Qualification proposals will be evaluated in Phase 1 to determine which offerors will submit proposals for Phase 2. One contract will be awarded using competitive negotiation. In Phase 1, GSA will select a short list of the most highly qualified offerors and request that those offerors submit Phase 2 proposals. A maximum of 5 firms will be selected to submit Phase 2 proposals. Only those selected offerors are authorized to submit Phase 2 proposals. Those offerors not selected for participation in Phase 2 will be notified in accordance with FAR 15.503(a).

Proposals: Proposals shall consist of the following documents, completed and executed in accordance with this Phase 1 Solicitation:

(1) Technical Proposal VMO00166_Company name

(2) Other Documents as Required VMO00166_Company name

Proof of Registration in the System for Award Management (https://www.sam.gov) Proof of Bonding Capacity to $70,000,000.

Questionnaire-to be sent by reference

Evaluation: Proposals must address the technical approach, technical qualifications, and the other Phase 1 evaluation factors These factors are, in relative order of importance as follows :

Factor 1: Specialized Experience and Technical Competence.

Factor 2: Technical Approach.

Factor 3: Past Performance of Offeror’s Team

Questions: Contractors are to submit any questions in writing (via email) to the Project Team;

Project Manager, Matt Meeks (matthew.meeks@gsa.gov), Contracting Officer, Michael Flanigan (michael.flanigan@gsa.gov ) and Contracting Specialist, Audra Harrison (audra.harrison@gsa.gov) before close of business January 29, 2015. Questions must come through the prime contractor.

Amendments will be posted to FedBizOps as soon as questions are resolved.

Receipt of Qualification: In order to be considered for award, offers conforming to the requirements of the Solicitation must be received no later than 3:00 pm, (CST) February 18, 2015 at:

General Services Administration PBS Acquisition Management Division (6PQW) Attn: Michael Flanigan 1500 E. Bannister Road Kansas City, MO 64131

4. Questions GSA Team