Amendment 05 issued to incorporate RFIs-questions and answers, GSA Master Specification for the Fire Preventions and Protection in Construction and Demolition, GSA Security Vendor Training Manual and the Request For Proposal (RFP) Due Date remains Friday, July 21, 2017 at 3:00pm CST.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
Amendment 05 issued to incorporate questions and answers, GSA Master Specification for the Fire Preventions and Protection in Construction and Demolition, GSA Security Vendor Training Manual and the GSA Security Vendor Handout. (See Attached)
GSA PBS
Acquisition Management Division 230 S. Dearborn Street, Rm 3300 Chicago, IL 60604
9A. AMENDMENT OF SOLICITATION
NO.
GS-05-P-17-FB-C-0003
07/14/2017
9B. DATED (SEE ITEM 11)
06/06/2017 x x
INSTRUCTIONS
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contacting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Item 9, (Amendment of Solicitation No. - Dated), and 10, (Modification of Contract/Order No. - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries.
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g)
(h)
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
(1)
(2)
(3)
(4)
(5)
(6)
STANDARD FORM 30 (REV. 10-83) BACK
(1) Accounting classification Net increase $
VBA VARO – RFI
(Questions and Answers)
Solicitation # GS05P17FBC0003
VBA VARO
Amendment 05
VBA VARO – RFI (questions & answers)
Pinnacle Construction
1. Can anyone clarify the existing fire protection main elevation and the height to the bottom of the concrete deck above
Refer to RFI# 24 (Under Fredrick Construction).
floor to floor = 12’-10” Floor to bottom of beams = (varies) 11’-4” typical Ceiling will die into window’s top mullion at 9’-0”
MDG Enterprises
1. Is there a specified drywall partition cap for all the walls that meet the exterior window mullions?
Refer to details on AE501.
2. Do you have an actual product number for the Certain Teed Symphony F 2x2 ceiling tile?
Refer to the ceiling information on the finish schedule and specifications. - Certain Teed /
9/16" Elite Narrow Stab System (Grid) / Symphony f (Tile)
W.J. O'Neil Company
1. Electrical Specification section 260533, 3.2, A, states “thermostat” wall rough-ins are to be installed in a box with mud ring and extended into the ceiling cavity with 3/4” conduit.
a. Does this also apply to the temperature control space temperature sensors?
Yes. Temperature sensors, not thermostats are used on this project and the intent is that rough-ins be similarly provided. The requirements for these rough-ins are specified in 260533.3.2.A. (double gang extra deep box with single gang mud ring and ¾”C into the nearest accessible ceiling space). Specification 230900.3.5.B & 230950.3.1.G both indicate “All conduit, cable trays, raceways, wiring, accessories and wiring connections required for the installation of the Control System, and as herein specified, shall be provided by the Controls Contractor unless specifically shown on the Electrical Drawings”. These specifications further indicate that installation shall be in accordance with Division 26 (electrical specification) requirements. Since the electrical drawings do not show the rough-ins, responsibility for conduit associated with low voltage controls shall be assigned to the Controls Contractor. The Controls Contractor may choose to sub-contract conduit rough-in associated with his work to the Electrical Contractor.
2. The existing dampers at all shaft openings for both supply and return air are part of the buildings abandoned smoke control system. They are however, still connected to the pneumatic control system to keep them in an operational position. Demolition of the existing dampers/pneumatic system will cause all of the dampers on a respective floor to fail.
a. During construction phases, is the intent to rework the pneumatic lines on the dampers being removed to leave the remainder of the floor functional and then demo the pneumatic system once a floor is complete?
Yes. Existing controls need to remain active until last dependent phase is completed.
Ideally, when a phase of construction is complete, work in that area is also complete. If existing pneumatic lines are required to remain in place in a subsequent phase from current in order to retain functionality for future phases, then final demolition of pneumatic
Amendment 05 piping would need to occur upon completion of floor. This work would need to occur after hours through finished ceilings if necessary.
3. Is the Temperature Control contractor responsible for all 120v power circuits to their equipment and panels?
The intent is that the electrical contractor is responsible for providing line voltage electrical and the control contractor is responsible for low voltage. Circuiting and locations for all fans (VFDs) and electric heat are conveyed on electrical plans and panel schedules. Electrical plans also show circuiting to each of 2 secondary GUIs per floor.
Additional power that may be required for devices (terminal unit dampers, etc) is not reflected on electrical documents. Specification section 230900.3.5.A. (Electrical Wiring and Connection Installation) states: “It is the responsibility of the Controls Contractor to coordinate, integrate, and install all electrical wiring, connections, and power requirements for the control system”. Specification 230950.1.10. (Coordination) states “Coordinate supply of conditioned electrical circuits for control units and operator workstation”. The intent is that the control contractor shall coordinate power requirements regarding miscellaneous controls for the electrical contractor to provide 120 volt circuits wired to junction boxes from which the control contractor will transform and provide low voltage to devices. Specification 260533.3.2.B. implies electrical contractor coordination with low voltage system contractors.
4. Duct smoke detector and annunciator work, as well as the relocation of Fire Alarm conduits interfering with new ductwork, appear to only be shown on the mechanical drawings.
a. Due to licensing and certifications, will this work, and any other life safety work be performed by the electrical contractor?
In addition to mechanical plans, duct smoke detectors are shown on fire alarm plans (FA101, FA102, and FA103). Although Details 1 and 2 on mechanical drawing M501 do indicate smoke detector relocation and fire alarm conduit relocation, it is the intent that this work be performed by neither the mechanical nor the mechanical controls contractor.
Note J of detail 1 states “spot type duct detector must be relocated by a NICT certified alarm system authorized technician”. Smoke detectors, remote test stations, annunciator work, and wiring is to be provided by the Fire Alarm Contractor. Specification 283104.3.2.B indicates that all fire alarm cabling shall be installed in conduit.
Antler Construction
1. Takeform needs more information on the ethos product. Specifically: Message or letter quantity for the ethos product. Also for the ethos, the size, depth, material finish, mounting method and the mounting surface.
Size: 8" Hight Depth: .75" Material Finish: Solid aluminum, brushed clear Mounting Method: Stud flush Mounting Surface: Drywall
Gardiner C. Vose, Inc.
1. Regarding the Demountable Partitions by Trendway, Will you kindly consider an Addendum to require a Certified Trendwall Distributor/Installer to perform all of the Demo, Storage, Stage, Purchase and Reinstall of the private offices?
Refer to Addendum No. 2 for allowance increase for demountable wall repair and materials.
Refer to Addendum No. 2 for early removal of demountable wall from Phase 3.
Refer to Addendum No. 2 for all demountable wall work to be performed by a certified
Trendway installer.
2. A considerable amount of new product will be necessary to supplement the existing partitions for the required new layout and the Warranty of the existing materials cannot be comprised for your maximum efficiency. Any demo of Trendway products by someone other than a Certified Installer will void the manufacturer’s warranty.
Refer to Addendum No. 2 for allowance increase for demountable wall repair and materials.
Refer to Addendum No. 2 for early removal of demountable wall from Phase 3.
Refer to Addendum No. 2 for all demountable wall work to be performed by a certified
Trendway installer.
A&H-Ambica JV
1. In RFP documents, CPT-1 calls for Interface Carpet Tile or Equal…. style and color TBD….No specific style mentioned. As cost varies best of style picked, we suggest one of teh three styles, Plainweave, Equilibrium, or Alliteration. Please confirm this is acceptable.
Refer to RFI 17 (under Fredrick Construction RFI). CPT-1 provide an allowance of $45 sq.yd. for carpet material only. Allowance will be called out in Addendum #2 due different styles of pricing.
PDSI Contractors
1. The drawings show the demo of existing panels in the electrical rooms. I have not found any riser in the drawings showing the addition of panels tied to any power source or indication any additional buss plugs for new panels. Please advise.
Refer to RFI GG.1 (under PDSI RFI).
A. Sheet GC 101 shows considerable more laydown area than what was discussed at the pre bid conference. Also the location of the staging seems different. Please provide documents showing actual laydown areas available to contractors.
GSA Property Management can provide office / staging space. Location and quantity of space provided is at GSA discretion.
A.2. In the RFP it only ask for past performance from the contractor. Can additional information be provided if decided to by the contractor? I.e key subs, org charts, resumes etc.
Additional Information is always welcomed and can be provided as well
B. Confirm that once gang boxes and equipment has entered the secured area that a space will be provided to allow those items to be staged within the building until the next phase is made available.
GSA Property Management can provide office / staging space. Location and quantity of space provided is at GSA discretion.
C. Please confirm this is not a LEED project.
This is not a LEED project.
D. In regards to IAQ, the space to be flushed prior to occupancy. Is this to be performed prior to furniture installation and for each phase completion?
See RFI 54
E. Confirm requirement to run negative air through removal of window pane, or if construction space is adequately sealed at the perimeter would the HEPA filtration be adequate?
See RFI 5
F. Confirm that all furniture and office equipment will be removed from the space by others.
Office workstations are to be removed by others.
Demountable walls are to be removed by contractor.
Refer to Allowance number 2 in spec section 012100 for staff relocation.
G. Confirm this contract does not include the purchase, procurement or installation of furniture or office equipment other than that equipment stated on the equipment legend in the documents.
Confirmed
H. Confirm that the electricians are to provide physical connection to furniture panels, or will a junction box in the location of a power pole be acceptable for future hook up by others?
Furniture power connections at the ceiling will be made by the electrical contractor during the construction of the space.
I. If contractor electricians are used please provide the manufacture of the furniture system for coordination purposes of the bid.
owner currently procuring, information not available at this time
J. In review of the demountable panels from the walk through please confirm that no cleaning or repairs to the finishes are required.
Refer to Allowance number 3 in spec section 012100 for demountable wall repair.
K. Please confirm there are no extra parts available for the demountable partitions.
Refer to Allowance number 3 in spec section 012100 for demountable wall missing components or shortfall in materials.
L. Please confirm my understanding that an addendum would be issued regarding the replacement of parts and partitions.
Refer to Allowance number 3 in spec section 012100 for demountable wall missing components or shortfall in materials.
M. It is my understanding that the 11th floor swing space will still be part of the base bid even if the 12th floor option is not exercised, and an addendum will be issued showing other swing space locations.
Please confirm this is correct.
Correct refer to Addendum No. 1.
N. What phase is swing space work to be completed.
Refer to the phase schedule in spec section 011000
O. Please confirm that the only scope in the swing space areas will be to provide electrical hook up to relocated furniture.
Swing space is mostly electrical hook up of workstations.
Some demountable wall work is included in some of the swing spaces.
Refer to addendum No 1 for work scope in swing spaces.
P. The 11th floor swing space shows a wall with a door to be demolished. We were not able to review the conditions at this space during the pre bid. There is no indication of relocating electrical fixtures or mechanical diffusers. Also it is unclear of the finishes in this space. Please provide more information of scope of work for this wall removal.
Omit the dashed wall and door shown on the plans near the 11th floor swing space.
Refer to addendum No 1 for work scope in swing spaces.
Q. Confirm that the existing walls used as a phase separation will need to have fire rated properties added but not sound properties, and fire dampers in duct work is not required.
See RFI 20 (Fredrick Construction RFI).
Where fire dampers are required in phase separation walls, they are shown on HVAC plans.
R. The rating designation on the architectural floor plans and the phase separation are the same symbol. This represents a 2 hour rated wall system, but only a 1 hour system is needed for separation walls. Please confirm the only new rated walls can be found on the code compliance plans and that the separation walls are 1 hour rated unless in a sprinkled space.
Some sheets show the phasing lines with a line type that matches the 2-hour rated wall line type. This line type does not represent the phasing wall fire rating. See RFI 20 for construction wall fire rating requirements.
S. If the space on one side of the phasing wall is sprinkled, will that suffice to remove the 1 hour rated wall requirement for the phasing wall.
See RFI 20 (Fredrick Construction RFI).
T. Phase 4 on the 14th floor will not have any HVAC once phase 2 begins. This was discussed at the pre bid and the A/E rep indicated they worked out the phasing to avoid this. Please explain how they are receiving climate control once phase 2 begins. I would suggest if possible that the small area of phase 4 be added to the phase 2 scope.
Phase 4 will remain. Refer to Addendum No. 02 for revisions.
The HVAC design makes the best use of the phasing boundaries given which we understand cannot change. If it were possible to remove phase 4 and incorporate it into phase 2, HVAC could be redesigned as suggested to eliminate this issue as suggested. The current design better equalizes air distribution from shafts.
The following approach is recommended:
(1) During phase 2 (after hours), extend existing induction terminal unit duct system serving office 1401, mail room 1402, and office 1403 to also now serve storage 1404 and storage 1405. At the perimeter, this will involve adding connecting 12” diameter flex duct between perimeter ductwork served by separate existing induction terminal units and capping this existing duct at the right side of the perimeter duct near column H7. At the interior, this will involve adding a 10” diameter flex jumper duct to the continuous linear slot diffuser so that phase 4 is fed from existing induction terminal also serving phase 3.
(2) During phase 3. Break loose the temporary ductwork installed in phase 2. Route new temporary ductwork connected to new phase 2 ductwork into phase 4 boundary (after hours). Temporary HVAC consists of terminal unit VAV-14.01, 3 diffusers, and temperature sensor (all initially designated for phase 4 construction. Note that size of 14NE trunk duct needs to be revised.
(3) During phase 4, complete remainder of demolition in phase boundary. Revise locations of VAV-14.01 and its associated temperature sensor and diffusers to final designated location and revise ductwork accordingly. Note this terminal unit location needs to revise slightly from previously shown location. Complete remainder of new hvac designated to occur in phase.
Addendum 2 drawings will be issued to clarify all required changes.
U. Confirm that it is the intent of the 12th floor phase to be accessed through the adjacent door in the phase 5 area.
Refer to Addendum No 1. For additional egress information.
V. Several demolition notes indicate salvage of ceiling tile, casework, doors, frames, hardware, and access floor. In the pre bid there was discussion that salvage of some or all of these items are not required. Please define clearly what items are to be salvaged as this will impact the bid and increase the need for storage space until turn over.
See RFI 27
W. If doors, frames, and hardware are to be salvaged, are they to be salvaged as a unit?
Yes. Owner wants to review salvageable materials / items, however, contractor remains responsible for disposal .
X. It was discussed that the electrical feeds in the walker duct system may feed multiple phases. Please address how the contractor is to remove that portion of service without effecting the remaining phase. Will the contractor be allowed temporary measures to be left within the walker system until the next phase addresses the system.
The end goal is to have all unused cabling removed from the floor ducts. Cabling should be mostly loose in the duct or made loose when work is being done within that phase. This loose cabling should be easily pulled from one neighboring phase to another. If this is not possible contractors should be able to double back into occupied phases during unoccupied hours and access the floor ducts and remove abandoned cabling. This should only require removal of some carpet squares that should be reinstalled same day. If there is an unforeseen issue that makes this work extremely difficult like not having access to a length of walker duct because of new construction or a workstation; this can be reviewed by GSA, VBA, and architect during construction to determine if these portions of cabling can be abandoned in place.
Y. Please provide fire protection pressure(s) The last pump test results that I possess has the following flows at 100% capacity Static: 286 psi Residual: 276 psi
Flowing: 990 gpm
Z. Section 102219 demountable partitions, 211315 sprinkler system modifications, and 283104 fire alarm system modifications indicates contractor to provide cad generated drawings of the demountable partition, sprinkler as build and fire alarm system. During the discussion of the pre bid conference no cad drawing are required. Please confirm only redline as built documents turned over to GSA will be required.
These will require CAD drawings to be provided to the AE. Contractor is also required to submit shop drawings including plan drawings for these systems. CAD files should already be created for these submittals.
AA. Confirm no abatement for hazardous material is known at this time.
We did not receive a copy of a test report but were verbally told by the GSA that this was handled in a previous project. If the GSA has access to a passed test report this would be the only way to confirm at this time.
BB. Confirm that spaces that span phases when complete do not require finishes to be installed until last phase of space is built out.
Refer to general note No. 3 on the phasing plans.
Some finishes may need to wait until the later phase for these rooms.
CC. Af102 unable to understand some symbols used as they are not identified in the legend i.e. dashed circle with an S. also some are in conflict of light fixtures or diffusers. Please clarify legend and ensure all ceiling mounted devices are shown and coordinated.
SV = Speaker Visual – refer to Fire alarm drawings S = Speaker – refer to File alarm drawings
DD. Are examples of artist panels available via a picture.
no image will be provided until award issued. Refer to Addendum #2 for further info
EE. Please confirm no fire suppression scope will be in the elevators or duct shafts. Note shows that core areas are to have heads replaced and both elevators and shafts are indicated.
No fire suppression scope will be in elevators or duct shafts. Where are elevators and shafts indicated? For floors included in remodel, fire protection heads are to be replaced in same location with quick response type. This includes exposed upright pendants in stairwells of floors 12, 13, and 14.
FF. Is an electrical one line diagram designed?
No
GG. New panels do not show the power source or wire configuration usually found on a one line diagram.
See keynote #11 and panel schedules for panel information as requested
HH. Where is panel RP12DA. Unable to locate on plans.
Disregard references to panel RP-12DA. See Addendum #02 for revised circuit designations for devices previously fed from this panel.
FF. An addendum is posted however it requires a password to access. Please remove password or provide access. We are unable to confirm content.
Amendment 3 was posted with Adendum#01 and a password referenced as a file link But Amendment 3 is only the SF30 without Addendum 01 being attached. However Amendment 4 was issued and has all the Addendum documents attached with no password required. I just confirmed the information on FBO as well.
GG. Quality Assurance: Installer Qualifications: will Carpet installers be required to be certified through the International Certified Floorcovering Installers Association at the Commercial II or Master II certification level.
See RFI 36
Fredrick Construction
1. Due to the number of questions on this project, we ask that a bid date extension of 1 week be considered to allow contractor sufficient time to react to the responses received.
Extension issued.
2. Will the contractor be able to stage a dumpster or multiple dumpsters in the basement / loading dock area? If so how long can the dumpster stay in the loading dock area and how many at one time?
Yes. GSA Property Management can block our 1 dock bay, 24/7 for contractor dumpster(s). It is feasible for a 40yd and a 20yd to be positioned there at the same time. The goal is to not interrupt changing out of existing compactor, and/or adjacent dock bays.
3. Is the contractor free to use the Owner’s existing toilet facilities or will temporary toilets need to be provided?
Existing facilities to be used, contractors to maintain cleanliness.
4. Will all contractors and employees working on the project need to have security clearances or can they be escorted by an employee that already has a full security clearance? If all contractors are to obtain security clearances, please provide specific information related to this process so that the contractor is able to include any costs associated with the clearance process in their base bid.
Please see attached vendor manuals for security clearance information.
5. It was noted at the pre‐proposal conference that the construction areas under each phase are to be placed under negative air and that exterior windows could be removed and boarded up to achieve this. Has this been verified as being acceptable to the property management and security for the building? We have worked in this facility many times and have never been allowed to take out exterior windows and temporary board them up to exhaust a HEPA air machine.
Yes... GSA Property Management will permit removal of a single widow for NAM exhaust purposes. Placement to be discussed / confirmed by GSA Property Management. If more than one window is needed, this will require additional conversations with GSA Property Management. It is paramount that the exhaust is properly monitored.Contractor is responsible for the condition, and storing of the removed window as well as proper replacement. Window blinds are to be fully functional after window replacement is completed. All abatement plans approved by construction team MUST be reviewed by PVM Property Management for impacts to building operations.
6. Who is the proprietary contractor for the fire alarm work within the building? Who is the proprietary contractor for the building controls for the BMS system, Graphics, and HVAC Controls? Were either of the proprietary contractors involved in the design phase? Do they know to have pricing ready for this project?
We do not have proprietary contractors. GSA has an Operations & Maintenance Contractor. They in turn have maintenance agreements with multiple subcontractors.
Because KCorp Support Services (O&M) is responsible for the operations and maintenance of ALL building systems. KCorp will be the primary contact for all building system needs / inquires.
No. KCorp has not yet reviewed project requirements.
No. KCorp does not have pricing available as they were not yet asked to provide. It is the responsibility of the GC to seek costs.
7. Who is responsible for the O&M costs related to the project? O&M items would include drain down fees, after hour utility shut downs, testing, etc.
Contractor not responsible for costs.
7. Can the fire suppression work be completed during normal working hours? Is there a certain time that the fire suppression system needs to be back on‐line working each day?
The fire suppression work cannot be completed during the normal work hours and needs to remain operation during normal building work hours.
9. If the fire suppression system work needs to be completed after hours, what time will the system need to be re‐filled and in working order the next morning? Who will be responsible for “fire watch”? What is the process for “fire watch” in the building?
Work shall be done in such a manner as allows for the return to service of all sprinklers at the end of the work shift
The contractor is responsible for the fire watch because it is their work that has taken the sprinkler/fire alarm system out of service.
Where a fire watch is required by GSA standards or codes referenced therein, that fire watch shall be provided with at least one approved means for notification of the fire department, and their sole duty shall be to perform constant patrols and watch for the occurrence of fire. Fire watches assigned as a part of any fire safety or impairment plan shall be trained and have documentation of hands on fire extinguisher training complying with 29 CFR 1910 within the previous twelve months. Likewise, they shall be trained on how to sound the alarm within the building during any impairment and to independently notify the public fire department of a fire emergency within the building. All fire watch personnel shall have a direct means of communication with the project superintendent.
I have attached our Master Specification for Fire Prevention and Protection in Construction and Demolition.
10. Will additional building security be required for after‐hours work that would take place on 2nd or 3rd shift? If there is a fee, who is responsible for the fee?
No. Additional 2nd & 3rd shift security is not required. However, after hours entrance will be available via access card and PIN... tools / materials are required to be screened. Guard staff is at a minimum after hours. Additional security and/or fees are the responsibility of the requester.
11. Who is responsible for the costs associated with the labor and material for the installation of final door key cores?
Spec section 087100 2.5 list the core and keying requirements and is the responsibility of the contractors.
12. Is there existing spray applied fireproofing that will require patching? If so, please identify the locations or a square foot amount to include in the base bid.
We do not believe there is any existing spray fire proofing given the concrete structure system and our limited field verifying. We will remove the note. I was hoping the GSA could confirm if this was an issue on past projects.
13. Specification Section 012100 – Paragraph 3.3.A – Allowances: What size of sprinkler piping is the allowance and unit pricing to be based upon? Will the SF1442 bid form be modified and include spots for submitting that allowance pricing and unit pricing? Is the allowance price to be included in our base bid or option 1 pricing?
Replace with new piping consistent with new construction. Refer to the Fire Protection plans for the range of piping sizes called out for new construction. Create an average cost based on sizes and quantities shown.
Create an allowance for base bid and a separate allowance for the 12th floor option.
14. Specification Section 01500 provides information for temporary facilities and the areas in which they are to be staged. Is the contractor allowed to set up a temporary field office space within the basement storage area or will a separate mobile office trailer be required for this project?
Yes... GSA Property Management can provide office / staging space. Location and quantity of space provided is at GSA discretion.
15. If the area being reserved on 1st street is used for construction staging, will the area require any type of temporary construction fencing?
Fencing should be provided.
16. Specification Section 081113 – Hollow Metal Doors & Frames: Knocked down construction is specified for both heavy duty and extra heavy duty hollow metal frames. Is the use of fully welded frames acceptable in lieu of knocked down construction?
Fully welded frames are acceptable.
17. Sheet IN602 – Finish Key: What style and pattern is to be used for bidding purposes for Carpet 1 (CPT‐1)? A specification has been provided for CPT‐1, however there are many different carpets that will meet this requirement and have a large range of cost. Please confirm that CPT‐3 will come from either salvaged material or attic stock and that we are to exclude the cost of providing any new material for this particular carpet.
CPT-1 – provide an allowance of $45 per square yard for carpet material only.
CPT-3 will be from Attic stock or salvaged material.
18. Sheet G1002 contains a general note that fire extinguishers are to be provided per the fire code and to refer to the floor plan for fire extinguisher cabinet locations. We do not find any new fire extinguishers or cabinets located within the project drawings or a specification within the project manual. Are fire extinguishers required for this project? If yes, please provide quantities, locations, and a specification.
There are no new fire extinguisher cabinets on this project. The core area corridors have an existing fire extinguisher next to a drinking fountain in all 4 corners of the core space that are to remain. The tenant will be responsible for any additional fire extinguishers needed with in each tenant space or suite.
19. Sheet G1101 requires providing a temporary egress door during phase 5. Is it acceptable to re‐ use a door, frame, and hardware saved from the demolition of a previous phase?
Yes this is acceptable.
20. Throughout the project drawings, it is noted that construction areas are to be separated with 1 hour partitions. Please provide a plan showing the expected locations and placement of the temporary partitions. Are the temporary partitions to be finished and painted or only fire taped?
Please confirm that the temporary partitions DO NOT require a 1 hour rating nor a 45 min. door since the space under construction must have the existing fire suppression active for the duration of construction.
The phase lines represent the basic locations of the construction separation walls. Refer to general note 3 on phasing plans – exact locations to be determined by team in field.
Some partitions could be part of the final wall layout and could be constructed and finished accordingly.
Temporary partitions require 1 hour rating. Doors to be rated at 45 min.
Contractor responsible for dust prevention into adjacent spaces with regards to air quality.
21. Specification Section 015000 – Paragraph 1.1.C indicates that an area within the basement is being established for temporary storage. It appears this is being reserved for salvaged items and government furnished items. Can this area be utilized to store contractor provided materials, tools, etc., or is the contractor required to provide an office or storage trailer for these items?
No. Basement area(s) may not be available. GSA Property Management can provide office / staging space. Location and quantity of space provided is at GSA discretion.
21. Specification Section 015000 – Paragraph 3.3.A indicates that use of the existing elevators are not permitted. Please confirm that this is correct and that all materials are to be transported by the use of stairwells.
Spec section notes - “Use of GSA's existing freight or passenger elevators will be not be permitted unless approved by the GSA Building Manager.” GSA indicated at the pre-bid walk through that use of the freight elevator will be permitted.
23. Sheets AD101 – AD103: Demolition Key Note 4 indicates that the existing floor is to be ground to provide a smooth and uniform finish. Are we to assume that all areas of the existing concrete floor need ground?
Only at areas that are not smooth. Provide a smooth uniform surface for new finishes.
24. Please provide a typical detail/cross‐section of the exterior perimeter in relation to the existing concrete floor, window opening, and deck above.
Detail will not be provided at this time.
floor to floor = 12’-10” Floor to bottom of beams = (varies) 11’-4” typical Ceiling will die into window’s top mullion at 9’-0”
25. Specification Section 024119 – Paragraph 1.7.B.1 indicates that the Owner will be removing the demountable walls. Note 7 on the demolition plans suggests that this would be by the contractor.
Please confirm if the Owner is to remove and store the demountable walls and associated doors or if the contractor is to complete this work.
Omit note in spec section 024119. Contractor is responsible for removal of demountable walls as indicated elsewhere throughout the documents.
26. Specification Section 024119 – Paragraph 3.1.D indicates engaging a professional engineer to perform and engineering survey within the construction to determine if removing any element might result in structural deficiency of the structure. Is this required for this project?
Locations are unknown at this time but may present themselves during the course of construction.
27. Sheets AD101 – AD103: Demolition Key Note 5 indicates removing the existing ceiling tile and grid system and turning it over to the government or salvaging the ceiling tile for recycling. Please clarify this work item. Are both the ceiling tile and grid to be turned over to the Government or only the ceiling tile? For bidding purposes, should we plan on recycling the ceiling tile or turning this over to the government?
The GSA will want a portion of the materials salvaged and turned over to them.
The remaining materials can be disposed of.
28. Sheets AD101 – AD103 indicate salvaging and turning over many items being removed during demolition. Please clearly indicate which items are to be salved for bidding purposes as this impacts the means and methods used during demo and cost.
The GSA will want a portion of the materials salvaged and turned over to them.
The remaining materials can be disposed of.
29. Sheets AD101 – AD103 all have areas where small portions of the existing building core walls are being removed. These walls are of concrete/plaster construction. Please confirm that we are to remove these areas per the demolition plan. Will any additional structural support be required? If yes, please indicate the support requirements.
Contractors are to assume these few existing walls and door locations in the main corridor off the elevator lobby and gang bathrooms are constructed of concrete and plaster and should bid accordingly for demolition. For new construction or patching in these areas contractors are to assume metal stud and drywall is to be used as noted on the drawings. The construction/ design team is willing to review alternate ideas from the contractor for these areas to simplify construction. Bidders are to assume no additional steel support is needed at this time. Team will verify at a later date.
30. Sheet AD103 indicates demountable partitions with light lines on the West side of the building. Sheet AE104 indicates the very same light color lines for the demountable partitions. Are these partitions existing to remain throughout construction? Please clarify.
These existing demountable partitions are to remain throughout construction.
31. Sheet AD103 indicates removing the existing floor covering at Break Room 1468. The Finish Schedule on Sheet IN602 indicates that the floor covering is existing to remain. Please clarify what is required for flooring at this location.
Existing flooring is to remain. Omit flooring demolition note on AD103 for Break Room 1468.
32. Will each phase require a separate GSA testing, inspection, and closeout process for the fire suppression modifications?
Yes.
33. Please confirm if pre‐construction test and balance measurements noted in Specification Section 230593 are to be performed at the beginning of each separate phase, or if this can be completed for all phases at the same time. Please confirm if each phase will require its own separate final test and balance.
Pre-construction measurements should be done prior to the first phase of construction. 230593.3.1. indicates TAB shall occur at completion of each construction phase. Upon completion of all phases, measure and record conditions at 20% of terminal units. TAB reports shall be submitted at completion of each phase. At completion of project, a representative sample (20% randomly taken from all phases) shall be measured and recorded with report submitted to demonstrate difference between values submitted at completion of phase reports and completion of project. If significant discrepancies exist in this sampling at end of project, some additional balance may be necessary. It is not the intent that a comprehensive final test and balance report be completed at the end of the project.
34. During the pre‐proposal conference, contractors were not allowed to review all of the areas where is will be conducted. Each area reviewed during the walk‐thru contained 100% existing carpet tile. Are we to assume that the balance of the areas also contain 100% carpet tile? Please note any other existing floor covering types to be removed and their locations.
The vast majority of the existing flooring is carpet tile. Assume VCT at existing break rooms.
35. During the pre‐proposal conference, contractors could not access all ceiling areas. Is the contractor to assume that all new HVAC equipment has been laid out in a manner to avoid interference with existing sprinkler main piping?
New HVAC has been laid out in a manner to avoid interference with existing fire protection where possible. A few locations may exist where new HVAC requires coordination/modification of existing fire protection which are not shown on plans. Existing fire protection piping layout was based on provided as-built drawings and was not accurately field verified during design process. Actual height of piping may also vary which could create interference where not anticipated. Specification 211315.3.4.A.
(Coordination of work) should include both existing to remain and new work from all trades. Where mechanical can work around existing fire protection, they shall, but some locations may require fp rework.
36. Specification Section 096813 – Paragraph 1.7.A indicates that carpet installers are required to be certified by the International Certified Floorcovering Installers Association at Commercial II or Master II Level. Is this applicable to this project? Some GSA cleared installers might not have this specific certification. Can non‐certified installers be utilized on this project as long as they have a successful past history of installing carpet within Federal Buildings for GSA?
Per the spec, Carpet installers are required to be certified by the International Certified Floorcovering Installers Association at Commercial II or Master II Level.
37. Specification Section 096813 – Paragraph 2.2.B.3 indicates that additional adhesive is required over the existing walker duct system. Please indicate the locations of the walker duct system on the project plans.
Assume walker duct is 2% of the floor surface for additional adhesive purposes.
38. Specification Section 096519 – Paragraph 3.4.D.1 indicates applying 3 coats of floor polish to the new resilient flooring and to confirm GSA standards. Have GSA standards been confirmed for bidding purposes?
Assume 3 coats for bidding purposes.
39. Specification Section 064116 – Paragraph 1.4 indicates the fabricator and installers are to be AWI Certified. Can this requirement be waived for this project to allow the participation of Non‐ AWI contractors as long as AWI standards are followed?
Per spec, the fabricator and installers are to be AWI Certified.
40. Specification Section 102219 – Paragraph 1.4.A & B indicate that the contractor is to provide CAD drawings of the current location and final location of the demountable partitions. It appears this information is currently on the construction plans. Is this submittal still required?
Yes – Contractor is to verify the existing layout and components. This would be needed to coordinate storage and relocation schedule.
41. Specification Section 102219 – Please confirm if the removal and re‐installation of the demountable wall panel system is to be by the contractor, or if this work is to be by the Government. If by the contractor, is a fully certified installation contractor required for this work?
Removal and re-installation is the responsibility of the contractor.
A Trendway certified distributor and installer must be used for the demolition, storage, and reinstallation of all the demountable wall scope.
42. Specification Section 084229.23 – Paragraph 1.5.E indicates a delegated design submittal for the automatic entrances. Does this design submittal require an engineer’s stamp?
No stamp required.
43. Specification Section 088000 – Paragraph 1.3.D indicates a delegated design submittal stamped by an engineer for the glass. Please confirm that this is required for this project.
No stamp required.
44. Specification Section 095123 – Paragraph 3.1.G.5 indicates a level 5 finish for the drywall. Will a level 5 finish be required for this project? If yes, please provide areas where this is to take place.
Only if noted elsewhere in the construction documents.
45. Specification Section 087100 contains notes within hardware sets that certain components of the door hardware package will be furnished and installed by the Security Contractor. Is the Owner contracting directly with the security contractor? If so, please provide a description of any work items that the security contractor is expecting to be completed under our contract. Examples would include rough‐in, installing wire, terminations, etc.
Contractor will be responsible for furnishing and installing all hardware sets and components; contractor is responsible for contracting directly to security contractor.
46. Sheet AE501 includes details of the exterior windows and wall construction. We believe if this detail is followed, it will make it almost impossible for the O&M contractor to remove the interior “storm” windows. Is this acceptable?
AE firm referenced this detail in the building standards. Contractors are to bid accordingly. A revision to this detail may occur post bid.
47. Sheet AE104 – Will corner guards be required at the square column and at the outside corner of the wall associated with Conference Room 1442? Will new corner guards be required at the interior of the existing North wall of Training Room 1426? Will corner guards be required for the new wall on either side of opening 1473B?
Yes Yes Yes
48. Are we to assume that the existing height from floor to deck is…