P. V. McNamara Federal Building PCN: RMI00663 PVM VBA Renovations (12th, 13th, & 14th Floors) GSA PBS Region 5
SUMMARY 011000
PROPERTY OF THE UNITED STATES GOVERNMENT
FOR OFFICIAL USE ONLY
Do not remove this notice
Properly destroy documents when no longer needed
SECTION 011000 – SUMMARY
PART 1 - GENERAL
1.1 PROJECT INFORMATION
A. Project Name and Location:
1. Patrick V. McNamara Federal Building - Veterans Business Administrations Renovations.
Patrick V. McNamara Federal Building 477 Michigan Ave. Detroit, MI 48226
B. Project Summary Description:
1. A renovation project of the Veterans Business Administrations (VBA) within their existing tenant space on the 12 th , 13 th & 14 th floors of the Patrick V. McNamara Federal Building
(MI0131MC) in Detroit Michigan.
Architect: The term Architect refers to the project designer. The Architect's status relative to the construction will be stated in writing by the Contracting Officer prior to the pre-construction conference. The project was designed by:
Diekema Hamann Architecture & Engineering
612 South Park St Kalamazoo, MI 49007 Attn: Gabe Alvey, Architect 269-373-1108
C. Project Delivery Method: traditional
D. (CMa) to be provided by Client.
E. The Contracting Officer for the project is: Marilyn Roldan, 5P1QCD phone (312) 353-3959.
1.2 WORK SEQUENCE`
A. The work shall be conducted in phases in this building on floors 12 th , 13 th and 14th: Work is in an occupied building and phased; coordinate with Phasing Plans and drawings. All floors under construction will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area. Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1. Phases (as indicated on drawings): The following work shall be substantially complete, ready for occupancy, after notice to proceed: See schedule at end of this spec section.
2. Move-in Periods: See schedule at end of this spec section.
1.3 WORK BY OTHER CONTRACTORS (There is a FAR clause; coordinate with Legal, ok to leave to reinforce an existing requirement.) Reminder: FAR clause always trumps the specification
A. The Contractor shall cooperate with other contractors performing related work, including providing labor, materials and other costs necessary to satisfactorily coordinate the Contract work with work performed under other contracts.
1.4 SCHEDULE OF GOVERNMENT-FURNISHED PROPERTY
A. The project includes the following Government furnished property to be installed by the Contractor.
The contractor shall advise GSA at least 30 days in advance of when the property should be delivered.
1. Refer to Equipment schedule in the drawings.
1.5 MISCELLANEOUS PROVISIONS
A. Work in existing facilities shall correspond in all respects with the existing conditions to which it connects, or to similar existing conditions, in materials, workmanship and finish.
B. Alterations to Existing Conditions: Existing conditions shall be cut, drilled, removed, temporarily removed, or removed and replaced, as necessary for performance of Work under the Contract.
Work out of alignment where exposed by removal of existing work shall be called to the attention of GSA. Necessary corrective work shall be as directed.
1. Replacements of existing conditions that are removed shall match similar existing conditions.
2. Unless otherwise indicated, existing structural members shall not be cut or altered without authorization by the Contracting Officer.
3. Conditions remaining in place, which are damaged or defaced during the Work, shall be restored to the condition existing at time of award of Contract.
4. Discolored or unfinished surfaces exposed by removal of existing conditions, that are indicated to be final exposed surfaces, shall be refinished or replaced as necessary to produce uniform and harmonious contiguous surfaces.
C. Existing structures will remain in place.
D. Existing utility services with related meters and equipment will remain in place.
E. Removed items indicated to remain the property of the Government shall be stored on site where directed by the Contracting Officer.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - Schedule:
END OF SECTION 011000
ALLOWANCES 012100
SECTION 012100 - ALLOWANCES
1.1 RELATED DOCUMENTS
A. The Government is providing the references included in this sub-section for information purposes only and is not intended to provide a comprehensive, all-inclusive list of any and all potentially relevant portions of the Contract Documents. Drawings and general provisions of the Contract, including Federal Acquisition Regulations (FAR) and General Services Administration Acquisition Regulations (GSAR) contract clauses, and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements governing allowances.
1. Certain items are described in the Contract Documents as allowance items. The purpose of allowance items is to defer selection of actual products and systems to a later date when direction will be provided to the Contractor. The Contracting Officer will issue Modifications to incorporate allowance items in the Work after actual products and systems have been determined.
B. Types of allowance items may include the following :
1. Lump-sum allowance items.
2. Unit-price allowance items.
3. Quantity allowance items.
1.3 SELECTION AND PURCHASE
A. At the earliest practical date after award of the Contract, advise the contracting officer of the date when final selection and purchase of each product or system described by an allowance item must be completed to avoid delaying the Work. Allowances must be included in all schedule submissions
1.4 ACTION SUBMITTALS
A. Submit proposals for products or systems described by allowance items in the form specified for Change Orders.
1.5 INFORMATIONAL SUBMITTALS
A. Submit copies of invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each unit-price and quantity allowance item.
B. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.
1.6 COORDINATION
A. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation.
B. Modifications based on an allowance item shall include cost to Contractor of specific products and systems selected by the contracting officer under allowance and shall include taxes, freight, delivery to Project site, Contractor's costs for receiving and handling at Project site, labor, installation, overhead, and profit.
1. If requested by the contracting officer, purchase additional quantities under unit-price or quantity allowances and prepare unused material for storage by Contracting officer.
Deliver unused material to Contracting officer's storage space as directed.
1.7 ADJUSTMENT OF ALLOWANCE ITEMS
A. Modifications to an allowance item shall comply with the changes clauses and any other contract modifications procedures found in the Contract Documents.
B. Contracting officer reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine products covered by an allowance item promptly on delivery for damage or defects.
Return damaged or defective products to manufacturer for replacement.
3.2 PREPARATION
A. Coordinate materials and their installation for each allowance item with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
3.3 SCHEDULE OF ALLOWANCE ITEMS
A. Allowance Item No. 01: Unit-Price/ Lump-sum Allowance:
The majority of the existing sprinkler piping has been verified as black steel and some piping has been documented to remain. There may be areas of unanticipated galvanized sprinkler piping. If this is found during the construction process and has been documented to remain, the contractor is to coordinate with the government and architect on how to proceed. Coordinate with drawings and Specs.
For bidding purposes the contractor is to assume 1,000 L.F. of unanticipated existing galvanized piping will need to be removed and replaced with new sprinkler piping (schedule 10).
Provide a lump-sum allowance for the cost of the labor, materials, and other associated costs for this assumed 1,000 L.F. of piping as described above. $____________
Provide a unit price per linear foot if additional work/ or deduct is required above/ or below the 1,000 L.F.:
1. Removal and demolition of galvanized piping. $____ per L.F.
2. Replace with new piping consistent with new construction. $____ per L.F.
B. Allowance Item No. 02: Lump-sum Allowance:
For bidding purposes the contractor is to assume a lump sum allowance of $50,000 for contracted labor, materials, and other associated cost in covering the relocation of the staff workstation items throughout the phased project. Items will include personal belongings, chairs, files, paper and other media items. The contractor is expected to coordinate and facilitate Move-In and Move-Out services with the GSA and their Tenants.
C. Allowance Item No. 03: Lump-sum Allowance:
For bidding purposes the contractor is to assume a lump sum allowance of $25,000 for contracted labor, materials, and other associated cost in covering any salvaged and reinstalled demountable wall panels and or demountable wall doors & frames – that have been determined to be too damaged to be re-used. This allowance is to be used either to cover the repair cost or the replacement cost depending on the level of damage. This allowance is to also cover any missing items or shortfall in the existing demountable wall panels and or demountable wall doors & frames. This allowance is in addition to the base bid scope of work that is required in the bid documents for salvage and re-use of existing demountable partitions. Coordinate with drawings and specs. See spec section 102219 – Demountable wall system.
END OF SECTION 012100
CRITICAL PATH METHOD 013110
SECTION 013110 - CRITICAL PATH METHOD SCHEDULING
1.01 SUMMARY
A. The Contractor shall use a Critical Path Method ("CPM") Project Schedule to plan, coordinate, and perform the Work. The Project Schedule shall be produced using widely used, commercially available computer software that is capable of generating and monitoring a CPM schedule and is compatible with Meridian Proliance. Develop a detailed Network Plan demonstrating complete fulfillment of all Work shown in the contract documents. Regularly update the Network Plan in accordance with the requirements of this Section, and use it in planning, coordinating, and performing all the Work under this contract. Schedule activities shall accurately depict the contractor’s means and methods to complete the entire scope of work including, but not limited to, activities of subcontractors, consultants, equipment vendors and suppliers, GSA, and others, as required. The contractor is required to follow the Network Plan in the execution of the work.
B. The purpose of the Project Schedule shall be to:
1. Plan the project and communicate that plan.
2. Provide the status and forecast the timely completion of the work.
3. Record the actual start dates, actual finish dates and actual sequence of the work.
4. Ensure adequate planning, staffing, scheduling and reporting during execution of the Work by the Contractor;
5. Ensure coordination of the Work among all affected parties;
6. Assist the Contractor and GSA in the preparation and evaluation of the Contractor’s monthly progress payments; and
7. Assist the Contractor and GSA in monitoring the progress of the work, and evaluating proposed changes to the Contract and/or requests for additional time to Project Completion.
1.02 RELATED SECTIONS
A. The Government is providing the references included in this sub-section for information purposes only and is not intended to provide a comprehensive, all-inclusive list of any and all potentially relevant portions of the Contract Documents. Drawings and provisions of the Contract including General and Supplementary Conditions apply to this Section as if repeated herein.
B. Section 012600 – Contract Modification Procedures
C. Section 012900 – Payment Procedures
D. Section 013200 – Construction Progress Documentation
E. Section 017700 – Close Out Procedures
1.03 DEFINITIONS
A. Definitions applicable to this Section include the following:
1. Activity - An element of the Work or task performed during the course of the project. Each schedule activity shall be a clearly defined, manageable and monitorable task depicting an estimated duration, an estimated cost, and estimated manpower requirements. Each activity shall be limited to one trade unless the GSA specifically approves otherwise on an exception basis.
2. Baseline Schedule - The original work plan approved by GSA as the Project Schedule depicting the contractor’s plan to prosecute the work.
3. Constraint - A scheduling restriction imposed on the start date, finish date or float of an activity. No constraints will be allowed. Exception: for projects with limited or no storage areas requiring “just in time” deliveries, a zero free float may be acceptable.
4. Critical Path - The Project critical path is defined as the longest, continuous path of interrelated activities depicting project work from notice of award (or NTP) to project completion. All reports and graphics indicating the Critical Path shall depict the longest path of interrelated activities. Unless otherwise approved by GSA, the Baseline Schedule Critical Path shall use all allotted Contract time. The contractor has the right to develop a schedule that forecasts an early finish. However, all time between the forecasted early finish of substantial completion and the contractual substantial completion date shall be shown as float and shall be available to the Project team.
5. Critical Path Method (CPM) - A scheduling technique using activities, durations, and interrelationships/dependencies (logic), such that all activities are interrelated with logic ties from the beginning of the project to the completion of the project. There shall be no open ended relationships in the schedule. All activities shall have at least one successor with a finish relationship (“finish to start” or “finish to finish” except the last activity in the network.
6. Data Date - The date to which progress is updated. In most scheduling software, the data date represents the next day of work and all progress is updated through the day prior to the data date.
7. Float – The amount of time an activity can be delayed in a project network without causing delay to subsequent activities (free float) or the project completion date (total float). Float is considered a project commodity jointly shared between GSA and the Contractor and shall be used in the best interest of completing the Project on time.
8. Free Float - the amount of time that an activity can be delayed without delaying a successor activity.
9. Total Float - The amount of time an activity (or chain of activities) can be delayed without affecting the Project Substantial Completion Date. Float is considered a project commodity jointly shared between GSA and the Contractor and shall be used in the best interest of completing the Project on time. The critical path is not dependent on float. Float is calculated after the critical (longest) path has been determined.
10. Float Suppression - the masking of available float through the use of constraints, unreasonable logical relationships or unreasonable durations. Float suppression techniques are not be allowed. On an exception basis, the use of a zero free float constraint to depict “just in time” deliveries on projects with little or no storage might be acceptable. .
11. Fragnet – A subset group of interrelated activities representing only a portion of the CPM schedule.
12. Key Plans - Key Plans are graphic representations on prints of the Contract Documents of the Contractor’s planned breakdown of the project for scheduling purposes. The key plans will clearly define the boundaries of the work for each designated area. The alphanumeric codes on the key plans shall match the code values for the activity code "Area" in the Project schedule.
13. Network Plan - The Network Plan is the entire database of activities, logic, durations, and all items relating to any activity input into the scheduling software and is the complete representation of the Project Schedule prepared using the Critical Path Method and graphically shown in a time-scaled form. The network shows the sequence and interdependence of the activities, and planned and actual progress by activity, required for complete performance of the Work.
14. Project Schedule - The Project Schedule includes the Preliminary Schedule (submitted at bid or as determined by the CO), the approved Baseline Schedule (developed based on the Preliminary Schedule), and all subsequent Schedule Updates, Schedule Revisions, Recovery Schedules, and As-Built Schedule.
15. Recovery Schedule – A schedule depicting the Contractor's plan for recovery of time lost on the project.
16. Retained Logic – When you choose Retained Logic, the remaining duration of a progressed activity is not scheduled until the logical relationships of all predecessors are satisfied. When you choose Progress Override, network logic is ignored and the activity can progress without delay
17. Schedule Revision - A schedule in which the plan for the work is revised. A Schedule
Revision is required when the current schedule no longer represents the actual or planned prosecution of the Work.
18. Schedule Update - A schedule in which only actual start dates, actual finish dates and duration percent completes are updated from the prior data date to the current data date. No revisions will be permitted in a Schedule Update.(i.e. added activities, deleted activities, logical relationships, etc.)
19. Time Impact Analysis - A technique to demonstrate a revision or proposed revision against the current approved Project Schedule.
20. Working Day - A Working Day is a calendar day scheduled for active prosecution of the work.
1.04 CRITICAL PATH METHOD SCHEDULE
A. Provide a detailed, time-scaled computer generated Project Schedule with activities representing each portion of the Work for the entire Contract Performance Period. The Project Schedule shall use the Critical Path Method (CPM) for the planning, scheduling and reporting of the work to be performed under the contract, and will be produced using the most current version of scheduling software, compatible with Meridian Proliance. The CPM scheduling software shall be capable of generating and depicting the longest path of the schedule network. For project collaboration and project reporting of the electronic CPM database with the GSA and others, over enterprise software & servers, the project elements such as resources, calendars, and activity codes, etc.
need to be defined at the “Project Level” rather than the “Global Level”.
B. No Constraints Float suppression techniques shall be used in the Project Schedule without a specific request from the contractor and a specific approval from the GSA. CPM calculations to be based on retained logic software setting. No out-of-sequence progress is allowed in schedule revisions. Out of sequence progressed activities shall be corrected with the proper logic and progress override will not be allowed.
C. As defined by the Contract, the entire project performance period shall establish the Project
Substantial Completion Date which shall be used in the planning and presentation of the Contractor’s Project Schedule. If the Contractor forecasts a planned early Substantial Completion Date in the Baseline Project Schedule, Approval of a planned early completion date is solely at the discretion of GSA. GSA reserves the right not to approve any schedule deemed to have an unrealistic forecasted Substantial Completion Date. Government approval of an early completion Project Schedule shall not modify the Contract directed Substantial Completion Date or Project Completion Date. The time difference between the Contractor’s planned Substantial Completion Date and the Contract directed Substantial Completion Date shall be considered Project Float, jointly owned and for the mutual use of both the Contractor and GSA. All indirect costs (home office general conditions, field general conditions, etc. shall be included through the final Contract Completion date.
D. The Contractor shall provide the computer processing of the CPM schedule, graphics, cost and resource reports required under this Section and/or as requested by the GSA at no additional cost to GSA throughout the entire project performance period until Project completion is achieved.
1.05 SUBMITTALS and MEETINGS
A. Project Schedule Requirements Meeting:
1. The Contractor shall meet with GSA within (1) week after Notice of Award to conduct a joint review of the Project Schedule requirements in this Section.
B. Preliminary Schedule:
1. Within (2) weeks after Notice of Award, Contractor shall submit a Preliminary Schedule detailing the entire scope of the contract. Only the scope, durations and logical relationships will be included in the Preliminary Schedule. (No cost loading or resource loading shall be included in the Preliminary Schedule.)
2. Within (1) week of receipt by the GSA of the Preliminary Schedule, the Contractor and GSA shall meet to discuss the results of GSA's schedule review. To the extent that revisions are required, the Contractor shall resubmit the Preliminary Schedule to the GSA for approval within five (5) work days of receipt of the GSA's comments.
3. Unless otherwise approved by the GSA, the Project Schedule shall include, but is not limited to, the following items:
a. Activities, for major submittals and long lead items including activities representing: (1)
Submittals, (2) Review & Approvals, (3) Fabrication, and (4) Deliveries, design, construction, inspections, close-out, start-up, testing and balancing, commissioning and turnover, and work by separate contractors. Submittal activities and fabrication activities shall not be cost loaded.
b. The Project Schedule shall indicate intended submittal dates, and depict the review period as defined in the Contract or Supplementary Provisions for A/E/GSA review.
Procurement/submittal activities shall be assigned codes that will allow these activities to be sorted and printed separately from the construction/close-out/commissioning work activities.
c. The Baseline Schedule shall have a Data Date no later than NTP, and no activities shall be progressed later than the data date
d. Activity descriptions of the work shall include area designators sufficient to identify where the Work will occur and match the Key Plans. The work related to each Activity shall be limited to one work trade and one area. All activity descriptions shall be unique. No two activities can have the same description.
e. Establish a schedule calendar as it relates to durations for activities (proposed number of working days per week, holidays to be observed, planned number of shifts per day, weather affected activities such as roofing or landscaping that normally cannot occur in the winter/fall months).
f. Interrelationships (logic) and sequencing for ALL activities. Each activity shall have at least one successor (except for the last activity) relationship to form a logically connected Network Plan from NTP to the Contract Completion Date. For each activity, at least one successor must be a finish relationship (finish to start or finish to finish).
g. The contractor shall provide (screen shots of) the schedule software settings used under each tab of User Preferences, Admin Preferences, and Schedule Options with the baseline schedule and each subsequent schedule submittal.
h. Activity durations shall be in units of whole work days and scope of work shall be limited to one trade each. Except submittal and procurement activities, durations shall not exceed 1 month unless approved by the GSA. Durations for Government submittal reviews shall meet the requirements set forth in the Contract Documents.
i. Incorporate seasonal weather conditions in the project’s geographic area into the project planning and include an average number of days lost to weather per month using the NOAA historical data five (5) year averages.
j. Contractual milestone events as defined in the Contract Documents including, but not limited to, phased work, work restrictions/access/shift work, and work being performed by separate contractors. The Contractor is prohibited from assigning milestones that are NOT consistent with key dates shown by GSA in the Contract Documents without specific GSA approval.
k. ALL activities shall at a minimum shall be coded by AREA, RESPONSIBILITY (trade/ subcontractor), and PHASE. Additional codes are allowed to sufficiently identify where work will occur. Codes shall be a maximum of six (6) characters and abbreviations shall be fully described in the Project Schedule. Include an activity code field Schedule of Values (SOV) for the coding of each schedule activity; this is for the tabulation and summarization of contractor assigned cost-loading Schedule of Values for application of Progress Payment Request reporting. (see 1.05.E.3 provides crosswalk of schedule to cost reporting) . The Contractor’s self-performed work shall be clearly identifiable.
C. Baseline Project Schedule
1. Upon approval of the Preliminary Schedule (scope and logic), the contractor shall cost load and manpower load the schedule and submit it as the proposed Baseline Schedule within (30) days of Notice of Award.
2. The Contractor shall submit to the Contracting Officer and in ePM the Baseline Project
Schedule per the CPM Project Schedule in the Agreement.
3. Except for certain procurement activities (not including fabrication or delivery), each Activity representing a portion of the work shall be cost and manpower loaded, unless otherwise approved by the GSA.
D. Baseline Schedule Review Process and Submittal Requirements
1. The GSA will review the Baseline Schedule and provide comments to the Contractor within one week of receipt of submittal and, if needed, will arrange for a Baseline Schedule Review
Meeting with the Contractor for discussion of the schedule. The Baseline Schedule, when approved, shall become the basis for the next monthly Schedule Update and Schedule Revision submitted by the Contractor.
a. In the event that GSA provides comments or the Baseline Schedule does NOT meet the requirements of this specification, the contractor shall, within five (5) work days, revise the Project Schedule to bring it into compliance with these requirements, and Contractor shall make a full Baseline Schedule submission for GSA’s review and approval.
b. Upon approval of the Baseline Schedule by the GSA, the cost-loaded values shown in the
Project Schedule and progress of activities will be used as a basis for determining progress payments. Monthly progress payments shall be based upon information developed using the current monthly Schedule Update. The computer generated cost report will be used by the GSA for verification of the Application for Payment submitted by the Contractor.
c. GSA's approval of the Baseline Project Schedule does not relieve the Contractor of responsibility whatsoever for the accuracy or feasibility of the Project Schedule, or of the Contractor’s ability to meet the Substantial Completion Date. Such acceptance does not create a warranty, expressed or implied, or acknowledge or admit the reasonableness of the activities, logic, durations, manpower, cost or equipment loading of the Contractor’s Project Schedule.
If the Contractor fails to timely submit the Baseline Schedule, the GSA shall withhold approval of progress payments until the Contractor submits the required Project Schedule.
2. The Baseline Schedule submission shall be comprised of the following, unless otherwise requested by GSA:
a. One (1) electronic copy of the entire Project Schedule shall be uploaded into ePM and one copy electronic copy in native format (that is, the format of the scheduling software) The electronic copy shall be in a compressed format. The electronic filename shall have a unique identifier. The file naming structure shall be concise and accurately describe the file (i.e. Irish Hall U1 (for update) or Irish Hall R1 for revision.) Hard copy prints and reports shall be generated from the same version of the Project Schedule that is provided in electronic form.
b. Hard copy print outs of reports as requested by the GSA including the information as requested by the GSA and sorted and organized in the manner requested by the GSA (i.e.One (1) Detailed Cost Report sorted by Responsibility (trade) code.then activity ID)
c. The Contractor shall prepare and submit cost loading graphic charts (i.e., S-Curve and monthly histogram), and it shall be computer generated from the Contractor’s schedule data. The graphic shall show actual and forecasted monthly cash flow in a histogram format, and the actual and forecasted cost over the planned project execution period shown on a cumulative cost curve using actual dates, early dates, and late dates.
d. The Contractor shall prepare and submit a manpower histogram depicting the monthly (or weekly if requested by the GSA) actual and forecasted manpower usage (in a histogram format) and the actual and forecasted cumulative manpower for the project execution period. The manpower-loading shall indicate the total number of workers, not total number of crews. The manpower charts shall be computer generated from the Contractor’s schedule data.
e. The Contractor shall submit a Schedule Calculation Summary Report which includes listings of constraints, open-ends, out-of-sequence work, and scheduling statistics. This report is computer-generated when the Project Schedule is calculated.
f. A narrative providing additional clarification/explanation of items such that GSA is informed of the approach used to plan and sequence the work, coordinate with other separate contractors to the extent applicable, and resource and cost load the Project Schedule.
E. Schedule Updates
1. The Contractor shall make at least two (2) separate Project Schedule submittals each month;
1) a Schedule Update that indicates only actual start dates, actual finish dates and duration percent completes since approval of the prior schedule. No new actual dates will be allowed prior to the data date of the current approved schedule ; and, if necessary, 2) a Schedule Revision incorporating changes (i.e., logic, durations, addition/deletion of activities, calendar, etc.) made to the schedule other than progress update information. The Schedule Update and Schedule Revisions shall be submitted together.
2. The Project Schedule shall be updated on a monthly basis throughout the entire Project performance period until Project completion is achieved.
3. The Contractor shall meet with the GSA each month at a Schedule Update Meeting to review the Contractor’s requested percent complete for actual progress achieved through the Data Date of the Schedule Update, and actual date information for activities that were started and/or completed during the reporting period. The Contractor’s progress payment request shall be computer-generated from the schedule data. The Contractor shall prepare a detailed cost report based on the prior month's progress payment request. Information to be shown on the computer-generated report shall include the prior month's percent complete, costs incurred during the period, costs incurred to date, and costs anticipated to completion. For each task, the costs shall be linked to and generated from the duration percent complete.
This report is to be used in the Schedule Update Meeting to present the current month's marked-ups detailing the Contractor's requested percent complete and costs earned this period.
4. The Schedule Update submission shall be comprised of the following:
one (1) electronic copy in native format (that is, the format generated from scheduling software0The electronic copy shall be in a compressed format. The electronic filename shall have a unique identifier referencing the Project name and shall include a sequential number for each monthly update. Hard copy prints and reports shall be generated from the same version of the Project Schedule that is provided in electronic form.
b. One (1) Cost Report sorted by Responsibility (trade) code unless otherwise requested by GSA.
c. One (1) Summary Cost Report sorted by Area code by Early Start.
F. Schedule Revisions:
1. Either GSA or the Contractor may request a Schedule Revision. Updating the Project
Schedule to reflect actual progress shall not be considered revisions to the Project Schedule.
2. A Schedule Revision is considered necessary under the following conditions:
a. If there is a significant change in the Contractor’s operations that will affect the Project
Critical Path.
b. Actual prosecution of the Work differs from that represented on the latest Schedule
Update.
c. There are additions, deletions, or revisions to activities required by Contract modification.
d. The GSA determines there is a reasonable doubt that milestones or the Substantial
Completion Date will not be met. The Schedule Revision (also known as a Recovery Schedule) shall demonstrate how the Contractor will reschedule the remaining work, at no additional cost to the government, through re-sequencing and/or reallocating its forces to complete the Work within the Substantial Completion Date.
3. The Schedule Revision submission shall be comprised of the following:
electronic copy in native format. The electronic copy shall be in a compressed format.
The electronic filename shall have a unique identifier referencing the Project name and shall include a sequential number for each Schedule Revision.
The following reports are not required with the “Update” submittal, but should be provided with the schedule “Revision”.
b. The Contractor shall prepare and submit cost loading graphic charts (i.e., S-Curve and monthly histogram), and it shall be computer generated from the Contractor’s schedule data. The graphic shall show the actual and forecasted monthly cash flow in a histogram format, and the actual and forecasted cost over the planned project execution period shown on a cumulative cost curve using actual dates, early dates, and late dates.
c. The Contractor shall prepare and submit a manpower histogram depicting both the monthly (or other time period as requested by the GSA) manpower usage (actual and forecasted in a histogram format) and the cumulative manpower for the planned project execution period. The manpower-loading shall indicate the total number of workers, not total number of crews. The manpower charts shall be computer generated from the Contractor’s schedule data.
d. Monthly narrative shall address the following:
i. Discussion of the longest path in the previous schedule at the beginning of the period.
ii. Discussion of progress achieved on the longest path.
iii. Explanation of any variance between the progress planned on the longest path and the actual progress achieved on the longest path.
iv. Discussion of the first three (3) near longest paths in the previous schedule at the beginning of the period.
v. Discussion of progress achieved on each of the first three (3) near longest paths.
vi. Explanation of any variance between the progress planned on the first three (3) near longest paths and the actual progress achieved on each of them.
vii. General description of the work on the forecasted longest path for the remainder of the project.
viii. Identification and discussion of work on the longest path planned to be performed during the next reporting period.
ix. Identification and discussion of work on the first three (3) near longest paths planned to be performed during the next reporting period.
x. Description of other Work (as requested by the GSA or that the Contractor deems necessary for communication purposes) anticipated to be performed during the next reporting period.
xi. Discussion of changes to the longest Path since the prior month’s approved schedule.
xii. Description of problem areas and anticipated problem areas.
xiii. Current and anticipated delays including cause of delay, corrective actions taken, and impact of the delay on other activities, milestones, and completion dates
xiv. Pending items (Change Orders, requests for time-extensions, etc.), and status thereof.
xv. Identification and explanation of items or information required from the GSA or third parties to avoid schedule impacts.
4. GSA will review and provide comments on the Schedule Update within one week of receipt of the Contractor’s submission.
5. If the Contractor fails to timely submit the Schedule Update, the GSA may withhold approval of progress payments until the Contractor submits the required Project Schedule Update and Revision.
a. All changes included in the Schedule Revision shall be documented. Contractor shall submit to GSA an audit trail report that has been prepared using schedule comparison software (i.e., Claim Digger, Project Investigator, etc.).
6. In the event of change modifications:
a. As determined by CPM schedule analysis, only delays determined to be solely caused beyond the control of the Contractor that protract the Substantial Completion Date will be considered for a time extension.
b. When change modifications are proposed, potential delays are anticipated, or delays are experienced, the Contractor shall submit to the GSA a written Time Impact Analysis describing the affect of each modification, potential delay, delay, or Contractor request on the Substantial Completion Date. This analysis shall be developed and submitted at the earliest time the Contractor becomes aware of a delay or potential delay, or as requested by the GSA. The preparation of Time Impact Analyses is considered part of the construction process and will be performed at no additional cost to the Government.
c. The time impact analysis (TIA) shall be performed on the current schedule of record at the time the impact or delay occurred. Because many schedule updates include forecasted recovery efforts, prior to performing the TIA, a status analysis shall be performed to determine schedule delays to date at the time of the impact. The status analysis shall compare the progress of work in the current schedule (or time of the impact if required by the GSA) against the approved baseline schedule or (subsequent approved, revised baseline schedule).
d. Schedule delays determined by the status analysis shall be quantified and assigned to the responsible party prior to incorporation of the time impact analysis into the current schedule of record. (For instance, if comparison of the current monthly update to the approved baseline schedule results in showing the project is behind schedule by one month, that one month of delay shall be inserted back into the current schedule as a fragnet prior to insertion of the fragnet representing the current impact or delay.)
e. Contractor shall submit its proposed schedule revisions in Fragnet form. Fragnets shall be accompanied by a detailed narrative explaining the reason for the revision, the anticipated effect of the revision on the Project Schedule and Substantial Completion Date, including describing the change in the affected activities’ Total Float value.
7. On Projects in which many fragnets are submitted in support of impacts to the Project, the
GSA may require periodic (weekly or monthly) Fragnet Meetings. Either party can propose fragnets in the fragnet meeting. In the Fragnet Meeting, each fragnet shall be accompanied with a spreadsheet depicting the following:
a. unique Fragnet Number,
b. date of the Fragnet,
c. schedule for the Fragnet to be inserted into,
d. data date of the schedule the fragnet is to be inserted into,
e. the predecessor activity ID and activity name the fragnet is proposed to be linked to,
f. The successor activity ID and activity name the fragnet is proposed to be linked to,
g. total float for the path prior to insertion of the fragnet,
h. anticipated total float after the fragnet is inserted.
i. Anticipated impact to the forecasted substantial completion date.
j. Failure of the Contractor to timely submit a Time Impact Analysis within the time stated in Paragraph 1.05.F.4.e below, shall mean that it is mutually agreed that the particular modification, delay, or Contractor request does not require an extension of the contract time.
k. Approval or rejection of each Time Impact Analysis by the GSA shall be made within one week after receipt of each Time Impact Analysis, unless subsequent meetings and negotiations are necessary. Upon approval, a copy of the Time Impact Analysis signed by the GSA shall be returned to the Contractor and incorporated into the Project Schedule at the next Schedule Revision which will be become the current approved Project Schedule.
l. The Contractor shall submit a Time Impact Analysis as follows:
i. Within five (5) work days after receipt of a written change modification.
ii. Within five (5) work days after receipt of a written notice by the GSA.
iii. Within five (5) work days from the beginning of a delay caused by unforeseeable circumstances.
m. The Time Impact Analysis shall meet the requirements for submittal of a Schedule
Revision including a Fragnet (see Section 1.05.F.3.c) with sufficient supporting documentation to enable the GSA to make a determination on the Contractor’s request for time extension.
G. As-Built Schedule
1. Along with the final pay application, the Contractor shall submit an As-Built Schedule documenting actual start and actual finish dates for all activities, and logic ties between all activities to show the actual sequence in which the work was performed.
1.06 RESPONSIBILITY FOR COMPLETION
A. If, in the opinion of the GSA, the Contractor falls behind the planned progress as noted by negative float shown on the current monthly Schedule Update, the Contractor shall take any and all steps necessary to improve its progress at no additional cost to the Government. This shall not be construed as prohibiting the Contractor from increasing the number of working hours, shifts per day, working days per week, or the amount of construction equipment, or any combination of the foregoing, to eliminate the delay in the scheduled progress.
B. Failure of the Contractor to comply with the requirements of the GSA under Paragraph 1.06.A shall be grounds for determination by the GSA that the Contractor is not prosecuting the work with such diligence as will ensure completion within the contract time. Upon such determination, the GSA may terminate the Contractor's right to proceed with the work, or any separable part thereof, in accordance with the applicable provisions of the contract.
1.07 PAYMENTS TO CONTRACTOR
A. The GSA shall review the Contractor's monthly request for payment upon receipt and shall process the request for payment based upon the current approved Schedule Update. The GSA will consider the Contractor's overall progress toward Project Completion along with the progress for discrete activities to determine the amount to be approved for the monthly payment request.
1.08 PERFORMANCE MONITORING
A. The GSA may elect throughout, or at any time during the Project, to record the number of workers and construction equipment working on each construction schedule activity in each area of the Project. The GSA's request for this information will be without additional cost to the Government and shall be provided within one week of receipt of the GSA's written request. This information will be used by the GSA to evaluate the adequacy of the Contractor’s performance and project manpower staffing, as well as any Contractor claims.
B. The Contractor is required to attend construction coordination meetings. As such, the Contractor shall present a printout of the current approved schedule depicting only the work planned for the month The bar chart should be sorted by Area by Total Float or as requested by the GSA.
Information to be shown on the bar chart includes: Activity ID, calendar, Activity Description, Original Duration, Remaining Duration, Percent Complete, Early Start/Actual Start, Early Finish, and Total Float.
1.09 SCHEDULER REQUIREMENTS/QUALIFICATIONS
A. Within five (5) work days after the date of Notice to Proceed, the Contractor shall designate in writing an authorized scheduler or scheduling representative in the Contractor’s organization who shall be responsible for coordinating with the GSA during the preparation and maintenance of the Project Schedule. Contractor's scheduler shall possess demonstrated proficiency in CPM schedule methodology and use of the current version of a Project Planner software.
B. The Contractor’s scheduling representative is considered key personnel by GSA. As such, GSA shall have the right to review the qualifications of the individual assigned as the scheduling representative. The Contractor’s scheduling representative shall have complete authority to act on behalf of the Contractor in fulfilling the Project Schedule requirements of the Contract. The Contractor shall notify GSA in writing of any proposed changes in this position, and shall not change/substitute the scheduling representative without the prior written consent of the GSA.
C. The Contractor agrees that whenever GSA shall inform the Contractor in writing that the
Contractor’s scheduling representative is not performing his duties to the satisfaction of the Government, the Contractor shall change such representative at no additional cost to the Government and designate in writing, within one week of notification from the GSA, a new authorized representative satisfactory to the GSA.
D. The Contractor’s project superintendent, and the scheduling representative and, to the extent applicable, the personnel responsible for developing and inputting information into the Project Schedule shall attend schedule related meetings and monthly update meetings throughout the duration of the Project.
END OF SECTION
CABLE TRAYS FOR ELECTRICAL SYSTEMS 260536
SECTION 260536 – CABLE TRAYS FOR ELECTRICAL SYSTEMS
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This section includes cable trays and accessories.
1.3 SUBMITTALS
A. Product Data: Include data indicating dimensions and finishes for each type of cable tray indicated.
1.4 QUALITY ASSURANCE
A. Source Limitations: Obtain cable tray components through one source from a single manufacturer.
B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.
C. Comply with NFPA 70.
1.5 DELIVERY, STORAGE, AND HANDLING
A. Steel, electrogalvanized cable tray shall be stored in a well-ventilated, dry location. Unpack and dry wet materials before storage.
1.6 PROJECT CONDITIONS
A. Environmental Limitations: Do not deliver or install cables and connecting materials until wet work in spaces is complete and dry, and temporary HVAC system is operating and maintaining ambient temperature and humidity conditions at occupancy levels during the remainder of the construction period.
PART 2 - PRODUCTS
2.1 PATHWAYS
A. General Requirements: Comply with TIA/EIA-569-A.
B. Cable Support: NRTL labeled for support of Category 6 cabling, designed to prevent degradation of cable performance and pinch points that could damage cable.
1. Support brackets with cable tie slots for fastening cable ties to brackets.
2. Lacing bars, spools, J-hooks, and D-rings.
3. Straps and other devices.
C. Cable Trays:
1. Manufacturers: Subject to compliance with requirements, Provide products by one of the following:
a. Cable Management Solutions, Inc.
b. Cablofil Inc.
c. Cooper B-Line.
2. Cable Trays, Fittings, and Accessories: Steel, complying with NEMA VE 1.
a. Electrogalvanized zinc, complying with ASTM B 633; with hardware galvanized according to ASTM B 633.
b. Basket Cable Trays: To be used outside of telecommunication closets, 4” deep with width as indicated on plans. Field verify and coordinate with other trades to provide adequate space.
c. Sizes and Configurations: Four inch deep wire mesh with widths as indicated on plans.
1) Center-hanger supports may not be used.
2.2 CABLE TRAY ACCESSORIES
A. Fittings: Tees, crosses, risers, elbows, and other fittings as indicated, of same materials and finishes as cable tray.
B. Cable tray supports and connectors, including bonding jumpers, as recommended by cable tray manufacturer.
C. Cable Support To/From Cabletray: NRTL labeled for support of Category 6 cabling, designed to prevent degradation of cable performance and pinch points that could damage cable.
1. Support brackets with cable tie slots for fastening cable ties to brackets.
2. Lacing bars, spools, J-hooks, and D-rings.
3. Straps and other devices.
PART 3 - EXECUTION
3.1 CABLE TRAY INSTALLATION
A. Cable Trays: Comply with NEMA VE 2 and TIA/EIA-569-A-7.
B. Cable trays shall be installed per manufacturer’s instructions.
C. Cable trays shall be grounded and all subsequent individual pieces shall be bonded together.
D. Cable trays shall be installed with a minimum of 12 inches of clearance above finished ceiling.
E. Comply with recommendations in NEMA VE 2. Install as a complete system, including all necessary fasteners, hold-down clips, splice-plate support systems, barrier strips, hinged horizontal and vertical splice plates, elbows, reducers, tees, and crosses.
F. Remove burrs and sharp edges from cable trays.
G. Fasten…