Addendum No. 1
Project: GSA McNamara Federal Building Project No: 15005.00
Date: June 22, 2017
Notice
This addendum is issued by the Architect to all known individuals, firms or corporations who have obtained or received bidding documents and contract documents for the above-listed project. This addendum is hereby made a portion of bidding documents or contract documents, as appropriate. It is issued for the purpose of amplifying, clarifying or correcting originally issued bid documents. Bidders are required to acknowledge receipt of this addendum in the appropriate space on bid form.
I . T .
Item AD1-G1 – I.T. Documents Refer to Attached Schneider Electric Documents:
A R C H I T E C T U R A L
Item AD1-A1 – 11TH Floor Swing Space Refer to Sheet AE101:
Additional swing space information has been provided.
Item AD1-A2 – 12TH Floor Swing Space Refer to Sketch AD101:
Item AD1-A3 – 14TH Floor Swing Space Refer to Sketch AD103:
Item AD1-A4 – 12TH Floor Phasing 3A & 3B areas swapped.
Refer to all 12th floor plans:
Phases are to be swapped. Phase 3A will be on the East side and Phase 3B on the West side.
Item AD1-A5 – Revise Spec Section 012100 Allowances Refer to attached Spec Section 012110:
Allowance No. 2 has been added for the relocation of staff items.
Allowance No. 3 has been added for damaged or shortfall in demountable wall panels and demountable wall doors and frames.
Item AD1-A6 – Add Spec Section 013110 Critical Path Method Sched.
Refer to attached Spec Section 013110:
Entire spec section is to be added to the documents.
Item AD1-A7 – Revise Spec Section 013110 Summary Refer to attached Spec Section 011000:
Entire schedule is replaced.
Item AD1-A8 – Revise Phasing Plans to include Maintained Egress Paths through construction zones.
Refer to attached Sheets GC102, GC103, GC104:
Maintain egress path - the construction area is to provide a clear exit path to the exit door from the neighboring occupied phase in the case of a fire alarm. The door in the rated construction wall separating the occupied space and the construction phase is to be secured electronically and tied to the security/ alarm system and is to fail safe (unlocked) in the case of alarm or power failure. This door can be re-used from phase to phase in the construction walls. The path from this door to the exit door on the construction side into the main corridor is to remain clear during occupied hours. It should be free of construction materials, tools, trash, etc. Work in this path area should be performed during unoccupied hours.
F I R E S U P P R E S S I O N
Item AD1-F1 – Fire Suppression Revisions Refer to Reissued Drawing FX101:
Revise designations at phasing boundaries: Previous phase 3A, now phase 3B.
Previous phase 3B, now phase 3A.
P L U M B I N G
Item AD1-P1 – Plumbing Revisions Refer to Reissued Drawing P102:
M E C H A N I C A L
Item AD1-P1 – Mechanical Revisions Refer to Reissued Drawing MD101:
Revise designations at phasing boundaries: Previous phase 3A, now phase 3B.
Previous phase 3B, now phase 3A.
Refer to Reissued Drawing M101:
Revise location of SF-12.N, VFD-12.N, EDH-12.N, duct smoke detector from NW to
NE corner of building. Revise layout and duct sizes to reflect opposite end feed.
Revise location of SF-12.E, VFD-12.E, EDH-12.E, duct smoke detector from SE to NE corner of building. Revise layout and duct sizes to reflect opposite end feed.
E L E C T R I C A L
Item AD1-E1 – Power Revisions Refer to Re-issued Sheet FA101:
See revised locations of duct smoke detectors associated with SF-12.N & SF-12.E.
Refer to Re-issued Sheets ED101 & ED103:
Provide branch circuits and data drops for swing spaces designated with keynote #4.
Refer to Re-issued Sheet EP101:
See note pertaining to additional electrical work on eleventh floor.
See (10) additional security device power transformer locations.
Omit (4) security device power transformer locations in core telephone closets.
Refer to Appeals 1241 o Provide (1) additional receptacle for wall mounted television, fed from circuit as shown.
See revised location of mechanical equipment:
o SF-12.N, VFD-12.N, EDH-12.N o SF-12.E , VFD-12.E, EDH-12.E
Refer to Re-issued Sheet EP102:
See (6) additional security device power transformer locations.
Omit (4) security device power transformer locations in core telephone closets.
Refer to Open Office 1303 o See revised printer and copier locations.
Refer to Training Room 1306 o North receptacle revised from double duplex to duplex.
Refer to A/V Room 1307 o Provide (1) additional branch circuit and receptacle for security panel as shown.
Refer to Corridor 1313 o Omit receptacle.
Refer to Training Room 1312 o North receptacle revised from double duplex to duplex.
Refer to Open Office 1318 o Omit utility circuit feeding workstation locations WP-1 through WP-4.
o Omit (1) circuit feeding workstation locations WP-14, 15, 18, 19 & 20.
Refer to Open Office 1323 o Omit (1) circuit feeding office furniture for workstation locations WP-48, WP-
49 & WP-52.
o Feed workstation location WP-66 from circuit as shown.
Refer to Open Office 1329 o Omit (1) circuit feeding column mounted receptacle as shown.
o Revise circuit of printer 17 from RP13B-11 to RP13B-14.
o Revise circuit of printer 11 from RP13B-12 to RP13B-4.
Refer to Office 1338 o Provide (2) additional branch circuits as shown.
Refer to Re-issued Sheet EP103:
See (12) additional security device power transformer locations.
Omit (4) security device power transformer locations in core telephone closets.
Refer to Conference 1401 o Revise circuiting of utility receptacles as shown.
o Omit utility circuit from (3) power poles as shown.
Refer to Mailroom 1416, Special OPS 1419, IPC Distribution 1421.
o Revise circuiting of utility receptacles as shown.
Refer to Conference 1442 o Provide (1) additional branch circuit as shown.
Refer to OI&T 1469 o Omit utility circuit feeding workstation locations WP-72 through WP-74.
Refer to SD 1411 o Omit utility circuit feeding workstation locations WP-59 through WP-60.
Refer to Special OPS 1419 & IPC Sorting / Distribution 1421 o Omit (5) utility circuits feeding workstation locations.
Refer to Re-issued Sheet ET101 & ET103:
See revised cable tray paths.
Refer to Re-issued Sheet EY102:
Omit (6) maglock locations.
Refer to Re-issued Sheet EY103:
Omit (5) maglock locations.
Refer to Re-issued Sheet EL101:
Refer to Shared Conference Room 1239 o Omit (4) fixtures of type RA.
o Provide (6) fixtures of type RD in locations as shown.
Refer to Sheets E602,E603 & E604 re-issued for clarification:
See revised panel circuit descriptions.
END OF ADDENDUM No. 1