MD Repair and Alteration IDIQ Federal contract opportunity
Solicitation number
GS-03-P-16-CD-D-7000
Issued by
General Services Administration Public Buildings Service Central Office Acquisition Services Division

About this file

Not Listed

View the file

Other files for this federal contract opportunity

Other files attached to MD Repair and Alteration IDIQ, newest first.
File Type Posted
Amendment_0002.pdf PDF
Solicitation_Package_(GS-03-P-16-CD-D-7000).zip ZIP file
GS-03-P-16-CD-D-7000_Generated_PDF_with_TOC.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

Description of Amendment/Modification

Amendment 0001 hereby amends Solicitation GS-03P-16-CD-D-7000 to include the following: -Delete Sec. IIB., number 2 (page 72), âBid Scheduleâ from the solicitation. However, this item shall be replaced with an âOfferor Provided Cost Structureâ using guidance in Sec, II.C. âPrice Proposal,â number 1 (page 72). -Correct SF1442 to require a bid bond. -Amend VI. A, 2) "Non-Price Factors" (page

86) to state the following: (2) Non-Price Factors, when combined, are significantly more important than Total Evaluated Price. -Block 13

d. of the SF 1442 shall be filled in with "Offers providing less than_130____calendar days..." -Corrects the contract number in solicitation package to GS-03P-16-CD-D-7000. Amendment 0001 also incorporates Q&A, meeting minutes and the sign in sheet from the pre-proposal meeting on January 5, 2016. An extension to the due date is not anticipated. The closing date remains the same at January 22, 2016.

1). Section II.D (1) Past Performance states that “All completed Owner Reference/Evaluation forms shall be completed by the owner and mailed directly to the GSA Contracting Officer…”. Is it possible for our POCs for the evaluation form to email DIRECTLY to the Contracting Officer instead of postal mail?

Emails will be accepted as long as they are sent from the reference and are addressed ONLY to samantha.bohne@gsa.gov.

2). Section II.D (2) Prior Experience requests that 2 of the projects be at least $75,000 in value. It doesn’t state if the two projects need to stay within the $150,000 threshold or if they can be more than $150,000. Please clarify.

Prior experience should be of similar projects within a similar threshold. It is beneficial to show us that you have successfully completed projects similar to the task orders the field office will be awarding, which will be between $30150K.

3). Was this resolicited? If so, then why was the first solicitation for this term contract cancelled in the first place?

Yes, this term contract was resolicited. The first solicitation was cancelled due to the solicitation language for technical proposal criteria differing from our source selection plan. Due to this, a vast majority of offerors submitted projects in their proposal that were not deemed relevant to the term contract. After discovery the discrepancy in the solicitation language, it was decided to cancel the solicitation.

4). C (1) states “The Price Proposal shall consist of the SF 1442 and the Agreement, with prices and/or rates indicated for labor, materials, markups, and overhead and profit. Indicate the Base Contract Price, or if no such distinction is made, the Contract Price, in Block 17 of the SF 1442, which must be fully executed by the Offeror.” In Review of the solicitation we found no price, cost or bid form. Please clarify.

Please submit your offer on the SF 1442 and submit a separate sheet breaking out the prices/rates for labor, materials, markups, and overhead and profit.

5). There is a sample project included in the solicitation. Is this to be priced and included in the proposal?

Yes, the project should be priced.

6). II.B states that a completed bid schedule is to be included in the proposal.

Has the bid schedule been omitted?

mailto:samantha.bohne@gsa.gov

Amendment 0001 will delete Sec. IIB., number 2 (page 72), “Bid Schedule” from the solicitation. However, this item shall be replaced with a “Offeror Provided Cost Structure” using guidance in Sec, II.C. “Price Proposal,” number 1 (page 72).

7). SF1442 13b states that a bid bond is not required however 4.a states that a 20% bid is required. Please clarify.

Please submit a bid bond for the seed project. Amendment 0001 corrects SF1442. A bid bond will be required.

9). II.D (1) Note 1 requires “Owner Reference/Evaluation” form to completed by the owner and sent directly to GSA.There is no Owner Reference/Evaluation form in the solicitation.

This sheet is included in the package. Please see pages 636639

10). VI.2 states “(2) NonPrice Factors, when combined, are significantly more important than/significantly less important than/equal in importance to Total Evaluated Price.” Please clarify.

VI. A, 2) will be amended to state the following:

(2) NonPrice Factors, when combined, are significantly more important than Total Evaluated Price.

11). Page 103 of 659 contains a sample project. Is the offeror to price this project for the proposal?

Yes.

12). What is the deadline for questions?

1/12/2016

13). Standard Form 1442. Please provide a value for Block 13d.

d. Offers providing less than_130____calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

This will be corrected in Amendment 0001.

14). MD Repair and Alteration IDIQ, Section I.D, PreProposal Conference. Please provide minutes and list of all attendees from this conference.

Meeting minutes and the signin sheet are attached.

15). MD Repair and Alteration IDIQ, Section II.B, Proposal Format (page 72). Please clarify the number of hard and electronic copies of the Price and Technical Proposals.

This section also refers to a “Completed Bid Schedule”. Where is the template for this?

Amendment 001 clarifies language for Sec, II. B “Proposal Format”: Please provide one electronic copy of the price and technical proposal. There is no bid schedule. Please see the answer for question 6.

16). MD Repair and Alteration IDIQ, Section II.C.(1), Price Proposal, Contents (page 72).

The first sentence mentions an “Agreement”. What is being referred to here?

The “Agreement” is the C101 included in the solicitation package.

17). MD Repair and Alteration IDIQ, Section II.D.(2), Prior Experience on Comparable Projects (page 74). This section calls for projects with a construction value between $2,000 and $150,000. Will we be penalized for submitting projects in excess of $150,000?

Seems like larger projects are just as relevant, maybe more so in terms of being able to manage schedule, cost, and quality.

Please refer to the answer for question number 2.

18). Basement Corridor Paint and Wallguard Project, Drawing (page 635). Is this drawing to scale? If so, what is the scale?

No

19). Do you have a linear footage measurement for the basement corridors? As well, how high are the ceilings in the basement? Are the ceilings the standard 8’ or are they higher due to it being a basement area? I cannot read any scale off the drawing.

330’ of corridor walls with 8’6” ceiling height (drop ceiling).

75’ of corridor walls with 14’4” ceiling height (drywall ceiling w/exposed plumbing & electrical pipes).

The linear feet measurements above includes door openings.

20). We are looking to team with our mentor and one other company. Is it required that we have a formal teaming agreement submitted with our proposal and do all teaming partners have to complete the 527 form?

Offerors must submit a SBA approved teaming agreement, specifically 8(a) certification.

21). According to the solicitation, paragraph II.C, each offeror must submit a cost structure containing pricing for labor hours, materials, and markups. However, at the prebid conference, the CO mentioned that he didn’t need a breakdown on pricing, but just the lump sum. Could you confirm. Also, the mention of completions of a bid schedule per paragraph II.B. We did not see a template of form to follow.

Please create and submit your own pricing sheet containing pricing for the areas stated in the solicitation.

22). While onsite we noticed more than one area that requires door stops, within the scope of work area. Please confirm quantity.

This may be correct, but the scope of work remains the same.

23). Does a joint venture between an 8(a) and a non8(a) have to be already approved by the SBA?

Yes, please submit SBA approval.

24). According to Section II. C., paragraph 3, there is mention of negotiated rates. Will the Government be providing labor categories for offerors to supply pricing? Please clarify.

No, the government will not provide labor categories for the seed project.

25).Can you tell me if there is commissioning on this project? We are very interested in providing commissioning services for the GSA and PBS.

This is a repair and alteration contract.

26). I just noticed that the solicitation package for the above job has been posted yesterday. When opening the documents they both refer to

GA03P16CDD0007.

Please refer to this project as GS03P16CDD7000. The amendment will correct this.

PRE-PROPOSAL CONFERENCE

Repair and Alteration Services

January 5, 2016, 10:30 a.m.

Maryland IDIQ for Repair and Alteration Services George H. Fallon Federal Building, 31 Hopkins Place, Baltimore, MD

• Sign In/ Welcome/Introduction of GSA personnel

• Daniel Langan, GSA Contracting Officer

• Samantha Bohne, GSA Contract Specialist

• Paul Alba, GSA Contracting Officer’s Representative

• Patrick Acierto, GSA Source Selection Board Member

• Oliver Lester, GSA Source Selection Board Member

THE PURPOSE OF THIS CONFERENCE IS TO ANSWER ANY QUESTIONS AND TO GIVE OFFERORS THE OPPORTUNITY TO IDENTIFY AMBIGUITIES IN THE SPECS, DRAWINGS OR SOLICITATION REQUIREMENTS.

WHEN POSSIBLE, PROSPECTIVE OFFERORS QUESTIONS SHALL BE ANSWERED. THOSE ANSWERS

WHICH REQUIRE FURTHER STUDY SHALL BE DEFERRED. QUESTIONS SHOULD BE EMAILED TO GSA, ATTENTION SAM BOHNE AT SAMANTHA.BOHNE@GSA.GOV.

CONTRACTORS ARE NOT TO CALL THE COR OR OTHER BOARD MEMBERS DIRECTLY. OFFERORS ARE ADVISED THAT ORAL REMARKS & EXPLANATIONS MADE BY GOVERNMENT REPRESENTATIVES DURING THIS CONFERENCE DO NOT QUALIFY THE WRITTEN PROVISIONS OF THE REQUEST FOR PROPOSAL DRAWINGS & SPECS. ONLY THOSE CHANGES TO PROVISIONS OF RFP, DRAWINGS & SPECS THAT ARE COVERED BY A WRITTEN AMENDMENT SHALL BE CONSIDERED OFFICIAL. WHEN THE AMENDMENT IS

ISSUED,PROCEDURES RELATED TO THE ACKNOWLEDGMENT & RECEIPT OF THE SOLICITATION

AMENDMENTS SHALL BE NOTED.

1. Contract Type: Firm Fixed Price

2. This procurement is under NAICS code 236220 (Commercial and Institutional Building

Construction)

3. Procurement Preference: Eligible 8(a) Concerns

4. Period of Contract: One year base with five option years.

5. Bonding Requirements (for individual task orders) :

a. A bid bond in the amount of 20% of the proposed price must be submitted along with the actual bid.

b. (For future projects a performance bond may be required) A performance bond, for 100% of the contract price, and a payment bond, for 100% of the contract price, will be required within 10 days after award of the project.

6. Green Purchasing Requirements: The scope of work requires the use of applicable green products. The contractor must submit at least one Green Products Final Report to GSA that states the actual quantity and cost of the green products used on the contract. The contractor must state in the Green Products Final Report the total combined cost of all products (both green and non-green products) used on the contract.

mailto:SAMANTHA.BOHNE@GSA.GOV

7. Insurance Requirements: After contract award, the contractor must furnish the Contracting Officer with a current Certificate of Insurance, listing the Government as co-insured party and meeting the requirements specified in this solicitation (C 101.

Sec. III. L, Insurance Requirements). The contractor may not begin actual work on site until this certificate has been received and found acceptable.

8. Financial information is also required. We prefer the GSA Form 527 to be submitted with the bid.

9. Other submission requirements:

• C. 301, Offeror Representations and Certifications

• Owner Reference/Evaluation Worksheets (Completed and submitted by reference)

• SF1442

10. Contractors are to pay the Minimum Wage and Fringe Benefits required by the

Davis-Bacon Act. Wages should be based on General Decision Number

MD150045, 07/31/2015.

11. PROPOSAL DUE DATE:

January 22, 2016, 4 p.m. Eastern Time

12. Submit Offerors to:

General Services Administration The DOW Building 100 S. Independence Mall W#5 ATTN: Samantha Bohne, 3PQXA Philadelphia, PA 1916-2321

13. *All contractors are reminded that anything said at this meeting or at any time before the Proposal Due date does not constitute a change in the solicitation. The only changes to the solicitation will be those made in a formal amendment issued only on the fedbizopps.gov website.

14. QUESTIONS AND COMMENTS

Do we need to submit projects of the same scope and dollar value on references?

Yes.

Do the reference sheets have to be sent to you by the 22?

Yes.

What will be the dollar value of each task order?

$30K-150K Is there a cap on how much each offeror could get?

$7.5 million -You should be submitting a solid proposal. It is the intent to streamline and not do much negotiation.

Is today’s meeting mandatory?

No Could we have more information on the $2,500 minimum guarantee?

Contractors who are chosen for the IDIQ will be guaranteed $2,500 if they are not awarded a task order within the first year. However, contractors must submit bids to projects in order to be eligible.

When are questions due?

Submit questions in writing by COB next week on Tuesday, January 12, 2016.

What areas does this IDIQ cover?

The whole state of Maryland.

-Pricing should be submitted on your own pricing sheet including the categories discussed in the solicitation.

15. WALK THROUGH

topmostSubform[0]:
Page1[0]:
Code[0]: 3PQXA
Copies[0]: 1
CheckBox9[0]: 1
Code[2]: 3PQXA
NameandTitleOfficer[0]: Daniel Langan
Is[0]: 1
CheckBox10[0]:
NameandAddress[0]:
DateSigned[1]:
Pages[0]: 3
AmendmentNo[0]: 0001
Dated10B[0]:
ModificationNo[0]:
AdministeredBy[0]: GSA REGIONAL CONTRACT SUPPORT SVCS BRANCH

100 S. INDEPENDENCE MALL WEST

PHILADELPHIA, PA 19106

FacilityCode[0]:
CheckBox13B[0]:
CheckBox13D[0]:
ReqNumber[0]: EQ3PSSB-16-5009
Dated9B[0]: 12/14/2015
C13[0]:
Description[0]: See Attached
NotExtended[0]: 1
Code[1]:
AmendmentNo[1]: GS-03-P-16-CD-D-7000
ContractIDCode[0]:
DateSigned[0]:
CheckBox11[0]: 1
Page[0]: 1
AccountingData[0]:
CopiesReturned[0]: 1.
CheckBox13A[0]:
IsNot[0]:
EffectiveDate[0]: 1/14/2016
A13[0]:
ProjectNo[0]:
CheckBox13C[0]:
Extended[0]: 0
D13[0]:
IssuedBy[0]: GSA REGIONAL CONTRACT SUPPORT SVCS BRANCH