ARRA: COMMERCIAL ITEMS PROCUREMENT FOR TECOGEN CO-GENERATION UNIT ADVANCED METERING INSTALLATION WILLIAMS COAST GUARD BUILDING

GS-01P-11-BZ-C-0032

Questions & Answers (Current as of 20 September 11)

1. Question: Does the scope include metering the PV? Can GSA clarify this requirement?

Answer: Yes. the metering project is envisions metering the CoGen unit, installation of a Btu meter, and monitoring the PV system, all connected to the existing advanced metering ION 7650, so that we can get the data on our server.

1. Question: Does the job require a security clearance?

Answer: Yes. If contractors do not have a full NACI clearance, contractors and subcontractors may still be able to perform work in the federal building with either an escort or a pre-favorable clearance letter. If you are awarded the contract, PBS Security staff will assist you in application for clearances.