This is a Pre-Proposal Conference presentation for a federal dredging contract solicitation issued by the U.S. Army Corps of Engineers Jacksonville District.
Solicitation Details and Scope: Solicitation Number GROUP1-26-R-J002 covers maintenance dredging of Fort Myers Beach Harbor in Lee County, Florida. The work includes dredging the channel, wideners, and settling basin, with excavated material to be transported to and placed in a nearshore placement area. Incidental work encompasses environmental and water quality monitoring. The estimated construction magnitude ranges from $5,000,000 to $10,000,000. The contract utilizes a Small Business Dredging MATOC (Multiple Award Task Order Contract) task order mechanism under a 100% small business set-aside with a Firm-Fixed Price (FFP) contract type governed by FAR Part 15. Proposals will only be considered from firms listed in the Group 1 Dredging MATOC Pool.
Key Administrative Requirements and Timelines: Proposals must be submitted electronically via PIEE (Procurement Integrated Enterprise Environment) no later than May 15, 2026, at 2:00 p.m. EDT. The contractor must commence work within 60 calendar days of receiving the notice to proceed and complete all work within 210 calendar days total (140 days base plus 70 days for Option A), with liquidated damages set at $1,277 per day of delay. A bid guarantee of 20% of the bid price or $3,000,000, whichever is less, is required. The applicable NAICS code is 237990 with a small business size standard of $37.0 million. Award will be made using a Lowest Price, Technically Acceptable (LPTA) evaluation method based on three factors: Availability of Technically Acceptable Dredge(s), Past Performance (no submission required), and Price. Technical inquiries must be submitted via ProjNet, which closes May 1, 2026, at 5:00 p.m. EDT. A site visit was held on April 22, 2026, and the pre-proposal conference occurred on April 29, 2026.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| GROUP1-26-R-J002 Site Visit Sign_In Sheet_April 22 2026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Working Today to Build a Better Tomorrow
Pre-Proposal Conference
Presented by:
Jacksonville District
April 29, 2026
SOLICITATION NO. GROUP1-26-R-J002
FORT MYERS BEACH HARBOR, MAINTENANCE DREDGING
LEE COUNTY, FLORIDA
Thank you for joining, we will begin shortly.
Please mute your microphone and put your name/company in the chat.
PRE-PROPOSAL CONFERENCE: AGENDA
• INTRODUCTION
• PROJECT OVERVIEW
• CONTRACTING OVERVIEW
• OTHER ADMINISTRATIVE ITEMS
• RESOURCES
• CLOSING REMARKS
CONTRACTING OVERVIEW
Timothy Humphrey, Contracting Officer
Email: Timothy.G.Humphrey@usace.army.mil
Guesley Leger, Contract Specialist Email: Guesley.Leger@usace.army.mil mailto:Griselle.Gonzalez@usace.army.mil mailto:Meredith.C.Gonzalez@usace.army.mil
PROJECT OVERVIEW
PRE-PROPOSAL CONFERENCE: PROJECT OVERVIEW
SOLICITATION NUMBER: GROUP126RJ002
PROJECT TITLE: Fort Myers Beach Harbor, Maintenance Dredging Lee County, Florida
DESCRIPTION OF WORK: Project work consists of maintenance dredging Fort Myers Beach Harbor including the channel, wideners, and settling basin. Excavated material must be transported to and placed in the nearshore placement area. Incidental work includes but is not limited to environmental and water quality monitoring.
CONTRACTING OVERVIEW
7PRE-PROPOSAL CONFERENCE: ACQUISITION
APPROACH
Solicitation No. GROUP126J002
• Contracting Method: Small Business Dredging MATOC Task Order – Request for Proposals (RFP) IAW Far Part 15, 100% Small Business Set-Aside.
***Proposals will not be considered from any entity other than the listed firms included in the Group 1 Dredging MATOC Pool***
• Type of Contract: Firm-Fixed Price (FFP). (FAR clause 52.216-1)
• Transmission Method: Electronically via Procurement Integrated Enterprise Environment (PIEE). Proposals must be received by the Government no later than May 15, 2026, at 2:00 pm (EDT). Please see Enclosure 2, Proposal Submission Requirements, for more details.
PRE-PROPOSAL CONFERENCE: GENERAL INFORMATION
• Estimated Magnitude of Construction: $5,000,000.00 - $10,000,000.00.
• Applicable North American Industry Classification System (NAICS): 237990 (Exception), Dredging and Surface Cleanup Activities. The Small Business Size Standard for dredging is $37.0 million.
• Estimated Period of Performance: The Contractor shall be required to (a) commence work under this contract within sixty (60) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than two hundred and ten (210) calendar days after the Contractor receives the notice to proceed. Total includes 140 calendar days for the Base and 70 calendar days for Option A. The time stated for completion shall include final cleanup of the premises..
52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR
1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the contractor on or before September 30, 2026. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
• Liquidated Damages: $1,277.00 for each calendar day of delay until the work is completed or accepted. (FAR clause 52.211-12)
• Bid Guarantee: electronic copy of the bid guarantee shall be submitted with the bid. The bid guarantee shall be 20% of bid price or $3,000,000.00, whichever is less. (FAR 52.228-1)
• Evaluation: Task Order award will be made on the basis of Lowest Price, Technical Acceptable (LPTA) evaluation method. To be considered technically acceptable, an offeror’s proposal must be rated “Acceptable” under all non-price factors.
• FACTOR 1 – Availability of Technically Acceptable Dredge(s)
• FACTOR 2 – Past Performance (NO SUBMISSION REQUIREMENT)
• FACTOR 3 – Price
SITE VISIT:
• Held on Wednesday, April 22, 2026, at 10:30 am EDT.
TECHNICAL INQUIRIES AND QUESTIONS:
• ProjNet closes on May 1, 2026, at 5:00 pm, EDT.
• All Inquiries must be submitted via ProjNet for an official answer.
PRE-PROPOSAL CONFERENCE: OTHER ADMINISTRATIVE
ITEMS
PRE-PROPOSAL CONFERENCE: RESOURCES
System for Award Management (SAM):
www.sam.gov
Procurement Integrated Enterprise Environment (PIEE):
https://piee.eb.mil/
ProjNet:
www.projnet.org http://www.sam.gov/ https://piee.eb.mil/ http://www.projnet.org/
PRE-PROPOSAL CONFERENCE: QUESTIONS
Please submit any questions via ProjNet.
ProjNet closes on May 1, 2026, by 5PM EDT.
Solicitation Number is: GROUP126RJ002 Bidder Inquiry Key is: REMJ79-SXA7SQ
PRE-PROPOSAL CONFERENCE: CLOSING REMARKS
Thank you!
Presenter Notes Presentation Notes According to the Town, the use of Palm Ave for crane access to the nearby house construction project is planned for on approximately April 27-28, May 25-26, June 21-22 and July 30-31. The dates provided may differ by several days but should generally be when the crane accesses the beach. The house builder must provide notification at least 48 hours in advance for each time when the crane is proposed to access the beach.
| ����Solicitation No. group1-26-R-j002��Fort Myers Beach Harbor, Maintenance Dredging Lee County, Florida���� |
| PRE-PROPOSAL CONFERENCE: AGENDA |
| Slide Number 3 |
| Slide Number 4 |
| ��PRE-PROPOSAL CONFERENCE: PROJECT OVERVIEW�� |
| Slide Number 6 |
| PRE-PROPOSAL CONFERENCE: Acquisition APPROACH |
| PRE-proposal CONFERENCE: GENERAL INFORMATION |
| PRE-proposal CONFERENCE: GENERAL INFORMATION |
| PRE-proposal CONFERENCE: GENERAL INFORMATION |
| ��PRE-proposal CONFERENCE: OTHER ADMINISTRATIVE ITEMS�� |
| ��PRE-proposal CONFERENCE: resources�� |
| PRE-proposal CONFERENCE: Questions |
| �PRE-proposal CONFERENCE: CLOSING REMARKS� |
File details come from the government source that posted it. Updated .