Grant Administration and Construction Oversight Services.pdf

PDF 355 KB Posted

Attached to
Community Development Block Grant Administration and Construction Oversight
Solicitation number
RFP EM FY27-001
Issued by
Beaufort County, Lasker Town, North Carolina

About this file

This is a Request for Proposals (RFP) issued by Beaufort County, North Carolina for grant administration and construction oversight services related to a Community Development Block Grant-Neighborhood Revitalization (CDBG-NR) program. The County has been awarded $950,000 under the North Carolina Department of Commerce, Rural Economic Development Division (REDD) to reconstruct eligible owner-occupied housing units for low- and moderate-income households. The selected firm will serve as the County's day-to-day administrator, prepare environmental review records, maintain compliance documentation, process drawdown requests and reports to REDD, conduct construction inspections, prepare work write-ups and bid specifications, assist with contractor procurement, and manage construction oversight without serving as the general contractor. The project involves four primary housing units and two alternates, with a grant period extending through June 28, 2029 for closeout. Key deadlines include release of Funding Approval Conditions by December 28, 2026; environmental review and compliance plans by January 28, 2027; Request for Release of Funds by February 28, 2027; obligation of funds by December 28, 2028; and expenditure completion by March 28, 2029. Proposals are due Tuesday, November 24, 2026 at 2:00 p.m. Eastern Time, submitted to the Beaufort County Purchasing Officer. Board consideration of the award is anticipated for Monday, December 7, 2026.

The cost proposal must clearly separate program administration costs from activity delivery and construction oversight costs, each submitted as not-to-exceed fees itemized by major task. Minimum qualifications require demonstrated experience administering more than one CDBG project, successful completion of at least two housing rehabilitation or reconstruction projects funded by CDBG or equivalent federal or state housing programs, knowledge of applicable federal and state regulations, and adequate staffing capacity to meet the Section 30 schedule. No debarment, suspension, or exclusion under SAM.gov or the North Carolina debarred-vendors list is required. The evaluation committee will score proposals on a 100-point scale emphasizing CDBG experience (30 points), staff qualifications (25 points), capacity and availability (15 points), approach and understanding (15 points), cost proposal reasonableness (10 points), and optional documentation of HUB, M/WBE, SDVOB, or Section 3 business concern status (5 points). The selected firm must provide certificates of insurance including Workers' Compensation (statutory), Commercial General Liability ($1,000,000 per occurrence/$2,000,000 aggregate), Automobile Liability ($1,000,000 combined single limit), and Professional Liability ($1,000,000 per claim) before work begins. Beaufort County shall be named as an additional insured on the general liability policy. The anticipated contract will include required CDBG program clauses and obligate the administrator to reimburse the County for any improperly expended grant funds resulting from the administrator's error or noncompliance.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BEAUFORT COUNTY, NORTH CAROLINA | CDBG-NR Grant Administration RFP RFP EM FY27-001

CDBG-NR 24-C-4217 • Page 1

REQUEST FOR PROPOSALS

Grant Administration and Construction Oversight Services

Community Development Block Grant – Neighborhood Revitalization

Grant No. 24-C-4217 • $950,000 • Beaufort County, North Carolina

1. Purpose and Background

Beaufort County has been awarded $950,000 under the North Carolina Department of Commerce, Rural Economic Development Division (REDD), Community Development Block Grant – Neighborhood Revitalization (CDBG-NR) program, Grant No. 24-C-4217. The project will reconstruct eligible owner-occupied housing units for low- and moderate-income households in Beaufort County. The County is soliciting competitive proposals from qualified firms to provide grant administration and construction oversight services for the full grant period.

Funding Approval Condition B requires that no administration funds may be obligated until the Chairman certifies that the County is using an experienced CDBG administrator (or local staff) who has administered more than one CDBG project. Proposals must demonstrate that the firm and its proposed project manager meet this standard. Other Funding Approval conditions (environmental review, Performance Based Contract, citizen participation documentation, BABA acknowledgment, and Section 3 acknowledgment) must also be satisfied before non-administration funds can be drawn. This solicitation is for professional services only. The selected firm will administer the grant, prepare work write-ups and bid documents, assist with procurement of construction contractors, and monitor construction. The selected firm will not serve as the general contractor for the housing units. Construction will be procured separately under a later solicitation open to licensed North Carolina general contractors.

This RFP is issued under 2 CFR Part 200.320 (competitive proposals) and North Carolina CDBG Bulletin 10-15.

Proposals will be evaluated on qualifications, capacity, approach, and cost. Selection will not be based on price alone.

2. Project Summary

• Grant: CDBG-NR 24-C-4217, North Carolina Department of Commerce / REDD.

• Award amount: $950,000.

• Activity: reconstruction of eligible owner-occupied single-family housing units (demolition and new construction on a permanent foundation), plus required program compliance.

• Units: four primary units and two alternates, as identified in the approved application. Final unit list is subject to title review, eligibility confirmation, and REDD approval.

• Grant period and Section 30 schedule (as extended): Release of Funding Approval Conditions by December 28, 2026 (extended from the printed September 28, 2026 date by approved extension); Environmental Review and required compliance plans by January 28, 2027; Request for Release of Funds by February 28, 2027; obligation of funds by December 28, 2028; expenditure and completion of activities by March 28, 2029;

closeout documents to REDD by June 28, 2029.

• Program administration costs are limited by CDBG rules. Activity delivery costs associated with housing reconstruction are separate from the administration cap. Proposers must clearly separate the two in the cost proposal.

3. Scope of Services

The selected firm shall provide all professional services necessary to implement and close the project in compliance with HUD regulations, 2 CFR Part 200, 24 CFR Part 58, 24 CFR Part 75 (Section 3), North Carolina CDBG program requirements, and the Grant Agreement. Services include, but are not limited to:

A. Grant Administration

CDBG-NR 24-C-4217 • Page 2

• Serve as the County’s day-to-day administrator for CDBG-NR 24-C-4217, under the direction of the County’s designated project manager.

• Satisfy remaining Funding Approval conditions and prepare the environmental review record and Request for Release of Funds under 24 CFR Part 58.

• Prepare and maintain required compliance plans and documentation, including Equal Employment and Procurement, Fair Housing, Section 3, Section 504, Language Access, and Analysis of Impediments, and support required fair housing activities.

• Establish and maintain complete grant files, case files, and financial records sufficient for REDD monitoring and audit.

• Prepare and submit all required reports, drawdown requests, and documentation to REDD.

• Verify beneficiary eligibility and income qualification, and document the low- and moderate-income benefit.

• Coordinate with County staff, REDD, property owners, contractors, and other stakeholders.

• Monitor compliance with federal cross-cutting requirements, including Section 3, equal opportunity, M/WBE outreach, debarment (SAM.gov), labor standards if applicable, lead-based paint, and Build America, Buy America (BABA) ,where required, for FY24 and newer funds.

• Prepare for and support REDD monitoring visits.

• Complete grant closeout and final reporting.

B. Construction Oversight (not general contracting)

• Inspect existing units, prepare work write-ups, cost estimates, and bid specifications for reconstruction consistent with CDBG-NR standards and the approved application.

• Assist the County in preparing and advertising separate competitive solicitations for licensed general contractors. The administrator shall not bid on or perform the construction work.

• Assist with bid opening, responsiveness review, and recommendation for award of construction contracts.

• Coordinate temporary relocation if required, consistent with the Uniform Relocation Act and CDBG rules.

• Conduct progress inspections, review contractor payment applications and lien waivers, and recommend County approval or denial of payments.

• Maintain construction records, change-order documentation, and quality-control files.

• Coordinate final inspections, punch-list completion, and warranty follow-up.

• Advise the County on Davis-Bacon applicability. Single-family owner-occupied reconstruction under CDBG is often exempt; the administrator shall document the determination for each unit.

C. Exclusions

The following are not part of this contract: general contracting; acting as the builder of record; holding a construction contract for the housing units; or performing work that would create a conflict with the firm’s oversight role. Firms that wish to perform construction must respond only to the separate construction solicitation and may not also serve as administrators.

4. Minimum Qualifications

To be considered responsive, a firm must demonstrate:

• Demonstrated experience administering more than one CDBG project, consistent with Funding Approval Condition B. The selected firm or its assigned project manager must be able to support the Chairman’s certification that the County is using an experienced CDBG administrator who has administered more than one CDBG project. Equivalent HUD CPD or federal housing-program experience may be considered, but CDBG project administration experience is required to satisfy Condition B.

• Successful completion of at least two housing rehabilitation or reconstruction projects funded by CDBG, CDBG-DR, HOME, or an equivalent federal or state housing program. North Carolina CDBG experience is preferred but is not required if equivalent experience is documented.

• Knowledge of 2 CFR Part 200, 24 CFR Part 58, Section 3 (24 CFR Part 75), and North Carolina Department of Commerce CDBG procedures.

CDBG-NR 24-C-4217 • Page 3

• Adequate staffing and capacity to meet the Section 30 schedule, including the December 28, 2026 conditions deadline.

• No debarment, suspension, or exclusion under SAM.gov or the North Carolina debarred-vendors list.

A North Carolina general contractor license is not required for this professional-services contract and will not be scored.

5. Proposal Content

Proposals shall be organized as follows and shall not exceed 25 pages, excluding resumes, licenses, and required forms.

A. Firm Information

• Legal name, address, telephone, email, and primary contact.

• Organizational structure and years providing CDBG or equivalent grant-administration services.

• Statement that the firm is not debarred and will maintain SAM.gov registration.

B. Experience

• Up to five comparable projects completed in the last seven years. For each: client, location, funding source and amount, number of housing units, services provided, and outcome.

• At least three references from local-government clients for CDBG or equivalent housing-grant work. Include name, title, telephone, and email.

C. Project Team and Staffing Plan

• Name the project manager and key personnel who will be assigned.

• Resumes and a staffing plan that identifies each person’s role and approximate time commitment. REDD requires the selected response to contain a staffing plan identifying key personnel and their responsibilities.

• Identify any subcontractors and their roles.

D. Approach and Schedule

• Understanding of the project and of CDBG-NR reconstruction rules.

• Proposed methodology for administration, environmental review, eligibility, work write-ups, construction procurement support, and oversight.

• Proposed schedule aligned to the Section 30 dates above, including a plan to meet the December 28, 2026 conditions deadline.

• Approach to risk management, owner communication, and quality control.

E. Cost Proposal

• Not-to-exceed fee for grant administration (program administration), itemized by major task.

• Not-to-exceed fee for activity delivery / construction-oversight tasks, itemized separately.

• Hourly rates for any work outside the not-to-exceed scope.

• Identification of any reimbursable expenses. Travel within Beaufort County is not reimbursable unless pre-approved.

• Total proposed cost. The administrative program cost must be clearly identified so the County can complete the REDD procurement monitoring form.

F. Required Disclosures and Certifications

• Conflict-of-interest disclosure. Disclose any current or former Beaufort County employee, official, or agent who is now employed by, contracted with, or has a financial interest in the firm, and any role the firm or its personnel played in preparing the County’s CDBG-NR application or this solicitation. Failure to disclose is grounds for rejection or contract termination.

• E-Verify affidavit.

• Non-collusion and non-debarment certification.

CDBG-NR 24-C-4217 • Page 4

• Insurance certificates or a commitment to provide the coverages in Section 10 upon award.

• Optional: documentation of current HUB, M/WBE, SDVOB, or Section 3 business concern status, if claiming those evaluation points.

6. Evaluation Criteria

An evaluation committee appointed by the County will score proposals using the written criteria below. The County will document the evaluation and the basis for selection.

Evaluation Factor Maximum Points

Experience with CDBG or equivalent HUD CPD / federal housing programs 30

Staff qualifications and proposed staffing plan 25

Capacity, availability, and ability to meet the Section 30 schedule 15

Approach, understanding, and proposed methodology 15

Cost proposal (reasonableness, completeness, and separation of admin vs. activity delivery)

Documented HUB, M/WBE, SDVOB, or Section 3 business concern status 5

Total 100

Experience (30 points). The County will consider the number, size, complexity, and successful completion of comparable CDBG, CDBG-DR, HOME, or equivalent federal housing rehabilitation or reconstruction projects. North Carolina CDBG experience is valued but is not the sole measure. Equivalent experience with other HUD CPD or federal housing programs will be scored.

Staff qualifications (25 points). Qualifications, relevant certifications, and experience of the project manager and key personnel, and clarity of the staffing plan.

Capacity and availability (15 points). Ability to dedicate sufficient personnel to meet the December 28, 2026 conditions deadline and the remaining Section 30 schedule.

Approach (15 points). Understanding of CDBG-NR reconstruction, environmental review, eligibility, construction procurement support, and risk management.

Cost (10 points). Reasonableness and completeness of the fee, and clear separation of program administration from activity delivery costs. Price is a factor but is not the primary basis of award.

HUB / M/WBE / SDVOB / Section 3 (5 points). Firms that submit current certification as a North Carolina HUB, a certified M/WBE or SDVOB, or a Section 3 business concern under 24 CFR Part 75 may receive up to 5 points.

Certification is optional and is not a condition of award.

7. Conflict of Interest and Fairness

This solicitation was prepared by County staff. Firms must disclose any relationship with a current or former County employee or official, and any role in the original application. The County will evaluate all disclosures and may reject a proposal, or impose mitigation, if a conflict cannot be avoided.

County employees and officials involved in evaluation or award shall have no financial or other interest in a competing firm. The evaluation committee will score proposals against the published criteria only.

8. Selection Process

CDBG-NR 24-C-4217 • Page 5

The County reserves the right to reject any or all proposals, waive minor informalities, request clarification or additional information, conduct interviews, negotiate scope and price with one or more firms, and award the contract that is most advantageous to the County considering the evaluation factors. Award is contingent on Board of Commissioners approval and on execution of a contract containing the clauses required by REDD.

If fewer than two responsive proposals are received, the County will re-advertise and expand direct solicitation before proceeding, consistent with applicable guidance.

9. Anticipated Contract Terms

The contract will include, at a minimum, the clauses required by the CDBG program and the REDD contract-management checklist:

• Conflict of interest.

• Legal remedies.

• Termination (required for contracts of $10,000 or more).

• Nondiscrimination, age discrimination, and handicap discrimination.

• Section 3 (24 CFR Part 75).

• Access to records and record retention (minimum five years after closeout or final audit).

• Anti-lobbying.

• Build America, Buy America (BABA) preference for FY24 and newer CDBG funds.

• Reimbursement: the administrator shall reimburse the County for any improperly expended grant funds that the County is required to return to REDD as a result of the administrator’s error or noncompliance.

The County will check SAM.gov and the North Carolina debarred-vendors list before executing the contract.

10. Insurance

The selected firm shall provide certificates of insurance before work begins:

• Workers’ Compensation: statutory.

• Commercial General Liability: $1,000,000 per occurrence / $2,000,000 aggregate.

• Automobile Liability: $1,000,000 combined single limit.

• Professional Liability (Errors and Omissions): $1,000,000 per claim.

• Each certificate of insurance cannot be cancelled, reduced in amount, or cancelled without 30 days written notice by email, followed by registered mail. Satisfactory proof of new coverage must be given to the county immediately.

Beaufort County shall be named as an additional insured on the general liability policy.

11. Schedule and Submission

The following schedule is established to allow scoring by close of business Monday, November 30, 2026, so the award recommendation can meet the Board Clerk’s Tuesday, December 1, 2026 agenda deadline for the December 7, 2026 Board of Commissioners meeting.

• RFP issued / advertised: Friday, November 7, 2026.

• Questions due by email: Friday, November 14, 2026, 5:00 p.m. Eastern Time.

• Addenda issued (if any): Monday, November 17, 2026.

• Proposals due: Tuesday, November 24, 2026, 2:00 p.m. Eastern Time.

• Evaluation and scoring complete: by close of business Monday, November 30, 2026. Anticipated Board consideration: Monday, December 7, 2026.

Submit one original and three complete copies, sealed, to:

Hollie Jones, Purchasing Officer

Beaufort County Government

132 West 2nd Street

CDBG-NR 24-C-4217 • Page 6

Washington, NC 27889

Mark the package or envelope: “ATTN: RFP – CDBG-NR 24-C-4217 Grant Administration – Do Not Open Until Tues, November 24th 2:00pm.”

Proposals delivered by telephone, fax, or email will not be accepted. Late proposals will not be considered. It is the proposer’s responsibility to ensure timely delivery to the address above.

Questions must be submitted in writing to hollie.jones@beaufortcountync.gov by the question deadline. Answers will be issued by addendum to all known proposers and posted with the solicitation. Contact with other County officials or employees regarding this RFP, other than the designated contact, may be grounds for disqualification.

12. Equal Opportunity and Outreach

Beaufort County is an Equal Opportunity Employer. Minority-owned, women-owned, historically underutilized, veteran-owned, small, and Section 3 business concerns are encouraged to submit proposals. The County will directly solicit qualified HUB, M/WBE, veteran-owned, and Section 3 firms in addition to public advertisement, consistent with the REDD procurement monitoring form.

13. Reservation of Rights and General Terms

• The County may amend or cancel this solicitation at any time before award.

• Costs of proposal preparation are the sole responsibility of the proposer.

• A proposal may be withdrawn before the deadline. After the deadline, a proposal is an irrevocable offer for 90 days.

• The County may request clarification and additional information.

• Award is subject to availability of funds and to REDD requirements.

Project contact for technical questions after award will be the Director of Emergency Services or a designee. All pre-award communications shall go through the Purchasing Officer named above.

1. Purpose and Background
2. Project Summary
3. Scope of Services
A. Grant Administration
B. Construction Oversight (not general contracting)
C. Exclusions
4. Minimum Qualifications
5. Proposal Content
A. Firm Information
B. Experience
C. Project Team and Staffing Plan
D. Approach and Schedule
E. Cost Proposal
F. Required Disclosures and Certifications
6. Evaluation Criteria
7. Conflict of Interest and Fairness
8. Selection Process
9. Anticipated Contract Terms
10. Insurance
11. Schedule and Submission
12. Equal Opportunity and Outreach
13. Reservation of Rights and General Terms

File details come from the government source that posted it. Updated .